CN109915096A - Method for steam-assisted gravity drainage in later huff and puff period of thickened oil horizontal well - Google Patents

Method for steam-assisted gravity drainage in later huff and puff period of thickened oil horizontal well Download PDF

Info

Publication number
CN109915096A
CN109915096A CN201711330379.2A CN201711330379A CN109915096A CN 109915096 A CN109915096 A CN 109915096A CN 201711330379 A CN201711330379 A CN 201711330379A CN 109915096 A CN109915096 A CN 109915096A
Authority
CN
China
Prior art keywords
well
pitch
oil
reservoir
steam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711330379.2A
Other languages
Chinese (zh)
Inventor
王延杰
罗池辉
赵睿
杨智
张效恭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Petrochina Co Ltd
Original Assignee
Petrochina Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Petrochina Co Ltd filed Critical Petrochina Co Ltd
Priority to CN201711330379.2A priority Critical patent/CN109915096A/en
Publication of CN109915096A publication Critical patent/CN109915096A/en
Pending legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The invention provides a method for steam assisted gravity drainage at the later period of huff and puff of a thickened oil horizontal well, which comprises the following steps of: step S1: drilling a huff-and-puff horizontal well in the oil reservoir area to perform production operation on an oil layer of the oil reservoir area, and huff-and-puff the horizontal well to enable part of the oil reservoir area to form a first heating zone; step S2: after the first preset time, an adding horizontal well is added in the oil reservoir area to carry out production operation on the oil layer of the oil reservoir area, and the adding horizontal well is added to enable the other part of the oil reservoir area to form a second heating zone; step S3: and after the second preset time, the first heating zone is in thermal communication with the second heating zone, and then a horizontal well is added for continuously injecting steam into the oil reservoir area and continuously producing the horizontal well until the oil extraction of the oil reservoir area is finished. By adopting the method for the combined exploitation of the heavy oil reservoir and the horizontal well, the reservoir utilization rate of an oil reservoir area can be effectively improved, and the recovery ratio is improved.

Description

Thick oil horizontal well later period of handling up turns the method for steam assisted gravity drainage
Technical field
The present invention relates to technical field of petroleum extraction, turn steam in particular to a kind of thick oil horizontal well later period of handling up The method of assisted gravity drainage.
Background technique
The horizontal well technology of handling up is one of effective means of Development of Viscous Crude Oil, and application range is big, and scale is wide.Horizontal well gulps down Spit that initial stage of development yield is higher, but with the increase of production round, the production time in period extends, and production decline is fast, rate of oil production compared with Low, recovery percent of reserves is low.For viscosity compared with mammoth pool, handles up and involve that radius is small, and oil reservoir development degree is restricted.Conventional level Well later period of handling up turns horizontal well vapour and drives mode, and steam injection horizontal well is located at two production level well middle positions, and steam injection well is from producing well Farther out, based on steam flooding, steam single-point or one direction is easy to cause to break through, manipulation difficulty is big, causes oil-producing low efficiency Problem.
Summary of the invention
The main purpose of the present invention is to provide a kind of thick oil horizontal well later periods of handling up to turn the side of steam assisted gravity drainage Method, to solve the problems, such as oil-producing low efficiency in the prior art.
To achieve the goals above, according to an aspect of the invention, there is provided a kind of thick oil horizontal well is handled up, the later period turns The method of steam assisted gravity drainage, method is the following steps are included: step S1: boring throughput level well to reservoir region in reservoir region Oil reservoir carries out production operation, and throughput level well makes the reservoir region of part form the first heating tape;Step S2: through the first preset time Afterwards, pitch-based sphere well being added in reservoir region and production operation being carried out to the oil reservoir of reservoir region, pitch-based sphere well makes the oil of another part Tibetan area forms the second heating tape;Step S3: after the second preset time, thermal communication is established in the first heating tape and the second heating tape Afterwards, pitch-based sphere well is for persistently injecting steam to reservoir region, until terminating to reservoir region oil recovery, wherein horizontal well is held Continuous production model.
Further, the thickness of oil reservoir is greater than or equal to 8m;The porosity of oil reservoir is greater than 0.2;The horizontal permeability of oil reservoir Greater than 500mD;The vertical permeability of oil reservoir and the ratio of horizontal permeability are greater than 0.5;The oil saturation of oil reservoir is greater than 0.5; Oil reservoir oil viscosity at 50 DEG C is less than 50000mPa.s.
Further, throughput level well is multiple, and multiple throughput level wells are opened in the bottom section of oil reservoir, two neighboring The distance between throughput level well is L, wherein 60m≤L≤100m.
Further, in step S2 further include: after the first preset time, when the recovery ratio of throughput level well is greater than or waits When 20%, throughput level well is closed until handling up when the pressure depth pressure and hydrostatic pressure corresponding with oil reservoir of oil reservoir is equal The oblique upper of horizontal well opens up pitch-based sphere well.
Further, in step S2, pitch-based sphere well uses thermal cycle oil production method, uses long tube by pitch-based sphere well Steam is injected to reservoir region, is recovered the oil using oil reservoir of the short tube to reservoir region, wherein the mass dryness fraction of the steam of long tube injection is greater than 60%;The speed of the steam of long tube injection is v1, wherein 60t/d≤v1≤1000t/d;The pressure of steam of long tube injection is P1, the formation fracture pressure of reservoir region are P2, wherein P1≤10%P2 or P1≤15%P2;The production-injection ratio of reservoir region is T1, wherein 0.8≤t1≤1.
Further, in step s 2, the method that pitch-based sphere well uses huff and puff oil recovery, wherein pass through pitch-based sphere well The mass dryness fraction for injecting the steam of reservoir region is greater than 60%;The speed that pitch-based sphere well injects the steam of reservoir region is v2, wherein 200t/d≤v2≤300t/d;The gas injection intensity that pitch-based sphere well injects the steam of reservoir region is Q, wherein 8t/m≤Q≤20t/ m;The pressure that pitch-based sphere well injects the steam of reservoir region is less than the formation fracture pressure of reservoir region;The production-injection ratio of reservoir region is T2, wherein 0.7≤t2≤1.2.
Further, after the second preset time, the viscosity of crude between throughput level well and pitch-based sphere well be less than or Equal to 100mPa.s.
