CN109811938A - A kind of assembled filling wall, frame system and its engineering method of the connection of track card slot type - Google Patents

A kind of assembled filling wall, frame system and its engineering method of the connection of track card slot type Download PDF

Info

Publication number
CN109811938A
CN109811938A CN201910213197.XA CN201910213197A CN109811938A CN 109811938 A CN109811938 A CN 109811938A CN 201910213197 A CN201910213197 A CN 201910213197A CN 109811938 A CN109811938 A CN 109811938A
Authority
CN
China
Prior art keywords
steel
frame
wall
card slot
assembled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910213197.XA
Other languages
Chinese (zh)
Other versions
CN109811938B (en
Inventor
麻建锁
程元鹏
蔡焕琴
梁玲玉
肜超
阚玥
陈瑞峰
华志岩
董元尚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tangshan Zhuchao New Building Materials Co ltd
Original Assignee
Hebei University of Architecture
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei University of Architecture filed Critical Hebei University of Architecture
Priority to CN201910213197.XA priority Critical patent/CN109811938B/en
Publication of CN109811938A publication Critical patent/CN109811938A/en
Application granted granted Critical
Publication of CN109811938B publication Critical patent/CN109811938B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

A kind of assembled filling wall of track card slot type connection, frame system and its engineering method, it includes rectangular wall body and wall connecting piece that assembled, which fills wall, rectangular wall body includes steel skeleton, insulating layer, reinforced mesh and concrete layer, wall connecting piece includes T steel link block and pre-buried card slot, steel skeleton includes steel frame and lightgage steel joist, insulating layer is embedded between steel frame and preceding lightgage steel joist, reinforced mesh is fixedly connected on the outer surface of lightgage steel joist, concrete layer wraps up the lightgage steel joist and reinforced mesh for pouring every side respectively, T steel link block is embarked on journey between two parties in the uper side surface of top margin frame is aligned interval setting, T steel link block is embedded in pre-buried card slot can opposite sliding along length direction of steel frame or so.The present invention can carry out opposite sliding under geological process, so that prefabricated filling wall can achieve in coming earthquake not to be influenced by seismic force, effectively increase the shock resistance of assembled filled wall system by the type of attachment of change filled wall system.

