CN109936129A - A kind of power failure and Accident Handling Method - Google Patents

A kind of power failure and Accident Handling Method Download PDF

Info

Publication number
CN109936129A
CN109936129A CN201811615481.1A CN201811615481A CN109936129A CN 109936129 A CN109936129 A CN 109936129A CN 201811615481 A CN201811615481 A CN 201811615481A CN 109936129 A CN109936129 A CN 109936129A
Authority
CN
China
Prior art keywords
generator
power failure
handling method
judge
accident handling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811615481.1A
Other languages
Chinese (zh)
Other versions
CN109936129B (en
Inventor
不公告发明人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Xunhui Technology Co.,Ltd.
Original Assignee
Shandong Noyuan Power Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Noyuan Power Equipment Co Ltd filed Critical Shandong Noyuan Power Equipment Co Ltd
Priority to CN201811615481.1A priority Critical patent/CN109936129B/en
Publication of CN109936129A publication Critical patent/CN109936129A/en
Application granted granted Critical
Publication of CN109936129B publication Critical patent/CN109936129B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)
  • Protection Of Generators And Motors (AREA)

Abstract

The invention discloses a kind of power failure and Accident Handling Methods, comprising: (1) judges the voltage of generator, transformer and route, electric current, active and reactive indicates whether that generating period is substantially gone up and down;(2) judge headlamp whether with voltage fluctuation light and dark;(3) judge whether generator issues rhythmical ring sound;(4) judge whether generation is acted down to chaser for unit loss of synchronism protection;(5) it determines fault signature occur, starts processing routine.Power failure and accident treatment mode of the invention applies generator of the violent oscillation perhaps in power plant whether occurs whether lose the same period to occur to realize processing so that power plant is always maintained at safe and stable operating status if violent oscillation or generator lose the same period rapidly if electric system for detecting electric system in power plant.

