CN109881910A - Floor ruggedized construction - Google Patents

Floor ruggedized construction Download PDF

Info

Publication number
CN109881910A
CN109881910A CN201910176576.6A CN201910176576A CN109881910A CN 109881910 A CN109881910 A CN 109881910A CN 201910176576 A CN201910176576 A CN 201910176576A CN 109881910 A CN109881910 A CN 109881910A
Authority
CN
China
Prior art keywords
concrete
steel plate
steel
strand wires
steel strand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910176576.6A
Other languages
Chinese (zh)
Other versions
CN109881910B (en
Inventor
朱奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beiyuan Construction (Beijing) Co.,Ltd.
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201910176576.6A priority Critical patent/CN109881910B/en
Publication of CN109881910A publication Critical patent/CN109881910A/en
Application granted granted Critical
Publication of CN109881910B publication Critical patent/CN109881910B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • E04G23/0237Increasing or restoring the load-bearing capacity of building construction elements of storey floors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0288Repairing or restoring floor slabs

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Working Measures On Existing Buildindgs (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of floor ruggedized constructions, it is characterized in that concrete floor and gunite concrete are unified by steel strand wires in concrete floor following settings gunite concrete, steel strand wires use bowl-type, and oblique part upper end is fixed on angle steel by anchorage;Cushion block is set between horizontal component steel strand wires and concrete floor;Gunite concrete is set between steel strand wires and concrete floor bottom;Steel strand wires following settings steel plate, steel plate are embedded in concrete column, pre-stressed struts are arranged above steel plate;Rubber spacer is set between concrete floor edge position concrete floor and steel plate.

