CN109853340A - A kind of sliding formwork kerbstone paver - Google Patents

A kind of sliding formwork kerbstone paver Download PDF

Info

Publication number
CN109853340A
CN109853340A CN201811349940.6A CN201811349940A CN109853340A CN 109853340 A CN109853340 A CN 109853340A CN 201811349940 A CN201811349940 A CN 201811349940A CN 109853340 A CN109853340 A CN 109853340A
Authority
CN
China
Prior art keywords
rubble
delivery board
plate
fixed
rubble delivery
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811349940.6A
Other languages
Chinese (zh)
Other versions
CN109853340B (en
Inventor
齐从军
尹畅
李相权
杨森
李红伟
石淮什
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuzhou New Curber Machinery Technology Co Ltd
Original Assignee
Xuzhou New Curber Machinery Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xuzhou New Curber Machinery Technology Co Ltd filed Critical Xuzhou New Curber Machinery Technology Co Ltd
Priority to CN201811349940.6A priority Critical patent/CN109853340B/en
Publication of CN109853340A publication Critical patent/CN109853340A/en
Application granted granted Critical
Publication of CN109853340B publication Critical patent/CN109853340B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Road Paving Structures (AREA)

Abstract

A kind of sliding formwork kerbstone paver, including screw conveyor and mold, rotating lip-type sealing ring A and rotating lip-type sealing ring B are fixed on the axis of screw conveyor, circlip stationary annular water fender is used between, and the gap between ring-shaped splash guard excircle and helical feed machine tail end casing is not more than 1mm;Die nose is concrete discharging area, consolidates guidance set on concrete discharging area rear mould side wall, the second guidance set is fixed at the rear of guidance set.The service life is longer for the paver screw conveyer bearing, and the cost that paves is lower.