Description

A kind of assembled filling wall, frame system and its engineering method of the connection of track card slot type
Technical field
The invention belongs to prefabricated member, especially a kind of filling wall of track card slot type connection, frame system and its apply Work method.
Background technique
Frame wall filled with masonry mostly uses some small-sized hollow building blocks or porous brick to be built at present, passes through with main structure A certain number of lacing wire connections, but there are certain defects for this structure.For structure tension performance, due to masonry quality Problem, filling wall overall performance is poor, and under geological process, filling wall is easy to appear the sliding rupture of masonry mortar layer.Meanwhile it building It builds mortar and is easy to appear shrinkage phenomenon during air-dried, cause filled wall that sedimentation occurs and is detached from Vierendeel girder, thus Generate crack.
For structural seismic performance, filling wall and main body frame are rigidly connected, once wall arrangement is improper, just will affect The shock resistance of structure, for example, filling wall be vertically unevenly distributed weighing apparatus if, be easy for that structure is made weak floor occur, if wall water Plain cloth set it is unreasonable if, it is also possible to cause the torque failure of structure.Meanwhile that frame column may be made to be formed is short for the presence for filling wall Column, Vierendeel girder form short beam, form security risk.
From construction, the masonry of building block or brick body is time-consuming and laborious, increases cost of labor, reduces construction efficiency, The requirement of China's architectural industrialization is not met, meanwhile, there are buildings and resources wasting phenomenons in work progress.
For the energy-saving heat preserving angle of wall, existing building block and brick body material cannot reach wall energy-saving heat preserving mostly and want It asks, needs to do external thermal insulation processing in surface of wall, and external thermal insulation, frequently with the inflammable plate such as styrofoam, extruded sheet, building is deposited In fire hazard, security risk is increased.
Summary of the invention
The object of the present invention is to provide a kind of assembleds of track card slot type connection to fill wall, frame system and its engineering method, It solves existing masonry filler wall system sedimentation easily occurs and is detached from Vierendeel girder and generates crack, poor seismic behavior, construction efficiency The technical issues of low, poor thermal insulation property;
To achieve the above object, the present invention adopts the following technical scheme:
A kind of assembled filling wall of track card slot type connection, including rectangular wall body and wall connecting piece, the rectangular wall body packet Steel skeleton, insulating layer, reinforced mesh and concrete layer are included, the wall connecting piece includes T steel link block,
The steel skeleton includes steel frame and lightgage steel joist, and the steel frame is total to twice, including be located at rectangular wall body it is upper, Lower end and the top margin frame and boundary frame area being oppositely arranged, two layers totally of the lightgage steel joist, are divided into the two sides of steel frame, lightgage steel joist Upper surface it is concordant with the upper surface of top margin frame, the lower end surface of lightgage steel joist and the lower end surface of boundary frame area are concordant, the light steel dragon in every side The upper and lower end of bone is fixedly connected with the top margin frame and boundary frame area of the side respectively,
The installation space adaptable with the size of insulating layer, institute are formed between upper and lower twice steel frame and two layers of front and back lightgage steel joist Insulating layer to be stated to be embedded in the installation space, the width of the insulating layer is identical as the length of steel frame,
Two layers totally of the reinforced mesh, be respectively fixedly connected with the outer surface in two layers of lightgage steel joist, the width of reinforced mesh with The length of steel frame is identical, and reinforced mesh upper surface is concordant with the upper surface of top margin frame, reinforced mesh lower end surface and top margin frame Lower end surface is concordant,
Two layers totally of the concrete layer, the lightgage steel joist and reinforced mesh for pouring every side, upper and lower two sides are wrapped up in front and rear sides respectively Top margin frame is wrapped up respectively and boundary frame area forms concrete protective, and the left and right ends and steel frame left and right ends of concrete layer are flat Together,
The T steel link block shares one group, embarks on journey between two parties in the uper side surface of top margin frame and is aligned interval setting, the T steel Link block includes horizonal base plate and riser, and the horizonal base plate is fixedly connected with top margin frame.