Description

Floor ruggedized construction
Technical field
The present invention relates to a kind of ruggedized construction, in particular to a kind of floor ruggedized construction.
Background technique
Concrete floor is the primary structural member of building, and bearing capacity occurs in use in individual concrete floor Inadequate phenomenon, in order to guarantee using function, it is clear that concrete floor will be reinforced, but due to thickness of concrete floor Relatively thin, ruggedized construction also can be relatively thin in order to reduce weight and cost thickness, and the rigidity of structure is smaller, this results in reinforcing preceding knot It is difficult to form entirety after structure and reinforcing.But it is that engineering staff faces that structure and reinforcing pre-structure carry jointly after reinforcing Project, and the problem of cost is also intended to thinking how is reduced in the case where ensuring secured premise.
Summary of the invention
The present invention is to provide a kind of floor ruggedized construction, solve after reinforcing structure and reinforce pre-structure be difficult to carry jointly and Problem at high cost.
The present invention by concrete floor and sprays coagulation in concrete floor following settings gunite concrete, by steel strand wires Soil unifies, and steel strand wires use bowl-type, and oblique part upper end is fixed on angle steel by anchorage, oblique part lower extreme point position From 1/4 that concrete floor end position is concrete building span of slab, mainly consider in 1/4 position of concrete building span of slab Moment of flexure is smaller, and steel strand wires edge using it is oblique be also it is consistent with concrete floor moment of flexure situation, because of concrete building Edges of boards portion moment of flexure is usually hogging moment.Cushion block is set between horizontal component steel strand wires and concrete floor, and cushion block is concrete square Block, concrete square block length are 60~90mm, and small steel plate is arranged so as to the steel bar welding with concrete floor above concrete blocks It connects and unifies.On the one hand the purpose that cushion block is arranged makes steel strand wires avoid loss of prestress when turning to horizontal segment for oblique section, On the other hand steel strand wires are reduced in the span of horizontal segment to reduce loss of prestress.According to Experimental Comparison, the pre- of bed course is set Stress loss and the loss of prestress difference for being not provided with bed course are larger, and setting bed course has more significant effect to loss of prestress is reduced Fruit optimizes comparison according to test result, and cushion block spacing uses 0.5m~0.6m.Between steel strand wires and concrete floor bottom Gunite concrete is set, and gunite concrete is with a thickness of 60~90mm.Steel strand wires following settings steel plate, steel plate width be 120~ 150mm, steel plate thickness are 12~14mm, and steel plate is embedded in concrete column, and embedded length is 100~120mm, and setting is pre- above steel plate Stress strut, pre-stressed struts diameter are 18~22mm, and pre-stressed struts horizontal space is 0.6m~0.7m, and pre-stressed struts are solid It is scheduled on above concrete floor.It is vertical along concrete floor to steel plate in order to play maximization and the save the cost of mechanical advantage Fem Computer sunykatuib analysis is carried out to direction setting spacing, table 2 is steel plate along between the setting of concrete floor longitudinal direction Away from the ratio to promotion mechanical property, show power when steel plate is greater than 0.8m along concrete floor longitudinal direction setting spacing in table Amplitude of variation is little when learning improving performance to be weakened, and being less than 0.7m, and comprehensive mechanical property and cost factor, steel plate is along mixed Solidifying Tulou plate longitudinal direction setting spacing is 0.7m~0.8m.
Rubber spacer is set between concrete floor edge position concrete floor and steel plate, and rubber spacer length is 0.6~0.9m, rubber spacer width is identical as steel plate width, and rubber spacer is identical as gunite concrete thickness, and rubber pad is arranged The effect of layer is the ductility of concrete after increasing reinforcing, and rubber spacer can play buffer function under geological process.Concrete building The assembly of rubber spacer and gunite concrete is arranged below in plate, can be very good to resist under external force especially geological process.
The loss of prestress reduced value of bed course is whether arranged in table 1
Spacing is arranged to the ratio for promoting mechanical property in table 2
Construction procedure includes:
(1) oblique hole of embedded steel strand wires is bored in concrete floor, oblique bore dia is 3~4mm bigger than steel strand wires diameter. Concrete floor bottom reinforcement bars protective layer is removed, the small steel plate in cushion block top is welded on concrete floor bottom reinforcement bars and is carried out It is fixed.
(2) the vertical hole of embedded pre-stressed struts is bored in concrete floor, vertical bore dia is than pre-stressed struts diameter Big 3~4mm.
(3) concrete column protective layer is cut in angle steel installation position, angle steel is welded in concrete column main reinforcement.It is installing Groove is arranged in steel plate part cutting machine, and depth of groove is 100~120mm, and groove height is 14~16mm, recess width and steel Board width is identical.
(4) prestressed stretch-draw is carried out after steel strand wires being passed through oblique hole.Steel strand tension is divided into two-stage, and the first order is 0~ 30% stretching force, the second level are 30%~100% stretching force.Steel strand tension uses dual control, that is, controls the pulling force of steel strand wires, stretches Long value.After the completion of steel strand tension, check and correction should be measured immediately.If tensioning should be suspended by noting abnormalities, arranged wait ascertain the reason and take Tensioning is further continued for after applying.It can be using length of the steel strand wires under the effect of 20% pretightning force as original length, when tensioning is complete before tensioning Cheng Hou measures former free portion length again, and the difference of the two is actual elongation value.
Be fixed on angle steel after prestressed stretch-draw with anchorage, finally using epoxy resin base joint grouting glue closing steel strand wires and Gap between oblique hole.
(5) by rubber spacer fixation with steel wire on the reinforcing bar of concrete floor, pre-stressed struts are buried in vertical hole.
(6) construction gunite concrete.The wind pressure of work and injection direction, mix conveying distance, concrete matched of spraying machine Composition and division in a proportion, water content etc. are related.Suitable wind pressure of work, it is possible to reduce springback capacity increases the thickness once sprayed, and guarantees to spray Quality.The wind pressure of work of spraying machine will guarantee the pressure for having 0.1MPa at nozzle.
One time jet thickness is too thin, and aggregate is easily sprung back;One time jet thickness is too thick, easily occur spray-up tenesmus trickling or with There is ghost between bottom surface in concrete floor.It is determined according to test, gunite concrete is sprayed using layering, and primary injection is thick Degree is 25~30mm, to reduce rebound degree.When mixing accelerator, a jet thickness is 30~35mm.It mixes accelerator or uses rapid hardening When cement, the minimum interval sprayed twice is 15~20min;Accelerator is not mixed when with ordinary cement, is sprayed twice Minimum interval is 2~4h.It is more than 2h when interval time, should first sprays water before multiple spray wet.
Nozzle should be constantly adjusted with the fluctuation of wind pressure at a distance from by spray plane and angle.Nozzle with by spray plane Vertical line angle uses 10~15 °, experiments have shown that this angle jeting effect is best.Nozzle can be moved along helical trajectory, spiral Diameter is 250~300mm.
(7) concrete strength to be sprayed reaches 75% or more design strength and installs steel plate, uses epoxy after steel plate insertion groove Resin base joint grouting glue dead air space.Pre-stressed struts weld after the embedded hole of steel plate with steel plate integral.
(8) prestressing force is applied to pre-stressed struts, pre-stressed struts top is equipped with screw thread, tightens prestressing force support by nut The screw thread of bar applies prestressing force to pre-stressed struts, is arranged stress meter test stress situation at the top of pre-stressed struts, nut and mixed Valve rubber is equipped between solidifying Tulou plate to avoid local stress destruction.It is sealed after prestress application using epoxy resin base joint grouting glue Close gap between pre-stressed struts and vertical hole.
So that steel plate predeformation is occurred by prestress application of the pre-stressed struts to steel plate, is very beneficial for steel plate participation and holds It carries.
The present invention has a safety feature, and project cost is low.
Detailed description of the invention
Fig. 1, concrete floor ruggedized construction schematic diagram.
1, steel strand wires, 2, cushion block, 3, steel plate, 4, pre-stressed struts, 5, anchorage, 6, angle steel, 7, rubber spacer, 8, injection it is mixed Solidifying soil, 9, concrete floor, 10, concrete column.
Specific embodiment
In 9 following settings gunite concrete 8 of concrete floor in embodiment, by concrete floor 9 and sprayed by steel strand wires 1 It penetrates concrete eight to unify, steel strand wires 1 use bowl-type, and oblique part upper end is fixed on angle steel 6 by anchorage 5, oblique part Lower extreme point position is from 1/4 that 9 end position of concrete floor is 9 span of concrete floor.Horizontal component steel strand wires 1 and concrete Cushion block 2 is set between floor 9, and cushion block 2 is concrete blocks, and concrete square block length is 70mm, is arranged above concrete blocks Small steel plate.Cushion block spacing uses 0.6m.Gunite concrete 8 is set between 9 bottom of steel strand wires 1 and concrete floor, sprays coagulation Soil 8 is with a thickness of 70mm.1 following settings steel plate 3 of steel strand wires, 3 width of steel plate are 130mm, and steel plate 3 is embedded in a thickness of 13mm, steel plate 3 Pre-stressed struts 4 are arranged in concrete column 10, embedded length 110mm, steel plate 3 above, and 4 diameter of pre-stressed struts is 20mm, in advance 4 horizontal space of stress strut is 0.6m, and pre-stressed struts 4 are fixed on above concrete floor 9.Steel plate 3 is along concrete floor 9 It is 0.7m that spacing, which is arranged, in longitudinal direction.
Rubber spacer 7 is set between 9 edge position concrete floor 9 of concrete floor and steel plate 3, and rubber spacer 7 is long Degree is 0.6m, and 7 width of rubber spacer and steel plate 3 are of same size, and rubber spacer 7 is identical as 8 thickness of gunite concrete.
Construction procedure includes:
(1) oblique hole of embedded steel strand wires 1 is bored in concrete floor 9, oblique bore dia is 3mm bigger than 1 diameter of steel strand wires. 9 bottom reinforcement bars protective layer of concrete floor is removed, the small steel plate in 2 top of cushion block is welded on 9 bottom reinforcement bars of concrete floor It is fixed.
(2) the vertical hole of embedded pre-stressed struts 4 is bored in concrete floor 9, vertical bore dia is more straight than pre-stressed struts 4 The big 3mm of diameter.
(3) 10 protective layer of concrete column is cut in 6 installation position of angle steel, angle steel 6 is welded in 10 main reinforcement of concrete column. Groove, depth of groove 110mm, groove height 15mm, recess width and steel plate are set with cutting machine at installation 3 position of steel plate 3 is of same size.
(4) prestressed stretch-draw is carried out after steel strand wires 1 being passed through oblique hole.1 tensioning of steel strand wires is divided into two-stage, the first order 0 ~30% stretching force, the second level are 30%~100% stretching force.1 tensioning of steel strand wires uses dual control, that is, controls the drawing of steel strand wires 1 Power, stretch value.After the completion of 1 tensioning of steel strand wires, check and correction should be measured immediately.If tensioning should be suspended by noting abnormalities, wait ascertain the reason simultaneously It is further continued for tensioning after taking measures.Before tensioning can using length of the steel strand wires 1 under the effect of 20% pretightning force as original length, when After the completion of tensioning, former free portion length is measured again, the difference of the two is actual elongation value.
It is fixed on angle steel 6 after prestressed stretch-draw with anchorage 5, steel strand wires is finally closed using epoxy resin base joint grouting glue Gap between 1 and oblique hole.
(5) it uses fixation with steel wire on the reinforcing bar of concrete floor 9 rubber spacer 7, buries pre-stressed struts in vertical hole 4。
(6) construction injection concrete eight.The wind pressure of work of spraying machine will guarantee the pressure for having 0.1MPa at nozzle.
Gunite concrete 8 is sprayed using layering, and a jet thickness is 25~30mm.It is primary to spray when mixing accelerator It penetrates with a thickness of 30~35mm.It mixes accelerator or when with accelerated cement, the minimum interval sprayed twice is 15~20min;No Accelerator is mixed when with ordinary cement, and the minimum interval sprayed twice is 2~4h.It is more than 2h when interval time, before multiple spray It should first spray water wet.
Nozzle should be constantly adjusted with the fluctuation of wind pressure at a distance from by spray plane and angle.Nozzle with by spray plane Vertical line angle uses 10~15 °.Nozzle is moved along helical trajectory, and screw diameter is 250~300mm.
(7) concrete eight intensity to be sprayed reaches 75% or more design strength installation steel plate 3, and steel plate 3 uses ring after being embedded in groove Oxygen resin base joint grouting glue dead air space.Pre-stressed struts 4 weld after the embedded hole of steel plate 3 with steel plate 3 integral.
(8) prestressing force is applied to pre-stressed struts 4,4 top of pre-stressed struts is equipped with screw thread, tightens prestressing force by nut The screw thread of strut 4 applies prestressing force to pre-stressed struts 4, and stress meter test stress situation, nut is arranged at the top of pre-stressed struts 4 Valve rubber is equipped between concrete floor 9.Pre-stressed struts 4 are closed using epoxy resin base joint grouting glue after prestress application The gap between vertical hole.

Claims (1)

1. a kind of floor ruggedized construction, it is characterized in that will be mixed in concrete floor following settings gunite concrete by steel strand wires Solidifying Tulou plate and gunite concrete unify, and steel strand wires use bowl-type, and oblique part upper end is fixed on angle steel by anchorage, Oblique part lower extreme point position is from 1/4 that concrete floor end position is concrete building span of slab;Horizontal component steel strand wires with Cushion block is set between concrete floor, and cushion block is concrete blocks, and concrete square block length is 60~90mm, on concrete blocks Small steel plate is arranged in face;Cushion block spacing uses 0.5m~0.6m;Gunite concrete is set between steel strand wires and concrete floor bottom, Gunite concrete is with a thickness of 60~90mm;Steel strand wires following settings steel plate, steel plate width are 120~150mm, steel plate thickness 12 ~14mm, steel plate are embedded in concrete column, and embedded length is 100~120mm, and pre-stressed struts, prestressing force support are arranged above steel plate Shank diameter is 18~22mm, and pre-stressed struts horizontal space is 0.6m~0.7m, and pre-stressed struts are fixed on concrete floor Face;Steel plate is 0.7m~0.8m along concrete floor longitudinal direction setting spacing;In concrete floor edge position concrete Rubber spacer is set between floor and steel plate, and rubber spacer length is 0.6~0.9m, rubber spacer width and steel plate width phase Together, rubber spacer is identical as gunite concrete thickness;
Construction procedure includes:
(1) oblique hole of embedded steel strand wires is bored in concrete floor, oblique bore dia is 3~4mm bigger than steel strand wires diameter;It will mix Solidifying soil floor slab bottoms cover to reinforcement removing, the small steel plate in cushion block top is welded on concrete floor bottom reinforcement bars and is consolidated It is fixed;
(2) the vertical hole of embedded pre-stressed struts is bored in concrete floor, vertical bore dia is bigger than pre-stressed struts diameter by 3~ 4mm;
(3) concrete column protective layer is cut in angle steel installation position, angle steel is welded in concrete column main reinforcement;In installation steel plate Groove is arranged in position cutting machine, and depth of groove is 100~120mm, and groove height is 14~16mm, and recess width is wide with steel plate It spends identical;
(4) prestressed stretch-draw is carried out after steel strand wires being passed through oblique hole;Steel strand tension is divided into two-stage, and the first order is 0~30% Stretching force, the second level are 30%~100% stretching force;Steel strand tension uses dual control, the i.e. pulling force of control steel strand wires, elongation Value;After the completion of steel strand tension, check and correction should be measured immediately;If tensioning should be suspended by noting abnormalities, wait ascertain the reason and take measures After be further continued for tensioning;Length before tensioning using steel strand wires under the effect of 20% pretightning force is as original length, after the completion of tensioning, Former free portion length is measured again, and the difference of the two is actual elongation value;
It is fixed on angle steel after prestressed stretch-draw with anchorage, finally using epoxy resin base joint grouting glue closing steel strand wires and oblique Gap between hole;
(5) by rubber spacer fixation with steel wire on the reinforcing bar of concrete floor, pre-stressed struts are buried in vertical hole;
(6) construction gunite concrete;
The wind pressure of work of spraying machine will guarantee the pressure for having 0.1MPa at nozzle in gunite concrete step;
(7) concrete strength to be sprayed reaches 75% or more design strength and installs steel plate, uses epoxy resin after steel plate insertion groove Base joint grouting glue dead air space;Pre-stressed struts weld after the embedded hole of steel plate with steel plate integral;
(8) prestressing force is applied to pre-stressed struts;Stress meter test stress situation, nut and coagulation are set at the top of pre-stressed struts Valve rubber is equipped between Tulou plate;Using epoxy resin base joint grouting glue closing pre-stressed struts and vertical hole after prestress application Between gap;
Pre-stressed struts top is equipped with screw thread, is answered in advance by the screw thread that nut tightens pre-stressed struts pre-stressed struts application Power;Steel plate is set predeformation occur by prestress application of the pre-stressed struts to steel plate.
CN201910176576.6A 2017-07-30 2017-07-30 Floor reinforcing structure Active CN109881910B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910176576.6A CN109881910B (en) 2017-07-30 2017-07-30 Floor reinforcing structure

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201910176576.6A CN109881910B (en) 2017-07-30 2017-07-30 Floor reinforcing structure
CN201710635339.2A CN107227861B (en) 2017-07-30 2017-07-30 Concrete floor ruggedized construction

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201710635339.2A Division CN107227861B (en) 2017-07-30 2017-07-30 Concrete floor ruggedized construction

Publications (2)

Publication Number Publication Date
CN109881910A true CN109881910A (en) 2019-06-14
CN109881910B CN109881910B (en) 2021-06-29

Family

ID=59956649

Family Applications (5)

Application Number Title Priority Date Filing Date
CN201910173957.9A Active CN109853981B (en) 2017-07-30 2017-07-30 Concrete floor reinforcing construction method
CN201710635339.2A Active CN107227861B (en) 2017-07-30 2017-07-30 Concrete floor ruggedized construction
CN201910173990.1A Withdrawn CN109853983A (en) 2017-07-30 2017-07-30 Concrete floor strengthening construction construction
CN201910176576.6A Active CN109881910B (en) 2017-07-30 2017-07-30 Floor reinforcing structure
CN201910173962.XA Withdrawn CN109853982A (en) 2017-07-30 2017-07-30 Concrete floor reinforcement construction technology

Family Applications Before (3)

Application Number Title Priority Date Filing Date
CN201910173957.9A Active CN109853981B (en) 2017-07-30 2017-07-30 Concrete floor reinforcing construction method
CN201710635339.2A Active CN107227861B (en) 2017-07-30 2017-07-30 Concrete floor ruggedized construction
CN201910173990.1A Withdrawn CN109853983A (en) 2017-07-30 2017-07-30 Concrete floor strengthening construction construction

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201910173962.XA Withdrawn CN109853982A (en) 2017-07-30 2017-07-30 Concrete floor reinforcement construction technology

Country Status (1)

Country Link
CN (5) CN109853981B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110821204A (en) * 2017-10-16 2020-02-21 叶长青 Reinforcement construction method of concrete roof beam
CN107605173A (en) * 2017-10-17 2018-01-19 叶香雄 The ruggedized construction of building
CN107869270B (en) * 2017-11-20 2023-11-03 中交建宏峰集团有限公司 Shockproof building
CN110318557B (en) * 2019-07-19 2023-12-19 江苏东南特种技术工程有限公司 Prestressed concrete hollow slab reinforcing device and method
CN111719883B (en) * 2020-03-21 2021-08-31 东莞市大乘建筑工程技术有限公司 Joint structure for reinforcing new and old concrete by increasing section and construction method
CN112854024A (en) * 2021-01-10 2021-05-28 山西省交通新技术发展有限公司 Construction method of bonded prestressed structure for reinforcing hollow slab bridge
CN116717105B (en) * 2023-08-09 2023-10-20 山西八建集团有限公司 Floor inclination treatment construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006219943A (en) * 2005-02-14 2006-08-24 Toda Constr Co Ltd Construction method of floor reinforcing structure
CN103306492A (en) * 2013-05-29 2013-09-18 朱奎 Method for reinforcing concrete weak beam
CN103321444A (en) * 2013-06-14 2013-09-25 罗海军 Construction method for strengthening concrete floor
CN203403691U (en) * 2013-08-06 2014-01-22 中铁西北科学研究院有限公司 Floor slab reinforcing device
CN206279788U (en) * 2016-10-21 2017-06-27 江苏东南特种技术工程有限公司 A kind of structure reinforced using prestressed cable in plate face

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8572913B2 (en) * 2008-06-09 2013-11-05 Chris Stubblefield System and method for plugging core holes
CN104818861A (en) * 2013-08-03 2015-08-05 叶香竹 Pre-stress floor reinforcement method
CN104929381A (en) * 2015-06-02 2015-09-23 项剑锋 Steel-support non-cohesive steel strand lower support type prestress floor reinforcing method
RU168410U1 (en) * 2016-11-09 2017-02-02 федеральное государственное бюджетное образовательное учреждение высшего образования "Донской государственный технический университет" (ДГТУ) STRUCTURE REINFORCEMENT STRUCTURE OF A MULTI-HOLE PLATE
CN106639355A (en) * 2017-01-12 2017-05-10 叶香竹 Reinforced concrete beam structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006219943A (en) * 2005-02-14 2006-08-24 Toda Constr Co Ltd Construction method of floor reinforcing structure
CN103306492A (en) * 2013-05-29 2013-09-18 朱奎 Method for reinforcing concrete weak beam
CN103321444A (en) * 2013-06-14 2013-09-25 罗海军 Construction method for strengthening concrete floor
CN203403691U (en) * 2013-08-06 2014-01-22 中铁西北科学研究院有限公司 Floor slab reinforcing device
CN206279788U (en) * 2016-10-21 2017-06-27 江苏东南特种技术工程有限公司 A kind of structure reinforced using prestressed cable in plate face

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
曹文达编: "混凝土", 《新编建筑工程材料手册》 *
朱红兴等编著: "上部结构施工标准化管理", 《高速公路施工标准化管理手册》 *
罗国强等编著: "钢筋混凝土楼板加固方法", 《混凝土与砌体结构裂缝控制技术》 *

Also Published As

Publication number Publication date
CN107227861B (en) 2019-06-28
CN107227861A (en) 2017-10-03
CN109853983A (en) 2019-06-07
CN109853981B (en) 2021-05-04
CN109881910B (en) 2021-06-29
CN109853981A (en) 2019-06-07
CN109853982A (en) 2019-06-07

Similar Documents

Publication Publication Date Title
CN107227861B (en) Concrete floor ruggedized construction
CN106382011B (en) Concrete structure pre-stressed carbon fiber plate tensioning rollering fastening system and method
CN206593955U (en) A kind of axially loaded supplementary structure of pseudo-static experimental
CN101424061A (en) Unballasted track construction
CN204357147U (en) The composite reinforcing structure of prestressed reinforced concrete construction flexural member
CN107327157B (en) Reinforced structure of concrete floor
CN203904855U (en) Bridge prestress carbon fiber plate tensioning and anchoring system device
CN106401041A (en) Cast-in-situ concrete construction method for pseudo-classic architecture slope roof
CN106917517B (en) Construction method of prestress high-strength fiber cloth reinforced column member
CN215888972U (en) Large-span slow-bonding prestressed beam
CN105113781B (en) Device is set up in a kind of overhanging complete pre-buried installation in side of setting a roof beam in place
CN202047353U (en) Concrete bridge body of expressway or railway and prestressed concrete continuous box girder
CN110029777A (en) A kind of prestressed FRP rebar fiber high-strength light aggregate concrete beam and preparation method thereof
CN104806031B (en) Timber structure reinforced construction method
CN106638334B (en) A kind of external prestressing strengthening device and its construction method
CN105735666B (en) A kind of method of rapid reinforcement concrete column
CN106836021A (en) A kind of pre-stress FRP sheet material Shear Strengthening beams of concrete experimental provision
CN204385941U (en) Prestressing force buckling restrained brace
CN205421992U (en) Floor reinforced structure that bearing capacity is not enough
KR200268159Y1 (en) Device for anchoring outer steel wire for reinforcing concrete structures
CN108222534A (en) Concrete flexural member tensioned anchorage system
CN212983531U (en) Steady basic unit construction of water is with limit portion template reinforcing apparatus
CN209990177U (en) Prestress reinforced bamboo-wood bending component
JP2002332645A (en) Foundation structure of rail for ground-traveling crane and laying method for foundation
CN105804425A (en) Construction method for reinforcing T-beam through partially-bonded prestressed FRP

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240327

Address after: Room 301, Unit 2, Building 18, No.1 Anshun North Road, Huangcun Town, Daxing District, Beijing, 102600

Patentee after: Han Ying

Country or region after: China

Address before: 325000 No. 48 Xinghai Road, Jingshan Street, Ouhai District, Wenzhou City, Zhejiang Province

Patentee before: Ye Changqing

Country or region before: China

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240416

Address after: J94, 1st Floor, Building 1, No. 73 Changhong West Road, Xilu Street, Fangshan District, Beijing, 102400 (Cluster Registration)

Patentee after: Beiyuan Construction (Beijing) Co.,Ltd.

Country or region after: China

Address before: Room 301, Unit 2, Building 18, No.1 Anshun North Road, Huangcun Town, Daxing District, Beijing, 102600

Patentee before: Han Ying

Country or region before: China