Further, in step S3, it is greater than 60% by the mass dryness fraction that pitch-based sphere well injects the steam of reservoir region;Add water The speed that horizontal well injects the steam of reservoir region is v3, wherein 50t/d≤v3≤70t/d;Reservoir region is injected by pitch-based sphere well Maximum gas injection pressure be P3, the formation fracture pressure of reservoir region is P4, wherein P3≤15%P4 or P3≤20%P4.
Further, in step S3, the absolute value of the difference of the pressure and the pressure of throughput level well of pitch-based sphere well is less than 0.5MPa。
Further, in step S3, the liquid outlet quantity and pitch-based sphere well and throughput level well of throughput level well extraction are injected The ratio of the quantity of steam of reservoir region is q, wherein 1≤q≤1.2.
Further, pitch-based sphere well spacing it is vertical from throughput level well on displacement be L1, pitch-based sphere well spacing is from handling up The displacement of the horizontal direction of horizontal well is L2, wherein 3m≤L1≤5m, 6m≤L2≤15m.
Further, pitch-based sphere well is set in parallel with throughput level well, the length of the horizontal segment of pitch-based sphere well with The length of the horizontal segment of throughput level well is identical, alternatively, the length of the horizontal segment of pitch-based sphere well and two to three throughput levels It is the length of the horizontal segment of well and identical.
It applies the technical scheme of the present invention, using the method for horizontal wells in heavy oil reservoir combination exploitation, can effectively mention The high reservoir utilization rate to oil reservoir region, while improving recovery ratio.
Detailed description of the invention
The accompanying drawings constituting a part of this application is used to provide further understanding of the present invention, and of the invention shows Examples and descriptions thereof are used to explain the present invention for meaning property, does not constitute improper limitations of the present invention.In the accompanying drawings:
Fig. 1 shows the schematic diagram of the embodiment of the position of pitch-based sphere well according to the present invention and throughput level well;
Fig. 2 shows the signals of embodiment when the first heating tape according to the present invention and the second heating tape generation thermal communication Figure;
Fig. 3 show thick oil horizontal well according to the present invention handle up the later period turn steam assisted gravity drainage method process Figure.
Wherein, the above drawings include the following reference numerals:
10, throughput level well;20, pitch-based sphere well;A, the first heating tape;B, top of oil horizon;C, oil reservoir bottom;F1, steaming Vapour;F2, non-condensate gas;F3, hot oil and condensed liquid;M, the second heating tape.
Specific embodiment
It should be noted that in the absence of conflict, the features in the embodiments and the embodiments of the present application can phase Mutually combination.The present invention will be described in detail below with reference to the accompanying drawings and embodiments.
It should be noted that term used herein above is merely to describe specific embodiment, and be not intended to restricted root According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singular Also it is intended to include plural form, additionally, it should be understood that, when in the present specification using term "comprising" and/or " packet Include " when, indicate existing characteristics, step, operation, device, component and/or their combination.
It should be noted that term " first ", " second " etc. in the description and claims of this application and attached drawing It is to be used to distinguish similar objects, without being used to describe a particular order or precedence order.It should be understood that the art used in this way Language is interchangeable under appropriate circumstances, so that presently filed embodiment described herein for example can be in addition to illustrating herein Or the sequence other than those of description is implemented.In addition, term " includes " and " having " and their any deformation, it is intended that Cover it is non-exclusive include, for example, containing the process, method, system, product or equipment of a series of steps or units need not limit In step or unit those of is clearly listed, but may include be not clearly listed or for these process, methods, produce The other step or units of product or equipment inherently.
For ease of description, spatially relative term can be used herein, as " ... on ", " ... top ", " ... upper surface ", " above " etc., for describing such as a device shown in the figure or feature and other devices or spy The spatial relation of sign.It should be understood that spatially relative term is intended to comprising the orientation in addition to device described in figure Except different direction in use or operation.For example, being described as if the device in attached drawing is squeezed " in other devices It will be positioned as " under other devices or construction after part or construction top " or the device of " on other devices or construction " Side " or " under other devices or construction ".Thus, exemplary term " ... top " may include " ... top " and " in ... lower section " two kinds of orientation.The device can also be positioned with other different modes and (is rotated by 90 ° or in other orientation), and And respective explanations are made to the opposite description in space used herein above.
Now, the illustrative embodiments according to the application are more fully described with reference to the accompanying drawings.However, these are exemplary Embodiment can be implemented by many different forms, and should not be construed to be limited solely to embodiment party set forth herein Formula.It should be understood that it is thoroughly and complete to these embodiments are provided so that disclosure herein, and these are shown The design of example property embodiment is fully conveyed to those of ordinary skill in the art, in the accompanying drawings, for the sake of clarity, it is possible to expand The big thickness of layer and region, and make that identical device is presented with like reference characters, thus omission retouches them It states.
In conjunction with shown in Fig. 1 to Fig. 3, turn to steam according to an embodiment of the invention, providing a kind of thick oil horizontal well later period of handling up The method of vapour assisted gravity drainage.
Specifically, method includes the following steps: step S1: reservoir region bore throughput level well to the oil reservoir of reservoir region into Row production operation, throughput level well make the reservoir region of part form the first heating tape.Step S2: after the first preset time, Reservoir region adds pitch-based sphere well and carries out production operation to the oil reservoir of reservoir region, and pitch-based sphere well makes the reservoir region shape of another part At the second heating tape.Step S3: after the second preset time, after thermal communication is established with the second heating tape in the first heating tape, addition Horizontal well is for persistently injecting steam to reservoir region, until terminating to reservoir region oil recovery, during this, horizontal well keeps continuing Production model.
In the present embodiment, it using the method for horizontal wells in heavy oil reservoir combination exploitation, can effectively improve to oil The reservoir utilization rate in Tibetan area domain, while improving recovery ratio.I.e. the mining method newly bores addition well above throughput level hole deviation, Two wells are produced in a manner of steam assisted gravity drainage can effectively improve reservoir utilization rate, greatly improve horizontal wells in heavy oil reservoir It handles up later period recovery ratio.The mining method newly bores addition well above throughput level hole deviation, can avoid low oil-containing saturation after handling up Band is spent, while drilling risk can be reduced.
Specifically, the thickness of oil reservoir is greater than or equal to 8m, and the porosity of oil reservoir is greater than 0.2, and the horizontal permeability of oil reservoir is big In 500mD, the vertical permeability of oil reservoir and the ratio of horizontal permeability are greater than 0.5, and the oil saturation of oil reservoir is greater than 0.5;Oil Layer oil viscosity at 50 DEG C is less than 50000mPa.s.
Throughput level well can be to be multiple, and multiple throughput level wells are opened in the bottom section of oil reservoir, two neighboring to handle up The distance between horizontal well is L, wherein 60m≤L≤100m.
It wherein, further include after the first preset time, when the recovery ratio of throughput level well is greater than or equal in step S2 When 20%, throughput level well is closed when the pressure depth pressure and hydrostatic pressure corresponding with oil reservoir of oil reservoir is equal, in water of handling up The oblique upper of horizontal well opens up pitch-based sphere well.
In step s 2, pitch-based sphere well uses thermal cycle oil production method, uses long tube to oil reservoir by pitch-based sphere well Steam is injected in area, is recovered the oil using oil reservoir of the short tube to reservoir region, wherein and the mass dryness fraction of the steam of long tube injection is greater than 60%, The speed of the steam of long tube injection is v1, wherein 60t/d≤v1≤1000t/d, the pressure of the steam of long tube injection are P1, oil The formation fracture pressure of Tibetan area is P2, wherein P1≤10%P2 or P1≤15%P2;The production-injection ratio of reservoir region is t1, In, 0.8≤t1≤1.
Certainly, in step s 2, the method that pitch-based sphere well can also use huff and puff oil recovery, wherein pass through pitch-based sphere The mass dryness fraction that well injects the steam of reservoir region is greater than 60%, and the speed that pitch-based sphere well injects the steam of reservoir region is v2, wherein 200t/d≤v2≤300t/d.The gas injection intensity that pitch-based sphere well injects the steam of reservoir region is Q, wherein 8t/m≤Q≤20t/ m.The pressure that pitch-based sphere well injects the steam of reservoir region is less than the formation fracture pressure of reservoir region, and the production-injection ratio of reservoir region is T2, wherein 2-7 days well time is boiled in a covered pot over a slow fire in 0.7≤t2≤1.2.
Further, after the second preset time, the viscosity of crude between throughput level well and pitch-based sphere well be less than or Equal to 100mPa.s.
In step s3, the mass dryness fraction that the steam of reservoir region is injected by pitch-based sphere well is greater than 60%, pitch-based sphere well note The speed for entering the steam of reservoir region is v3, wherein 50t/d≤v3≤70t/d.The maximum of reservoir region is injected by pitch-based sphere well Gas injection pressure is P3, and the formation fracture pressure of reservoir region is P4, wherein P3≤15%P4 or P3≤20%P4.Pitch-based sphere The absolute value of the difference of the pressure of the pressure and throughput level well of well is less than 0.5MPa.The liquid outlet quantity and addition of throughput level well extraction The ratio of the quantity of steam of horizontal well and throughput level well injection reservoir region is q, wherein 1≤q≤1.2.
Specifically, this method comprises: preferred levels well is handled up the later period be suitble to condition target reservoir, on horizontal hole deviation top New to bore a bite pitch-based sphere well, pitch-based sphere well is recycled or is handled up production, after two horizontal wells establish thermal communication, pitch-based sphere Well continues steam injection, and raw water horizontal well continuous production maintains balanced flood, until terminating.Using the effective raising reservoir utilization rate, Greatly improve recovery ratio.Wherein, after two horizontal wells establish thermal communication, pitch-based sphere well switchs to continue steam injection, and raw water horizontal well continues In production process, adjustment note adopts parameter, maintains balanced flood, until terminating.
The application provides a kind of horizontal wells in heavy oil reservoir and handles up the method that the later period improves recovery ratio, which can be Horizontal well is handled up the later period, is combined by new horizontal well drilling with raw water horizontal well, is produced in a manner of steam assisted gravity drainage, substantially mentioned High viscous oil oil recovery.First preferred levels well handle up the later period be suitble to condition target reservoir, select proper moment in level Newly bore a bite pitch-based sphere well in hole deviation top;Pitch-based sphere well is recycled or is handled up production later, when two horizontal wells establish heat After connection, pitch-based sphere well continues steam injection, and raw water horizontal well continuous production maintains balanced flood, until terminating.The present invention can have The raising reservoir utilization rate of effect, greatly improves recovery ratio.
The coarse sizing for being suitble to oil reservoir is carried out in this method first, in the oil reservoir for handling up technological development using horizontal well, Select reservoir oil layer thickness >=8m, oil reservoir porosity > 0.2, horizontal permeability > 500mD, vertical permeability and horizontal permeability ratio Value > 0.5, oil saturation > 0.5,50 DEG C oil viscosity < 50000mPa.s, horizontal well disposes well spacing 60- in oil reservoir 100m, it is vertical upper positioned at oil reservoir middle and lower part.
When throughput level well is handled up more wheels, recovery ratio up to 20% or more, close to handle up economic limit when, closing well.Work as pressure When being down to corresponding depth pressure and hydrostatic pressure, a bite pitch-based sphere well is bored in horizontal well oblique upper, considers handle up heated perimeter and brill Well requirement, the displacement on pitch-based sphere well spacing is vertical from throughput level well are L1, water of the pitch-based sphere well spacing from throughput level well Square to displacement be L2, wherein 3m≤L1≤5m, 6m≤L2≤15m.Pitch-based sphere well is set in parallel with throughput level well It sets, the length of the horizontal segment of pitch-based sphere well is identical as the length of the horizontal segment of throughput level well, alternatively, the water of pitch-based sphere well The length of flat section with it is the length of the horizontal segment of two to three throughput level wells and identical.
Specifically, oil reservoir coarse sizing, selected oil reservoir buried depth 450m, core intersection 9.4m, oil reservoir porosity 0.28, water are carried out Flat permeability 815mD, vertical permeability and horizontal permeability ratio 0.6, oil saturation 0.68 are developed in oil reservoir discontinuous Lithology, physical property interlayer, 2.1 ten thousand centipoise of degassed crude viscosity under the conditions of 50 DEG C.
The reservoir horizontal well has been handled up 14 wheels, recovery percent of reserves 21.2%, accumulates gas oil ratio 0.113, well spacing 70m, horizontal well Away from oil reservoir bottom 2m, horizontal section length 240m;At away from throughput level well vertical deviation 4m, horizontal displacement 10m and throughput level Well disposes a bite pitch-based sphere well, horizontal section length 240m in parallel.
Pitch-based sphere well long tube steam injection, short tube recover the oil, and carry out circulation production.Steam injection rate is 60-80t/d, steam injection pressure 4.5-5.0MPa, production-injection ratio 0.9 establish thermal communication between well after recycling 0.5 year.
Addition well continues steam injection, throughput level well continuous production after establishing connection, and injection steam quality is greater than 60%, steam injection Speed is 50t/d-60t/d, and steam injection pressure 4.5-5.5MPa, less than 0.5MPa, control whole production-injection ratio is two horizontal well pressure differences 1.0-1.2 until terminating.
The average daily yield of the mining method can reach 6t/d, and ultimate recovery latter stage of relatively handling up improves 30.5 percentage points, oil Vapour is than improving 0.02.
According to another embodiment of the application, oil reservoir coarse sizing, selected oil reservoir buried depth 440m, core intersection are carried out 8.5m, oil reservoir porosity 0.27, horizontal permeability 960mD, vertical permeability and horizontal permeability ratio 0.6, oil saturation 0.68, discontinuous lithology, physical property interlayer are developed in oil reservoir, 1.5 ten thousand centipoise of degassed crude viscosity under the conditions of 50 DEG C.
The reservoir horizontal well has been handled up 13 wheels, recovery percent of reserves 20.5%, accumulates gas oil ratio 0.108, well spacing 70m, horizontal well Away from oil reservoir bottom 2m, horizontal section length 200m;At away from throughput level well vertical deviation 4.5m, horizontal displacement 12m with handle up water Horizontal well disposes a bite pitch-based sphere well, horizontal section length 450m in parallel.
Pitch-based sphere well long tube steam injection, short tube recover the oil, and carry out circulation production;Steam injection rate is 60-80t/d;Steam injection pressure 4.5-5.0MPa, production-injection ratio 0.9 establish thermal communication between well after recycling 0.4 year.
Addition well continues steam injection, throughput level well continuous production after establishing connection, and injection steam quality is greater than 60%, steam injection Speed is 60t/d-80t/d, and steam injection pressure 4.5-5.5MPa, less than 0.5MPa, control whole production-injection ratio is two horizontal well pressure differences 1.0-1.2 until terminating.
The average daily yield of the mining method can reach 13t/d, and ultimate recovery latter stage of relatively handling up improves 32.1 percentage points, oil Vapour is than improving 0.02.
The mining method newly bores pitch-based sphere well above throughput level hole deviation, and two wells are in a manner of steam assisted gravity drainage Production can effectively improve reservoir utilization rate, greatly improve horizontal wells in heavy oil reservoir and handle up later period recovery ratio.It can avoid handling up Low oil saturation sandstone band afterwards, while drilling risk can be reduced.Wherein, in fig. 1 and 2,10 be throughput level well, and 20 be to add Add horizontal well, A is the first heating tape, and B is top of oil horizon, and C is oil reservoir bottom, and F1 is steam, and F2 is non-condensate gas, and F3 is hot oil And condensed liquid, M are the second heating tape.
Than that described above, it is also necessary to which explanation is " one embodiment " spoken of in the present specification, " another implementation Example ", " embodiment " etc. refer to that specific features, structure or the feature of embodiment description is combined to be included in the application summary Property description at least one embodiment in.It is not centainly to refer to the same reality that statement of the same race, which occur, in multiple places in the description Apply example.Furthermore, it is understood that is advocated is knot when describing a specific features, structure or feature in conjunction with any embodiment Other embodiments are closed to realize that this feature, structure or feature are also fallen within the scope of the present invention.
In the above-described embodiments, it all emphasizes particularly on different fields to the description of each embodiment, there is no the portion being described in detail in some embodiment Point, reference can be made to the related descriptions of other embodiments.
The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, for the skill of this field For art personnel, the invention may be variously modified and varied.All within the spirits and principles of the present invention, made any to repair Change, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.

Claims (12)

1. a kind of thick oil horizontal well is handled up, the later period turns the method for steam assisted gravity drainage, which is characterized in that the method includes Following steps:
Step S1: throughput level well is bored in reservoir region, production operation, the throughput level well are carried out to the oil reservoir of the reservoir region The reservoir region of part is set to form the first heating tape;
Step S2: after the first preset time, pitch-based sphere well is added in the reservoir region, the oil reservoir of the reservoir region is carried out Production operation, the pitch-based sphere well make the reservoir region of another part form the second heating tape;
Step S3: described to add after thermal communication is established with second heating tape in first heating tape after the second preset time Add horizontal well for persistently injecting steam to the reservoir region, until terminating to reservoir region oil recovery, wherein the horizontal well Keep continuous production mode.
2. the method according to claim 1, wherein
The thickness of the oil reservoir is greater than or equal to 8m;
The porosity of the oil reservoir is greater than 0.2;
The horizontal permeability of the oil reservoir is greater than 500mD;
The ratio of the vertical permeability of the oil reservoir and the horizontal permeability is greater than 0.5;
The oil saturation of the oil reservoir is greater than 0.5;
Oil reservoir oil viscosity at 50 DEG C is less than 50000mPa.s.
3. the method according to claim 1, wherein the throughput level well is multiple, multiple water of handling up Horizontal well is opened in the bottom section of the oil reservoir, and the distance between two neighboring described throughput level well is L, wherein 60m≤L ≤100m。
4. the method according to claim 1, wherein in the step S2 further include:
After the first preset time, when the recovery ratio of the throughput level well is greater than or equal to 20%, water of handling up described in closing Horizontal well is when the pressure depth pressure and hydrostatic pressure corresponding with the oil reservoir of the oil reservoir is equal, in the throughput level well Oblique upper opens up the pitch-based sphere well.
5. the method according to claim 1, wherein the pitch-based sphere well is followed using heat in the step S2 Ring oil production method injects steam to the reservoir region using long tube by the pitch-based sphere well, using short tube to the oil reservoir The oil reservoir in area recovers the oil, wherein
The mass dryness fraction of the steam of the long tube injection is greater than 60%;
The speed of the steam of the long tube injection is v1, wherein 60t/d≤v1≤1000t/d;
The pressure of the steam of the long tube injection is P1, and the formation fracture pressure of the reservoir region is P2, wherein P1≤10% P2 or P1≤15%P2;
The production-injection ratio of the reservoir region is t1, wherein 0.8≤t1≤1.
6. the method according to claim 1, wherein the pitch-based sphere well is used and is gulped down in the step S2 The method for spitting oil recovery, wherein
It is greater than 60% by the mass dryness fraction that the pitch-based sphere well injects the steam of reservoir region;
The speed of the steam of the pitch-based sphere well injection reservoir region is v2, wherein 200t/d≤v2≤300t/d;
The gas injection intensity of the steam of the pitch-based sphere well injection reservoir region is Q, wherein 8t/m≤Q≤20t/m;
The pressure of the steam of the pitch-based sphere well injection reservoir region is less than the formation fracture pressure of the reservoir region;
The production-injection ratio of the reservoir region is t2, wherein 0.7≤t2≤1.2.
7. the method according to claim 1, wherein after second preset time, the throughput level well Viscosity of crude between the pitch-based sphere well is less than or equal to 100mPa.s.
8. the method according to claim 1, wherein in the step S3,
It is greater than 60% by the mass dryness fraction that the pitch-based sphere well injects the steam of reservoir region;
The speed of the steam of the pitch-based sphere well injection reservoir region is v3, wherein 50t/d≤v3≤70t/d;
The maximum gas injection pressure that reservoir region is injected by the pitch-based sphere well is P3, and the formation fracture pressure of the reservoir region is P4, wherein P3≤15%P4 or P3≤20%P4.
9. the method according to claim 1, wherein in the step S3, the pressure of the pitch-based sphere well with The absolute value of the difference of the pressure of the throughput level well is less than 0.5MPa.
10. the method according to claim 1, wherein the throughput level well extraction goes out in the step S3 The ratio that liquid measure and the pitch-based sphere well and the throughput level well inject the quantity of steam of the reservoir region is q, wherein 1≤q≤ 1.2。
11. the method according to claim 1, wherein the pitch-based sphere well spacing is hung down from the throughput level well Upward displacement is L1, and the displacement of horizontal direction of the pitch-based sphere well spacing from the throughput level well is L2, wherein 3m≤ L1≤5m, 6m≤L2≤15m.
12. the method according to claim 1, wherein the pitch-based sphere well is parallel with the throughput level well Ground setting, the length of the horizontal segment of the pitch-based sphere well is identical as the length of horizontal segment of the throughput level well, alternatively, institute State the length of the horizontal segment of pitch-based sphere well with it is the length of the horizontal segment of two to three throughput level wells and identical.
CN201711330379.2A 2017-12-13 2017-12-13 Method for steam-assisted gravity drainage in later huff and puff period of thickened oil horizontal well Pending CN109915096A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711330379.2A CN109915096A (en) 2017-12-13 2017-12-13 Method for steam-assisted gravity drainage in later huff and puff period of thickened oil horizontal well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711330379.2A CN109915096A (en) 2017-12-13 2017-12-13 Method for steam-assisted gravity drainage in later huff and puff period of thickened oil horizontal well

Publications (1)

Publication Number Publication Date
CN109915096A true CN109915096A (en) 2019-06-21

Family

ID=66958965

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711330379.2A Pending CN109915096A (en) 2017-12-13 2017-12-13 Method for steam-assisted gravity drainage in later huff and puff period of thickened oil horizontal well

Country Status (1)

Country Link
CN (1) CN109915096A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101122224A (en) * 2006-08-11 2008-02-13 中国石油天然气股份有限公司 Gravity assisted steam flooding exploitation method for thick-layer common heavy oil reservoir
CN102268983A (en) * 2011-06-23 2011-12-07 李剑 Mixed mining method capable of improving recovery ratio of thick oil in shallow oil reservoir
CN102518415A (en) * 2011-12-13 2012-06-27 中国石油天然气股份有限公司 Steam assisted gravity drainage method for fractured single horizontal well
US20140041852A1 (en) * 2009-10-22 2014-02-13 Chevron U.S.A. Inc. Steam distribution apparatus and method for enhanced oil recovery of viscous oil
CN103615224A (en) * 2013-11-08 2014-03-05 中国石油天然气股份有限公司 Method for exploiting heavy oil reservoir by improving steam assisted gravity drainage through solvent and well pattern structure
CN105986793A (en) * 2015-02-11 2016-10-05 中国石油化工股份有限公司 Improved steam assisting gravity oil discharging oil producing method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101122224A (en) * 2006-08-11 2008-02-13 中国石油天然气股份有限公司 Gravity assisted steam flooding exploitation method for thick-layer common heavy oil reservoir
US20140041852A1 (en) * 2009-10-22 2014-02-13 Chevron U.S.A. Inc. Steam distribution apparatus and method for enhanced oil recovery of viscous oil
CN102268983A (en) * 2011-06-23 2011-12-07 李剑 Mixed mining method capable of improving recovery ratio of thick oil in shallow oil reservoir
CN102518415A (en) * 2011-12-13 2012-06-27 中国石油天然气股份有限公司 Steam assisted gravity drainage method for fractured single horizontal well
CN103615224A (en) * 2013-11-08 2014-03-05 中国石油天然气股份有限公司 Method for exploiting heavy oil reservoir by improving steam assisted gravity drainage through solvent and well pattern structure
CN105986793A (en) * 2015-02-11 2016-10-05 中国石油化工股份有限公司 Improved steam assisting gravity oil discharging oil producing method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
邹才能 等: "《非常规油气地质》", 31 January 2013, 地质出版社 *

Similar Documents

Publication Publication Date Title
CN107664031B (en) Method for improving recovery efficiency by determining steam flooding well pattern form of horizontal well
CN102278103B (en) Method for improving deep super heavy oil reservoir recovery ratio by gravity drainage assisted steam flooding
CN101484662B (en) Recovery of hydrocarbons using horizontal wells
CN101255788B (en) Thermochemistry auxiliary reinforced steam flooding method
CN105649588B (en) Method for exploiting heavy oil reservoir by using SAGD (steam assisted gravity drainage)
CN103939069B (en) Steam-gas displacement and gravity oil drain composite exploiting method
CN103174403B (en) Gravity and steam flooding combined mining method for thick-layer interlayer-containing common heavy oil reservoir
CN108708699B (en) A kind of super heavy oil development method strengthened SAGD vapor chamber and break through low physical property reservoir
CN109838224A (en) Method for exploiting super-thick oil by combining auxiliary oil production well and SAGD (steam assisted gravity drainage)
CN202325428U (en) Drive and let out compound oil recovery system
US4503910A (en) Viscous oil recovery method
US20150107834A1 (en) Method for producing heavy oil
CN106593368B (en) Pretreatment method for improving SAGD development effect
RU2675114C1 (en) Method of super-viscous oil field development
CN107313760B (en) The method of layer steam injection improvement development result of heavy oil reservoirs
CN105986793B (en) Improved steam assisted gravity drainage oil production method
CN109630080A (en) Exploitation method for super heavy oil reservoir steam assisted gravity drainage production initial stage
CN109915096A (en) Method for steam-assisted gravity drainage in later huff and puff period of thickened oil horizontal well
CN107701158B (en) Method for exploiting foam type superheavy oil
CN205638410U (en) Gravity drainage assisted steam flooding three-dimensional well pattern structure
CN107916916B (en) method and device for improving foam oil development effect
CN110952967A (en) Thickened oil recovery method
CN111441756A (en) Method for oil exploitation
RU2524580C1 (en) Development of oil deposit by heat and water-gas impacts in vertical, horizontal and multihole wells system
CN108119112A (en) Steam assisted gravity drainage exploitation method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190621