Description

A kind of sliding formwork kerbstone paver
Technical field
The present invention relates to a kind of pavers, and in particular to a kind of conveying of paver and formation system.
Background technique
The concrete of paver is conveyed by screw conveyor, and existing existing screw conveyor end bearing is prevented Shield, it is most of to use simple rotating lip-type sealing ring, but rotating lip-type sealing ring is easily damaged for a long time and after waste water, To cause sewage and bearing touch, accelerate the abrasion of bearing.
In addition, existing paver concrete usage amount is high, it is at high cost.
Summary of the invention
The object of the present invention is to provide a kind of guard assemblies for preventing waste water bearing, and the cunning at low cost that paves Mould kerbstone paver.
To achieve the goals above, the present invention includes a kind of sliding formwork kerbstone paver, is fixed on the axis of screw conveyor Rotating lip-type sealing ring A and rotating lip-type sealing ring B uses circlip stationary annular water fender, annular water blocking between Gap between plate excircle and helical feed machine tail end casing is not more than 1mm;
Die nose is concrete discharging area, solid guidance set, guiding group on concrete discharging area rear mould side wall The second guidance set is fixed at the rear of part;
The guidance set include two guiding inclined plates and two first clamping plates, guiding inclined plate it is vertically arranged, one side and Mould side wall sealing is fixed, and is extended in the middle part of another lateral mold and is sealed with first clamping plate and fixes, and first clamping plate is vertically arranged, and Parallel with mould side wall, two guiding inclined plates and two first clamping plates are symmetrical arranged;
Second guidance set includes two rubble conveying board groups and two second clamping plates, and the rubble conveys board group packet The first rubble delivery board and the second rubble delivery board are included, the first rubble delivery board is parallelogram, one side and mould inner wall Sealing is fixed, and is extended to seal with the vacant end of first clamping plate in the middle part of another lateral mold and be fixed, the first rubble delivery board and mold The top of side wall connecting side is higher than the top of itself and first clamping plate connecting side, and the second rubble delivery board is also parallel four side Shape, one side and mould side wall sealing are fixed, and the other side and second clamping plate sealing are fixed, and second clamping plate is vertically arranged, and and mould Tool side wall is parallel, and the second rubble delivery board top margin is parallel with the top margin of the first rubble delivery board, and bottom edge and the first rubble convey The bottom edge of plate is parallel, and the second rubble delivery board bottom edge is fixedly connected with the bottom edge of the first rubble delivery board by bottom plate, and first Rubble delivery board and the second rubble delivery board are connected to the surface of mould side wall junction with rubble feeder pipe, two rubbles It conveys board group and two second clamping plates is symmetrical arranged, the plane of symmetry is overlapped with the plane of symmetry of guidance set, and the top margin of second clamping plate is Bevel edge, the vertex connecting with the second rubble delivery board are higher than the vertex of vacant side;
The distance between described two second clamping plates are not less than the distance between two first clamping plates, and difference is in 0-10cm In range;
Fixation clip component on the roof of the mold comprising the first inclined plate, first horizontal plate, the second inclined plate, First inclined plate top margin and the sealing of mold roof are fixed, the vertex at bottom edge both ends and two guidings inclined plates and mould side wall affixed side It is fixedly connected, side and mould side wall sealing are fixed, and two sides of the first horizontal plate are respectively at two first clamping plates Top margin sealing is fixed, and front and the bottom edge sealing of the first inclined plate are fixed, first horizontal plate length and first clamping plate front-rear direction Length it is identical, the back of the second inclined plate top margin and first horizontal plate, which seals, to be fixed, the top margin of side and second clamping plate Sealing is fixed.
Further, fixed a pair of third clamping plate after second clamping plate, fixes one on the rear top of third clamping plate Horizontal scraper plate.
Further, vibration machine is installed on the third clamping plate wall.
Further, on the opposite face of two first clamping plates on be fixed with horizontally disposed multiple strip projected parts.
Further, the downward raised line of multiple tilted rearwards is set on the first rubble delivery board, the second rubble is defeated It send and one-to-one raised line is set on plate, raised line rear end extends to the rear side of the first rubble delivery board and the second rubble delivery board, There are the gap of 5-8cm, the conveyings of the first rubble for the front end of raised line and the front side of the first rubble delivery board and the second rubble delivery board The gap between raised line raised line corresponding with the horizontal position on the second rubble delivery board on plate is not more than 20mm.
The beneficial effects of the present invention are can effectively reduce and be applied to screw conveyor driving unit axial impact Power.The usage amount that concrete can be reduced simultaneously, is greatly reduced cost.
Detailed description of the invention
Fig. 1 is the antifouling water assembly of screw conveyor.
Fig. 2 is mold top view.
Fig. 3 is mold left view.
Fig. 4 is first clamping plate main view.
Fig. 5 is the first rubble delivery board main view.
Fig. 6 is rubble conveying board group structural schematic diagram.
Fig. 7 is Anchor plate kit structural schematic diagram.
Fig. 8 is molding rear part Longitudinal cross section schematic.
Fig. 9 is paver overall structure diagram.
Specific embodiment
Invention is described in detail with reference to the accompanying drawing.
As shown in Figure 1, increasing ring-shaped splash guard 5 on axis 6, ring-shaped splash guard 5 is fixed on axis 6 by circlip for shaft 4 On, it is rotated with axis 6, with after the damage of sewage Long Term Contact, sewage trickles rotating lip-type sealing ring B2 along axis 6, can be by annular water blocking Plate 5 blocks, and sewage will not be contacted further with rotating lip-type sealing ring A1, and the service life of rotating lip-type sealing ring A1 can prolong It is long, to increase the service life of bearing 3.
