CN109930628A - A kind of pre-buried mounting device and method for breathing out fragrant slot - Google Patents

A kind of pre-buried mounting device and method for breathing out fragrant slot Download PDF

Info

Publication number
CN109930628A
CN109930628A CN201910248982.9A CN201910248982A CN109930628A CN 109930628 A CN109930628 A CN 109930628A CN 201910248982 A CN201910248982 A CN 201910248982A CN 109930628 A CN109930628 A CN 109930628A
Authority
CN
China
Prior art keywords
fragrant slot
slot
breathing out
building template
bolt anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910248982.9A
Other languages
Chinese (zh)
Inventor
王敉鹏
何伟
孙金辉
董玉坤
杨克文
张文平
康亚林
刘坤
冯泽权
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN201910248982.9A priority Critical patent/CN109930628A/en
Publication of CN109930628A publication Critical patent/CN109930628A/en
Pending legal-status Critical Current

Links

Abstract

A kind of pre-buried mounting device and method for breathing out fragrant slot, suitable for concrete component to the location and installation for breathing out fragrant slot, including the reinforcing bar and Ha Fen slot in building template with interior cavity and building template, the Kazakhstan sweet smell slot extends along the length direction of building template, the rear side of the Kazakhstan sweet smell slot is equipped with multiple bolt anchors, one or more of multiple bolt anchor is connected and fixed by positioning bar and reinforcing bar, and building template side is close at the front openings of the Kazakhstan sweet smell slot.The pre-buried mounting device and method for breathing out fragrant slot of one kind provided in an embodiment of the present invention, design rationally, realize the simplification of the precision and construction of breathing out the pre-buried installation positioning of fragrant slot, meet the needs of site operation repeatability and replicability.

