CN109827067A - A kind of Large LNG bimetallic full-capacity tank - Google Patents

A kind of Large LNG bimetallic full-capacity tank Download PDF

Info

Publication number
CN109827067A
CN109827067A CN201910083117.3A CN201910083117A CN109827067A CN 109827067 A CN109827067 A CN 109827067A CN 201910083117 A CN201910083117 A CN 201910083117A CN 109827067 A CN109827067 A CN 109827067A
Authority
CN
China
Prior art keywords
primary tank
anchor
tank
hot angle
seat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910083117.3A
Other languages
Chinese (zh)
Other versions
CN109827067B (en
Inventor
郭旭
吴桂兰
高明明
曾旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Doer Gaseous Chemical Equipment Co ltd
Original Assignee
SUZHOU DOER GAS CHEMICAL EQUIPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUZHOU DOER GAS CHEMICAL EQUIPMENT Co Ltd filed Critical SUZHOU DOER GAS CHEMICAL EQUIPMENT Co Ltd
Priority to CN201910083117.3A priority Critical patent/CN109827067B/en
Publication of CN109827067A publication Critical patent/CN109827067A/en
Application granted granted Critical
Publication of CN109827067B publication Critical patent/CN109827067B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

The invention discloses a kind of Large LNG bimetallic full-capacity tanks, primary tank cylinder of the invention is designed using not uniform thickness, and the reinforcement of multi-turn reinforcing rib is set, top stiffener uses T-shaped structure, guarantee rigidity, prevent unstability under negative pressure condition, improves the force stability of primary tank cylinder, combined type flexible elastic layer can be used for buffering pearlife lateral pressure, guarantee that primary tank and time container interlayer annular space fill closely knit pearlife for completely cutting off the transmitting of primary tank sidewall direction cooling capacity;Using the composite structure of flat casing when anchor of the present invention is across hot angle protection bottom plate; minimize the stress that hot angle protective layer bottom plate is transmitted to by anchor; the setting of wedge groove and wedge-shaped heat-insulating plug, can reduce the heat transfer property of anchor pole, improve hot angle protective value.

Description

A kind of Large LNG bimetallic full-capacity tank
Technical field
The present invention relates to full appearance tank technical field, specifically a kind of Large LNG bimetallic full-capacity tank.
Background technique
LNG, i.e. liquefied natural gas have the characteristics that low temperature, volatile, inflammable, explosive.In recent years, China's Coastal Areas LNG engineering project all shows the trend of scale, and the LNG storage tank built tends to enlargement, once leakage fire occurs, will have It may cause the explosion of periphery storage tank and cause land used outside the factories such as residential block in region, industrial and mining enterprises, urban operating mechanism affected " Domino effect ".Therefore, LNG storage tank is most important as its performance of main hazard source in project.
Domestic LNG industry rapidly develops, and the storage capacity of receiving station is increasing, requires the security performance of storage tank also more next It is higher.For full-capacity tank as a kind of pot of LNG aboveground storage, opposite single appearance tank and double volume tank have higher safety coefficient and skill Art economy.However, standard system is not perfect, and designer is to specification since China LNG Engineering Project Construction experience is insufficient There is also uncertain places for understanding with standard.The design of current bimetallic full appearance tank is generally relatively simple, there are earthquakes And in the case that LNG is leaked, it is easy to cause the accident, there is biggish security threat.
Therefore, those skilled in the art provide a kind of Large LNG bimetallic full-capacity tank, to solve above-mentioned background technique The problem of middle proposition.
Summary of the invention
The purpose of the present invention is to provide a kind of Large LNG bimetallic full-capacity tanks, to solve to mention in above-mentioned background technique Out the problem of.
To achieve the above object, the invention provides the following technical scheme:
A kind of Large LNG bimetallic full-capacity tank, including primary tank, secondary container, foundation platform, the protection of hot angle component, anchor It is fixedly mounted with and sets and anchor insulating assembly, wherein the primary tank, secondary container, which support, to be arranged on the foundation platform, and basis Cushion cap is arranged on mattess using more pillar supports, to make the minimum between the foundation platform and ground high Degree difference is 800mm;
The primary tank is self-support type, steel, open top, the single wall tank for not storing product boil-off gas, described time Container is to have vaulted self-support type, steel, closed storage tank, time of the primary tank cylinder of the primary tank and time chamber wall It is provided with interlayer space between shell, fills closely knit pearlife inside interlayer space, which is characterized in that
The primary tank cylinder is designed using not uniform thickness, and the reinforcement of multi-turn reinforcing rib is arranged, and top reinforcing rib uses T shape knot Structure guarantees that rigidity prevents unstability under negative pressure condition;And
The distance for extending the primary tank cylinder body outer wall of the reinforcing rib of T-shaped structure in top is greater than adjacent thereto The T-shaped structure being below reinforcing rib the distance for extending the primary tank cylinder body outer wall;And the T shape of the top The end face of the reinforcing rib of structure just abuts the inner wall of the secondary shell;And
It is additionally provided between multi-turn between the external wall of upper portion of the primary tank cylinder and the upper inside wall of the secondary shell Every the combined type flexible elastic layer of arrangement, for buffering pearlife lateral pressure;
The primary tank, secondary container bottom and the foundation platform between be additionally provided with insulation support component;
The hot angle protection component is additionally provided between the primary tank and secondary container;
The primary tank, secondary container bottom be all made of anchor anchor connection on the foundation platform, and it is described Anchor is passed down through at the position of the hot angle protection bottom plate of the hot angle protection component and is also arranged with anchoring insulating assembly, with Just the stress that hot angle protective layer bottom plate is transmitted to by anchor is maximally reduced.
As a further solution of the present invention: the anchor uses anchor rod, wherein the anchoring insulating assembly packet Include flat casing, collet and heat-insulating plug, wherein the flat casing is oval structure, and the ratio between elliptical long axis and short axle More than or equal to three, the anchor rod is located at the center of the flat casing, and the flat casing and the anchor rod it Between filling be sealed with collet, multiple spaced apart wedge grooves, and each wedge groove are provided in the axial direction of the anchor rod In the radially interlaced arrangement of the anchor rod;Heat-insulating plug is filled in the wedge groove, and the wedge groove is located at the anchor The radially inner side of solid rod is wedge-shaped big end, and radial outside is wedge-shaped small end, passes through the heat-insulated of the wedge groove and wedge structure The setting of plug, reduces the heat transfer property of the anchor rod, and guarantees anchoring property.
As a further solution of the present invention: the combined type flexible elastic layer is followed successively by cotton by primary tank outer wall outward Cloth, elastic cotton, cotton, glass wool cloth.
As a further solution of the present invention: the hot angle protection component include hot angle protection siding, hot angle protection bottom plate, Hot angle protection top plate, foam glass brick and connection compensation component, wherein the hot angle protection siding uses the foam glass brick Support is connected on the inner wall of the secondary shell, and the bottom of the hot angle protection siding is also connected with hot angle protection bottom plate, The hot angle protection top plate, and the brushing low temperature between layers of foam glass brick are provided at the top of the hot angle protection siding Glue also fills up the glass fibre cotton after compression with a thickness of mm as binder in hot angle protection top plate, the hot angle protection bottom plate, The bottom of hot angle protection siding and time shell is arranged in the connection compensation component, the connection compensation component with every Heat effect and can be carried out under the stress of the temperature difference it is deformation-compensated, so as to reduce to secondary shell installation junction stress It influences.
As a further solution of the present invention: the connection compensation component includes heat insulation pedestal, upper connection pedestal, lower connection Pedestal, separate seat, levelling seat, concrete support seat and vertical flexible anchoring connector and horizontal flexibility anchor connector, wherein The hot angle protection bottom plate, hot angle protect the bottom of siding, primary tank cylinder to be mounted in the heat insulation pedestal, the heat-insulated bottom Seat is fixedly connected on the upper connection pedestal of its bottom, and separate seat is connected with lower connection bottom between the lower part use of upper connection pedestal is described The bottom of seat, the lower connection pedestal is mounted on concrete support seat by levelling seat, the surrounding of the concrete support seat It is fixed on insulation pedestal using horizontal flexibility anchor connector, the insulation pedestal is fixed on foundation platform, the upper company It connects pedestal, separate seat, lower connection pedestal, be connected with vertical flexible anchoring connector between concrete support seat, pass through institute It states vertical flexible anchoring connector and horizontal flexibility anchor connector is realized to the benefit between primary tank cylinder and secondary shell Repay can Light deformation connection, the secondary shell using rigid holder it is fixed be anchored at foundation platform be located at the upper connection bottom Seat, it is lower connection pedestal, separate seat outer fix at.
