CN109859866A - 一种缓解主蒸汽管道破裂事故后果的方法 - Google Patents
一种缓解主蒸汽管道破裂事故后果的方法 Download PDFInfo
- Publication number
- CN109859866A CN109859866A CN201910167974.1A CN201910167974A CN109859866A CN 109859866 A CN109859866 A CN 109859866A CN 201910167974 A CN201910167974 A CN 201910167974A CN 109859866 A CN109859866 A CN 109859866A
- Authority
- CN
- China
- Prior art keywords
- steam
- main
- low
- reactor
- rupture accident
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E30/00—Energy generation of nuclear origin
- Y02E30/30—Nuclear fission reactors
Landscapes
- Structure Of Emergency Protection For Nuclear Reactors (AREA)
Abstract
本发明涉及一种压水堆核电站缓解主蒸汽管道破裂事故后果的方法,包括以下步骤:第一步:主蒸汽管道破裂事故发生后,“蒸汽流量高与反应堆冷却剂平均温度低或补偿蒸汽管线压力低符合”信号触发,关闭所有主蒸汽和主给水隔离阀;第二步:“蒸汽管线压力低‑3”信号触发冷却剂泵停运。本发明需要在反应堆保护系统中新增“蒸汽管线压力低‑3”停运冷却剂泵信号。本发明能够显著减缓主蒸汽管道破裂事故中冷却剂的降温速率,解决了现有技术中主蒸汽管道破裂事故过程中的冷却剂降温速率快的本质问题。本发明通过降低堆芯重返临界后的功率峰值,从而有效降低燃料元件烧毁的风险,达到缓解事故后果的目的。
Description
技术领域
本发明涉及压水堆核电厂安全领域,具体涉及一种缓解主蒸汽管道破裂事故后果的方法。
背景技术
对蒸汽系统管道破裂事故而言,最严重的情况是蒸汽管道双端剪切断裂,它将引起大量的蒸汽快速排放,导致从反应堆冷却剂系统导出的能量增加,冷却剂的温度和压力大幅下降。由于慢化剂温度效应导致的正反应性引入堆芯,反应堆可能重返临界并返回功率运行,从而可能导致燃料元件烧毁。因此设计上需要考虑采用缓解措施以应对主蒸汽管道破裂事故下燃料元件烧毁的风险。
传统百万千瓦级压水堆核电站在发生主蒸汽管道破裂事故时主要采取向堆芯注入浓硼溶液的措施来控制反应性,抑制堆芯重返临界后的功率峰值,降低燃料元件发生烧毁的可能性。此措施主要从控制由冷却剂降温引入的正反馈效应来缓解事故,并没有解决冷却剂降温快的本质问题。
发明内容
本发明所要解决的技术问题是:主蒸汽管道破裂事故过程中的冷却剂降温速率快的问题。通过设置合理的自动停运冷却剂泵信号,在达到相应环路冷却剂泵停运整定值时,停运相应环路冷却剂泵。在不对其他事故产生影响的情况下,可减缓主蒸汽管道破裂事故中冷却剂的降温速率,降低堆芯重返临界后的功率峰值,从而达到有效降低燃料元件烧毁风险的目的。
本发明通过下述技术方案实现:
一种缓解主蒸汽管道破裂事故后果的方法,包括如下步骤:
第一步:“蒸汽流量高与反应堆冷却剂平均温度低或补偿蒸汽管线压力低符合”信号的触发,关闭所有主蒸汽和主给水隔离阀;
第二步:新增“蒸汽管线压力低-3”信号触发冷却剂泵停运。
所述的第一步为,发生主蒸汽管道破裂事故后,由于二回路大量蒸汽快速排放,当二回路蒸汽流量和二回路蒸汽压力分别增高或降低到相应流量高整定值或压力低整定值;或者二回路蒸汽流量和反应堆平均温度分别增高或降低到流量高整定值或温度低整定值时,反应堆保护系统触发“蒸汽流量高与反应堆冷却剂平均温度低或补偿蒸汽管线压力低符合”信号,关闭所有主蒸汽和主给水隔离阀;
所述的第二步为,所有主蒸汽隔离阀和主给水隔离阀关闭后,由于破损环路的主蒸汽隔离阀和主给水隔离阀不能起到隔离作用,该环路蒸汽管线压力降继续降低,当其压力降至“蒸汽管线压力低-3”整定值时,反应堆保护系统触发该环路的冷却剂泵停运。因此,需要在反应堆保护系统中新增“蒸汽管线压力低-3”停泵信号。
在压水堆核电厂的反应堆保护系统中,由于已有“蒸汽管线压力低(或称为任一蒸汽管线流量高与同一蒸汽管道压力低符合)”和“蒸汽管线压力低低”两个信号,其功能主要为触发安全注射和隔离蒸汽管道。因此,本发明中新增触发冷却剂泵停运的信号命名为“蒸汽管线压力低-3”。
本发明与现有技术相比,具有如下的优点和有益效果:
1、本发明在已有的反应堆保护逻辑基础上,通过新增“蒸汽管线压力低-3”信号触发停运破损环路冷却剂泵,在不对其他事故产生影响的情况下,可有效降低破损环路蒸汽发生器一、二次侧之间的换热,减缓冷却剂的降温速率,降低堆芯重返临界后的功率峰值,从而有效降低燃料元件烧毁的风险;
2、本发明达到“自动触发,自动动作”的效果,不需要操作员执行任何操作,从而避免了人因的影响,操作更加准确。
具体实施方式
为使本发明的目的、技术方案和优点更加清楚明白,下面结合实施例对本发明作进一步的详细说明,本发明的示意性实施方式及其说明仅用于解释本发明,并不作为对本发明的限定。
实施例
以下结合实施例对本发明做进一步描述。
本发明是一种缓解主蒸汽管道破裂事故后果的方法,包括以下步骤:
第一步:核电厂发生主蒸汽管道破裂事故后,由于二回路大量的蒸汽快速排放,当二回路蒸汽流量和二回路蒸汽压力分别增高或降低到相应流量高整定值或压力低整定值;或者二回路蒸汽流量和反应堆平均温度分别增高或降低到流量高整定值或温度低整定值时;反应堆保护系统触发“蒸汽流量高与反应堆冷却剂平均温度低或补偿蒸汽管线压力低符合”信号触发,关闭所有主蒸汽隔离阀和主给水隔离阀;
第二步:在所有主蒸汽隔离阀和主给水隔离阀关闭后,由于破损环路的主蒸汽隔离阀和主给水隔离阀不能起到隔离作用,该环路蒸汽管线压力降继续降低,当其压力降至“蒸汽管线压力低-3”整定值时,反应堆保护系统触发该环路的冷却剂泵停运。
操作员干预之后,采用相应的事故处理规程将反应堆带入相应的处理状态。
以上所述的具体实施方式,对本发明的目的、技术方案和有益效果进行了进一步详细说明,所应理解的是,以上所述仅为本发明的具体实施方式而已,并不用于限定本发明的保护范围,凡在本发明的精神和原则之内,所做的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。
Claims (3)
1.一种缓解主蒸汽管道破裂事故后果的方法,其特征在于:包括如下步骤:
第一步:“蒸汽流量高与反应堆冷却剂平均温度低或补偿蒸汽管线压力低符合”信号的触发,关闭所有主蒸汽和主给水隔离阀;
第二步:新增“蒸汽管线压力低-3”信号触发冷却剂泵停运。
2.根据权利要求1所述的一种缓解主蒸汽管道破裂事故后果的方法,其特征在于:所述的第一步为,发生主蒸汽管道破裂事故后,由于二回路大量的蒸汽快速排放,当二回路蒸汽流量和二回路蒸汽压力分别增高或降低到相应流量高整定值或压力低整定值;或者二回路蒸汽流量和反应堆平均温度分别增高或降低到流量高整定值或温度低整定值时,反应堆保护系统触发“蒸汽流量高与反应堆冷却剂平均温度低或补偿蒸汽管线压力低符合”信号,关闭所有主蒸汽隔离阀和主给水隔离阀。
3.根据权利要求1所述的一种缓解主蒸汽管道破裂事故后果的方法,其特征在于:所述的第二步为,所有主蒸汽隔离阀和主给水隔离阀关闭后,由于破损环路的主蒸汽隔离阀和主给水隔离阀不能起到隔离作用,该环路的蒸汽管线压力将继续降低,当其压力降至“蒸汽管线压力低-3”整定值时,反应堆保护系统触发该环路的冷却剂泵停运。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910167974.1A CN109859866B (zh) | 2019-03-06 | 2019-03-06 | 一种缓解主蒸汽管道破裂事故后果的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910167974.1A CN109859866B (zh) | 2019-03-06 | 2019-03-06 | 一种缓解主蒸汽管道破裂事故后果的方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109859866A true CN109859866A (zh) | 2019-06-07 |
CN109859866B CN109859866B (zh) | 2022-02-22 |
Family
ID=66899928
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910167974.1A Active CN109859866B (zh) | 2019-03-06 | 2019-03-06 | 一种缓解主蒸汽管道破裂事故后果的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109859866B (zh) |
Citations (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02268295A (ja) * | 1989-03-20 | 1990-11-01 | General Electric Co <Ge> | 原子炉系 |
CN1080769A (zh) * | 1992-06-24 | 1994-01-12 | 西屋电气公司 | 用无源安全系统缓解压水堆中蒸汽发生器管的破裂事故 |
CN201698775U (zh) * | 2010-06-04 | 2011-01-05 | 中科华核电技术研究院有限公司 | 用于核反应堆压力容器的直接安注系统 |
CN102867550A (zh) * | 2012-08-20 | 2013-01-09 | 中国核电工程有限公司 | 一种应对全厂断电事故的非能动排热装置 |
US20130070887A1 (en) * | 2011-09-19 | 2013-03-21 | Korea Atomic Energy Research Institute | Reactor adapted for mitigating loss-of-coolant accident and mitigation method thereof |
CN103050161A (zh) * | 2012-12-11 | 2013-04-17 | 中国核电工程有限公司 | 辅助给水管线自动隔离的方法 |
CN203366762U (zh) * | 2013-07-31 | 2013-12-25 | 中科华核电技术研究院有限公司 | 蒸汽发生器应急给水系统 |
CN103700411A (zh) * | 2013-12-15 | 2014-04-02 | 中广核工程有限公司 | 核电站冷却剂失流事故的处理方法和系统 |
CN103871506A (zh) * | 2012-12-11 | 2014-06-18 | 中国核动力研究设计院 | 一种核电站高压安全注射系统 |
CN104332207A (zh) * | 2013-07-22 | 2015-02-04 | 中国核动力研究设计院 | 一种反应堆冷却剂丧失事故工况下自动停运冷却剂泵方法 |
CN104538068A (zh) * | 2013-07-22 | 2015-04-22 | 中国核动力研究设计院 | 一种传热管破裂事故工况下防止蒸汽发生器满溢的方法 |
CN105810256A (zh) * | 2014-12-29 | 2016-07-27 | 国核华清(北京)核电技术研发中心有限公司 | 一种核电站非能动余热排出系统 |
US20170148533A1 (en) * | 2014-07-23 | 2017-05-25 | Korea Atomic Energy Research Institute | Passive heat removal system and nuclear power plant including same |
CN107112059A (zh) * | 2014-10-22 | 2017-08-29 | 韩国原子力研究院 | 停止冷却系统及具有该停止冷却系统的核设施 |
CN206595042U (zh) * | 2017-03-09 | 2017-10-27 | 中广核工程有限公司 | 核电站蒸汽发生器冷却及循环装置 |
CN108257691A (zh) * | 2016-12-29 | 2018-07-06 | 福建福清核电有限公司 | 一种研究全厂断电和壳内大破口事故对安全壳影响的装置 |
-
2019
- 2019-03-06 CN CN201910167974.1A patent/CN109859866B/zh active Active
Patent Citations (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02268295A (ja) * | 1989-03-20 | 1990-11-01 | General Electric Co <Ge> | 原子炉系 |
CN1080769A (zh) * | 1992-06-24 | 1994-01-12 | 西屋电气公司 | 用无源安全系统缓解压水堆中蒸汽发生器管的破裂事故 |
US5309487A (en) * | 1992-06-24 | 1994-05-03 | Westinghouse Electric Corp. | Mitigation of steam generator tube rupture in a pressurized water reactor with passive safety systems |
DE69313046D1 (de) * | 1992-06-24 | 1997-09-18 | Westinghouse Electric Corp | Abschwächung eines Dampferzeugerrohrbruches in einem Druckwasserreaktor mit einem passivem Sicherheitssystem |
CN201698775U (zh) * | 2010-06-04 | 2011-01-05 | 中科华核电技术研究院有限公司 | 用于核反应堆压力容器的直接安注系统 |
US20130070887A1 (en) * | 2011-09-19 | 2013-03-21 | Korea Atomic Energy Research Institute | Reactor adapted for mitigating loss-of-coolant accident and mitigation method thereof |
CN102867550A (zh) * | 2012-08-20 | 2013-01-09 | 中国核电工程有限公司 | 一种应对全厂断电事故的非能动排热装置 |
CN103871506A (zh) * | 2012-12-11 | 2014-06-18 | 中国核动力研究设计院 | 一种核电站高压安全注射系统 |
CN103050161A (zh) * | 2012-12-11 | 2013-04-17 | 中国核电工程有限公司 | 辅助给水管线自动隔离的方法 |
CN104538068A (zh) * | 2013-07-22 | 2015-04-22 | 中国核动力研究设计院 | 一种传热管破裂事故工况下防止蒸汽发生器满溢的方法 |
CN104332207A (zh) * | 2013-07-22 | 2015-02-04 | 中国核动力研究设计院 | 一种反应堆冷却剂丧失事故工况下自动停运冷却剂泵方法 |
CN203366762U (zh) * | 2013-07-31 | 2013-12-25 | 中科华核电技术研究院有限公司 | 蒸汽发生器应急给水系统 |
CN103700411A (zh) * | 2013-12-15 | 2014-04-02 | 中广核工程有限公司 | 核电站冷却剂失流事故的处理方法和系统 |
US20170148533A1 (en) * | 2014-07-23 | 2017-05-25 | Korea Atomic Energy Research Institute | Passive heat removal system and nuclear power plant including same |
CN107112059A (zh) * | 2014-10-22 | 2017-08-29 | 韩国原子力研究院 | 停止冷却系统及具有该停止冷却系统的核设施 |
CN105810256A (zh) * | 2014-12-29 | 2016-07-27 | 国核华清(北京)核电技术研发中心有限公司 | 一种核电站非能动余热排出系统 |
CN108257691A (zh) * | 2016-12-29 | 2018-07-06 | 福建福清核电有限公司 | 一种研究全厂断电和壳内大破口事故对安全壳影响的装置 |
CN206595042U (zh) * | 2017-03-09 | 2017-10-27 | 中广核工程有限公司 | 核电站蒸汽发生器冷却及循环装置 |
Non-Patent Citations (2)
Title |
---|
张世顺 等: "岭澳核电站1号机组第三循环主蒸汽管道断裂事故堆芯后果分析", 《核动力工程》 * |
詹经祥: "《第十四届全国反应堆热工流体学术会议暨中核核反应堆热工水力技术重点实验室2015年度学术年会论文集》", 23 September 2015 * |
Also Published As
Publication number | Publication date |
---|---|
CN109859866B (zh) | 2022-02-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102163469B (zh) | 一种核电站非能动专设安全系统 | |
CN111322440B (zh) | 减压阀 | |
CN101847451A (zh) | 一种安全注入系统 | |
WO2014090106A1 (zh) | 一种核电站高压安全注射系统 | |
CN102034559B (zh) | 一种核电站的快速互备系统及其互备方法 | |
CN110097982A (zh) | 一种核电厂安全注入及余热排出系统 | |
KR20130000572A (ko) | 안전보호용기를 구비한 피동형 비상노심냉각설비 및 이를 이용한 열 전달량 증가 방법 | |
CN109859866A (zh) | 一种缓解主蒸汽管道破裂事故后果的方法 | |
CN104332188A (zh) | 一种丧失正常给水-atws事故下缓解一回路超压的方法 | |
CN103426484A (zh) | 一种防止反应堆堆内熔融物熔损压力容器的方法以及用于实施这种方法的系统 | |
JPH03269297A (ja) | 原子力発電所の非常用炉心冷却系 | |
CN107221361B (zh) | 一种核电厂安全壳事故早期降压系统 | |
CN106898392B (zh) | 一种全压设计的主蒸汽系统 | |
CN206054010U (zh) | 汽轮发电机组opc超速保护动作eh油系统稳压装置 | |
CN104269193A (zh) | 次临界能源包层事故缓解系统 | |
CN101727995B (zh) | 一种核电站控制配电盘掉电试验的防误安注、喷淋方法 | |
CN214279616U (zh) | 一种防止蒸汽发生器满溢的核电站保护系统 | |
Xu et al. | Transient Analysis of Dedicated Pressure Relief Valve Under High-Pressure Condition in Severe Accident for Tianwan 56 Nuclear Power Plant | |
CN115274152A (zh) | 一种非能动中压安注系统及核电厂系统 | |
Liang et al. | Low temperature overpressurization analysis for CPR1000 | |
CN116705368A (zh) | 一种核电蒸汽大气排放系统的控制方法 | |
Ke et al. | The emergency operating strategy analysis of medium LOCA with MHSI unavailable | |
Toth | Safety analyses supporting the symptom oriented emergency operating procedures | |
Lv et al. | Depressurization Strategy of China's Advanced Pressurized Water Reactor Under Typical Accidents | |
CN104347132A (zh) | 核电厂停堆工况下保护主泵的方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |