CN109798871A - Native face height controls measurement method after a kind of cubic meter of backfill - Google Patents
Native face height controls measurement method after a kind of cubic meter of backfill Download PDFInfo
- Publication number
- CN109798871A CN109798871A CN201910220063.0A CN201910220063A CN109798871A CN 109798871 A CN109798871 A CN 109798871A CN 201910220063 A CN201910220063 A CN 201910220063A CN 109798871 A CN109798871 A CN 109798871A
- Authority
- CN
- China
- Prior art keywords
- point
- foundation pit
- central point
- measurement
- cubic meter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
The invention discloses native face height after a kind of cubic meter of backfill to control measurement method, it is related to a cubic meter stemming operation technical field, after the present invention is the following steps are included: backfill one layer of cubic metre of earth and stone in foundation pit, middle section chooses a central point N on the native face of this layer, n root is taken to both pass through the reference line of central point N in foundation pit earth face, n >=3, angle per adjacent two foundation directrix is equal and is δ, δ=180 °/n, two ends of all reference lines and margin of foundation pit all have an intersection point, respectively take a midpoint as measurement point on central point N to the line section between all intersection points, central point N is also measurement point, the present invention has easy to operate, measurement point reconnaissance specification, the accurate and reliable advantage of measurement data.
Description
Technical field
The present invention relates to cubic metre of earth and stone stemming operation technical fields, high more particularly to native face after a kind of cubic meter of backfill
Degree control measurement method.
Background technique
The cubic metre of earth and stone, is the general name of the earthwork and the cubic meter of stone, is Tu Heshi, and measurement unit is to be generally cubic meter.Common soil
Stonework has: levelling of the land, foundation pit (slot) and pipe canal digging, road excavation, civil air defense constructions and installations excavation, terrace banket, and roadbed is filled out
It builds and foundation pit backfills.Reasonable arrangement construction plan is wanted, tries not to be arranged in rainy season, while applying to reduce earth and rock works
Expenses of labour is used, and is implemented and is not accounted for or account for less farmland and arable land and be conducive to the principle built up fields with changing, to make the reasonable tune of the cubic metre of earth and stone
With scheme, overall arrangement.Earth and rock works are an engineering projects wide, amount is big, labour is heavy, in the construction process,
The condition of construction is also extremely complex.
In cubic metre of earth and stone stemming operation, the foundation pits such as pond, hollow are filled generally by way of back-filling in layers, often
It backfills one layer to need to measure backfill height (i.e. flatness), the native face height of this layer after filling cannot be excessive or crosses and be less than
This layer of absolute altitude, measurement result in error range after, just can be carried out next layer and fill, be all at present random for its elevation carrection
Several points are selected on the native face of this layer, are measured by level meter in each reconnaissance, when the levelness that all the points are measured is certain
It in error range, just carries out next layer and fills, otherwise continue to roll until meet the requirements, the mode of this random measurement not section
It learns, the data measured are inaccurate, and have randomness, measure if being to try to choose more point, operation is again pretty troublesome, surveys
Amount efficiency is low.
Therefore above-mentioned technical problem how is solved, there is very much realistic meaning to those skilled in the art.
Summary of the invention
It is an object of the invention to: in order to solve after every one layer of the backfill of the existing cubic metre of earth and stone, to measure the layer height be by random
The method for selecting several points to measure on the native face of this layer has randomness, the data inaccuracy measured, if be to try to choose compared with
More points measure, and pretty troublesome, the low technical problem of measurement efficiency, the present invention provide soil after a kind of cubic meter of backfill again for operation
Face height controls measurement method.
The present invention specifically uses following technical scheme to achieve the goals above:
Native face height controls measurement method after a kind of cubic meter of backfill, comprising the following steps: one layer of soil is backfilled in foundation pit
After the cubic meter of stone, middle section chooses a central point N on the native face of this layer, takes n root to both pass through the benchmark of central point N in foundation pit earth face
Line, n >=3, the angle per adjacent two foundation directrix is equal and is δ, δ=180 °/n, two ends of all reference lines and foundation pit
Edge all has an intersection point, respectively takes a midpoint as measurement point, central point on central point N to the line section between all intersection points
N is also measurement point.