Description

A kind of pre-buried mounting device and method for breathing out fragrant slot
Technical field
The present invention relates to a kind of pre-buried mounting devices and method for breathing out fragrant slot.
Background technique
Underground pipe gallery construction is the short slab for mending urban infrastructure, treats one good recipe of urban disease, breathes out fragrant slot and makees It for a kind of built-in fitting for building, is had very important effect in underground pipe gallery equipment installation project, breathes out the pre-buried of fragrant slot Quality affects the quality of subsequent installation engineer operation, it is ensured that its pre-buried quality is to guarantee the inevitable requirement of construction quality qualification.
It is " a kind of to nuzzle in advance the peace of concrete component for that breathe out fragrant slot that application No. is the patents of CN201710399840.3 Assembling structure and method " will be breathed out fragrant slot using T-bolt and nut and be fixed on building template, basic construction technological process packet Include: preparation of construction, piping lane main body are equipped with building template, number, the building template hole of installation T-bolt are opened on building template, will It breathes out fragrant slot to be fixed on building template using T-bolt and nut assembly, wall breathes out the installation of fragrant slot and building template fixing piece And verticality adjustment, concreting, nut and building template are removed, finished product protection and etc..This method installation and dismounting Complex procedures, to fragrant slot being pre-positioned on building template is breathed out, requirement is high, and not easy to operate, T-bolt is fixed with building template Part is both needed to punch on building template, larger to building template damage, influences the continuity of building template back cord reinforcing and builds Building mould is used in turn number, at high cost, and narrow application range, and it is easy to be only applicable to wood building formwork and plastic building template etc. In the building template to punch, it is difficult to apply in the building templates support systems such as aluminium building template, steel building template, in addition tears open Heavy workload when except building template, the accumulation striking time in linear engineering is longer, influences process handover and work progress Continuity can cause to damage during demoulding to T-bolt and nut, cause increased costs and later period fixing piece to install not beautiful The problems such as sight.
Summary of the invention
The present invention provides a kind of pre-buried mounting devices and method for breathing out fragrant slot, realize the pre-buried installation positioning of the fragrant slot in Kazakhstan Precision and construction simplification, solve problems of the prior art.
The present invention is in order to solve the above technical problems, in a first aspect, the embodiment of the invention provides a kind of pre-buried fragrant slots in Kazakhstan Mounting device, suitable for concrete component to the location and installation for breathing out fragrant slot, including building template with interior cavity and building Reinforcing bar and Ha Fen slot in template, the Kazakhstan sweet smell slot extend along the length direction of building template, and the rear side of the Kazakhstan sweet smell slot is equipped with multiple Bolt anchor, one or more of multiple bolt anchor are connected and fixed by positioning bar and reinforcing bar, the front openings of the Kazakhstan sweet smell slot It is close on the inside of building template at place.Reinforcing bar and bolt anchor are connected by positioning bar, can effectively fix the fragrant slot in Kazakhstan, here Reinforcing bar come from wall main reinforcement net, be fixed on building template using bolt and nut component by fragrant slot is breathed out compared to existing Method, the present invention is simpler for the fixed operation for breathing out fragrant slot, more accurate positioning.
In one example, the bolt anchor is between the length direction interval setting for breathing out fragrant slot, the two neighboring bolt anchor 20 centimetres -30 centimetres of interval.
In one example, in multiple bolt anchor, connected close to the bolt anchor for breathing out fragrant slot end by positioning bar and reinforcing bar It connects.Fragrant slot and bolt anchor will be breathed out from the fragrant slot both ends in Kazakhstan to be fixed together with positioning bar, not only save positioning bar, but also can stablize fixation Breathe out fragrant slot.
In one example, this Kazakhstan sweet smell slot is vertical with bolt anchor connect, the bolt anchor and positioning bar to link together is same On one horizontal line, then the protective layer thickness of the reinforcing bar, the length of positioning bar, the length of bolt anchor and breathe out fragrant slot thickness it With the thickness for being equal to building template inner cavity.After the thickness of building template inner cavity determines, the length of positioning bar also just be can determine that down Come, after the positioning bar of exact length installs, the bolt anchor breathed out on fragrant slot can be directly welded on positioning bar, without again Measurement, construction is simple, a location and installation are avoided increasing working procedure, not only saved manually, but also accelerate speed;Meanwhile The length of positioning bar is determined according to the thickness of building template inner cavity, that is, the thickness after concrete component formation determines positioning The length of muscle avoids breathing out the pre-buried position deviation of fragrant slot and the later period is caused to pick chisel construction.
In one example, the both ends of the bolt anchor respectively include the first disk and the second disk, first disk and Kazakhstan Fragrant slot connection, second disk is idle or connect with positioning bar.The diameter of first disk and the second disk is greater than among bolt anchor Partial diameter can facilitate and the connection of breathing out fragrant slot and positioning bar.
In one example, the side of the bolt anchor is equipped with anti-skidding wing, and the easy removal of solid of filling is filled out in the Kazakhstan sweet smell slot Fill object.The setting of bolt anchor further enhances the combination breathed out between fragrant slot and concrete, prevent vibrating head to concrete into When row vibrates, breathes out and relatively moved between fragrant slot and concrete.
Second aspect is breathed out the pre-buried installation method of fragrant slot the embodiment of the invention provides a kind of, is suitable in concrete structure To the location and installation for breathing out fragrant slot in part, comprising:
Fragrant slot, which is breathed out, in building template internal labeling buries altitude line;Wherein, cavity is set in the building template;
Determine the length l of positioning bar;
According to the altitude line marked, positioning bar one end is welded on the reinforcing bar in building template;
Breathe out the other end that the part bolt anchor on fragrant slot is welded on positioning bar;Wherein, fragrant close to breathing out in multiple bolt anchors The bolt anchor of slot end is connect by positioning bar with reinforcing bar.
In one example, this is described in the embedded altitude line of the fragrant slot in template internal labeling Kazakhstan, specifically includes:
The elevation control point for breathing out fragrant slot is released into building template with theodolite;
Bracing wire or each control point of light beam connection issued with laser between control point;
The inbuilt altitude line of the fragrant slot in Kazakhstan is marked on reinforcing bar and building template along bracing wire or light beam.
In one example, the length of the determination positioning bar, specifically includes: the thickness a of measurement building template inner cavity, breathing out Positioning bar is calculated according to l=a-b-c-d in the protective layer thickness d of the thickness b of fragrant slot, the length c of bolt anchor and reinforcing bar Length l.
The pre-buried mounting device and method for breathing out fragrant slot of one kind provided in an embodiment of the present invention, design is reasonable, construction is simple, Location and installation is avoided increasing working procedure, not only saved manually, but also accelerate speed;Accurate positioning, it is mixed according to design Solidifying soil component thickness determines positioning bar length, avoids pre-buried position deviation that the later period is caused to pick chisel construction;It is pre-buried to realize the fragrant slot in Kazakhstan The precision of positioning and the simplification of construction are installed, the needs of site operation repeatability and replicability are met.Meanwhile The pre-buried mounting device and method for breathing out fragrant slot of one kind provided in an embodiment of the present invention, convenient for promoting, technical difficulty is low, Gong Renyi Application is grasped in skilled.
Detailed description of the invention
Fig. 1 is the pre-buried mounting device structural schematic diagram for breathing out fragrant slot of one kind provided in an embodiment of the present invention;
Fig. 2 is the pre-buried mounting device top view for breathing out fragrant slot of one kind provided in an embodiment of the present invention;
Fig. 3 is the partial enlarged view in Fig. 2;
Fig. 4 is the pre-buried installation method flow chart for breathing out fragrant slot of one kind provided in an embodiment of the present invention.
In figure, 1, building template, 2, reinforcing bar, 3, the fragrant slot in Kazakhstan, 4, bolt anchor, 5, positioning bar, the 6, first disk, 7, second Disk, 8, anti-skidding wing.
Specific embodiment
In order to clarify the technical characteristics of the invention, below by specific embodiment, and its attached drawing is combined, to this Invention is described in detail.
Many details are explained in the following description in order to fully understand the application, still, the application may be used also To be implemented using other than the one described here other modes, therefore, the protection scope of the application is not by described below Specific embodiment limitation.
In addition, in the description of the present application, it is to be understood that term " center ", "upper", "lower", "front", "rear", The orientation of the instructions such as "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside", " axial direction ", " radial direction ", " circumferential direction " Or positional relationship is to be based on the orientation or positional relationship shown in the drawings, and is merely for convenience of description the application and simplifies description, and It is not that the device of indication or suggestion meaning or element must have a particular orientation, be constructed and operated in a specific orientation, therefore It should not be understood as the limitation to the application.
In addition, term " first ", " second " are used for description purposes only, it is not understood to indicate or imply relatively important Property or implicitly indicate the quantity of indicated technical characteristic." first " is defined as a result, the feature of " second " can be expressed Or implicitly include one or more this feature.In the description of the present application, the meaning of " plurality " is two or two with On, unless otherwise specifically defined.
In this application unless specifically defined or limited otherwise, term " installation ", " connected ", " connection ", " fixation " Equal terms shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integral;It can be machine Tool connection, is also possible to be electrically connected, can also be communication;It can be directly connected, the indirect phase of intermediary can also be passed through Even, the connection inside two elements or the interaction relationship of two elements be can be.For those of ordinary skill in the art For, the concrete meaning of above-mentioned term in this application can be understood as the case may be.
In this application unless specifically defined or limited otherwise, fisrt feature in the second feature " on " or " down " can be with It is that the first and second features directly contact or the first and second features pass through intermediary mediate contact.In retouching for this specification In stating, reference term " one embodiment ", " some embodiments ", " example ", " specific example " or " some examples " etc. are retouched It states and means particular features, structures, materials, or characteristics described in conjunction with this embodiment or example are contained in the application at least one In a embodiment or example.In the present specification, schematic expression of the above terms are necessarily directed to identical implementation Example or example.Moreover, particular features, structures, materials, or characteristics described can be in any one or more embodiment or examples In can be combined in any suitable manner.
As shown in Figure 1-3, the embodiment of the invention provides a kind of pre-buried mounting devices for breathing out fragrant slot.The mounting device is suitable For in concrete component to the location and installation for breathing out fragrant slot 3.Here concrete component refers to made of armored concrete The components such as beam, plate, column, basis, also referred to as reinforced concrete member are directly process by scene.