As shown in Fig. 2 to 7,10 front end of mold is concrete discharging area, on 10 side wall of concrete discharging area rear mold Gu the second guidance set 30 is fixed at the rear of guidance set 20, guidance set 20;
The guidance set 20 includes two guiding inclined plates 21 and two first clamping plates 22, and guiding inclined plate 21 is vertically arranged, One side and the sealing of 10 side wall of mold are fixed, and are extended in the middle part of another lateral mold and are sealed with first clamping plate 22 and fix, the first folder Plate 22 is vertically arranged, and parallel with mould side wall, and two guiding inclined plates 21 and two first clamping plates 22 are symmetrical arranged;
Second guidance set 30 includes two rubble conveying board groups 31 and two second clamping plates 22, the rubble conveying Board group 31 includes the first rubble delivery board 311 and the second rubble delivery board 312, and the first rubble delivery board 311 is parallelogram, One side and the sealing of 10 inner wall of mold are fixed, and are extended to seal with the vacant end of first clamping plate 22 in the middle part of another lateral mold and be fixed, First rubble delivery board 311 is higher than the top of itself and 22 connecting side of first clamping plate with the top of 10 side wall connecting side of mold, described Second rubble delivery board 312 is also parallelogram, and one side and the sealing of 10 side wall of mold are fixed, the other side and second clamping plate 32 Sealing is fixed, and second clamping plate 32 is vertically arranged, and parallel with mould side wall, 312 top margin of the second rubble delivery board and the first rubble The top margin of delivery board 311 is parallel, and bottom edge is parallel with the bottom edge of the first rubble delivery board 312, and 312 bottom of the second rubble delivery board Side is fixedly connected with the bottom edge of the first rubble delivery board 311 by bottom plate, the first rubble delivery board 311 and the second rubble delivery board 312 are connected to the surface of mould side wall junction with rubble feeder pipe 15, and two rubbles of institute convey board groups 31 and two second Clamping plate 22 is symmetrical arranged, and the plane of symmetry is overlapped with the plane of symmetry of guidance set 20, and the top margin of second clamping plate 32 is bevel edge, with second The vertex that rubble delivery board 312 connects is higher than the vertex of vacant side;
The distance between described two second clamping plates 32 are not less than the distance between two first clamping plates 22, and difference is in 0- Within the scope of 10cm.
Fixation clip component on the roof of the mold 10 comprising the first inclined plate 11, first horizontal plate 12, second are oblique Pressing plate 13,11 top margin of the first inclined plate and the sealing of 10 roof of mold are fixed, bottom edge both ends and two guiding inclined plates 21 and mold 10 The vertex of side wall affixed side is fixedly connected, and side and the sealing of 10 side wall of mold are fixed, 12 two sides of the first horizontal plate It seals and fixes respectively at the top margin of two first clamping plates 22, front and the bottom edge sealing of the first inclined plate 11 are fixed, first level Length is identical in the front-back direction with first clamping plate 22 for 12 length of plate, after 13 top margin of the second inclined plate and first horizontal plate 12 Side sealing is fixed, and the top margin of side and second clamping plate 32, which seals, to be fixed.
Concrete passes through screw conveyor, into the vibrating later through the first inclined plate 11 by vibrator 40 of mold 10 The extruding of inclined plate 21 is guided by forming idiosome after first clamping plate 22 with two.The rubble of gap gradation, mainly 26.5mm are left Right rubble enters idiosome by rubble conveying board group longitudinal arrangement, is then extruded in idiosome by the second inclined plate 13 Middle formation interlocking, while extra mortar preferably wraps up rubble under the extruding of the second inclined plate, the side of kerbstone at Type interlocking face improves kerbstone stability, while reducing the usage amount of concrete, and cost is greatly reduced.Certainly, according to concrete The characteristics of workability, the rubble that rubble can also select partial size lesser or bigger, but grade are excellent with one.
Concrete basic forming by second clamping plate 32 fixes a pair of of third clamping plate again preferably after second clamping plate 32 33, to strike off the side of concrete, a horizontal scraper plate is fixed on the rear top of third clamping plate 33, to strike off concrete top Face.
Horizontally disposed multiple strip projected parts 23 are fixed on the opposite face of described two first clamping plates 22.Strip projected parts Preferably spaced set.Be arranged strip projected parts purpose be in order to by the side plucking of idiosome, it is corrugated, be conducive to rubble Squeeze into idiosome.
The downward raised line of multiple tilted rearwards, the second rubble delivery board 312 are set on the first rubble delivery board 311 The upper one-to-one raised line of setting, after raised line rear end extends to the first rubble delivery board 311 and the second rubble delivery board 312 The front side of side, the front end of raised line and the first rubble delivery board 311 and the second rubble delivery board 312 is there are the gap of 5-8cm, and first The gap between raised line raised line corresponding with the horizontal position on the second rubble delivery board 312 on rubble delivery board 311 is little In 20mm.Rubble conveys board group 31 and is made of the plate and bottom plate of two parallelogram, and rubble under the effect of gravity can be to mold Middle part rolls, and raised line is arranged in the embedded lock blocking of conveying board group in rubble in order to prevent, allows between rubble upper and lower level and is spaced from each other, Guarantee that rubble can roll on raised line, can smoothly enter into idiosome.
The foregoing is merely the preferred embodiment of the present invention, are not intended to restrict the invention, for those skilled in the art For member, the invention may be variously modified and varied.All any modifications in spirit of that invention and principle, made are equal Replacement, improvement etc., should all be included in the protection scope of the present invention.