Description

A kind of power failure and Accident Handling Method
Technical field
The present invention relates to technical field of electric power, especially a kind of power failure and Accident Handling Method.
Background technique
As intelligentized demand is increasing, and various electric appliances are flooded with people's lives to living by people.And these are electric Device is due to using different principles, so that the load of single characteristic present in script electric system also becomes to be enriched, Whether load in nature or equal compared with the past realizes the variation of matter in the quantity of load.
And these are loaded so that the electric system of script becomes increasingly complex, as a result result in the obvious of buterfly effect plus Play, a very small problem would potentially result in the collapse of whole system.Therefore, it timely finds the problem and realizes that processing is current Electric system technical problem urgently to be resolved.
Summary of the invention
Therefore, it in view of the above-mentioned problems, the present invention provides a kind of power failure and Accident Handling Method, applies and is generating electricity For detecting whether the generator whether electric system occurs in violent oscillation or power plant loses the same period in factory, if electric Violent oscillation or generator occur for Force system lose the same period then to realize processing rapidly so that power plant is always maintained at safety, steady Fixed operating status.
In order to achieve the above object, the invention proposes a kind of power failure and Accident Handling Methods, which is characterized in that It applies in power plant for detecting whether the generator whether electric system occurs in violent oscillation or power plant loses The same period, if electric system occur if violent oscillation or generator lose the same period to realize processing rapidly so that power plant always Keep safe and stable operating status, the power failure and Accident Handling Method the following steps are included:
(1) judge the voltage of generator, transformer and route, electric current, active and reactive indicate whether that generating period substantially rises Drop, if it is goes to step (2), otherwise circulation step (1);
(2) judge headlamp whether with voltage fluctuation light and dark, if it is go to step (3), otherwise return to step (1);
(3) judge whether generator issues rhythmical ring sound, if it is go to step (4), otherwise return to step (1);
(4) judge whether generation movement down to chaser, if it is goes to step (5), otherwise returns to step for unit loss of synchronism protection (1);
(5) it determines fault signature occur, starts processing routine.
The power failure and Accident Handling Method, also meet the following conditions: the step (5) specifically include with Lower step:
(a) AVC is immediately exited from, increases exciting current manually, makes full use of the accident overload ability of generator, is gradually increased and is Voltage unite up to threshold limit value, whether fault signature described in real-time judge disappears in the process, terminates if disappearing, no Then go to step (b);
(b) judge the change direction of real-time frequency, if change direction is upward, i.e., frequency increases, and reduce rapidly generator has Function power output, until oscillation disappears, but frequency must not be lower than 49.5Hz;If change direction is downward, i.e., frequency reduces, and makes full use of Spare capacity and accident overload capacity increase the active power output of generator, until oscillation elimination or frequency back to normal;
(c) judge whether the fault signature disappears, terminate if disappearing, otherwise go to step (d);
(d) generated power power output is reduced, increases excitation, so that generator is dragged in synchronization;
(e) judge whether to restore synchronous operation and loss of synchronism protection is not operating, if it is off-the-line generating set and in time to scheduling Report information is issued, if otherwise restoring unit operation in the trouble-free situation of excitation system;
(f) judge whether the fault signature disappears, terminate if disappearing, otherwise go to step (g);
(g) implement through same period cyclization, a predetermined time judges whether the fault signature disappears after this, ties if disappearing Otherwise beam issues request processing information to scheduling.
The power failure and Accident Handling Method, also meet the following conditions: ensureing and do not understand at implementation steps (5) Arrange any unit.
The power failure and Accident Handling Method, also meet the following conditions: the predetermined time is 3 to 4 minutes.
The power failure and Accident Handling Method, also meet the following conditions: the request processing information passes through nothing Gauze network is issued.
The power failure and Accident Handling Method, also meet the following conditions: the wireless network be 3G, 4G, WIFI etc..
The power failure and Accident Handling Method, also meet the following conditions: the normal frequency is 50Hz.
Detailed description of the invention
Fig. 1 is the flow chart of power failure and Accident Handling Method.
Specific embodiment
Referring to Figure 1.
A kind of power failure and Accident Handling Method, which is characterized in that apply in power plant for detecting power train Whether the generator whether system occurs in violent oscillation or power plant loses the same period, if violent vibration occurs for electric system Swing or generator lose the same period then realize rapidly processing so that power plant is always maintained at safe and stable operating status, it is described Power failure and Accident Handling Method the following steps are included:
(1) judge the voltage of generator, transformer and route, electric current, active and reactive indicate whether that generating period substantially rises Drop, if it is goes to step (2), otherwise circulation step (1);
(2) judge headlamp whether with voltage fluctuation light and dark, if it is go to step (3), otherwise return to step (1);
(3) judge whether generator issues rhythmical ring sound, if it is go to step (4), otherwise return to step (1);
(4) judge whether generation movement down to chaser, if it is goes to step (5), otherwise returns to step for unit loss of synchronism protection (1);
(5) it determines fault signature occur, starts processing routine.
The power failure and Accident Handling Method, also meet the following conditions: the step (5) specifically include with Lower step:
(a) AVC is immediately exited from, increases exciting current manually, makes full use of the accident overload ability of generator, is gradually increased and is Voltage unite up to threshold limit value, whether fault signature described in real-time judge disappears in the process, terminates if disappearing, no Then go to step (b);
(b) judge the change direction of real-time frequency, if change direction is upward, i.e., frequency increases, and reduce rapidly generator has Function power output, until oscillation disappears, but frequency must not be lower than 49.5Hz;If change direction is downward, i.e., frequency reduces, and makes full use of Spare capacity and accident overload capacity increase the active power output of generator, until oscillation elimination or frequency back to normal;
(c) judge whether the fault signature disappears, terminate if disappearing, otherwise go to step (d);
(d) generated power power output is reduced, increases excitation, so that generator is dragged in synchronization;
(e) judge whether to restore synchronous operation and loss of synchronism protection is not operating, if it is off-the-line generating set and in time to scheduling Report information is issued, if otherwise restoring unit operation in the trouble-free situation of excitation system;
(f) judge whether the fault signature disappears, terminate if disappearing, otherwise go to step (g);
(g) implement through same period cyclization, a predetermined time judges whether the fault signature disappears after this, ties if disappearing Otherwise beam issues request processing information to scheduling.
Not any unit of off-the-line is ensured at implementation steps (5).
The predetermined time is 3 to 4 minutes.
The request processing information is issued by wireless network.
The wireless network is 3G, 4G, WIFI etc..
The normal frequency is 50Hz.
It should be noted that the above content is combine specific embodiment made for the present invention further specifically It is bright, and it cannot be said that a specific embodiment of the invention is only limitted to this, under above-mentioned guidance of the invention, those skilled in the art can To carry out various improvement and deformations on the basis of the above embodiments, and these are improved or deformation falls in protection model of the invention In enclosing.

Claims (7)

1. a kind of power failure and Accident Handling Method, which is characterized in that apply in power plant for detecting electric system Whether the generator whether occurred in violent oscillation or power plant loses the same period, if violent oscillation occurs for electric system Or generator lose the same period then rapidly realize processing so that power plant is always maintained at safe and stable operating status, the electricity Power failure and Accident Handling Method the following steps are included:
(1) judge the voltage of generator, transformer and route, electric current, active and reactive indicate whether that generating period substantially rises Drop, if it is goes to step (2), otherwise circulation step (1);
(2) judge headlamp whether with voltage fluctuation light and dark, if it is go to step (3), otherwise return to step (1);
(3) judge whether generator issues rhythmical ring sound, if it is go to step (4), otherwise return to step (1);
(4) judge whether generation movement down to chaser, if it is goes to step (5), otherwise returns to step for unit loss of synchronism protection (1);
(5) it determines fault signature occur, starts processing routine.
2. a kind of power failure according to claim 2 and Accident Handling Method, which is characterized in that the step (5) Specifically includes the following steps:
(a) AVC is immediately exited from, increases exciting current manually, makes full use of the accident overload ability of generator, is gradually increased and is Voltage unite up to threshold limit value, whether fault signature described in real-time judge disappears in the process, terminates if disappearing, no Then go to step (b);
(b) judge the change direction of real-time frequency, if change direction is upward, i.e., frequency increases, and reduce rapidly generator has Function power output, until oscillation disappears, but frequency must not be lower than 49.5Hz;If change direction is downward, i.e., frequency reduces, and makes full use of Spare capacity and accident overload capacity increase the active power output of generator, until oscillation elimination or frequency back to normal;
(c) judge whether the fault signature disappears, terminate if disappearing, otherwise go to step (d);
(d) generated power power output is reduced, increases excitation, so that generator is dragged in synchronization;
(e) judge whether to restore synchronous operation and loss of synchronism protection is not operating, if it is off-the-line generating set and in time to scheduling Report information is issued, if otherwise restoring unit operation in the trouble-free situation of excitation system;
(f) judge whether the fault signature disappears, terminate if disappearing, otherwise go to step (g);
(g) implement through same period cyclization, a predetermined time judges whether the fault signature disappears after this, ties if disappearing Otherwise beam issues request processing information to scheduling.
3. a kind of power failure according to claim 2 and Accident Handling Method, which is characterized in that in implementation steps (5) not any unit of off-the-line is ensured when.
4. a kind of power failure according to claim 3 and Accident Handling Method, which is characterized in that the predetermined time It is 3 to 4 minutes.
5. a kind of power failure according to claim 4 and Accident Handling Method, which is characterized in that the request processing Information is issued by wireless network.
6. a kind of power failure according to claim 5 and Accident Handling Method, which is characterized in that the wireless network For 3G, 4G, WIFI etc..
7. a kind of power failure according to claim 6 and Accident Handling Method, which is characterized in that the normal frequency For 50Hz.
CN201811615481.1A 2019-03-19 2019-03-19 Power failure and accident handling method Active CN109936129B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811615481.1A CN109936129B (en) 2019-03-19 2019-03-19 Power failure and accident handling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811615481.1A CN109936129B (en) 2019-03-19 2019-03-19 Power failure and accident handling method

Publications (2)

Publication Number Publication Date
CN109936129A true CN109936129A (en) 2019-06-25
CN109936129B CN109936129B (en) 2020-08-07

Family

ID=66984819

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811615481.1A Active CN109936129B (en) 2019-03-19 2019-03-19 Power failure and accident handling method

Country Status (1)

Country Link
CN (1) CN109936129B (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101741099A (en) * 2010-01-15 2010-06-16 国网电力科学研究院 Method for preventing false tripping of electric system out-of-step separating device in symmetrical fault
CN105529704A (en) * 2016-02-22 2016-04-27 东北大学 Power grid out-of-step disconnecting control system and method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101741099A (en) * 2010-01-15 2010-06-16 国网电力科学研究院 Method for preventing false tripping of electric system out-of-step separating device in symmetrical fault
CN105529704A (en) * 2016-02-22 2016-04-27 东北大学 Power grid out-of-step disconnecting control system and method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
王为国 等: "关于电厂AVC的若干技术问题", 《湖北电力》 *
胡本哲: "《电力生产过程》", 31 December 1983, 水利电力出版社 *

Also Published As

Publication number Publication date
CN109936129B (en) 2020-08-07

Similar Documents

Publication Publication Date Title
CN108626070B (en) Brake control method and system of wind generating set
CN202652141U (en) Coal feeder frequency converter low voltage crossover device
WO2021000682A1 (en) Direct current islanding detection method based on positive feedback of bus voltage having specific frequency
CN103457296B (en) A kind of independent operating micro-grid master control power-supply switching method
JP6410696B2 (en) System control device and system stabilization system
Jalali et al. Frequency stability provision from battery energy storage system considering cascading failure s with applications to separation events in Australia
JP2016226120A (en) Power conditioner operation controller, operation control method, operation control program, and photovoltaic system
JP2017163768A (en) Power conversion equipment and control method therefor
CN109936129A (en) A kind of power failure and Accident Handling Method
CN110838724B (en) Control method and system for preventing wind power plant from operating in isolated island mode
CN104637558B (en) Safe and stable control method for asynchronous oscillation of nuclear power unit
CN100452605C (en) Method and system for preventing electric network from collapsing
WO2023093304A1 (en) Emergency discharge control method for main and auxiliary integrated internal combustion locomotive
CN110171765A (en) A kind of escalator guard method and its system
CN105846548A (en) Power plant black start dedicated diesel generating set remote monitoring system
CN110365024A (en) A kind of emergency control method for inhibiting direct-current commutation failure to cause sending end blower off-grid
CN109921471A (en) A kind of multiple synchronization paralleling System and method for of generating set
CN109936118A (en) A kind of electricity generation system fault treating apparatus
KR20190085076A (en) A method for controlling a wind power plant
Imai et al. UFLS program to ensure stable island operation
CN104201675B (en) A kind of load of overload circuit is poured out and restoration methods automatically
CN104821608B (en) Micro-capacitance sensor frequency, active and time ternary establishment of coordinate system method
CN110429619A (en) A kind of disaster tolerance reaction method of the Demand-side frequency urgent control of ultra-large power grid
CN110460070A (en) A kind of quick reaction method of the Demand-side frequency urgent control of ultra-large power grid
Islam et al. A decentralized multi-agent approach to prevent voltage collapse in a large power system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20200714

Address after: 211300 No. 8 Flower Hill Road, Gaochun Economic Development Zone, Nanjing, Jiangsu

Applicant after: NANJING SINCERE TECHNOLOGY DEVELOPMENT Co.,Ltd.

Address before: 274009 room 2903, PEAK International Garden, the Yellow River Road, Mudan District, Heze, Shandong, China, 1

Applicant before: SHANDONG NUOYUAN POWER EQUIPMENT Co.,Ltd.

GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: No. 8, Huashan Road, Gaochun Economic Development Zone, Nanjing City, Jiangsu Province, 211300

Patentee after: Jiangsu Xunhui Technology Co.,Ltd.

Address before: No. 8, Huashan Road, Gaochun Economic Development Zone, Nanjing City, Jiangsu Province, 211300

Patentee before: NANJING SINCERE TECHNOLOGY DEVELOPMENT CO.,LTD.

CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: Building 1, No. 35 Xiushan Road, Economic Development Zone, Gaochun District, Nanjing City, Jiangsu Province, 211300

Patentee after: Jiangsu Xunhui Technology Co.,Ltd.

Address before: No. 8, Huashan Road, Gaochun Economic Development Zone, Nanjing City, Jiangsu Province, 211300

Patentee before: Jiangsu Xunhui Technology Co.,Ltd.