Further, reference line radical n=3, δ=60 °, two ends of reference line and the intersection point of margin of foundation pit be respectively A,
B, C, D, E, F, respectively take its midpoint A1, B1, C1, D1, E1, F1 on line segment NA, NB, NC, ND, NE, NF respectively, midpoint A1, B1,
C1, D1, E1, F1 and central point N are measurement point.
Further, be marked after having chosen central point N in the point, then draw graticule pass through central point N until
Graticule both ends and margin of foundation pit have intersection point A, B, are fixed graticule with timber in two intersection point A, B location, repeat above-mentioned behaviour
Make to pass through central point N with two graticules again, angle is 60 ° between adjacent two graticule, and the intersection point of two graticules and margin of foundation pit
Respectively C, D, E, F are fixed corresponding graticule with timber in the position intersection point C, D, E, F, then measured on three graticules NA,
Midpoint A1, B1, C1, D1, E1, F1 of NB, NC, ND, NE, NF, and marked in midpoint A1, B1, C1, D1, E1, F1.
Further, after having chosen measurement point, the reading of each measurement point is measured by air-bubble level, and is done easy to remember
Record.
Further, the sensitivity for selecting air-bubble level is 0.3mm/m or 0.4mm/m.
Beneficial effects of the present invention are as follows:
1, when choosing measurement point, the native face central area first after filling optionally takes a central point N as datum mark,
Central point N is also one of measurement point simultaneously, then takes n root to both pass through the reference line of central point N in foundation pit earth face, obtains for guarantee
Multiple groups correlation data, reference line are at least arranged three, and two ends of reference line and margin of foundation pit obtain an intersection point, central point N
It respectively takes a midpoint as measurement point on to the line section between all intersection points, to obtain all measurement points, is obtained according to this method
The measurement point distribution arrived is uniform, has broken randomness, measurement is more scientific, to guarantee the accuracy of measurement result.
Detailed description of the invention
Fig. 1 is the reconnaissance schematic diagram of native face height control measurement method after a kind of cubic meter of backfill of the present invention.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right
The present invention is further elaborated.It should be appreciated that described herein, specific examples are only used to explain the present invention, not
For limiting the present invention, i.e., described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is logical
The component for the embodiment of the present invention being often described and illustrated herein in the accompanying drawings can be arranged and be designed with a variety of different configurations.
Therefore, the detailed description of the embodiment of the present invention provided in the accompanying drawings is not intended to limit below claimed
The scope of the present invention, but be merely representative of selected embodiment of the invention.Based on the embodiment of the present invention, those skilled in the art
Member's every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
It should be noted that the relational terms of term " first " and " second " or the like be used merely to an entity or
Operation is distinguished with another entity or operation, and without necessarily requiring or implying between these entities or operation, there are any
This actual relationship or sequence.Moreover, the terms "include", "comprise" or its any other variant be intended to it is non-exclusive
Property include so that include a series of elements process, method, article or equipment not only include those elements, but also
Further include other elements that are not explicitly listed, or further include for this process, method, article or equipment it is intrinsic
Element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including described
There is also other identical elements in the process, method, article or equipment of element.
Feature and performance of the invention are described in further detail with reference to embodiments.
Embodiment 1
As shown in Figure 1, the present embodiment provides native face height after a kind of cubic meter of backfill to control measurement method, including following step
Rapid: after backfilling one layer of cubic metre of earth and stone in foundation pit, middle section chooses a central point N on the native face of this layer, takes n root in foundation pit earth face
The reference line of central point N is both passed through, n >=3, the angle per adjacent two foundation directrix is equal and is δ, δ=180 °/n, Suo Youji
Two ends of directrix and margin of foundation pit all have an intersection point, respectively take in one on central point N to the line section between all intersection points
Point is used as measurement point, and central point N is also measurement point.
In the present embodiment, when choosing measurement point, the native face central area first after filling optionally takes a central point N to make
On the basis of point, while central point N is also one of measurement point, then take n root to both pass through the reference line of central point N in foundation pit earth face,
To guarantee to obtain multiple groups correlation data, reference line is at least arranged three, and two ends of reference line and margin of foundation pit obtain a friendship
Point respectively takes a midpoint as measurement point on central point N to the line section between all intersection points, so that all measurement points are obtained, according to
The measurement point distribution obtained according to this method is uniform, has broken randomness, measurement is more scientific, to guarantee the accurate of measurement result
Property.
Embodiment 2
As shown in Figure 1, the present embodiment is to be further optimized on the basis of embodiment 1, and specifically, reference line radical
N=3, δ=60 °, two ends of reference line and the intersection point of margin of foundation pit are respectively A, B, C, D, E, F, respectively line segment NA, NB,
Its midpoint A1, B1, C1, D1, E1, F1 are respectively taken on NC, ND, NE, NF, midpoint A1, B1, C1, D1, E1, F1 and central point N are to survey
Amount point.
In the present embodiment, reference line radical n is generally determined according to foundation pit area size to be backfilled, most of foundation pit face
Product is not very big, therefore reference line is arranged 3 foundation and is originally able to satisfy measurement request, and foundation pit biggish for small part area can
Suitably to increase reference line radical, to obtain more measurement points, guarantee the accuracy of measurement result.
Embodiment 3
As shown in Figure 1, the present embodiment is further optimized on the basis of embodiment 2, specifically, center has been chosen
Be marked after point N in the point, then draw graticule pass through central point N until graticule both ends and margin of foundation pit have intersection point A,
B is fixed graticule with timber in two intersection point A, B location, repeats aforesaid operations and two graticules is used to pass through central point N, phase again
Angle is 60 ° between adjacent two graticules, and the intersection point of two graticules and margin of foundation pit is respectively C, D, E, F, at C, D, E, F, intersection point
Set and fixed corresponding graticule with timber, then measured on three graticules midpoint A1, B1 of NA, NB, NC, ND, NE, NF, C1,
D1, E1, F1, and marked in midpoint A1, B1, C1, D1, E1, F1, after having chosen measurement point, measured by air-bubble level
The reading of each measurement point, and make a record, selecting the sensitivity of air-bubble level is 0.3mm/m or 0.4mm/m.
In the present embodiment, found out by graticule and timber for measurement point, easy to operate, operation difficulty is low, together
When guarantee to take accuracy a little, using air-bubble level measurement, convenient reading when measurement.
The above, only presently preferred embodiments of the present invention, are not intended to limit the invention, patent protection model of the invention
It encloses and is subject to claims, it is all to change with equivalent structure made by specification and accompanying drawing content of the invention, similarly
It should be included within the scope of the present invention.
Claims (5)
1. native face height controls measurement method after a kind of cubic meter of backfill, which comprises the following steps: returned in foundation pit
After filling out one layer of cubic metre of earth and stone, middle section chooses a central point N on the native face of this layer, takes n root to both pass through central point N in foundation pit earth face
Reference line, n >=3, the angle per adjacent two foundation directrix is equal and be δ, δ=180 °/n, two ends of all reference lines
All there is an intersection point with margin of foundation pit, respectively take a midpoint as measurement point on central point N to the line section between all intersection points,
Central point N is also measurement point.
2. native face height controls measurement method after a kind of cubic meter of backfill according to claim 1, which is characterized in that benchmark
Line radical n=3, δ=60 °, two ends of reference line and the intersection point of margin of foundation pit are respectively A, B, C, D, E, F, respectively in line segment
Its midpoint A1, B1, C1, D1, E1, F1, midpoint A1, B1, c1, D1, E1, F1 and central point N are respectively taken on NA, NB, NC, ND, NE, NF
As measurement point.
3. native face height controls measurement method after a kind of cubic meter of backfill according to claim 2, which is characterized in that choose
It is marked after good central point N in the point, then drawing a graticule to pass through central point N has until graticule both ends with margin of foundation pit
Intersection point A, B are fixed graticule with timber in two intersection point A, B location, repeat aforesaid operations and two graticules is used to pass through center again
Point N, angle is 60 ° between adjacent two graticule, and the intersection point of two graticules and margin of foundation pit is respectively C, D, E, F, intersection point C,
D, corresponding graticule is fixed with timber in the position E, F, and the midpoint of NA, NB, NC, ND, NE, NF are then measured on three graticules
A1, B1, C1, D1, E1, F1, and marked in midpoint A1, B1, C1, D1, E1, F1.
4. native face height controls measurement method after a kind of cubic meter of backfill according to claim 1, which is characterized in that choose
After good measurement point, the reading of each measurement point is measured by air-bubble level, and is made a record.
5. native face height controls measurement method after a kind of cubic meter of backfill according to claim 5, which is characterized in that select
The sensitivity of air-bubble level is 0.3mm/m or 0.4mm/m.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910220063.0A CN109798871A (en) | 2019-03-21 | 2019-03-21 | Native face height controls measurement method after a kind of cubic meter of backfill |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910220063.0A CN109798871A (en) | 2019-03-21 | 2019-03-21 | Native face height controls measurement method after a kind of cubic meter of backfill |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109798871A true CN109798871A (en) | 2019-05-24 |
Family
ID=66562884
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910220063.0A Pending CN109798871A (en) | 2019-03-21 | 2019-03-21 | Native face height controls measurement method after a kind of cubic meter of backfill |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109798871A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114166173A (en) * | 2021-11-30 | 2022-03-11 | 深圳市蛇口招商港湾工程有限公司 | Earthwork is backfilled and is used high measuring device of soil level |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101319495A (en) * | 2008-07-12 | 2008-12-10 | 中铁西北科学研究院有限公司 | Layered deformation observation method and apparatus for deep part of groundwork |
CN106702997A (en) * | 2017-03-16 | 2017-05-24 | 中铁西北科学研究院有限公司 | Method of testing deadweight collapse settlement of soil layers at different depths of loess |
CN107268662A (en) * | 2017-06-05 | 2017-10-20 | 三峡大学 | A kind of power transmission line iron tower foundation point hole method |
-
2019
- 2019-03-21 CN CN201910220063.0A patent/CN109798871A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101319495A (en) * | 2008-07-12 | 2008-12-10 | 中铁西北科学研究院有限公司 | Layered deformation observation method and apparatus for deep part of groundwork |
CN106702997A (en) * | 2017-03-16 | 2017-05-24 | 中铁西北科学研究院有限公司 | Method of testing deadweight collapse settlement of soil layers at different depths of loess |
CN107268662A (en) * | 2017-06-05 | 2017-10-20 | 三峡大学 | A kind of power transmission line iron tower foundation point hole method |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114166173A (en) * | 2021-11-30 | 2022-03-11 | 深圳市蛇口招商港湾工程有限公司 | Earthwork is backfilled and is used high measuring device of soil level |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101625422B (en) | Method for monitoring time-lapse microgravity oil and gas reservoirs by fixed field method | |
CN106600661B (en) | The method for accurately generating segmental arc geologic section | |
CN109165406A (en) | The quick dynamic classification prediction technique of country rock during a kind of constructing tunnel | |
CN103650695B (en) | A kind of method carrying out prepartion of land according to soil thickness | |
CN205262429U (en) | Job site earth volume survey system | |
CN106682364A (en) | Method and system for determining the depth of each pile driven into rock layer | |
Stiros | Accurate measurements with primitive instruments: The “paradox” in the qanat design | |
CN111353681A (en) | BIM technology-based high-precision calculation method for in-site earth and stone engineering quantity | |
CN106769170A (en) | A kind of acquisition method of karst underground hole, crack and soil information | |
Berendsen et al. | New prospects in geomorphological and geological mapping of the Rhine-Meuse Delta-Application of detailed digital elevation maps based on laser altimetry | |
CN109798871A (en) | Native face height controls measurement method after a kind of cubic meter of backfill | |
CN104570070B (en) | A kind of method and apparatus for setting up two-dimentional near surface geological model | |
Ganiyev et al. | Examining the managerial structure and operational aspects of geodesy, cartography, and cadastre production | |
CN112199628B (en) | Engineering quantity calculating method and device for linear engineering | |
Guler et al. | Evaluation of the movements of the dam embankments by means of geodetic and geotechnical methods | |
CN110197013A (en) | Riverbed bedrock surface modeling method based on Morphing | |
CN102661741B (en) | Method for monitoring topography and erosion amount of head of small-sized gully | |
CN116305500A (en) | Automatic pile foundation engineering quantity generation method and system | |
CN104931015A (en) | Cross section automatic plotting system and method based on DTM data models | |
CN112529982B (en) | Foundation soil layer contour map drawing method | |
CN108897718A (en) | Quantitative description method for rock mass structure | |
CN114676545A (en) | Method for analyzing underground water pressure mining scheme effect based on GMS | |
CN102999706A (en) | Working route generation method for global positioning system (GPS) control land leveling system and working route | |
CN105445177B (en) | The monitoring method of bank erosion amount and erosion rate | |
CN103741658A (en) | Method for realizing joint survey of sand blowing and filling amount by adopting ground penetrating radar and static penetrometer |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190524 |