As a further solution of the present invention: the vertical flexible anchoring connector and horizontal flexibility anchor connector structure It is identical, including spring support and longitudinal spring steel seat in spring support lateral out, transverse direction, wherein the end of the longitudinal spring steel seat Portion's fixation is set in the transverse direction in spring support, and spring support is fixed in the transverse direction is set in the spring support lateral out.
As a further solution of the present invention: arranging plate at the top of the primary tank hangs top plate and passes through a plurality of stainless steel band steel It is reliably connected with secondary container top radial girders, ten layers of glass fibre cotton, every layer of glass fibre is laid on the outstanding top plate Cotton is with a thickness of mm.
As a further solution of the present invention: being additionally provided with levelling insulation between the bottom and foundation platform of the primary tank It is provided with outstanding top plate at the top of layer and insulation backplane level, primary tank and secondary container, and is set at the top of the primary tank and time container It setsShower water fire plant and dry powder extinguishing installation.
As a further solution of the present invention: primary tank bottom plate combines bearing structure with center plate using annular edge listrium, Margin plate uses butt welding, and center plate uses overlap welding;It is laid with layer glass fibre cotton on outstanding top plate, to keep at the top of primary tank There is good heat-insulating property in spatial dimension;Four sets of setting outstanding top ventholes on outstanding top plate, for balancing inside primary tank It is balanced with the gaseous pressure in space on outstanding top;A set of people's row hole is also set up on outstanding top plate, is passed through for primary tank ladder outstanding Personnel when top are current;Multi-turn reinforcing rib is arranged in outstanding top plate.
As a further solution of the present invention: the bottom plate of secondary container combines pressure-bearing knot with center plate using annular edge listrium Structure, margin plate use butt welding, and center plate uses overlap welding;
The anchor of primary tank is root, and the anchor of secondary container is root;
Main operation platform is arranged in tank top, and the centralized configuration such as external valve, on the spot display instrument is on main platform.
Compared with prior art, the beneficial effects of the present invention are:
(1) primary tank cylinder of the invention is designed using not uniform thickness, and the reinforcement of multi-turn reinforcing rib is arranged, and top stiffener is adopted With T-shaped structure, T-shaped structure guarantees that rigidity prevents unstability under negative pressure condition, moreover, the different T-shaped structure of development length can protect The more preferably regular arrangement of pearlife is demonstrate,proved, even if there is the oscillation such as earthquake, what pearlife will not be excessive to primary tank cylinder is lateral Extruding force improves the force stability of primary tank cylinder, meanwhile, combined type flexible elastic layer can be used for buffering pearlife side pressure Power guarantees that primary tank and time container interlayer annular space fill closely knit pearlife for completely cutting off primary tank sidewall direction cooling capacity Transmitting;
(2) using the composite structure of flat casing when anchor of the present invention is across hot angle protection bottom plate, subtract to greatest extent The small stress that hot angle protective layer bottom plate is transmitted to by anchor, the setting of wedge groove and wedge-shaped heat-insulating plug, can reduce anchor The heat transfer property of bar improves hot angle protective value;
(3) hot angle of the invention protection component is attached using connection compensation component, even if occurring leaking and temperature occur Difference transformation, it may have heat-blocking action and can be carried out under the stress of the temperature difference it is deformation-compensated, to reduce to secondary shell The stress influence of junction is installed.
(4) 10 layers of glass fibre cotton are laid on outstanding top plate of the invention, glass fibre cotton thickness in monolayer cannot be less than 100mm, within the scope of the overall thickness after the completion of being laid with is 800mm-1000mm, to keep that there is good insulation at the top of primary tank Performance;
(5) the primary tank vertical ladder from primary tank bottom to main operation platform is arranged in storage tank of the invention, facilitate installation and Maintenance uses.Storage tank is provided with from ground to the tower of secondary container top ladder, and personnel's passage is easy for going up and down, and can be tank top work Skill pipeline provides support down toward lower part process duct corridor.A set of emergency evacuation escape respectively is additionally provided in secondary container simultaneously Directly climb cage ladder.
Shower water fire plant and dry powder extinguishing installation is arranged in tank top
Detailed description of the invention
Fig. 1 is a kind of overall structure diagram of Large LNG bimetallic full-capacity tank;
Fig. 2 is a kind of arragement construction schematic diagram of the reinforcing rib of T-shaped structure in Large LNG bimetallic full-capacity tank;
Fig. 3 is a kind of structural schematic diagram of the hot angle protection component in Large LNG bimetallic full-capacity tank.
Fig. 4 is vertical flexible anchoring connector or horizontal flexibility anchor connection in a kind of Large LNG bimetallic full-capacity tank The structural schematic diagram of part;
Fig. 5 is a kind of vertical view schematic cross-sectional view of the anchoring insulating assembly of Large LNG bimetallic full-capacity tank;
Fig. 6 is a kind of schematic diagram of main cross-sectional structure of the anchoring insulating assembly of Large LNG bimetallic full-capacity tank;
Specific embodiment
Please refer to Fig. 1~6, in the embodiment of the present invention, a kind of Large LNG bimetallic full-capacity tank, including it is primary tank 15, secondary Container 16, foundation platform 2, hot angle protection component, anchor 11 and anchoring insulating assembly, wherein tank foundation of the invention Using overhead type, whole equipment is located on overhead flat foundation platform, and the primary tank 15, secondary container 16 support It is arranged on the foundation platform 2, and foundation platform 2 is arranged on mattess 1 using the more supports of pillar 3, it is desirable that high Minimum constructive height difference between posture slab-foundation and ground is 800mm, to keep Equipment Foundations gravity-flow ventilation and good damp proof insulation Effect;
The primary tank is self-support type, steel, open top, the single wall tank for not storing product boil-off gas, primary tank Entirely on located bottom thermal insulation layer, the interlayer space width with secondary chamber wall is 1200mm, and interlayer space is filled closely knit Pearlife, to keep storage tank that there is good heat-insulating property;Whole circle suspension a layer thickness is 150mm on primary tank cylinder siding Cylinder elastic cotton, to absorb primary tank side wall pearlife during first pre-cooling, equipment rise again (storage tank safety inspection etc.) To the lateral compression power of primary tank cylinder, the secondary container is to have vaulted self-support type, steel, closed storage tank, top Frame structure using radial girders and circumferential beam composition band rib structure, entire vessel top cover board be laid on top frame structure it On;Secondary container as the main boil-off gas container of storage, and supports the heat insulation layer material of primary tank under primary tank normal operating condition Material;Under the operating condition of primary tank leakage, whole LNG of leakage can be stored, and keep the air-tightness in structure, can be arranged Gas;Secondary shell setting multiple tracks reinforcing rib structure is reinforced, to guarantee to bear enough pressure and keep the stabilization of structure Property;Bottom plate combines bearing structure with center plate using annular edge listrium, and margin plate uses butt welding, and center plate uses overlap welding.
Interlayer space, interlayer are provided between the primary tank cylinder 4 of the primary tank and the secondary shell 5 of secondary chamber wall Space interior fills closely knit pearlife 6, and the primary tank cylinder 4 is arranged multi-turn reinforcing rib and reinforces, and top reinforcing rib 18 uses T Shape structure, T-shaped structure guarantee that rigidity prevents unstability under negative pressure condition;And as shown in Fig. 2, it is in the reinforcement of the T-shaped structure of top The distance for extending 4 outer wall of primary tank cylinder of muscle 18 is greater than the reinforcing rib of the T-shaped structure being below adjacent thereto 18 distance for extending 4 outer wall of primary tank cylinder;And the end face of the reinforcing rib 18 of the T-shaped structure of the top is just Abut the inner wall of the secondary shell 5.
Multi-turn is additionally provided between the external wall of upper portion of the primary tank cylinder 4 and the upper inside wall of the secondary shell 5 Spaced apart combined type flexible elastic layer 17, the combined type flexible elastic layer 17 are followed successively by cotton by primary tank outer wall outward Cloth, elastic cotton, cotton, glass wool cloth, for buffering pearlife lateral pressure, primary tank and time container interlayer annular space filling are close Real pearlife is used to completely cut off the transmitting of primary tank sidewall direction cooling capacity;
The primary tank 15, secondary container 16 bottom and the foundation platform 2 between be additionally provided with insulation support component;
The main function of the hot angle protection of hot angle protection component is additionally provided between the primary tank 15 and secondary container 16 Be leakage LNG when primary tank leaks, in bottom space cannot directly with secondary shell bottom and the direct phase of bottom plate Contact, also, leakage causes the temperature difference larger so that when stress occurs in time container, can weaken the influence of this rigid stress.
The primary tank 15, secondary container 16 bottom be all made of 11 anchor connection of anchor on the foundation platform 2, And the anchor is passed down through at the position of the hot angle protection bottom plate of the hot angle protection component that be also arranged with anchoring heat-insulated Component, to maximally reduce the stress for being transmitted to hot angle protective layer bottom plate by anchor.
In the present embodiment, the anchor uses anchor rod 33, wherein the anchoring insulating assembly includes flat set Pipe 32, collet 34 and heat-insulating plug 35, wherein the flat casing 32 is oval structure, and the ratio between elliptical long axis and short axle More than or equal to three, the anchor rod 33 is located at the center of the flat casing 32, and the flat casing 32 and the anchor Filling is sealed with collet 34 between solid rod, and multiple spaced apart wedge grooves are provided in the axial direction of the anchor rod 33, and Radially interlaced arrangement of each wedge groove in the anchor rod;Heat-insulating plug 35, and the wedge are filled in the wedge groove 35 Shape slot 35 is located at the radially inner side of the anchor rod for wedge-shaped big end, and radial outside is wedge-shaped small end, passes through the wedge groove 35 And the setting of the heat-insulating plug of wedge structure, the heat transfer property of the anchor rod is reduced, and guarantee anchoring property.The hot angle is protected Protecting assembly includes hot angle protection siding 19, hot angle protection bottom plate 21, hot angle protection top plate, foam glass brick 20 and connection compensation group Part, wherein the hot angle protection siding 19 is connected to the inner wall of the secondary shell 5 using the foam glass brick 20 support On, the bottom of the hot angle protection siding 19 is also connected with hot angle protection bottom plate 21, and the top of the hot angle protection siding 19 is set It is equipped with the hot angle protection top plate, and the low temperature glue of brushing between layers of foam glass brick 20 is as binder, hot angle protection The glass fibre cotton after compressing with a thickness of 50mm is also filled up in top plate, 19 and of siding is protected at the hot angle protection bottom plate 21, hot angle The bottom of secondary shell 5 is arranged in the connection compensation component, and the connection compensation component has heat-blocking action and can Carried out under the stress of the temperature difference it is deformation-compensated, so as to reduce to secondary shell 5 installation junction stress influence.Foam glass Glass brick one protects the plate of shell portion to provide support force for hot angle, and the two utilizes its lower thermal coefficient, prevents in master The big angle position while welding of time shell and bottom plate is transmitted to when container leaks by secondary container siding cooling capacity, so that big angle Weld seam bears huge thermal (temperature difference) stress;Hot angle protection bottom plate is used to contain the leakage LNG of bottom, hot angle protection bottom plate and time container The cooling capacity transmitting that multi-layered foamed glass block is used to completely cut off lower part is laid in floor space, to guarantee that time lower vessel portion is in higher Temperature avoids tank foundation and bears influence of the low temperature to its performance.
Specifically, the connection compensation component includes heat insulation pedestal 22, upper connection pedestal 23, lower connection pedestal such as Fig. 3-4 24, separate seat 25, levelling seat, concrete support seat 26 and vertical flexible anchoring connector 27 and horizontal flexibility anchor connector 28, wherein the hot angle protection bottom plate 21, hot angle protect the bottom of siding 19, primary tank cylinder 4 to be mounted on the heat insulation pedestal On 22, the heat insulation pedestal 22 is fixedly connected on the upper connection pedestal 23 of its bottom, and the lower part of upper connection pedestal 23 uses institute It states a separate seat 25 and is connected with lower connection pedestal 24, the bottom of the lower connection pedestal 24 is mounted on concrete support by levelling seat On seat 26, the surrounding of the concrete support seat 26 is fixed on insulation pedestal using horizontal flexibility anchor connector 28, described Insulation pedestal is fixed on foundation platform 2, the upper connection pedestal 23, separate seat 25, lower connection pedestal 24, concrete support seat It is connected with vertical flexible anchoring connector 27 between 26, passes through the vertical flexible anchoring connector 27 and horizontal flexibility anchor Be connected fitting 28 realize to the compensation between primary tank cylinder 4 and secondary shell 5 can Light deformation connect, the secondary shell 5 using rigid holder it is fixed be anchored at foundation platform 2 be located at the upper connection pedestal 23, lower connection pedestal 24, separate seat 25 At outer fix.