Claims (5)

1. a kind of sliding formwork kerbstone paver, including screw conveyor and mold, which is characterized in that solid on the axis of screw conveyor Determine rotating lip-type sealing ring A and rotating lip-type sealing ring B, uses circlip stationary annular water fender, annular gear between Gap between water plate excircle and helical feed machine tail end casing is not more than 1mm;
Die nose is concrete discharging area, solid guidance set, guidance set on concrete discharging area rear mould side wall The second guidance set is fixed at rear;
The guidance set includes two guiding inclined plates and two first clamping plates, and guiding inclined plate is vertically arranged, one side and mold Side wall sealing is fixed, and is extended in the middle part of another lateral mold and is sealed with first clamping plate and fix, first clamping plate is vertically arranged, and and mould It is parallel to have side wall, two guiding inclined plates and two first clamping plates are symmetrical arranged;
Second guidance set includes two rubbles conveying board groups and two second clamping plates, and the rubble conveying board group includes the One rubble delivery board and the second rubble delivery board, the first rubble delivery board are parallelogram, and one side and mould inner wall seal It is fixed, extend to seal with the vacant end of first clamping plate in the middle part of another lateral mold and fix, the first rubble delivery board and mould side wall The top of connecting side is higher than the top of itself and first clamping plate connecting side, and the second rubble delivery board is also parallelogram, Side and mould side wall sealing are fixed, and the other side and second clamping plate sealing are fixed, and second clamping plate is vertically arranged, and and mould side wall In parallel, the second rubble delivery board top margin is parallel with the top margin of the first rubble delivery board, the bottom on bottom edge and the first rubble delivery board Side is parallel, and the second rubble delivery board bottom edge is fixedly connected with the bottom edge of the first rubble delivery board by bottom plate, and the first rubble is defeated Plate and the second rubble delivery board is sent to be connected to the surface of mould side wall junction with rubble feeder pipe, two rubble delivery boards Group and two second clamping plates are symmetrical arranged, and the plane of symmetry is overlapped with the plane of symmetry of guidance set, and the top margin of second clamping plate is bevel edge, The vertex connecting with the second rubble delivery board is higher than the vertex of vacant side;
The distance between described two second clamping plates are not less than the distance between two first clamping plates, and difference is in 0-10cm range It is interior;
Fixation clip component on the roof of the mold comprising the first inclined plate, first horizontal plate, the second inclined plate, first Inclined plate top margin and the sealing of mold roof are fixed, and the vertex that bottom edge both ends guide inclined plate and mould side wall affixed side with two is fixed Connection, side and mould side wall sealing are fixed, top margin of two sides of the first horizontal plate respectively at two first clamping plates Sealing is fixed, and front and the bottom edge sealing of the first inclined plate are fixed, and first horizontal plate length is grown in the front-back direction with first clamping plate Spend identical, the back sealing fixation of the second inclined plate top margin and first horizontal plate, the top margin sealing of side and second clamping plate It is fixed.
2. sliding formwork kerbstone paver according to claim 1, which is characterized in that fixed a pair of the after second clamping plate Three-ply board fixes a horizontal scraper plate on the rear top of third clamping plate.
3. sliding formwork kerbstone paver according to claim 2, which is characterized in that install vibration on the third clamping plate wall Generator.
4. sliding formwork kerbstone paver according to claim 1, which is characterized in that on the opposite face of two first clamping plates It is fixed with horizontally disposed multiple strip projected parts.
5. sliding formwork kerbstone paver according to claim 1, which is characterized in that be arranged on the first rubble delivery board One-to-one raised line is arranged on the second rubble delivery board in the downward raised line of multiple tilted rearwards, and raised line rear end extends to The rear side of one rubble delivery board and the second rubble delivery board, the front end of raised line and the first rubble delivery board and the second rubble delivery board Front side there are the gap of 5-8cm, the raised line on the first rubble delivery board is corresponding with the horizontal position on the second rubble delivery board Raised line between gap be not more than 20mm.
CN201811349940.6A 2018-11-14 2018-11-14 Slipform curb paver Active CN109853340B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811349940.6A CN109853340B (en) 2018-11-14 2018-11-14 Slipform curb paver