The wall connecting piece further includes pre-buried card slot, the number and the number phase of T steel link block of the pre-buried card slot It together and is arranged in a one-to-one correspondence, it further includes that top cross section is that the pre-buried card slot, which includes the slide groove portion that top cross section is inverted U, The preburying part of T-type, the groove body size of the slide groove portion and the size of riser are adapted, along steel side in the riser insertion slide groove portion Length direction of frame or so opposite can slide, and the length of the pre-buried card slot is greater than the length of T steel link block, to guarantee T shape Subject to steel link block will not be skidded off from slide groove portion.
The steel frame is channel steel, and Open Side Down for top margin frame, and the opening upwards of boundary frame area, channel steel includes web and two sides Limb plate, be fixedly connected on the outside of the limb plate of the upper end of the lightgage steel joist and top margin frame, the lower end and bottom edge of the lightgage steel joist It is fixedly connected on the outside of the limb plate of frame, the T steel link block is fixedly connected on web.
Every layer of steel skeleton is in groined type, including twice horizontal keel and twice vertical keel, the length of the horizontal keel Equal to the length of steel frame.
Sliding layer is equipped between the riser and the sliding surface of slide groove portion, the sliding layer is rubber layer.
Hole for hoist is provided on the riser.
A kind of frame system of the assembled filling wall including the connection of track card slot type, further includes being enclosed in rectangular wall body four The frame structure that upper layer Vierendeel girder, lower layer's Vierendeel girder and the frame column of the left and right sides in week are formed,
The rectangular wall body falls the uper side surface set in lower layer's Vierendeel girder, the frame of rectangular wall body and upper layer Vierendeel girder and the left and right sides There are the disengagement gap of at least 60mm between trestle,
The pre-buried card slot is embedded in the bottom of upper layer Vierendeel girder, described to disengage in gap, on the uper side surface of lower layer's Vierendeel girder It is preset with the locating part being located at left and right sides of rectangular wall body, the steel frame end face on the locating part and rectangular wall body or so end face Between by the left and right mounting distance of the fixed rectangular wall body of welding welding plate,
Flexible flame retardant packing material is packed in the disengagement gap.
The locating part is steel billet, and the length of billet is not less than the distance between front and rear sides steel frame.
A kind of construction method of the assembled filling wall of track card slot type connection, which is characterized in that walked including following construction It is rapid:
Step 1 prepares two channel steels as steel frame, the groove body size and heat preservation of channel steel according to the design size of rectangular wall body The thickness of layer is adapted, and the opening direction of two channel steels is opposite, welds lightgage steel joist in the side of steel frame;
Step 2, insulating layer is laid in the steel skeleton in step 1, and insulating layer is embedded between two steel frames up and down against light The surface of steel joist;
Step 3, another layer of lightgage steel joist of the other side welding steel skeleton of steel frame in step 1;
Step 4 welds T steel link block in the upper surface of top margin frame;
Reinforced mesh is respectively welded on the lateral surface of the lightgage steel joist of two sides in step 5;
Step 6, supporting module, casting concrete layer.
A kind of construction method of the frame system of the assembled filling wall of track card slot type connection, including following construction step It is rapid:
Step 1, frame structure of constructing, the preburying part of pre-buried card slot are embedded in the bottom of upper layer Vierendeel girder, the sliding slot of pre-buried card slot The downside surface of upper layer Vierendeel girder is exposed in portion, is fixedly connected with locating part on lower layer's Vierendeel girder;
Step 2, snap the line pop up the position line of assembled filling wall on frame structure inner ring;
Step 3, lifting assembled fill wall, and first assembled filling wall is placed on lower layer's Vierendeel girder, then passes through crowbar etc. Tool manually moves horizontally assembled filling wall, makes the T steel link block and pre-buried card slot on the top of assembled filling wall Slide groove portion is well fitted into;
Step 4 is welded by welding plate between the two sides of the bottom of assembled filling wall exposed steel frame edge and locating part and is connected It connects, fixing assembling formula fills the position of wall;
Step 5 is clogged in the disengagement gap between the frame column that assembled fills wall and upper layer Vierendeel girder, left and right sides flexible Flame resistant filler material;
Step 6 does jointing processing with building sealant in marginal position.
Compared with prior art the invention has the characteristics that and the utility model has the advantages that
The prefabricated filling wall construction of the present invention is simple, and rationally, prefabrication is convenient for construction, has accomplished that structure is heat insulation integrated and keeps the temperature It is functional, while prefabricated filling wall has good globality.The prefabricated filling wall good integrity, construction is rationally simple, Prefabrication is convenient.
The prefabricated filling wall construction system of the present invention uses the form of fabricated construction, compared with existing masonry filler wall, The masonry time has been saved, construction cost has been reduced while guaranteeing wall quality, improves construction efficiency, and improve filling wall The overall performance of system reduces labor intensity of workers, improves architecture quality.
The present invention it is prefabricated filling wall construction system by change filled wall system type of attachment, using T-connecting piece with The cooperation of pre-buried card slot, the two can carry out opposite sliding under geological process, so that prefabricated filling wall can in coming earthquake It is not influenced by seismic force with reaching, prefabricated filling wall can be made not deform with the deformation of frame structure, effectively increase dress Shock resistance with formula filled wall system, accomplish in geological process fill wall do not stress to make fill wall in earthquake from Damage.
It the composite can be widely applied in concrete frame filling wall construction.
Detailed description of the invention
The present invention will be further described in detail with reference to the accompanying drawing.
Fig. 1 is the steel skeleton construction schematic diagram of assembled filling wall of the present invention.
Fig. 2 is the structural schematic diagram that insulating layer and plug-in reinforced mesh are installed in Fig. 1.
Fig. 3 is the structural schematic diagram of assembled filling wall of the present invention.
Fig. 4 is the schematic perspective view of T steel link block of the invention.
Fig. 5 is the schematic perspective view of pre-buried card slot of the invention.
Fig. 6 is the schematic perspective view of T steel link block of the present invention and the cooperation of pre-buried card slot assembled.
Fig. 7 is the side structure schematic view of Fig. 6.
Fig. 8 is the structural schematic diagram of assembled filling wall construction system of the present invention.
Fig. 9 is the structural schematic diagram of assembled filling wall construction system bottom limit in Fig. 8.
Appended drawing reference: 1- insulating layer, 2- reinforced mesh, 3- concrete layer, 4-T shape steel link block, 41- horizontal base Plate, 42- riser, 5- steel frame, 51- top margin frame, 52- boundary frame area, 5a- web, 5b- limb plate, 6- lightgage steel joist, 61- horizontal keel, 62- vertical keel, the pre-buried card slot of 7-, 71- slide groove portion, 72- preburying part, 8- sliding layer, 9- lifting Hole, the upper layer 10- Vierendeel girder, 11- lower layer Vierendeel girder, 12- frame column, 13- disengage gap, 14- locating part, 15- welding plate, 16- flexible flame retardant packing material.
Specific embodiment
For embodiment referring to shown in Fig. 1~7, a kind of assembled of track card slot type connection fills wall, including rectangular wall body and Wall connecting piece, the rectangular wall body include steel skeleton, insulating layer 1, reinforced mesh 2 and concrete layer 3, the wall connecting piece Including T steel link block 4.
Shown in Figure 1, the steel skeleton includes steel frame 5 and lightgage steel joist 6, and the steel frame is total to twice, including divides Not Wei Yu rectangular wall body upper and lower end and the top margin frame 51 and boundary frame area 52 that are oppositely arranged, two layers totally of the lightgage steel joist, set up separately In the two sides of steel frame, the upper surface of lightgage steel joist is concordant with the upper surface of top margin frame, the lower end surface of lightgage steel joist and boundary frame area Lower end surface it is concordant, the upper and lower end of every side lightgage steel joist is fixedly connected with the top margin frame and boundary frame area of the side respectively.Every layer of reinforcing bar Frame is in groined type, including twice horizontal keel 61 and twice vertical keel 62, and the length of the horizontal keel 61 is equal to steel frame Length.
It is shown in Figure 2, the size phase with insulating layer 1 is formed between upper and lower twice steel frame and two layers of front and back lightgage steel joist The installation space of adaptation, the insulating layer are embedded in the installation space, and the width of the insulating layer is identical as the length of steel frame. The steel frame is channel steel, and Open Side Down for top margin frame, the opening upwards of boundary frame area, and channel steel includes the limb plate of web 5a and two sides It is fixedly connected on the outside of 5b, the upper end of the lightgage steel joist 6 and the limb plate 5b of top margin frame, the lower end and bottom edge of the lightgage steel joist 6 It is fixedly connected on the outside of the limb plate 5b of frame, the T steel link block 4 is fixedly connected on web 5a.
Two layers totally of the reinforced mesh 2, is respectively fixedly connected with the outer surface in two layers of lightgage steel joist 6, reinforced mesh Width is identical as the length of steel frame, and reinforced mesh upper surface is concordant with the upper surface of top margin frame, reinforced mesh lower end surface and top The lower end surface of frame is concordant.
Shown in Figure 3,6 He of lightgage steel joist for pouring every side is wrapped up in two layers totally of the concrete layer 3, front and rear sides respectively Reinforced mesh 2, upper and lower two sides wrap up top margin frame and boundary frame area respectively and form concrete protective, the left and right ends of concrete layer with Steel frame left and right ends is concordant.
Referring to shown in Fig. 1~7, the T steel link block 4 shares one group, and three are arranged in the present embodiment.In top margin frame 51 Uper side surface embark on journey between two parties alignment interval setting, the T steel link block includes horizonal base plate 41 and riser 42, the level Bottom plate 41 is fixedly connected with top margin frame 51.
The wall connecting piece further includes pre-buried card slot 7, the number and the number phase of T steel link block of the pre-buried card slot It together and is arranged in a one-to-one correspondence, it further includes that top is transversal that the pre-buried card slot 7, which includes the slide groove portion 71 that lower cross section is inverted U, Face is the preburying part 72 of T-type, and the groove body size of the slide groove portion 71 and the size of riser 42 are adapted, and the insertion of riser 42 is slided It opposite can be slided in groove portion 71 along length direction of steel frame or so, the length of the pre-buried card slot 7 is greater than T steel link block 4 Length, be subject to and guarantee that T steel link block will not be skidded off from slide groove portion 71.The sliding surface of the riser 42 and slide groove portion 71 Between be equipped with sliding layer 8, the sliding layer be rubber layer.The sliding layer is rubber layer.Hole for hoist is provided on the riser 42 9。
Referring to shown in Fig. 1~7, the construction method of the assembled filling wall of this track card slot type connection, including following apply Work step is rapid:
Step 1 fills the design size of wall according to assembled, prepares two channel steels as steel frame 5, the groove body size of channel steel It is adapted with the thickness of insulating layer 1, the opening direction of two channel steels is opposite, welds lightgage steel joist 6 in the side of steel frame 5;
Step 2, insulating layer 1 is laid in the steel skeleton in step 1, and insulating layer 1 is embedded between two steel frames 5 up and down and abuts The surface of lightgage steel joist;
Step 3, another layer of lightgage steel joist 6 of the other side welding steel skeleton of steel frame 5 in step 1;
Step 4 welds T steel link block 4 in the upper surface of top margin frame 51;
Reinforced mesh 2 is respectively welded on the lateral surface of the lightgage steel joist 6 of two sides in step 5;
Step 6, supporting module, casting concrete layer 3.
Shown in Figure 8, the frame system of this assembled filling wall including the connection of track card slot type, further includes enclosing In the frame structure that the upper layer Vierendeel girder 10 of rectangular wall body surrounding, lower layer's Vierendeel girder 11 and the frame column 12 of the left and right sides are formed.
The rectangular wall body falls the uper side surface set in lower layer's Vierendeel girder 11, rectangular wall body and upper layer Vierendeel girder 10 and left and right There are the disengagement gaps 13 of at least 60mm between the frame column 12 of two sides.
Referring to shown in Fig. 8-9, the pre-buried card slot 7 is embedded in the bottom of upper layer Vierendeel girder 10, in the disengagement gap 13, The locating part 14 being preset on the uper side surface of lower layer's Vierendeel girder 11 at left and right sides of rectangular wall body, the locating part 14 and square Pass through the left and right mounting distance of the fixed rectangular wall body of welding welding plate 15, institute between 5 end face of steel frame on shape wall or so end face It states to disengage in gap and is packed with flexible flame retardant packing material 16.The locating part 14 is steel billet, and the length of billet is not less than The distance between front and rear sides steel frame.
Shown in referring to fig. 4~9, the construction method of the frame system of the assembled filling wall of this track card slot type connection, Including following construction procedure:
Step 1, frame structure of constructing, the preburying part 72 of pre-buried card slot 7 are embedded in the bottom of upper layer Vierendeel girder 10, pre-buried card slot 7 Slide groove portion 71 expose upper layer Vierendeel girder 10 downside surface, locating part 14 is fixedly connected on lower layer's Vierendeel girder 11.
Step 2, snap the line pop up the position line of assembled filling wall on frame structure inner ring.
Step 3, lifting assembled fill wall, and first assembled filling wall is placed on lower layer's Vierendeel girder 11, is then passed through The tools such as crowbar manually by assembled filling wall move horizontally, make assembled filling wall top T steel link block 4 with it is pre-buried The slide groove portion 71 of card slot 7 is well chimeric.
Step 4 passes through weldering between the two sides of the bottom of assembled filling wall exposed 5 edge of steel frame and locating part 14 Plate 15 is welded to connect, and fixing assembling formula fills the position of wall.
Step 5, the disengagement gap 13 between the frame column 12 that assembled fills wall and upper layer Vierendeel girder 10, left and right sides Interior filling flexible flame retardant packing material 16.
Step 6 does jointing processing with building sealant in marginal position.

Claims (10)

1. a kind of assembled of track card slot type connection fills wall, including rectangular wall body and wall connecting piece, it is characterised in that: institute Stating rectangular wall body includes steel skeleton, insulating layer (1), reinforced mesh (2) and concrete layer (3), and the wall connecting piece includes T shape Steel link block (4),
The steel skeleton includes steel frame (5) and lightgage steel joist (6), and the steel frame is total to twice, including is located at rectangle wall The upper and lower end of body and the top margin frame (51) and boundary frame area (52) being oppositely arranged, two layers totally of the lightgage steel joist, are divided into steel frame Two sides, the upper surface of lightgage steel joist is concordant with the upper surface of top margin frame, the lower end surface of lightgage steel joist and the lower end surface of boundary frame area Concordantly, the upper and lower end of every side lightgage steel joist is fixedly connected with the top margin frame and boundary frame area of the side respectively,
It is formed between upper and lower twice steel frame and two layers of front and back lightgage steel joist empty with the adaptable installation of the size of insulating layer (1) Between, the insulating layer is embedded in the installation space, and the width of the insulating layer is identical as the length of steel frame,
Two layers totally of the reinforced mesh (2), is respectively fixedly connected with the outer surface in two layers of lightgage steel joist (6), reinforced mesh Width is identical as the length of steel frame, and reinforced mesh upper surface is concordant with the upper surface of top margin frame, reinforced mesh lower end surface and top The lower end surface of frame is concordant,
The lightgage steel joist (6) and reinforced mesh (2) for pouring every side are wrapped up in two layers totally of the concrete layer (3), front and rear sides respectively, Top margin frame is wrapped up in upper and lower two sides respectively and boundary frame area forms concrete protective, the left and right ends of concrete layer and steel frame or so Both ends of the surface are concordant,
The T steel link block (4) shares one group, embarks on journey between two parties in the uper side surface of top margin frame (51) and is aligned interval setting, institute Stating T steel link block includes horizonal base plate (41) and riser (42), and the horizonal base plate (41) is fixedly connected with top margin frame (51).
2. the assembled of track card slot type connection according to claim 1 fills wall, it is characterised in that: the wall connecting Part further includes pre-buried card slot (7), and the number of the pre-buried card slot is identical as the number of T steel link block and is arranged in a one-to-one correspondence, The pre-buried card slot (7) include lower cross section be inverted U slide groove portion (71), further include top cross section be T-type it is pre-buried Portion (72), the groove body size of the slide groove portion (71) and the size of riser (42) are adapted, and the riser (42) is embedded in slide groove portion (71) it opposite can be slided in along length direction of steel frame or so, the length of the pre-buried card slot (7) is greater than T steel link block (4) length is subject to and guarantees that T steel link block will not be skidded off from slide groove portion (71) is inner.
3. the assembled of track card slot type according to claim 2 connection fills wall, it is characterised in that: the steel frame is Channel steel, Open Side Down for top margin frame, the opening upwards of boundary frame area, and channel steel includes the limb plate (5b) of web (5a) Yu two sides, described It is fixedly connected on the outside of the upper end of lightgage steel joist (6) and the limb plate (5b) of top margin frame, the lower end of the lightgage steel joist (6) and boundary frame area Limb plate (5b) on the outside of be fixedly connected, the T steel link block (4) is fixedly connected on web (5a).
4. the assembled of track card slot type according to claim 2 connection fills wall, it is characterised in that: every layer of steel skeleton be in The length of groined type, including twice horizontal keel (61) and twice vertical keel (62), the horizontal keel (61) is equal to steel side The length of frame.
5. the assembled of track card slot type connection according to claim 2 fills wall, it is characterised in that: the riser (42) Sliding layer (8) are equipped between the sliding surface of slide groove portion (71), the sliding layer is rubber layer.
6. the assembled of track card slot type connection according to claim 2 fills wall, it is characterised in that: the riser (42) On be provided with hole for hoist (9).
7. a kind of frame body of the assembled filling wall including the connection of track card slot type described in claim 2-6 any one System, it is characterised in that: further include the upper layer Vierendeel girder (10) for being enclosed in rectangular wall body surrounding, lower layer's Vierendeel girder (11) and left and right two The frame structure that the frame column (12) of side is formed,
The rectangular wall body falls the uper side surface set in lower layer's Vierendeel girder (11), rectangular wall body and upper layer Vierendeel girder (10) and left and right There are the disengagement gap (13) of at least 60mm between the frame column (12) of two sides,
The pre-buried card slot (7) is embedded in the bottom of upper layer Vierendeel girder (10), in the disengagement gap (13), lower layer's Vierendeel girder (11) locating part (14) being preset on uper side surface at left and right sides of rectangular wall body, the locating part (14) and rectangle wall The left and right mounting distance of rectangular wall body is fixed between steel frame (5) end face on body or so end face by welding welding plate (15),
Flexible flame retardant packing material (16) are packed in the disengagement gap.
8. the frame system of the assembled filling wall of track card slot type connection according to claim 7, it is characterised in that: institute Stating locating part (14) is steel billet, and the length of billet is not less than the distance between front and rear sides steel frame.
9. a kind of construction party of the assembled filling wall of track card slot type connection described in -6 any one according to claim 1 Method, which is characterized in that including following construction procedure:
Step 1 fills the design size of wall according to assembled, prepares two channel steels as steel frame (5), the groove body ruler of channel steel The very little thickness with insulating layer (1) is adapted, and the opening direction of two channel steels is opposite, welds light steel dragon in the side of steel frame (5) Bone (6);
Step 2 is laid with insulating layer (1) in the steel skeleton in step 1, insulating layer (1) insertion up and down two steel frames (5) it Between abut lightgage steel joist surface;
Step 3, another layer of lightgage steel joist (6) of the other side welding steel skeleton of steel frame (5) in step 1;
Step 4 welds T steel link block (4) in the upper surface of top margin frame (51);
Reinforced mesh (2) are respectively welded on the lateral surface of the lightgage steel joist (6) of two sides in step 5;
Step 6, supporting module, casting concrete layer (3).
10. a kind of construction of the frame system of the assembled filling wall of track card slot type connection according to claim 7 or 8 Method, which is characterized in that including following construction procedure:
Step 1, frame structure of constructing, the preburying part (72) of pre-buried card slot (7) are embedded in the bottom of upper layer Vierendeel girder (10), in advance The slide groove portion (71) for burying card slot (7) exposes the downside surface of upper layer Vierendeel girder (10), is fixedly connected on lower layer's Vierendeel girder (11) Locating part (14);
Step 2, snap the line pop up the position line of assembled filling wall on frame structure inner ring;
Step 3, lifting assembled fill wall, and first assembled filling wall is placed on lower layer's Vierendeel girder (11), then passes through sled The tools such as rod manually by assembled filling wall move horizontally, make assembled filling wall top T steel link block (4) with it is pre-buried The slide groove portion (71) of card slot (7) is well chimeric;
Step 4 passes through weldering between the two sides of the bottom of assembled filling wall exposed steel frame (5) edge and locating part (14) Plate (15) is welded to connect, and fixing assembling formula fills the position of wall;
Step 5, the disengagement gap between the frame column (12) that assembled fills wall and upper layer Vierendeel girder (10), left and right sides (13) flexible flame retardant packing material (16) are clogged in;
Step 6 does jointing processing with building sealant in marginal position.
CN201910213197.XA 2019-03-20 2019-03-20 Assembled filling wall and frame system connected in rail clamping groove mode and construction method thereof Active CN109811938B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910213197.XA CN109811938B (en) 2019-03-20 2019-03-20 Assembled filling wall and frame system connected in rail clamping groove mode and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910213197.XA CN109811938B (en) 2019-03-20 2019-03-20 Assembled filling wall and frame system connected in rail clamping groove mode and construction method thereof

Publications (2)

Publication Number Publication Date
CN109811938A true CN109811938A (en) 2019-05-28
CN109811938B CN109811938B (en) 2024-09-06

Family

ID=66609612

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910213197.XA Active CN109811938B (en) 2019-03-20 2019-03-20 Assembled filling wall and frame system connected in rail clamping groove mode and construction method thereof

Country Status (1)

Country Link
CN (1) CN109811938B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110158454A (en) * 2019-07-02 2019-08-23 叶锦华 A kind of connector for the assembled steel-concrete combined structure mixing combined bridge for steel-
CN113047111A (en) * 2021-05-08 2021-06-29 中铁北京工程局集团有限公司 Airport runway angle steel assembled type pavement panel structure
CN114000608A (en) * 2021-10-12 2022-02-01 深圳嘉西亚建筑设计有限公司 Cold-formed thin-wall light steel keel building structure
CN114150790A (en) * 2020-09-07 2022-03-08 漳州昊恒建材有限公司 Steel structure wall

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR0109431Y1 (en) * 1994-05-12 1997-12-27 Hyup Shin M E Co Framework and posts of metal for wall
CN2349283Y (en) * 1998-11-27 1999-11-17 鑫墙股份有限公司 Light earthquake-resistant wall
CN2460621Y (en) * 2001-01-17 2001-11-21 戴哲 Thermal insulation light conposite outer wallboard with resin and facing layer
KR20060068818A (en) * 2004-12-17 2006-06-21 주식회사 벽산 A method of construction of the dry process wall for construction
CN108708480A (en) * 2018-08-30 2018-10-26 河北建筑工程学院 A kind of the frame wall filled with masonry structural system and its construction method of sliding slot limit connection
CN108797847A (en) * 2018-08-30 2018-11-13 河北建筑工程学院 A kind of assembled steel frame wall filled with masonry structural system and its construction method
CN209924196U (en) * 2019-03-20 2020-01-10 河北建筑工程学院 Assembled infilled wall connected in rail clamping groove type and frame system thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR0109431Y1 (en) * 1994-05-12 1997-12-27 Hyup Shin M E Co Framework and posts of metal for wall
CN2349283Y (en) * 1998-11-27 1999-11-17 鑫墙股份有限公司 Light earthquake-resistant wall
CN2460621Y (en) * 2001-01-17 2001-11-21 戴哲 Thermal insulation light conposite outer wallboard with resin and facing layer
KR20060068818A (en) * 2004-12-17 2006-06-21 주식회사 벽산 A method of construction of the dry process wall for construction
CN108708480A (en) * 2018-08-30 2018-10-26 河北建筑工程学院 A kind of the frame wall filled with masonry structural system and its construction method of sliding slot limit connection
CN108797847A (en) * 2018-08-30 2018-11-13 河北建筑工程学院 A kind of assembled steel frame wall filled with masonry structural system and its construction method
CN209924196U (en) * 2019-03-20 2020-01-10 河北建筑工程学院 Assembled infilled wall connected in rail clamping groove type and frame system thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110158454A (en) * 2019-07-02 2019-08-23 叶锦华 A kind of connector for the assembled steel-concrete combined structure mixing combined bridge for steel-
CN110158454B (en) * 2019-07-02 2020-11-24 叶锦华 Connecting piece of assembled steel-concrete composite structure for steel-concrete composite bridge
CN114150790A (en) * 2020-09-07 2022-03-08 漳州昊恒建材有限公司 Steel structure wall
CN113047111A (en) * 2021-05-08 2021-06-29 中铁北京工程局集团有限公司 Airport runway angle steel assembled type pavement panel structure
CN113047111B (en) * 2021-05-08 2023-05-12 中铁北京工程局集团有限公司 Airfield runway angle steel assembly type pavement slab structure
CN114000608A (en) * 2021-10-12 2022-02-01 深圳嘉西亚建筑设计有限公司 Cold-formed thin-wall light steel keel building structure

Also Published As

Publication number Publication date
CN109811938B (en) 2024-09-06

Similar Documents

Publication Publication Date Title
CN109811938A (en) A kind of assembled filling wall, frame system and its engineering method of the connection of track card slot type
CN109024993B (en) Assembled concrete frame infilled wall structure system and construction method thereof
CN102433955B (en) Assembling prefabricated light steel composite load-bearing wall panel
CN209924196U (en) Assembled infilled wall connected in rail clamping groove type and frame system thereof
CN108978949A (en) The plug-in filling wall construction system of steel frame, assembled filled-in panel and construction method
CN108797847A (en) A kind of assembled steel frame wall filled with masonry structural system and its construction method
CN109811936B (en) Piston-type connected assembled filling wall, frame system and construction method thereof
CN110158969A (en) A kind of construction method of low temperature environment fabricated shear wall
CN209817249U (en) A compound wallboard of prefabricated foam concrete for building infilled wall
CN208934190U (en) A kind of assembled steel frame wall filled with masonry structural system
CN109811937A (en) A kind of deformable assembled filling wall of wallboard, filled wall system and construction method
CN210679912U (en) High-performance assembled combined external wallboard
CN106049717A (en) Cast-in-situ integral type steel frame filler wall system connected through springs and construction method thereof
CN110820955B (en) Flexible assembling unit for precast concrete outer wall
CN210288790U (en) Firstly assembled steel mesh frame perlite concrete heat-insulating sound-insulating fireproof partition plate
CN109267695B (en) Light assembled prefabricated wallboard with connecting structure and installation method thereof
CN103556758B (en) Lightweight steel construction lightweight concrete cast-in-place wall and construction method
CN108343196A (en) Assembled composite insulation tile unit and complex heat-preservation inclined roof system and construction method
CN205669283U (en) The cast-in-place Integral Steel frame wall filled with masonry system of the spacing connection of steel disc
CN104763149A (en) Light steel concrete construction method
CN205669284U (en) The cast-in-place Integral Steel frame wall filled with masonry system that a kind of spring connects
CN203583720U (en) Light-weight steel structure and light-weight concrete cast-in-place wall body
CN212053307U (en) Steel wire net frame cement light composite heat insulation wall
CN216516343U (en) Structure integration exempts from to tear open prefabricated hollow wall of mould
CN105937279A (en) Cast-in-situ integrated steel frame infilled wall system with steel sheets connected in limited mode and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20240808

Address after: 063700 North District, Luanzhou Economic Development Zone, Dong'angezhuang Town, Luanzhou City, Tangshan City, Hebei Province

Applicant after: Tangshan Zhuchao New Building Materials Co.,Ltd.

Country or region after: China

Address before: No. 13 Chaoyang Street, Zhangjiakou, Hebei, Hebei

Applicant before: HEBEI University OF ARCHITECTURE

Country or region before: China

TA01 Transfer of patent application right
GR01 Patent grant