The vertical flexible anchoring connector 27 is identical with 28 structure of horizontal flexibility anchor connector, including bullet lateral out Property seat 30, spring support 29 and longitudinal spring steel seat 31 in transverse direction, wherein the end fixation of the longitudinal spring steel seat 31 is set in Spring support 29 is fixed in the transverse direction in spring support 29, in the transverse direction is set in the spring support 30 lateral out.
The operating condition prime design requirement to be met, storage tank primary tank, secondary container and heat are operated according to bimetallic full appearance tank Angle protection materials select low temperature resistant austenitic stainless steel S30408, by GB24511-2009 " bearing device stainless-steel sheet And steel band " standard requirements are supplied with solution heat-treated condition., surface processing type is 1D.Steel plate must not have layering, and surface must not There is the defects of crackle, bubble, be mingled with, stammer.
Arranging plate 10 at the top of the primary tank hangs top plate 10 and passes through a plurality of stainless steel band steel 12 and time container top radial girders It is reliably connected, ten layers of glass fibre cotton 7 is laid on the outstanding top plate, every layer of glass fibre cotton 7 is with a thickness of 100mm.Institute It states and is additionally provided with levelling heat insulation layer 8 and insulation backplane level 9, primary tank and time container between the bottom of primary tank and foundation platform 2 Top be provided with outstanding top plate 13, and the top of the primary tank and time container settingShower water fire plant and dry-chemical fire extinguishing Device.Primary tank bottom plate combines bearing structure with center plate using annular edge listrium, and margin plate uses butt welding, and center plate uses Overlap welding;10 layers of glass fibre cotton are laid on outstanding top plate, to keep that there is good insulation within the scope of primary tank headspace Performance;Four sets of setting outstanding top ventholes on outstanding top plate, for balancing the gaseous pressure inside primary tank with space on outstanding top Balance;A set of people's row hole is also set up on outstanding top plate, personnel when passing through outstanding top for primary tank ladder are current;Outstanding top plate setting Multi-turn reinforcing rib.The bottom plate of secondary container combines bearing structure with center plate using annular edge listrium, and margin plate uses butt welding, in Former uses overlap welding;The anchor of primary tank is 56, and the anchor of secondary container is 72;Main behaviour is arranged in tank top Make platform, the centralized configuration such as external valve, on the spot display instrument is on main platform.
For equipment cryogenic piping material selection, equipment low temperature liquid phase, gas phase pipeline are (to interface point on outstanding top plate Within, containing hot angle protection pressure-equalizing pipe and hot angle protection interlayer space nitrogen purging inlet/outlet pipe etc.), material uses low temperature Seamless steel pipe, material selection S30408, execution standard are GB/T14976-2012 " fluid conveying stainless-steel seamless pipe ".It is right For the selection of equipment room temperature tube material, normal temperature pipeline uses carbon steel material, material 20#, and execution standard is GB/T8163- 2008 " seamless steel tubes for liquid service ", pipe fitting use 20# material, executions standard for GB/T12459-2005 " steel butt without Slit-tube part ".
Primary tank, secondary lower vessel portion surrounding have been uniformly arranged anchor, and primary tank is 56, and secondary container is 72, and It is reliably connected with the pre-buried anchor in basis, is anchored on primary tank, secondary container on tank foundation cushion cap, to prevent from setting It is standby to generate inclination under the action of service load and external force (such as wind load, seismic (seismal) and promoted.
For bottom thermal insulation layer, the foam glass brick conduct of ZES-800 type is laid between primary tank bottom plate and secondary container floor Bottom thermal insulation layer and the weight for bearing primary tank and medium, the big annular region of pressure-bearing immediately below primary tank barrel use pearl Light sand reinforced concrete circle beam (reinforcing bar requires to be stainless steel) carrys out distribution load, and concrete collar tie beam lower part is high using ZES-1200 type Density foam glass brick.
In addition, equipment of the invention is provided with more set pearlife charging ports in secondary container top, filled for pearlife.Storage Main operation platform is arranged in tank top, and the centralized configuration such as external valve, on the spot display instrument is on main platform, safe operation side Just.Safety relief operating platform is set in tank top leeward band range, storage tank breather valve, the outlet of nitrogen purging etc. are all set in It releases on platform, avoids top operator contact discharge gas for a long time, improve the safe operation of tank top.Storage tank Primary tank vertical ladder from primary tank bottom to main operation platform is set, and be easy to install and maintain use.Storage tank is provided with from ground To the tower ladder of secondary container top, personnel's passage is easy for going up and down, and can be tank top process pipe down toward lower part technique piping lane in face Frame provides support.A set of emergency evacuation escape respectively, which is additionally provided with, in secondary container simultaneously directly climbs cage ladder.
In addition, the invention also includes storage pressure control system, feed liquor system, pre-cooling pipeline, charging system, purging systems System, wherein the LNG liquefied natural gas sent from liquefying plant area is sent into through PIR (polyisocyanurate foam) cold insulation pipeline 100003The storage of LNG bimetallic full appearance tank, liquefied natural gas (LNG) are sent through the built-in low temperature immersed pump pipeline of storage tank to entrucking position Entrucking is taken out.In storage pressure control system, equipment is provided with 1 road DN100 and mends pipeline, and tonifying Qi gas source is pipe network natural gas;Top 1 road DN250BOG pipeline is arranged in portion;With each three sets of DN300 outlet valves;Mating two sets of DN300 inlet valves.
For feed liquor system, the liquefied natural gas sent from liquefying plant is sent into through DN150PIR cold insulation pipeline 10000m3The storage of LNG bimetallic full appearance tank can pass through top feed liquor pipeline or bottom liquid inlet pipeline feed liquor, bottom liquid inlet setting Long-range control DN150 quick action emergency valve, the long-range control DN150 quick action emergency valve of top feed liquor setting, for the tight of storage tank feed liquor Anxious long-range control.If respectively jacking liquid and the foundation of bottom liquid inlet switching are during normal operation: feed liquor material LNG similar density When, select bottom liquid inlet;When storage tank storage LNG density is greater than feed liquor material LNG density, bottom liquid inlet is selected;When storage tank stores up When depositing LNG density less than feed liquor material LNG density, top feed liquor is selected.
Storage tank setting is installed on setting band nozzle-type below outstanding top plate and pipeline is pre-chilled.Storage tank pre-cooling uses liquid nitrogen medium, liquid Nitrogen pre-cooling tank car access point is located at feed liquor house steward, and setting root valve prevents pre-cooling liquid nitrogen medium from flowing to ice chest workshop section certainly.
For charging system, 2 200m are arranged in storage tank3The built-in low temperature immersed pump (the using and the reserved) of/h, immersed pump drain Using pump plunger shaft pipe, liquid process duct of running on pump plunger shaft pipe, pipe diameter DN200, using PIR cold insulation, after 2 sets of drain pipes summarize Long-range control quick action emergency valve is set on general pipeline.
Reflux pipeline after immersed pump pumps is set on liquid header, and pipe diameter DN100 is used for storage tank using PIR cold insulation Liquid circulation during storage is equipped with Remote control valve on return pipe after pump.
For purge system, the Room-temperature low-pressure nitrogen that process unit area is sent be set the purging endless tube line in primary tank into Enter primary tank, enter tank bottom aster thermosphere through bottom thermal insulation layer nitrogen purge line, enters latent liquid through immersed pump blow line Pump sump is pumped, guarantees the air displacement in each corner of storage tank and the drying of internal insulation material.
In secondary container top setting nitrogen purging exhaust line, primary tank and hot angle protection bottom thermal insulation layer setting two all the way Road purges exhaust pipe and ring row tracheae all the way, the discharge of displaced air when for purging is arranged in interlayer space.It is protected at hot angle 1 road nitrogen purging inlet tube is arranged in heat insulation layer between shield and secondary container floor and 2 road nitrogen purge outlet, in the space Medium purging displacement.
In addition, in the present embodiment, in equipment instrument control parameter setting, with 10000m3(the design of LNG bimetallic full appearance tank Pressure: 25KPa designs liquid level: 21200mm) for:
(1) container gaseous pressure
3 sets of independently operated pressure transmitters are arranged for gaseous pressure detection and 1 set shows pressure gauge on the spot.Control system connects It collects mail and the control such as number is alarmed, is chain.
Storage pressure: 0-25KPa, analog signal;;
Pressure alarm (PAH): > 20KPa;High alarm interlocking (PAHH): the 22KPa of pressure
The low alarm of pressure interlocks (PAL): 8KPa;The low alarm of pressure interlocks (PALL): 2KPa
(2) tank level
2 sets of servo liquidometers (a wherein cuff Density Detection function) and 1 set of multi-point average thermometer is arranged in storage tank, needs Data are transmitted in complete offer intelligent temperature selection with servo liquidometer in real time, then complete Density Detection function by communication interface unit Energy.Carrying out filling tank when crossing high liquid level may cause liquid spilling, to ensure to fill safely tank and preventing the tank that overflows, with 1 radar level It counts to guarantee the reliable of high liquid level and low liquid level detection information, tank speed and monitoring high limit liquid is filled with effective monitoring storage tank Position.When detection liquid level reaches 20700mm, high liquid level warning (LAH);When liquid level reaches 21200mm, high high liquid level warning (LAHH), the quick action emergency valve interlocked in feed liquor pipeline system is closed, and feed liquor is stopped;It is low when detection liquid level reaches 1300mm Liquid level warning (LAL);Liquid level reaches 800mm, and low low liquid level warning (LSLL) interlocks the emergency cut-off in positive displacement pump pipeline system Valve is closed, and drain is stopped.
(3) temperature display
TE176f013-22 primary tank wall temperature monitoring: -200-+50 DEG C;Digital signal
TE176f027-33 primary tank baseplate temp monitoring: -200-+50 DEG C;Digital signal
TE176f023-26 interlayer monitoring temperature: -200-+60 DEG C;Digital signal
All temperature signals uniformly summarize to tank deck explosion-proof wiring box, by owner by all temperature teletransmissions out of this junction box Signal is sent to DCS.
In the present invention, storage tank superpressure security protection scheme is as follows:
(1) LNG storage tank BOG is discharged
When gaseous pressure rising reaches 18KPa in storage tank, low temperature pneumatic control valve is opened, and BOG pipeline is connected to gas row It puts, BOG compressor operating, extracts storage tank BOG over-pressure gas.When pressure of storage tank is down to 15KPa, low temperature pneumatic control valve is complete It closes.
(2) storage tank expiration scheme
Two outlet valves of configuration of storage tanks are dual-purpose one for state.When gaseous pressure reaches 24KPa, outlet valve is opened, warp Valve rear line is emitted into atmosphere.
(3) storage tank low-voltage safety protectiving scheme
Storage tank tonifying Qi scheme: when pressure of storage tank is down to 5KPa, tonifying Qi pipeline control valve is opened to 100%, into storage tank Portion's tonifying Qi, until storage tank completely closes after boosting to 10KPa.
The anti-negative pressure scheme of storage tank: two sets of inlet valves of configuration of storage tanks are the using and the reserved state.When storage tank gaseous pressure reaches- When 0.3KPa, inlet valve air-breathing guarantees storage tank safety.
(4) Requirements of Nondestructive Testing: storage tank primary tank, secondary container direct tube section butt welded joint must do 100% ray Flaw detection, transillumination quality are not less than AB grades, and meeting NB/T47013.2-2015, " pressure-bearing sets each non-destructive testing part 2: ray inspection Survey " provide that II grades are qualified.Bottom plate, top cover lap weld, the protection butt weld of hot angle are both needed to do 100%PT detection, meet NB/ The qualified hot angle protection weld seam of T47013.5-2015 " pressure-bearing sets each the 5th part of non-destructive testing: Liquid penetrant testing " regulation grade, bottom plate are taken Using the progress leak test of vacuum leakage test method, vacuum tank negative pressure is not less than for welding seam and cylinder and bottom plate corner connection welding point 55KPa, welding point must not leak.Storage tank time container butt welded joint is executed referring to GB26978-2011.Bottom plate overlap welding Using the progress leak test of vacuum leakage test method, vacuum tank negative pressure is not less than 55KPa for seam and cylinder and bottom plate corner connection welding point, Welding point must not leak.
(5) pipeline testing requirements: all butt welded joints do 100% radiographic inspection and meet NB/T47013,2-2015 " bearing device non-destructive testing part 2: ray detection " provides that II grades are qualified.Fillet welding joint press NB/T47013,52015 " the 5th part of bearing device non-destructive testing: Liquid penetrant testing " 100%PT flaw detection, I grades are qualification
(6) pressure testing primary tank strength test: 12720mmH2O+31.25kPa holds pressure 1h ne-leakage, deformation without exception;
Secondary container air-tightness test: 25kPa holds pressure 24 ne-leakages, deformation without exception.
It is above-described, it is merely preferred embodiments of the present invention, but protection scope of the present invention is not limited to This, anyone skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention And its inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.

Claims (10)

1. a kind of Large LNG bimetallic full-capacity tank, including primary tank (15), secondary container (16), foundation platform (2), hot angle guarantor Protecting assembly, anchor (11) and anchoring insulating assembly, wherein the primary tank (15), secondary container (16) support setting to exist On the foundation platform (2), and foundation platform (2) is arranged on mattess (1) using more pillar (3) supports, so as to So that the minimum constructive height difference between the foundation platform (2) and ground is 800mm;
The primary tank is self-support type, steel, open top, the single wall tank for not storing product boil-off gas, the secondary container To have vaulted self-support type, steel, closed storage tank, time of the primary tank cylinder (4) of the primary tank and time chamber wall It is provided with interlayer space between shell (5), fills closely knit pearlife (6) inside interlayer space, which is characterized in that
The primary tank cylinder (4) is designed using not uniform thickness, and the reinforcement of multi-turn reinforcing rib is arranged, and top reinforcing rib (18) uses T Shape structure guarantees that rigidity prevents unstability under negative pressure condition;And
The distance for extending primary tank cylinder (4) outer wall of the reinforcing rib (18) of T-shaped structure in top is greater than therewith The distance for extending primary tank cylinder (4) outer wall of the reinforcing rib (18) of the adjacent T-shaped structure being below;And it is most upper The end face of the reinforcing rib (18) of the T-shaped structure of side just abuts the inner wall of the secondary shell (5);And
Multi-turn is additionally provided between the external wall of upper portion of the primary tank cylinder (4) and the upper inside wall of the secondary shell (5) Spaced apart combined type flexible elastic layer (17), for buffering pearlife lateral pressure;
The primary tank (15), secondary container (16) bottom and the foundation platform (2) between be additionally provided with insulation support component;
The hot angle protection component is additionally provided between the primary tank (15) and time container (16);
The primary tank (15), secondary container (16) bottom be all made of anchor (11) anchor connection in the foundation platform (2) on, and the anchor is passed down through at the position of the hot angle protection bottom plate of the hot angle protection component and is also arranged with anchor Gu insulating assembly, to maximally reduce the stress for being transmitted to hot angle protective layer bottom plate by anchor.
2. a kind of Large LNG bimetallic full-capacity tank according to claim 1, which is characterized in that the anchor is adopted With anchor rod (33), wherein the anchoring insulating assembly includes flat casing (32), collet (34) and heat-insulating plug (35), In, the flat casing (32) is oval structure, and the ratio between elliptical long axis and short axle are more than or equal to three, the anchor rod (33) Positioned at the center of the flat casing (32), and between the flat casing (32) and the anchor rod filling be sealed with every Hot jacket (34) is provided with multiple spaced apart wedge grooves in the axial direction of the anchor rod (33), and each wedge groove is described The radially interlaced arrangement of anchor rod;Heat-insulating plug (35) are filled in the wedge groove (35), and the wedge groove (35) is located at The radially inner side of the anchor rod is wedge-shaped big end, and radial outside is wedge-shaped small end, passes through the wedge groove (35) and wedge shape The setting of the heat-insulating plug of structure, reduces the heat transfer property of the anchor rod, and guarantees anchoring property.
3. a kind of Large LNG bimetallic full-capacity tank according to claim 1, which is characterized in that the combined type flexible Elastic layer (17) is followed successively by cotton, elastic cotton, cotton, glass wool cloth by primary tank outer wall outward.
4. a kind of Large LNG bimetallic full-capacity tank according to claim 1, which is characterized in that the hot angle protection group Part includes hot angle protection siding (19), hot angle protection bottom plate (21), hot angle protection top plate, foam glass brick (20) and connection compensation Component, wherein hot angle protection siding (19) is connected to the secondary shell using the foam glass brick (20) support (5) on inner wall, the bottom of hot angle protection siding (19) is also connected with hot angle protection bottom plate (21), the hot angle protective bulkhead The hot angle protection top plate, and the low temperature glue conduct of brushing between layers of foam glass brick (20) are provided at the top of plate (19) Binder, also fills up the glass fibre cotton after compression with a thickness of 50mm in hot angle protection top plate, hot angle protection bottom plate (21), The bottom of hot angle protection siding (19) and time shell (5) is arranged in the connection compensation component, the connection compensation group Part have heat-blocking action and can be carried out under the stress of the temperature difference it is deformation-compensated, to reduce the installation to secondary shell (5) The stress influence of junction.
5. a kind of Large LNG bimetallic full-capacity tank according to claim 4, which is characterized in that the connection compensation group Part includes heat insulation pedestal (22), upper connection pedestal (23), lower connection pedestal (24), separate seat (25), levelling seat, concrete support Seat (26) and vertical flexible anchoring connector (27) and horizontal flexibility anchor connector (28), wherein protect bottom plate in the hot angle (21), hot angle protects the bottom of siding (19), primary tank cylinder (4) to be mounted on the heat insulation pedestal (22), the heat-insulated bottom Seat (22) is fixedly connected on the upper connection pedestal (23) of its bottom, separate seat between the lower part use of upper connection pedestal (23) is described (25) it is connected with lower connection pedestal (24), the bottom of lower connection pedestal (24) is mounted on concrete support seat by levelling seat (26) on, the surrounding of the concrete support seat (26) is fixed on insulation pedestal using horizontal flexibility anchor connector (28), The insulation pedestal is fixed on foundation platform (2), the upper connection pedestal (23), separate seat (25), lower connection pedestal (24), It is connected with vertical flexible anchoring connector (27) between concrete support seat (26), is connected by the vertical flexible anchoring Part (27) and horizontal flexibility anchor connector (28) are realized can to the compensation between primary tank cylinder (4) and time shell (5) Light deformation connection, the secondary shell (5) using rigid holder it is fixed be anchored at foundation platform (2) be located at the upper connection bottom Seat (23), it is lower connection pedestal (24), separate seat (25) outer fix at.
6. a kind of Large LNG bimetallic full-capacity tank according to claim 5, which is characterized in that the vertical flexible anchor Connected fitting (27) are identical with horizontal flexibility anchor connector (28) structure, including bullet in spring support (30) lateral out, transverse direction Property seat (29) and longitudinal spring steel seat (31), wherein the end fixation of the longitudinal spring steel seat (31) is set in the transverse direction Spring support (29) is fixed in interior spring support (29), in the transverse direction is set in the spring support (30) lateral out.
7. a kind of Large LNG bimetallic full-capacity tank according to claim 6, which is characterized in that at the top of the primary tank Arranging plate (10), outstanding top plate (10) are reliably connected by a plurality of stainless steel band steel (12) and time container top radial girders, described outstanding Ten layers of glass fibre cotton (7) are laid on top plate, every layer of glass fibre cotton (7) is with a thickness of 100mm.
8. a kind of Large LNG bimetallic full-capacity tank according to claim 7, which is characterized in that the bottom of the primary tank Levelling heat insulation layer (8) and insulation backplane level (9), the top of primary tank and time container are additionally provided between portion and foundation platform (2) It is provided with outstanding top plate (13), and the setting of the top of the primary tank and time containerShower water fire plant and dry-chemical fire extinguishing dress It sets.
9. a kind of Large LNG bimetallic full-capacity tank according to claim 7, which is characterized in that primary tank bottom plate uses Annular edge listrium combines bearing structure with center plate, and margin plate uses butt welding, and center plate uses overlap welding;The upper berth of outstanding top plate If 10 layers of glass fibre cotton, to keep that there is good heat-insulating property within the scope of primary tank headspace;It is arranged on outstanding top plate Four sets of outstanding top ventholes are balanced for balancing the gaseous pressure inside primary tank with space on outstanding top;It is also set on outstanding top plate A set of people's row hole is set, personnel when passing through outstanding top for primary tank ladder are current;Multi-turn reinforcing rib is arranged in outstanding top plate.
10. a kind of Large LNG bimetallic full-capacity tank according to claim 7, which is characterized in that the bottom plate of secondary container is adopted Bearing structure is combined with center plate with annular edge listrium, margin plate uses butt welding, and center plate uses overlap welding;
The anchor of primary tank is 56, and the anchor of secondary container is 72;
Main operation platform is arranged in tank top, and the centralized configuration such as external valve, on the spot display instrument is on main platform.
CN201910083117.3A 2019-01-28 2019-01-28 Large-scale bimetal full-capacity LNG storage tank Active CN109827067B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910083117.3A CN109827067B (en) 2019-01-28 2019-01-28 Large-scale bimetal full-capacity LNG storage tank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910083117.3A CN109827067B (en) 2019-01-28 2019-01-28 Large-scale bimetal full-capacity LNG storage tank

Publications (2)

Publication Number Publication Date
CN109827067A true CN109827067A (en) 2019-05-31
CN109827067B CN109827067B (en) 2020-08-21

Family

ID=66862684

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910083117.3A Active CN109827067B (en) 2019-01-28 2019-01-28 Large-scale bimetal full-capacity LNG storage tank

Country Status (1)

Country Link
CN (1) CN109827067B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112460470A (en) * 2019-09-09 2021-03-09 张家港中集圣达因低温装备有限公司 Vertical low-temperature storage tank
CN113198891A (en) * 2021-05-28 2021-08-03 中山精达特克机械有限公司 Pipe bending machine

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5455548A (en) * 1994-02-28 1995-10-03 General Signal Corporation Broadband rigid coaxial transmission line
CN104695438A (en) * 2015-03-09 2015-06-10 淮安信息职业技术学院 Ground anchor pull rod structure and machining method thereof
US9140001B1 (en) * 2014-06-24 2015-09-22 Columbia Insurance Company Thermal wall anchor
CN205101860U (en) * 2015-11-03 2016-03-23 张家港中集圣达因低温装备有限公司 Metal contains storage tank entirely with protection of hot angle
CN106641692A (en) * 2015-11-03 2017-05-10 张家港中集圣达因低温装备有限公司 Metal full-volume storage tank with secondary container protecting layer
US20170342707A1 (en) * 2015-12-04 2017-11-30 Columbia Insurance Company Thermal wall anchor
CN207112349U (en) * 2017-08-29 2018-03-16 张家港中集圣达因低温装备有限公司 low-temperature storage tank

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5455548A (en) * 1994-02-28 1995-10-03 General Signal Corporation Broadband rigid coaxial transmission line
US9140001B1 (en) * 2014-06-24 2015-09-22 Columbia Insurance Company Thermal wall anchor
CN104695438A (en) * 2015-03-09 2015-06-10 淮安信息职业技术学院 Ground anchor pull rod structure and machining method thereof
CN205101860U (en) * 2015-11-03 2016-03-23 张家港中集圣达因低温装备有限公司 Metal contains storage tank entirely with protection of hot angle
CN106641692A (en) * 2015-11-03 2017-05-10 张家港中集圣达因低温装备有限公司 Metal full-volume storage tank with secondary container protecting layer
US20170342707A1 (en) * 2015-12-04 2017-11-30 Columbia Insurance Company Thermal wall anchor
CN207112349U (en) * 2017-08-29 2018-03-16 张家港中集圣达因低温装备有限公司 low-temperature storage tank

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112460470A (en) * 2019-09-09 2021-03-09 张家港中集圣达因低温装备有限公司 Vertical low-temperature storage tank
CN112460470B (en) * 2019-09-09 2024-05-14 张家港中集圣达因低温装备有限公司 Vertical low-temperature storage tank
CN113198891A (en) * 2021-05-28 2021-08-03 中山精达特克机械有限公司 Pipe bending machine
CN113198891B (en) * 2021-05-28 2024-05-28 中山精达特克机械有限公司 Pipe bending machine

Also Published As

Publication number Publication date
CN109827067B (en) 2020-08-21

Similar Documents

Publication Publication Date Title
CN103162085B (en) Self-supporting type LNG (Liquefied Natural Gas) storage tank
CN203240268U (en) Self-support type LNG (Liquefied Natural Gas) storage tank
US20120132656A1 (en) Device for storing gas under pressure
Yang et al. Development of the world’s largest above-ground full containment LNG storage tank
CN108061242A (en) A kind of air hermetic whole concrete LNG full-capacity tanks
CN202171122U (en) Double-curvature steel inner tank body and cold insulation structure of large LNG storage tank
CN109827067A (en) A kind of Large LNG bimetallic full-capacity tank
CN107401677A (en) Pressure of Ambient Temperature stores the earthing formula tank system of Liquefied Hydrocarbon
CN109780416A (en) High-vacuum insulation Double-layer Spherical
JPS6247277B2 (en)
US4151689A (en) Nuclear engineering installation
CN211544655U (en) Low-temperature storage device
CN212268413U (en) Hot angle protection structure of low-temperature full-capacity storage tank
CN204387672U (en) Bimetal wall is appearance type low-temperature storage tank hot angle operator guards entirely
CN207471114U (en) High-vacuum insulation Double-layer Spherical
CN214535659U (en) Concrete full-capacity tank
CN205991324U (en) Three-layer metal wall contains storage tank entirely
CN213900703U (en) Liquid nitrogen storage tank
CN107795845A (en) Three-layer metal wall contains storage tank entirely
CN112963724A (en) Concrete full-capacity tank
CN114278859A (en) Vertical film type low-temperature normal-pressure liquid hydrogen storage tank
CN106641692A (en) Metal full-volume storage tank with secondary container protecting layer
CN206545778U (en) A kind of three wall metal atmospheric storage tanks stored for LNG
CN217763032U (en) Full-capacity tank for liquefied gas refrigeration
CN108302320B (en) Low-temp. liquefied gas metal full-containing tank

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220620

Address after: 473300 south section of Jingyi Road, industrial cluster area, Sheqi County, Nanyang City, Henan Province

Patentee after: NANYANG DOER GAS EQUIPMENT CO.,LTD.

Address before: 215100 No.398 Yuhang Road, Xiangcheng District, Suzhou City, Jiangsu Province

Patentee before: SUZHOU DOER GASEOUS CHEMICAL EQUIPMENT CO.,LTD.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220826

Address after: 215100 No.398 Yuhang Road, Xiangcheng District, Suzhou City, Jiangsu Province

Patentee after: SUZHOU DOER GASEOUS CHEMICAL EQUIPMENT CO.,LTD.

Address before: 473300 south section of Jingyi Road, industrial cluster area, Sheqi County, Nanyang City, Henan Province

Patentee before: NANYANG DOER GAS EQUIPMENT CO.,LTD.