The mounting device includes the reinforcing bar 2 and Ha Fen slot 3 in building template 1 and building template 1 with interior cavity, the Kazakhstan Fragrant slot 3 extends along the length direction of building template 1, and the rear side of the Kazakhstan sweet smell slot 3 is equipped with multiple bolt anchors 4, multiple bolt anchor 4 One or more of be connected and fixed with reinforcing bar 2 by positioning bar 5, abutting building template 1 at the front openings of the Kazakhstan sweet smell slot 3 Inside.Reinforcing bar 2 and bolt anchor 4 are connected by positioning bar 5, can effectively fix the fragrant slot 3 in Kazakhstan, reinforcing bar 2 here comes from The fragrant slot 3 in Kazakhstan is fixed on the method on building template 1 using bolt and nut component compared to existing by wall main reinforcement net, this Invention is simpler for the fixed operation for breathing out fragrant slot 3, more accurate positioning.
Kazakhstan sweet smell slot 3 in the present invention is C-shaped channel opening, and the vallecular cavity width of the C-shaped channel is 3.2 centimetres, and vallecular cavity depth is 1.5 centimetre.Easy removal of solid filler can be filled in the vallecular cavity of C-shaped channel, can effectively prevent mixing in concreting process The vallecular cavity that solidifying soil enters C-shaped channel is difficult to clean off.
The bolt anchor 4 is arranged along the length direction interval for breathing out fragrant slot 3, and 20 lis are spaced between the two neighboring bolt anchor 4 - 30 centimetres of rice.
In multiple bolt anchor 4, it is connect by positioning bar 5 with reinforcing bar 2 close to the bolt anchor 4 for breathing out 3 end of fragrant slot.From two End is fixed to breathe out fragrant slot 3, has not only saved positioning bar 5, but also can stablize to fix and breathe out fragrant slot 3.
Kazakhstan sweet smell slot 3 is vertical with bolt anchor 4 connect for this, and the bolt anchor 4 to link together and positioning bar 5 are in same horizontal line On, then the sum of the protective layer thickness of the reinforcing bar 2, the length of positioning bar 5, the length of bolt anchor 4 and thickness for breathing out fragrant slot 3 etc. Thickness in 1 inner cavity of building template.The protective layer thickness of reinforcing bar 2, the length of bolt anchor 4, breathes out fragrant slot 3 at the length of positioning bar 5 1 inner cavity of thickness and building template thickness in, the protective layer thickness of reinforcing bar 2, the length of bolt anchor 4 and the thickness for breathing out fragrant slot 3 It is all definite value, variable only has the thickness of 1 inner cavity of length and building template of positioning bar 5, so the thickness of 1 inner cavity of building template After determining, the length of positioning bar 5 also just can determine that, and after the positioning bar 5 of exact length installs, breathe out on fragrant slot 3 Bolt anchor 4 can be directly welded on positioning bar 5, and without measuring again, construction is simple a, location and installation is avoided increasing and be applied Work process had not only saved manually, but also has accelerated speed;Meanwhile the length of positioning bar 5 is determined according to the thickness of 1 inner cavity of building template Degree, that is, thickness after concrete component formation determine the length of positioning bar 5, avoid breathing out the pre-buried position deviation of fragrant slot 3 and cause Later period picks chisel construction.
The both ends of the bolt anchor 4 respectively include the first disk 6 and the second disk 7, and the fragrant slot 3 of first disk 6 and Kazakhstan connects It connects, second disk 7 is idle or connect with positioning bar 5.The diameter of first disk 6 and the second disk 7 is at 2 centimetres -2.5 centimetres In range, the diameter of 4 middle section of bolt anchor is in 1 centimetre of -1.5 cm range, the diameter of the first disk 6 and the second disk 7 Greater than the diameter of 4 middle section of bolt anchor, the setting of the first disk 6 can facilitate and breathe out fragrant slot 3 and connect, the second disk 7 Setting, can facilitate and connect with positioning bar 5.
The side of the bolt anchor 4 is equipped with anti-skidding wing 8.The setting of bolt anchor 4 is originally to enhance and breathe out fragrant slot 3 and coagulation Combination between soil, the setting of anti-skidding wing 8 further enhance the combination breathed out between fragrant slot 3 and concrete, prevent vibrating head When vibrating to concrete, breathes out and relatively moved between fragrant slot 3 and concrete.
Fig. 4 is the pre-buried installation method flow chart for breathing out fragrant slot 3 of one kind provided in an embodiment of the present invention.
The installation method suitable for concrete component to the location and installation for breathing out fragrant slot 3, comprising:
S401 releases the elevation control point for breathing out fragrant slot 3 with theodolite into building template 1.
S402, bracing wire or each control point of light beam connection issued with laser between control point.
S403 marks the inbuilt altitude line of the fragrant slot 3 in Kazakhstan along bracing wire or light beam on reinforcing bar 2 and building template 1.
S404 determines the length l of positioning bar 5.It specifically includes: the thickness a of measurement 1 inner cavity of building template, breathing out fragrant slot 3 The length of positioning bar 5 is calculated according to l=a-b-c-d in the protective layer thickness d of thickness b, the length c of bolt anchor 4 and reinforcing bar 2 Spend l.Here protective layer thickness d is the spacing between 2 outside of reinforcing bar and building template 1.
5 one end of positioning bar is welded on the reinforcing bar 2 in building template 1 by S405 according to the altitude line marked.Specifically , positioning bar 5 is arranged along the length direction of building template 1.
S406 breathes out the other end that the part bolt anchor 4 on fragrant slot 3 is welded on positioning bar 5.Particularly, close to the fragrant slot in Kazakhstan The bolt anchor 4 of 3 ends is connect by positioning bar 5 with reinforcing bar 2.
S407 is poured concrete into building template 1.It is poured in space i.e. between Xiang Hafen slot 3 and building template 1 Concrete.
S408, building template 1 are removed.After concrete formation, building template 1 is removed, the solid in fragrant slot 3 will be breathed out Filler takes out.
S409, finished product protection.
Above-mentioned specific embodiment cannot function as limiting the scope of the invention, for the technology of the art For personnel, any alternate modification or transformation made to embodiment of the present invention are fallen within the scope of protection of the present invention.
Place is not described in detail by the present invention, is the well-known technique of those skilled in the art of the present technique.

Claims (9)

1. a kind of pre-buried mounting device for breathing out fragrant slot, suitable for concrete component to the location and installation for breathing out fragrant slot, feature Be: including the reinforcing bar and Ha Fen slot in building template with interior cavity and building template, the fragrant slot in the Kazakhstan is along building template Length direction extends, and the rear side for breathing out fragrant slot is equipped with multiple bolt anchors, and one or more of the multiple bolt anchor passes through Positioning bar is connected and fixed with reinforcing bar, is close on the inside of building template at the front openings for breathing out fragrant slot.
2. the pre-buried mounting device for breathing out fragrant slot of one kind according to claim 1, it is characterised in that: the bolt anchor is fragrant along breathing out The length direction interval of slot is arranged, and 20 centimetres -30 centimetres are spaced between the two neighboring bolt anchor.
3. the pre-buried mounting device for breathing out fragrant slot of one kind according to claim 1 or 2, it is characterised in that: the multiple bolt In anchor, it is connect by positioning bar with reinforcing bar close to the bolt anchor for breathing out fragrant slot end.
4. the pre-buried mounting device for breathing out fragrant slot of one kind according to claim 1, it is characterised in that: the fragrant slot in the Kazakhstan and bolt Anchor vertically connects, and in the same horizontal line, the protective layer thickness of the reinforcing bar positions for the bolt anchor to link together and positioning bar The sum of the length of muscle, the length of bolt anchor and the thickness for breathing out fragrant slot are equal to the thickness of building template inner cavity.
5. the pre-buried mounting device for breathing out fragrant slot of one kind according to claim 1, it is characterised in that: the both ends of the bolt anchor Respectively include the first disk and the second disk, first disk connect with fragrant slot is breathed out, second disk leave unused or with positioning Muscle connection.
6. the pre-buried mounting device for breathing out fragrant slot of one kind according to claim 1, it is characterised in that: the side of the bolt anchor Equipped with anti-skidding wing, filled solid filler in the fragrant slot in the Kazakhstan.
7. a kind of breathe out the pre-buried installation method of fragrant slot, suitable for concrete component to the location and installation for breathing out fragrant slot, feature It is, comprising:
Fragrant slot, which is breathed out, in building template internal labeling buries altitude line;Wherein, cavity is set in the building template;
Determine the length l of positioning bar;
According to the altitude line marked, positioning bar one end is welded on the reinforcing bar in building template;
Breathe out the other end that multiple bolt anchors on fragrant slot are welded on positioning bar;Wherein, in multiple bolt anchors, close to Kazakhstan fragrant slot end Bolt anchor connect with reinforcing bar by positioning bar.
8. the pre-buried installation method for breathing out fragrant slot of one kind according to claim 7, which is characterized in that described in template internal labeling It breathes out fragrant slot and buries altitude line, specifically include:
The elevation control point for breathing out fragrant slot is released into building template with theodolite;
Bracing wire or each control point of light beam connection issued with laser between control point;
The inbuilt altitude line of the fragrant slot in Kazakhstan is marked on reinforcing bar and building template along bracing wire or light beam.
9. the pre-buried installation method for breathing out fragrant slot of one kind according to claim 7, which is characterized in that the determining positioning bar Length l, specifically includes: the thickness a of measurement building template inner cavity, thickness b, the length c of bolt anchor and the guarantor of reinforcing bar for breathing out fragrant slot The length l of positioning bar is calculated according to l=a-b-c-d in covering thickness d.
CN201910248982.9A 2019-03-29 2019-03-29 A kind of pre-buried mounting device and method for breathing out fragrant slot Pending CN109930628A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910248982.9A CN109930628A (en) 2019-03-29 2019-03-29 A kind of pre-buried mounting device and method for breathing out fragrant slot

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910248982.9A CN109930628A (en) 2019-03-29 2019-03-29 A kind of pre-buried mounting device and method for breathing out fragrant slot

Publications (1)

Publication Number Publication Date
CN109930628A true CN109930628A (en) 2019-06-25

Family

ID=66988658

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910248982.9A Pending CN109930628A (en) 2019-03-29 2019-03-29 A kind of pre-buried mounting device and method for breathing out fragrant slot

Country Status (1)

Country Link
CN (1) CN109930628A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110656559A (en) * 2019-08-23 2020-01-07 上海宝冶冶金工程有限公司 Device and method for controlling flatness of embedded part at top of cornice of racing track

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0742293A (en) * 1993-07-30 1995-02-10 Taisei Corp Reinforced concrete floor slab with reinforcing steel frame
JP2007009411A (en) * 2005-06-02 2007-01-18 Toshihisa Ebara Position holding metal fitting and position fixing structure of anchor bolt and erection method of steel frame using this structure
WO2013020287A1 (en) * 2011-08-10 2013-02-14 Yau Pak Sum Combined pre-embedded anchoring slot system
CN104769194A (en) * 2012-10-11 2015-07-08 株式会社世宗研究井发 Cast-in anchor channel having sub-anchor
CN205077655U (en) * 2015-10-09 2016-03-09 贵州安凯达实业股份有限公司 Coincide formula shear force wall
CN206052977U (en) * 2016-09-14 2017-03-29 中国建筑第八工程局有限公司 The ruggedized construction of built-in groove
CN107090915A (en) * 2017-05-31 2017-08-25 中建新疆建工(集团)有限公司 A kind of mounting structure and method for concrete component that the fragrant groove in Kazakhstan is nuzzled in advance
CN206562672U (en) * 2017-03-15 2017-10-17 青岛新华友建工集团股份有限公司 One kind breathes out fragrant groove type embedded part
CN207512776U (en) * 2017-10-31 2018-06-19 中国一冶集团有限公司 One kind is used to breathe out the fragrant fixed device of slot installation of embedded parts
CN108396875A (en) * 2018-03-09 2018-08-14 中国五冶集团有限公司 A kind of built-in groove steel construction and construction method
CN207776437U (en) * 2018-01-18 2018-08-28 福建易安特新型建材有限公司 It is a kind of that the fragrant groove top in Kazakhstan is leaned against into the supporting rod on concrete blinding
CN210066813U (en) * 2019-03-29 2020-02-14 中建八局第一建设有限公司 Pre-buried installation device who breathes out groove

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0742293A (en) * 1993-07-30 1995-02-10 Taisei Corp Reinforced concrete floor slab with reinforcing steel frame
JP2007009411A (en) * 2005-06-02 2007-01-18 Toshihisa Ebara Position holding metal fitting and position fixing structure of anchor bolt and erection method of steel frame using this structure
WO2013020287A1 (en) * 2011-08-10 2013-02-14 Yau Pak Sum Combined pre-embedded anchoring slot system
CN104769194A (en) * 2012-10-11 2015-07-08 株式会社世宗研究井发 Cast-in anchor channel having sub-anchor
CN205077655U (en) * 2015-10-09 2016-03-09 贵州安凯达实业股份有限公司 Coincide formula shear force wall
CN206052977U (en) * 2016-09-14 2017-03-29 中国建筑第八工程局有限公司 The ruggedized construction of built-in groove
CN206562672U (en) * 2017-03-15 2017-10-17 青岛新华友建工集团股份有限公司 One kind breathes out fragrant groove type embedded part
CN107090915A (en) * 2017-05-31 2017-08-25 中建新疆建工(集团)有限公司 A kind of mounting structure and method for concrete component that the fragrant groove in Kazakhstan is nuzzled in advance
CN207512776U (en) * 2017-10-31 2018-06-19 中国一冶集团有限公司 One kind is used to breathe out the fragrant fixed device of slot installation of embedded parts
CN207776437U (en) * 2018-01-18 2018-08-28 福建易安特新型建材有限公司 It is a kind of that the fragrant groove top in Kazakhstan is leaned against into the supporting rod on concrete blinding
CN108396875A (en) * 2018-03-09 2018-08-14 中国五冶集团有限公司 A kind of built-in groove steel construction and construction method
CN210066813U (en) * 2019-03-29 2020-02-14 中建八局第一建设有限公司 Pre-buried installation device who breathes out groove

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘兴军;徐小洋;王伟;: "升降看台的花瓣形组合、高精度预埋件施工", 上海建设科技, no. 06 *
李海龙;郝宁;陈博;刘俊;: "综合管廊模板施工中细节问题研究", 施工技术, no. 21 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110656559A (en) * 2019-08-23 2020-01-07 上海宝冶冶金工程有限公司 Device and method for controlling flatness of embedded part at top of cornice of racing track

Similar Documents

Publication Publication Date Title
CN108643217A (en) A kind of high-speed railway subgrade contact net upright post basic construction method
CN105128131A (en) Method for manufacturing prestressed hollow slab beam through polystyrene foam
CN109930628A (en) A kind of pre-buried mounting device and method for breathing out fragrant slot
CN106245770B (en) Expanded letter variable cross-section annular stiffness beam construction method
US20180010348A1 (en) Floor Levelling Arrangement and Method Therefor
KR20110128396A (en) Pre-embedded anchor frame equipped with coupler and anchoring method of steel column thereof
CN110359485A (en) A kind of pre-buried trough fixation device of steel form and its construction method
CN109296138A (en) The positioning device and construction method of reinforcing bar are planted after a kind of constructional column
CN109403466A (en) A kind of construction method of eminence reinforced concrete hanging beam diaphragm structure built-in fitting
CN104947853B (en) A kind of Inner standpipe formula cast-in-situ reinforced concrete column and construction method
CN210066813U (en) Pre-buried installation device who breathes out groove
CN108677722A (en) Hollow High Pier with Thin Wall stub top section construction technology
CN109208818A (en) A method of electronic box is fixed in precast shear wall template
JP6365551B2 (en) Replacement method and structure of concrete floor slab
CN114134927A (en) Device and method for embedding large power equipment foundation embedded pipe
CN206916609U (en) Regulation support component and track support component for track support component
JPH06316939A (en) Positioning jig for construction work, and construction of building therewith
JP3118630U (en) Gripping guide for floor concrete level
JP2901834B2 (en) Formwork for legal block
CN210738198U (en) Frame thin-wall type concrete granulation tower shell
CN219241344U (en) Pre-buried buckle formula template stop device
JP4676683B2 (en) Concrete wall
JPH07150764A (en) Tube for placing concrete
CN218323871U (en) Shear wall template installation positioner
CN211873882U (en) Prefabricated part exposes pre-buried muscle and buries device underground

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination