CN109886653A - A kind of construction project information management system - Google Patents
A kind of construction project information management system Download PDFInfo
- Publication number
- CN109886653A CN109886653A CN201910133945.3A CN201910133945A CN109886653A CN 109886653 A CN109886653 A CN 109886653A CN 201910133945 A CN201910133945 A CN 201910133945A CN 109886653 A CN109886653 A CN 109886653A
- Authority
- CN
- China
- Prior art keywords
- user
- time
- planning
- situation
- information management
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Traffic Control Systems (AREA)
Abstract
The present invention relates to a kind of construction project information management systems, it is related to the technical field of project supervision, personal office situation can wherein be set by construction project information management system by solving, but individual office set by existing construction project information management system must be by being inquired after login system, the problem of being more troublesome, it includes planning situation setting module for setting the individual office of individual office planning situation, controlling terminal, and it is stored with the mailbox of user account and corresponding user and the user contact details database of cell-phone number, short message sending device.The present invention, which has, facilitates user that can obtain most newly-installed individual office planning by mailbox and short message after setting individual office planning, thus the effect of office planning situation set before avoiding forgetting it when follow-up work.
Description
Technical field
The present invention relates to the technical fields of project supervision, more particularly, to a kind of construction project information management system.
Background technique
Business administration status and combination related rule of the Project Supervision information management software in design, in conjunction with construction
Model, management objectives, information-based requirement optimize combination, are to be covered based on construction project whole life cycle from throwing
Mark analysis, construction management to the performance of enterprises control, the overall process of goodwill guarantee dynamic manages.System design is looked forward to according to construction
The management characteristic of industry, fully demonstrates the characteristics of management of flattening, and bi-level optimization whole implementation realizes enterprises level and project layer service
The seamless combination of processing.Emphasis solves the core business content of enterprise operation and management and project management, looks forward in project management of linking closely
Industry management level and project management layer coordinate four four pipes one of control of project.
Personal office situation can wherein be set, but existing built by construction project information management system
If individual office set by engineering information management system must be more troublesome, also change by being inquired after login system
Into space.
Summary of the invention
Having the object of the present invention is to provide one kind facilitates user that can pass through mailbox after setting individual office planning
Most newly-installed individual office planning is obtained with short message, so that set before avoiding forgetting it when follow-up work do
The construction project information management system of the effect of public affairs planning situation.
Foregoing invention purpose of the invention has the technical scheme that
A kind of construction project information management system is set including the individual office planning situation for setting individual office planning situation
Cover half block, controlling terminal and it is stored with the mailbox of user account and corresponding user and the user contact details number of cell-phone number
According to library, short message sending device;
Controlling terminal plans that situation setting module sets the first time that situation is planned in individual office by individual office in user
To correspond to the account of user as query object in user contact details database, the mailbox and mobile phone of corresponding user are transferred out
Number, situation is planned in the individual office for sending corresponding user to subscriber mailbox, passes through the mobile phone by short message sending device to user
Situation is planned in the individual office for sending user.
By using above-mentioned technical proposal, situation setting module, controlling terminal, user's correspondent party are planned by individual office
The setting of formula database, short message sending device can plan the setting of situation setting module corresponding by individual office in user
When people's office planning situation, corresponding user can be notified by way of short message or mailbox.
The present invention is further arranged to: being defined and is equipped with mobile phone tracker in user mobile phone, individual office planning situation is set
The planning situation of individual office set by cover half block includes the position reached needed for time point and corresponding time point;
Construction project information management system further includes that real-time storage has user account and corresponding user to go out place and required to arrive
Up to user's field personnel situation database of outgoing place time, route planning device, voice notification device;
Controlling terminal is input in mobile phone tracker to inquire corresponding user position with user mobile phone number, at the same with
Family account goes out the outgoing place of corresponding user in user's field personnel situation data base querying as query object and required reach goes out ground
The point time;
Controlling terminal is using user position as starting point, and needs outgoing place conduct recently apart from user's current time
Terminal, pass course device for planning cook up the shortest distance that user reaches outgoing place, and using the shortest distance as dividend,
Controlling terminal preset average running time calculates user and arrives at the destination required time, together as divisor as dividend
When obtain current time and the required time difference for reaching the outgoing place time, if the time required to user arrives at the destination and the time difference
When identical, pass through voice notification device notice to corresponding user.
By using above-mentioned technical proposal, by mobile phone tracker, user's field personnel situation database, route planning device,
When voice notification device arrives at the destination needed for can may being late in user, notice is to application in the form of speech
Family, so as to cause the attention of user.
The present invention is further arranged to: if user plans required set by situation setting module go out by individual office
Place is several, then for controlling terminal using previous outgoing place as starting point, the latter goes out place as terminal, passes through road
Line device for planning cooks up minimal path, and controlling terminal preset average running time calculates as dividend as divisor
The time required to user arrives at the destination, while obtaining preset upper one place and setting out to the time difference in next place, if with
It is poor to corresponding user's modification time by voice notification device notice when family is identical with the time difference the time required to arriving at the destination.
It is more than the preset time there is required running time between different destinations by using above-mentioned technical proposal
When, corresponding user can be notified to modify personal office and advise in time by the setting of controlling terminal, voice notification device
Draw situation.
The present invention is further arranged to: construction project information management system further includes being stored with user account and to application
The user that family account is inclined to warning color is inclined to warning color database;
If time difference and user arrive at the destination the time required to and between the time difference in the controlling terminal preset time difference, control
Terminal is inclined to warning color database in user using user account as query object and inquires user's tendency warning color, under
One place and the required time for reaching next place are marked with user's tendency color and are loaded in short message.
By using above-mentioned technical proposal, warning color database is inclined to by user, the setting of controlling terminal can be
User may the time it is inadequate when, preferably cause the attention of user in short message with color mark.
The present invention is further arranged to: construction project information management system further includes being stored with user account and to application
The user of the driven a car license plate number of family account drives license plate number database and has the odd or even number limit of odd-and-even license plate rule road
Row transportation database;
Controlling terminal goes out corresponding user in user's driving license plate number data base querying using user account as query object and is driven
The license plate number of automobile, while the minimal path planned with current route device for planning and transferring in odd-and-even license plate rule road data
All odd-and-even license plate rule roads in library are compared, and consistent restricted driving road are compared if existing, with user's license plate number tail number
Odd or even number determines whether to restrict driving as judgment basis, if restricting driving, then excludes the shortest path that current route device for planning is planned
Line selects minimal path in remaining route.
By using above-mentioned technical proposal, license plate number database is driven by odd-and-even license plate rule transportation database, user
Being arranged can determine that planned minimal path is feasible minimal path, to improve the essence that user arrives at the destination the time
True property.
The present invention is further arranged to: the short message sending device is Short message alarm.
By using above-mentioned technical proposal, since short message sending device is Short message alarm, can be sent guaranteeing short message
While reduce corresponding cost.
The present invention is further arranged to: the voice notification device is phonetic alarm.
By using above-mentioned technical proposal, since voice notification device is phonetic alarm, it can guarantee verbal announcement
While reduce corresponding cost.
In conclusion advantageous effects of the invention are as follows: plan situation setting module, control eventually by individual office
Individual subscriber can be handled official business planning situation backup in user by the setting at end, user contact details database, short message sending device
Mailbox and short message in, so that facilitating user to pass through querying individual mailbox and short message when needed can obtain in time
Situation is planned in individual office.
Detailed description of the invention
Fig. 1 is the system schematic of construction project information management system of the present invention.
In figure, 1, individual office planning situation setting module;2, controlling terminal;3, user contact details database;4, short
Believe sending device;5, mobile phone tracker;6, user's field personnel situation database;7, route planning device;8, voice notification device;9,
User is inclined to warning color database;10, user drives license plate number database;11, odd-and-even license plate rule transportation database.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
It referring to Fig.1, is a kind of construction project information management system disclosed by the invention, including for setting individual office rule
The individual office for drawing situation plans situation setting module 1, controlling terminal 2 and is stored with user account and corresponds to user's
The user contact details database 3 of mailbox and cell-phone number, short message sending device 4, controlling terminal 2 is preferably central processing unit, short
Believe that sending device 4 is preferably Short message alarm.
The application process of the above technical characteristic is as follows: controlling terminal 2 plans that situation sets mould by individual office in user
Block 1 sets first time of individual office planning situation to correspond to the account of user as query object in user contact details number
According to the mailbox and cell-phone number in library 3, transferring out corresponding user, feelings are planned in the individual office for sending corresponding user to subscriber mailbox
Condition plans situation by the individual office for sending user by mobile phone of the short message sending device 4 to user.
In view of user, usually can be because of cannot fully consider oneself after having set the individual office time under actual conditions
Trip speed and point of destination position so that defining in user mobile phone there is a situation where late and being equipped with mobile phone tracking
Device 5, individual office plan that the planning situation of individual office set by situation setting module 1 includes time point and corresponding time point
The position of required arrival.
Construction project information management system further includes that real-time storage has user account and the outgoing place of corresponding user and institute
User's field personnel situation database 6, the route planning device 7, voice notification device 8 of outgoing place time, route planning need to be reached
Device 7 is preferably route planner, and voice notification device 8 is preferably phonetic alarm.
Controlling terminal 2 is input in mobile phone tracker 5 to inquire corresponding user position with user mobile phone number, together
When inquire corresponding user in user's field personnel situation database 6 using user account as query object and go out place and required arrival
The outgoing place time;
Controlling terminal 2 needs outgoing place to make recently using user position as starting point, and apart from user's current time
For terminal, pass course device for planning 7 cooks up the shortest distance that user reaches outgoing place, and using the shortest distance as being removed
Number, the preset average running time of controlling terminal 2 calculate user and arrive at the destination and taken as dividend as divisor
Between, while obtaining current time and the required time difference for reaching the outgoing place time, if the time required to user arrives at the destination and
When time difference is identical, pass through the notice of voice notification device 8 to corresponding user.
It in addition, usually can be because of individual in view of user is when formulating multiple destinations and the planning of corresponding time
The reasons such as carelessness are without considering the distance between different points of destination, so that next purpose can not be reached in time by being easy to appear
The case where ground, is controlled if user plans that required outgoing place set by situation setting module 1 is several by individual office
Terminal 2 processed is using previous outgoing place as starting point, and the latter goes out place as terminal, and pass course device for planning 7 is planned
Minimal path out, the preset average running time of controlling terminal 2 calculate user and arrive at the destination as dividend as divisor
Required time, while obtaining preset upper one place and setting out to the time difference in next place, the institute if user arrives at the destination
It is poor to corresponding user's modification time by the notice of voice notification device 8 when taking time identical with the time difference.
In addition when considering that the time for occurring arriving set by user between different destinations is more nervous,
Construction project information management system further includes being stored with user account and corresponding to user account to be inclined to warning color
User is inclined to warning color database 9;If time difference and user arrive at the destination the time required to and between the time difference control eventually
Held for 2 preset time differences, then controlling terminal 2 is inclined to warning color database 9 in user using user account as query object and is looked into
It askes out user and is inclined to warning color, color is inclined to user to next place and the required time for reaching next place and is carried out
It marks and loads in short message.
The case where route that route planning device 7 is planned can usually neglect odd-and-even license plate rule is further contemplated, is built
Engineering information management system further includes being stored with user account and the user of corresponding the driven a car license plate number of user account drives
It sails license plate number database 10 and has the odd-and-even license plate rule transportation database 11 of odd-and-even license plate rule road.
Controlling terminal 2 drives license plate number database 10 in user using user account as query object and inquires corresponding user
The license plate number to be driven a car, while the minimal path planned with current route device for planning 7 and transferring in odd-and-even license plate rule
All odd-and-even license plate rule roads of transportation database 11 are compared, and consistent restricted driving road are compared if existing, with user's vehicle
The odd or even number of trade mark tail number determines whether to restrict driving as judgment basis, if restricting driving, then excludes current route device for planning 7 and is advised
The minimal path drawn, selects minimal path in remaining route.
The implementation principle of the present embodiment are as follows:
By controlling terminal 2, individual office plan situation setting module 1, user contact details database 3 setting can with
It, can will be set by way of mailbox or short message when family sets completely new route by personal planning situation setting module
Fixed individual office planning situation is informed in user, in order to which user being capable of the corresponding individual office planning situation of immediate inquiring.
Additionally by mobile phone tracker 5, user's field personnel situation database 6, route planning device 7, voice notification device 8,
User is inclined to warning color database 9, user's driving license plate number database 10, odd-and-even license plate rule transportation database 11 being capable of basis
Personal planning situation set by user plans satisfactory shortest path, in order to which user can arrive at the destination in time.
The embodiment of present embodiment is presently preferred embodiments of the present invention, not limits protection of the invention according to this
Range, therefore: the equivalence changes that all structures under this invention, shape, principle are done, should all be covered by protection scope of the present invention it
It is interior.
Claims (7)
1. a kind of construction project information management system, it is characterised in that: including the individual for setting individual office planning situation
Office planning situation setting module (1), controlling terminal (2) and the mailbox and hand that are stored with user account and corresponding user
User contact details database (3), the short message sending device (4) of machine number;
Controlling terminal (2) set that situation is planned in individual office by individual office planning situation setting module (1) in user the
One time to correspond to the account of user as query object in user contact details database (3), transferred out corresponding user's
Mailbox and cell-phone number, situation is planned in the individual office for sending corresponding user to subscriber mailbox, by passing through short message sending device (4)
Situation is planned in the individual office for sending user to the mobile phone of user.
2. a kind of construction project information management system according to claim 1, it is characterised in that: define and pacify in user mobile phone
Equipped with mobile phone tracker (5), individual office plans that the planning situation of individual office set by situation setting module (1) includes the time
Point and the position reached needed for corresponding time point;
Construction project information management system further includes that real-time storage has user account and corresponding user to go out place and required to arrive
Up to user's field personnel situation database (6) of outgoing place time, route planning device (7), voice notification device (8);
Controlling terminal (2) is input in mobile phone tracker (5) to inquire corresponding user position with user mobile phone number, together
When inquire corresponding user in user's field personnel situation database (6) using user account as query object and go out place and required to arrive
Up to the outgoing place time;
Controlling terminal (2) is using user position as starting point, and needs outgoing place recently apart from user's current time
As terminal, pass course device for planning (7) cooks up the shortest distance that user reaches outgoing place, and using the shortest distance as
Dividend, controlling terminal (2) preset average running time calculate user and arrive at the destination institute as divisor as dividend
It takes time, while obtaining current time and the required time difference for reaching the outgoing place time, taken if user arrives at the destination
Between it is identical with the time difference when, pass through voice notification device (8) notice to corresponding user.
3. a kind of construction project information management system according to claim 2, it is characterised in that: if user is done by individual
Public affairs planning situation setting module (1) set by required outgoing place be several, then controlling terminal (2) with it is previous outgoingly
Point is used as starting point, and the latter goes out place as terminal, and pass course device for planning (7) cooks up minimal path, controlling terminal
(2) preset average running time as dividend as divisor, calculates user and arrives at the destination required time, obtain simultaneously
Preset upper one place set out to the time difference in next place, if user is identical with the time difference the time required to arriving at the destination
When, it is poor to corresponding user's modification time by voice notification device (8) notice.
4. a kind of construction project information management system according to claim 3, it is characterised in that: construction project information management
System further includes being stored with user account and corresponding to user account to be inclined to the user's tendency warning color data for warning color
Library (9);
The time required to if time difference and user arrive at the destination and between the time difference in controlling terminal (2) the preset time difference,
Controlling terminal (2) is inclined to warning color database (9) in user using user account as query object and inquires user tendency police
Show color, next place and the required time for reaching next place are marked with user's tendency color and load short
In letter.
5. a kind of construction project information management system according to claim 4, it is characterised in that: construction project information management
System further includes being stored with user's driving license plate number of user account and corresponding the driven a car license plate number of user account
Library (10) and the odd-and-even license plate rule transportation database (11) for having odd-and-even license plate rule road;
Controlling terminal (2) drives license plate number database (10) in user using user account as query object and inquires corresponding user
The license plate number to be driven a car, at the same the minimal path planned with current route device for planning (7) and transfer in odd or even number limit
All odd-and-even license plate rule roads of row transportation database (11) are compared, and compare consistent restricted driving road if existing, with
The odd or even number of family license plate number tail number determines whether to restrict driving as judgment basis, if restricting driving, then excludes current route device for planning
(7) minimal path planned selects minimal path in remaining route.
6. a kind of construction project information management system according to claim 5, it is characterised in that: the short message sending device
It (4) is Short message alarm.
7. a kind of construction project information management system according to claim 6, it is characterised in that: the voice notification device
It (8) is phonetic alarm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910133945.3A CN109886653A (en) | 2019-02-22 | 2019-02-22 | A kind of construction project information management system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910133945.3A CN109886653A (en) | 2019-02-22 | 2019-02-22 | A kind of construction project information management system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109886653A true CN109886653A (en) | 2019-06-14 |
Family
ID=66928871
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910133945.3A Pending CN109886653A (en) | 2019-02-22 | 2019-02-22 | A kind of construction project information management system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109886653A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112734368A (en) * | 2020-12-31 | 2021-04-30 | 大为国际工程咨询有限公司 | Engineering cost progress management method, system and storage medium |
CN113747361A (en) * | 2021-09-09 | 2021-12-03 | 深圳市芯中芯科技有限公司 | Regional position line management system and method |
-
2019
- 2019-02-22 CN CN201910133945.3A patent/CN109886653A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112734368A (en) * | 2020-12-31 | 2021-04-30 | 大为国际工程咨询有限公司 | Engineering cost progress management method, system and storage medium |
CN113747361A (en) * | 2021-09-09 | 2021-12-03 | 深圳市芯中芯科技有限公司 | Regional position line management system and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9146115B2 (en) | Location enhanced meetings and collaboration | |
US8706542B2 (en) | Allocation of location-based orders to mobile agents | |
US20090012802A1 (en) | Parcel retrieval system and method | |
CN102682593B (en) | Intelligent system and method for managing and scheduling taxis | |
US9001993B2 (en) | Universal queuing for inbound communications | |
CN105023126A (en) | Logistics speedy receiving and sending delivery method based on mobile terminal and system thereof | |
CN103218769A (en) | Taxi order allocation method | |
TW200401994A (en) | System and method of accessing and recording messages at coordinate way points | |
CN105894184A (en) | Combined logistics scheduling method, platform and system | |
KR20080059464A (en) | Intelligent meeting scheduler | |
US20050131625A1 (en) | Schoolchildren transportation management systems, methods and computer program products | |
US10212281B2 (en) | System and method for handling repetitive calls at call center | |
CN102077560A (en) | Location- and presence-based media session routing | |
US20190303866A1 (en) | Method of providing information about logistics delivery route by using future traffic information and server for performing the same | |
CN109886653A (en) | A kind of construction project information management system | |
CN102496253A (en) | Alarm processing commanding and scheduling checking system and method based on GPS | |
WO2015180643A1 (en) | Method and system for providing taxi calling service | |
CN106339790A (en) | GPS-based surveyor assignment method | |
CN107123012A (en) | A kind of method and system for automatically selecting ship-to | |
CN101426023A (en) | Method and apparatus for facilitating a location-based, distributed to-do list | |
CN108416567A (en) | One kind being based on full-range multi-functional synergetic office work method and device | |
KR20160025294A (en) | Goods transfer system using urban railload track network and method thereof | |
CN109062092A (en) | Weather monitoring system | |
CN107274022A (en) | A kind of command scheduling method based on internet | |
JP4985629B2 (en) | Incoming call notification command considering the dispatching vehicle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190614 |