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811349940.6A CN109853340B (en) 2018-11-14 2018-11-14 Slipform curb paver

Publications (2)

Publication Number Publication Date
CN109853340A true CN109853340A (en) 2019-06-07
CN109853340B CN109853340B (en) 2021-02-05

Family

ID=66890002

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811349940.6A Active CN109853340B (en) 2018-11-14 2018-11-14 Slipform curb paver

Country Status (1)

Country Link
CN (1) CN109853340B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4984932A (en) * 1989-03-28 1991-01-15 John Leone Apparatus for continuous formation of concrete curbs
JP3395128B2 (en) * 1998-09-30 2003-04-07 ニチレキ株式会社 Spray type surface treatment method
CN2924192Y (en) * 2006-07-25 2007-07-18 宝山钢铁股份有限公司 Output shaft waterproof sealing structure for high speed rotary equipment
KR20110016577A (en) * 2009-08-12 2011-02-18 황한재 Construction apparatus for boundary stone
CN206204743U (en) * 2016-08-30 2017-05-31 北京亿赫公路养护有限责任公司 The more uniform synchronization spread construction equipment of building stones spread

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4984932A (en) * 1989-03-28 1991-01-15 John Leone Apparatus for continuous formation of concrete curbs
JP3395128B2 (en) * 1998-09-30 2003-04-07 ニチレキ株式会社 Spray type surface treatment method
CN2924192Y (en) * 2006-07-25 2007-07-18 宝山钢铁股份有限公司 Output shaft waterproof sealing structure for high speed rotary equipment
KR20110016577A (en) * 2009-08-12 2011-02-18 황한재 Construction apparatus for boundary stone
CN206204743U (en) * 2016-08-30 2017-05-31 北京亿赫公路养护有限责任公司 The more uniform synchronization spread construction equipment of building stones spread

Also Published As

Publication number Publication date
CN109853340B (en) 2021-02-05

Similar Documents

Publication Publication Date Title
CN206032533U (en) Empty segment sweeper for belt conveyer
CN101423163B (en) Elevator running guiding device
CN202156718U (en) Edge-raised conveying belt for preventing splashing of materials
CN109853340A (en) A kind of sliding formwork kerbstone paver
CN203612511U (en) Material conveying device for paving machine
CN219620284U (en) Material pushing device of belt conveyor
CN107901375A (en) A kind of portable extrusion waste material environmental protection reception device
CN109653069A (en) A kind of paver conveying formation system
CN210531859U (en) Protection device for building pipeline
CN201644214U (en) Arc-shaped semi-countercurrent magnetic separator cell
CN203429535U (en) Scraper blade chain material conveying structure of spreading machine
CN210048019U (en) Dregs conveying equipment
CN209200588U (en) A kind of superimposed sheet integrated molding junction box structure
CN213767083U (en) Double-screw extrusion device for producing polyethylene cable sheath material
CN219520439U (en) Injection protection device of die casting machine
CN215564504U (en) Concrete pump convenient to move
CN215754804U (en) Wear-resisting heavy plate type ore feeder
CN215945771U (en) Scraper conveyor convenient for mounting motor for coal mine
CN218111260U (en) Regeneration concrete blowing device
CN217599653U (en) Belt conveyor unloading chute cleaning device
CN213772749U (en) Adjustable track laying vehicle
CN212831006U (en) Screw conveyer for engineering
CN203189033U (en) Wear-resistant rubber disk and rotor type injection machine
CN211000078U (en) Liquid filling tank of plate hydraulic machine
CN215589463U (en) Precast box girder concrete pedestal protection device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant