CN109736857A - A kind of spliced steel arch-shelf and preparation method thereof - Google Patents

A kind of spliced steel arch-shelf and preparation method thereof Download PDF

Info

Publication number
CN109736857A
CN109736857A CN201910043698.8A CN201910043698A CN109736857A CN 109736857 A CN109736857 A CN 109736857A CN 201910043698 A CN201910043698 A CN 201910043698A CN 109736857 A CN109736857 A CN 109736857A
Authority
CN
China
Prior art keywords
support
steel plate
fashioned iron
shelf
arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910043698.8A
Other languages
Chinese (zh)
Inventor
马保亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC SHEC Dong Meng Engineering Co Ltd
Original Assignee
CCCC SHEC Dong Meng Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHEC Dong Meng Engineering Co Ltd filed Critical CCCC SHEC Dong Meng Engineering Co Ltd
Priority to CN201910043698.8A priority Critical patent/CN109736857A/en
Publication of CN109736857A publication Critical patent/CN109736857A/en
Pending legal-status Critical Current

Links

Abstract

The present invention provides a kind of spliced steel arch-shelfs, including bow supporter, positioned at two pieces of abutment wall brackets at bow supporter both ends.Bow supporter is made of the connection of several first supports, and abutment wall bracket is made of the connection of several second supports.First support and second support include fashioned iron and junction steel plate, and junction steel plate is vertically welded in the both ends end of fashioned iron, two groups of symmetrical connecting holes are offered on junction steel plate.The fashioned iron length and width for making first support and second support are all the same, and at the center of junction steel plate, the groove for positioning and being inserted into for fashioned iron is washed in milling, and groove is identical as fashioned iron cross sectional shape and size.A kind of production method of steel arch-shelf, including steel arch-shelf design;Material prepares;Cold-bending deformation simultaneously welds;Storage.The spliced steel arch-shelf that the present invention has has the characteristics that structure is simple, is completely embedded, facilitates storage and transport, and the production method of spliced steel arch-shelf makes steel arch-shelf realize procedure operation, high yield rate.

Description

A kind of spliced steel arch-shelf and preparation method thereof
Technical field
The present invention relates to Tunnel technical fields more particularly to a kind of spliced steel arch-shelf and preparation method thereof.
Background technique
As China's road traffic construction scale constantly expands, under the background that speed is constantly promoted, Tunnel Engineering at It needs to carry out initial stage branch to tunnel using steel arch-shelf during constructing tunnel for the highly important construction link of one of them Shield, can ensure that the safety and stability of construction, it is therefore necessary to guarantee the intensity of steel arch-shelf in this way.
There are two types of structures for traditional steel arch-shelf tool, and one is semicircle steel arch-shelf, another kind is circular arch stalk steel arch-shelf.Circle Arch stalk steel arch-shelf is usually to be combined by three pieces of steel bracket groups, i.e. top semi-circular shape bracket, the vertical abutment wall bracket in two sides. Top-support is different with the specification of abutment wall bracket, it may be assumed that bending radius, length is not identical.Production when will appear fashioned iron raw material with Mismatching phenomenon is deformed, waste of material, claim for eot, person works is measured and increases.Also it will appear the problem that length is inadequate after splicing, The problem of supporting effect reduces.The specification difference of top-support and abutment wall bracket, the storage needed, transporting equipment are more, make work Place land occupation is big, scene is in disorder.Semicircle steel arch-shelf is integrally formed mostly or muti-piece fashioned iron be deformed into after splice composition. Integrally formed steel arch-shelf comparison is complicated, and it is higher to store and transport difficulty, and when splicing needs dedicated equipment conveying And it sets up.And spliced steel arch-shelf will appear adjacent arch trestle because arch trestle radian is inadequate, verticality not enough due to caused by arch The problem of splicing is not close, reduces supporting effect.
Moreover, tunnel support construction cycle operation is stronger, the time is saved without steel arch-shelf in traditional construction Examination is spelled, and it is inappropriate often directly to will appear arch radian for integrated steel arch in the supporting operation that tunnel carries out steel arch-shelf Situation needs again to set up steel arch-shelf dismounting.For spliced steel arch-shelf, often will appear deformation radian it is inadequate, steel arch-shelf branch The unsuitable situation of steel arch-shelf height, needs steel after the case where frame junction is not close, bracket specification difference does not match, splicing It is set up again after the disassembly of arch bracket.Make the reduction of work supporting effect, schedule delays, support cost increases.
In view of this, it is necessary to steel arch-shelf to tunnel support in the prior art and its production method improved, with It solves the above problems.
Summary of the invention
The purpose of the present invention is to provide a kind of structures simply, splicing is convenient, the spliced steel arch convenient for storing and transporting Frame.Simultaneously provide it is a kind of be able to achieve procedure operation, high yield rate spliced steel arch-shelf production method.
Realize the object of the invention technical solution it is as follows: a kind of spliced steel arch-shelf, including bow supporter, be located at vault branch Two pieces of abutment wall brackets at frame both ends, bow supporter center and the line of centres at tunnel center are vertical with tunnel ground, and two pieces of sides Wall bracket is bolted to connection between line of centres mirror symmetry, bow supporter and abutment wall bracket.If bow supporter by A dry first support forms after bolt is fixedly connected, abutment wall bracket group after bolt is fixedly connected by several second supports At.First support and second support include fashioned iron and junction steel plate, and the center of junction steel plate is overlapped with the center of fashioned iron end, Junction steel plate is vertically welded in the end of fashioned iron, and two groups of symmetrical connecting holes are offered on junction steel plate.Make first support and The fashioned iron length and width of second support are all the same.At the center of junction steel plate, milling, which is washed, positions for fashioned iron and is inserted into recessed Slot, groove are identical as fashioned iron cross sectional shape and size.When welding, first by the groove of junction steel plate and fashioned iron end alignment, by type Steel end is inserted into groove, then synchronizes two-sided side item welding in the junction of fashioned iron and junction steel plate.
Further, to be easily broken off after preventing junction steel plate from opening up groove or fashioned iron cannot be fully inserted into groove Portion makes the 1/5~1/2 of the depth fashioned iron thickness of groove.
As a further improvement of the present invention, it is additionally provided with supporter in fashioned iron and junction steel plate weld, supporter is used for Support and be bonded steel plate, the setting of supporter, the more fastening for connecting fashioned iron with connecting plate, another aspect In steel arch supporting, steel arch-shelf is unlikely to deform, and supporting effect is more preferable.
Wherein, supporter is rectangular triangle steel plate, and a right-angle side of rectangular triangle steel plate and fashioned iron weld, another side with Junction steel plate welding.Triangle has preferable stability, is not easy to deform in stress, triangular steel plate is welded on type The junction of steel and junction steel plate strengthens the stability of fashioned iron and junction steel plate, when using section-steel support, splices steel arch Fashioned iron is not easy to cause to destroy because stress is much with junction steel plate weld when frame, to influence supporting effect.
Wherein, supporter is steel bar, and steel bar one end is welded on fashioned iron, and the other end is welded on junction steel plate.Steel bar with After fashioned iron and junction steel plate connection, triangular support can be formed, triangular support stability is good, when using section-steel support, Fashioned iron is not easy to cause to destroy because stress is much with junction steel plate weld when splicing steel arch-shelf, to influence supporting effect.
A kind of production method of spliced steel arch-shelf: including the following steps,
Step 1: steel arch-shelf design: measurement tunnel size designs bow supporter, the abutment wall supporting structure of spliced steel arch-shelf;If Count the size and deformation radian of first support and second support;
Step 2: material prepare: fashioned iron raw material is cut into the size of design, with forming mill cold-bending deformation make first support and The fashioned iron of second support;Junction steel plate plate is cut into the size of design, and makes groove and connecting hole on junction steel plate;
Step 3: it assists transporting on track in forming mill that first support is made in the both ends of junction steel plate vertical welding to fashioned iron And second support;
Step 4: it is spare that first support and second support are placed into bracket storage region.
It further, further include being welded in the junction steel plate of first support and second support and deformation junction in step 3 Connect supporter.
Further, further include step 5, first support and second support are tried to spell in the area Shi Pin, remove underproof the One bracket or second support.
Compared with prior art, the invention has the advantage that:
1. it is identical as the fashioned iron specification of second support to make first support, the works such as cutting, cold-bending deformation, transport, storage of fashioned iron Sequence can realize orderly management.
2. spliced steel arch-shelf is made by being welded to connect steel plate after several fashioned iron cold-bending deformations, structure is simple, convenient for fortune Send the erection with steel arch-shelf.
3. first support and second support are tried to spell before steel arch-shelf erection, in the area Shi Pin, underproof steel arch-shelf is removed, It prevents from occurring steel arch-shelf connection when setting up not close and reduce supporting effect.
4. junction steel plate center milling washed groove identical with fashioned iron cross sectional shape and size so that fashioned iron with When junction steel plate is welded and fixed, junction steel plate can be accurately fixed to the center of fashioned iron, reduce first support or the The inferior rate of two bracket finished products.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the spliced steel arch-shelf embodiment 1 ~ 2 of the present invention;
Fig. 2 is the structural schematic diagram of the spliced steel arch-shelf embodiment 3 of the present invention;
Fig. 3 is the structural schematic diagram of junction steel plate in the present invention.
Specific embodiment
Invention is described in detail in each embodiment shown in reference to the accompanying drawing, but it should be stated that, these realities The mode of applying not is limitation of the present invention, those of ordinary skill in the art according to these embodiments made by function, method or Equivalent transformation or substitution in person's structure, all belong to the scope of protection of the present invention within.
In the description of the present embodiment, it is to be understood that term " center ", " longitudinal direction ", " transverse direction ", "upper", "lower", The orientation or positional relationship of the instructions such as "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside" is It is based on the orientation or positional relationship shown in the drawings, is merely for convenience of description the invention and simplifies description, rather than indicate Or imply that signified device or element must have a particular orientation, be constructed and operated in a specific orientation, therefore cannot understand For the limitation to the invention.
In addition, term " first ", " second ", " third " etc. are used for description purposes only, it is not understood to indicate or imply Relative importance or the quantity for implicitly indicating indicated technical characteristic.The feature of " first ", " second " etc. is defined as a result, It can explicitly or implicitly include one or more of the features.In the description of the invention, unless otherwise indicated, The meaning of " plurality " is two or more.
Term " installation ", " connected ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, be also possible to removable Connection is unloaded, or is integrally connected;It can be mechanical connection, be also possible to be electrically connected;It can be directly connected, it can also be in Between medium be indirectly connected, can be the connection inside two elements.For the ordinary skill in the art, can pass through Concrete condition understands concrete meaning of the above-mentioned term in the invention.
A kind of spliced steel arch-shelf:
It please join shown in Fig. 1 ~ 3,
Embodiment 1:
Refering to Figure 1, a kind of spliced semicircle steel arch-shelf, the abutment wall bracket 2 of bow supporter 1 and 2 piece mirror symmetry, arch Ceiling hold center 1 and the line of centres at tunnel center are vertical with tunnel ground, pass through spiral shell between bow supporter 1 and abutment wall bracket 2 Bolt is fixedly connected.
First support is identical with the length of second support, and deformation radian is identical, including fashioned iron and junction steel plate 6 form, even The center for connecing steel plate 6 is overlapped with the center of fashioned iron end, and fashioned iron is preferably I-steel, and connection 6 plate of steel is vertically welded in I-steel End, offer two groups of symmetrical connecting holes 8 on junction steel plate 6, there are two every group of connecting holes 8.
First support and second support are shared 9 a, including 1 first support is bow supporter 1, by 4 second supports It is bolted to connection the abutment wall bracket 2 of composition, the deformation radian of first support and second support is 20 °.
At the center of junction steel plate 6, the groove 7 for positioning and being inserted into for I-steel, groove 7 and I-steel section are washed in milling Form and dimension is identical, and the depth of groove 7 is the 1/2 of the thickness of junction steel plate 6.Make I-steel end is accurate poorly to weld It connects in the center of junction steel plate 6, and guarantees the verticality of junction steel plate 6 and I-steel weld.
Embodiment 2:
Refering to Figure 1, a kind of spliced semicircle steel arch-shelf, the abutment wall bracket 2 of bow supporter 1 and 2 piece mirror symmetry, arch Ceiling hold center 1 and the line of centres at tunnel center are vertical with tunnel ground, pass through spiral shell between bow supporter 1 and abutment wall bracket 2 Bolt is fixedly connected.
First support is identical with the length of second support, and deformation radian is identical, including fashioned iron and junction steel plate 6 form, even The center for connecing steel plate 6 is overlapped with the center of fashioned iron end, and junction steel plate 6 is vertically welded in the end of fashioned iron, is opened on junction steel plate 6 Equipped with two groups of symmetrical connecting holes 8, there are two every group of connecting holes 8.
First support and second support share 12, are composed of a fixed connection including 2 first supports by high-strength bolt Bow supporter 1, the abutment wall bracket 2 being composed of a fixed connection by 5 second supports by high-strength bolt, first support and second support Deformation radian be 15 °.
At the center of junction steel plate, the groove 7 for positioning and being inserted into for fashioned iron is washed in milling, groove 7 and fashioned iron cross sectional shape and Size is identical, and the depth of groove 7 is the 2/5 of the thickness of junction steel plate 6.Make fashioned iron end is accurate to be poorly welded on connection The center of steel plate 6, and guarantee the verticality of junction steel plate 6 and fashioned iron weld.
The supporter of rectangular triangle steel plate, the support of rectangular triangle steel plate are additionally provided in fashioned iron and 6 weld of junction steel plate Body is used to support and is bonded steel plate 6, and a right-angle side and fashioned iron for rectangular triangle steel plate welds, another side and junction steel plate 6 welding.Triangle has preferable stability, is not easy to deform in stress, triangular steel plate is welded on fashioned iron and company The junction for connecing steel plate 6 strengthens the stability of fashioned iron Yu junction steel plate 6, when using section-steel support, when splicing steel arch-shelf Fashioned iron is not easy to cause to destroy because stress is much with 6 weld of junction steel plate, to influence supporting effect.
Embodiment 3:
It please refers to shown in Fig. 2, a kind of spliced circular arch stalk steel arch-shelf, bow supporter 1 is semicircle arch, 2 pieces of abutment wall brackets 2 For vertical arch, bow supporter center 1 and the line of centres at tunnel center are vertical with tunnel ground, bow supporter 1 and abutment wall branch It is bolted to connection between frame 2.
Bow supporter 1 is bolted to connection by 5 first supports and is formed, and the deformation radian of first support is 36 °, side Wall arch 2 is bolted to connection by 8 second supports and is formed, and second support is indeformable.First support and second support The length of fashioned iron is same or different.
First support and second support are made of fashioned iron and junction steel plate 6, the center and 3 end of fashioned iron of junction steel plate 6 The center in portion is overlapped, and junction steel plate 6 is vertically welded in the end of fashioned iron, two groups of symmetrical connecting holes are offered on junction steel plate 6, Every group of connecting hole 8 has 3.
At the center of junction steel plate 6, the groove 8 for positioning and being inserted into for fashioned iron, groove 8 and fashioned iron cross sectional shape are washed in milling And size is identical, and the depth of groove 8 is the 3/10 of the thickness of junction steel plate 6.Make fashioned iron end is accurate to be poorly welded on The center of junction steel plate 6, and guarantee the verticality of junction steel plate 6 and fashioned iron weld.
It is additionally provided with the supporter of steel bar in fashioned iron and 6 weld of junction steel plate, steel bar one end is welded on fashioned iron, the other end It is welded on junction steel plate 6.After steel bar is connect with fashioned iron and junction steel plate 6, triangular support can be formed, triangular support is stablized Property it is good, when using section-steel support, steel arch-shelf fashioned iron and 6 weld of junction steel plate of splicing are not easy to cause because stress is much It destroys, to influence supporting effect.
Spliced semicircle steel arch stand manufacturing method 1:
The production method of the spliced semicircle steel arch-shelf of Examples 1 to 2:
Firstly, steel arch-shelf designs: measurement tunnel size designs bow supporter, the abutment wall supporting structure of spliced steel arch-shelf, designs The size and deformation radian of first support and second support;
Secondly, material prepares: fashioned iron raw material being cut into the size of needs, makes first support and the with forming mill cold-bending deformation Junction steel plate plate is cut into the size of needs by the fashioned iron of two brackets, and groove and connecting hole are made on junction steel plate;
Again, forming mill assist transport track on by junction steel plate vertical welding to fashioned iron both ends, then fashioned iron with connect steel Plate weld welds the supporter of straight triangular form, and first support and second support is made;
Finally, it is spare that first support and second support are placed into bracket storage region.
Spliced circular arch stalk steel arch stand manufacturing method 2:
The production method of the spliced circular arch stalk steel arch-shelf of embodiment 3:
Firstly, steel arch-shelf designs: measurement tunnel size designs bow supporter, the abutment wall supporting structure of spliced steel arch-shelf, designs First support deforms radian, designs the size of second support, the deformation radian of second support is zero;
Secondly, material prepares: fashioned iron raw material being cut into the size of needs, adjusts forming mill according to the deformation radian of first support Parameter, with forming mill cold-bending deformation production first support fashioned iron;The deformation radian of forming mill is adjusted to zero, uses forming mill Junction steel plate plate, is cut into the size of needs by the fashioned iron for making second support, and groove and company are made on junction steel plate Connect hole;
Again, forming mill assist transport track on by junction steel plate vertical welding to fashioned iron both ends, then fashioned iron with connect steel Plate weld welds the supporter of straight triangular form, and first support and second support is made;
Finally, it is spare that first support and second support are placed into bracket storage region.
The examination of spliced steel arch-shelf is spelled:
The spliced steel arch-shelf of embodiment 1 ~ 3, before for tunnel support, the also area Xu Shipin carries out examination spelling, is not conformed to removal The first support or second support of lattice, examination splicing method are as follows:
1. it is in place to connect tool used in high-strength bolt required for first support or second support and examination spelling, place Job platform.
2. releasing steel arch-shelf examination according to Design Requirement Drawing according to the size of 1:1 in the area Shi Pin and spelling full-page proof
3. required first support or second support in examination spelling are numbered one by one according to the dividing elements in design drawing.
4. first support or second support after the completion of number in a certain order, are sequentially placed operation platform, place Sequentially are as follows: first place bow supporter, play arch positioning action, then gradually symmetrically placed abutment wall arch.
5. the first support placed on job platform or second support are gradually fixedly connected with high-strength bolt.
6. checking the junction steel plate piece of steel arch-shelf, being bolted gap, junction steel plate and first support or second support Welding quality, plane warping degree, steel arch-shelf entirety radian and verticality.Remove underproof first support or second support.
7. completing assembled.
Spliced section-steel support:
The tunnel supporting method of the spliced steel arch-shelf of the present embodiment 1 ~ 3 is:
Firstly, tunnel excavation tunnel, both sides abutment wall divides left and right side to be staggered excavation;
Secondly, section-steel support, now installs bow supporter, abutment wall bracket, adjacent first support are being connected along bow supporter both ends Between, between first support and second support, be all made of high-strength bolt between adjacent second support will be by mutual corresponding company Hole is connect to connect;Upper padding plate and sand bedding course are padded at arch springing according to excavation method, when installation and is locked with lock foot anchoring stock, is convenient for Installation and excavation lower part;
Again, mounted steel arch-shelf is connected with longitudinally connected muscle, the tail portion of anchor pole is welded in by the assistant reinforcement of supporting On steel arch-shelf;Lock foot anchoring stock is accomplished fluently at arch springing in mounted steel arch-shelf, every side arch springing at least 4.(anchor pole model and length Construct by design drawing) it is adjacent to as far as possible between steel arch-shelf and first spray concrete;
Finally, injection fixation is carried out to supporting good steel arch-shelf concrete etc., especially when backbreaking excessive or Lack of support Basis is reinforced using jetting cement or Cast-in-place concrete.When concrete ejection is fixed, in strict accordance with vault after first abutment wall, what is got on, get off is suitable Sequence carry out, with reduce concrete due to gravity caused by sliding or obscission occur.
The series of detailed descriptions listed above only for feasible embodiment of the invention specifically Protection scope bright, that they are not intended to limit the invention, it is all without departing from equivalent implementations made by technical spirit of the present invention Or change should all be included in the protection scope of the present invention.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie In the case where without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power Benefit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent elements of the claims Variation is included within the present invention.Any reference signs in the claims should not be construed as limiting the involved claims.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (8)

1. a kind of spliced steel arch-shelf, including bow supporter (1), positioned at the abutment wall bracket (2) at bow supporter (1) both ends, vault Bracket (1) center and the line of centres at tunnel center are vertical with tunnel ground, and abutment wall bracket (2) is along line of centres mirror image pair Claim, be bolted to connection between bow supporter (1) and abutment wall bracket (2), it is characterised in that: the bow supporter (1) by Several first supports form after bolt is fixedly connected, and the abutment wall bracket (2) is fixed by several second supports through bolt It is formed after connection;
The first support and the second support include fashioned iron and junction steel plate (6), the center of junction steel plate (6) and fashioned iron The center of end is overlapped, and junction steel plate (6) is vertically welded in the end of fashioned iron, and offered on junction steel plate (6) two groups it is symmetrical Connecting hole (8);
The fashioned iron length and width for making the first support and the second support are all the same;
At the center of the junction steel plate (6), the groove (7) for positioning and being inserted into for fashioned iron, the groove (7) and institute are washed in milling It states fashioned iron cross sectional shape and size is identical.
2. a kind of spliced steel arch-shelf according to claim 1, it is characterised in that: the depth of the groove (7) is fashioned iron The 1/5~1/2 of thickness.
3. a kind of spliced steel arch-shelf according to claim 2, it is characterised in that: in the fashioned iron and the junction steel plate (6) weld is additionally provided with supporter, and the supporter is used to support and consolidates the junction steel plate (6).
4. a kind of spliced steel arch-shelf according to claim 3, it is characterised in that: the supporter is rectangular triangle steel Plate, a right-angle side and the fashioned iron for the rectangular triangle steel plate weld, and another side and the junction steel plate (6) are welded.
5. a kind of spliced steel arch-shelf according to claim 3, it is characterised in that: the supporter is steel bar, the steel One end is welded on the fashioned iron, and the other end is welded on the junction steel plate (6).
6. a kind of method for making spliced steel arch-shelf, it is characterised in that: include the following steps,
Step 1: steel arch-shelf design: measurement tunnel size designs bow supporter (1), the abutment wall bracket (2) of spliced steel arch-shelf Structure;Design the size and deformation radian of first support and second support;
Step 2: material prepare: fashioned iron raw material is cut into the size of design, with forming mill cold-bending deformation make first support and The fashioned iron of second support;Junction steel plate (6) plate is cut into the size of design, and makes groove (7) on junction steel plate (6) And connecting hole (8);
Step 3: it assists transporting on track in forming mill that junction steel plate (6) vertical welding to the both ends of fashioned iron is made first Frame and second support;
Step 4: it is spare that first support and second support are placed into bracket storage region.
7. a kind of method for making spliced steel arch-shelf according to claim 6, it is characterised in that: in the step 3, It further include in the junction steel plate (6) of first support and second support and deformation junction welding supporter.
8. a kind of method for making spliced steel arch-shelf according to claim 6, it is characterised in that: it further include step 5, First support and second support are tried to spell in the area Shi Pin, remove underproof first support or second support.
CN201910043698.8A 2019-01-17 2019-01-17 A kind of spliced steel arch-shelf and preparation method thereof Pending CN109736857A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910043698.8A CN109736857A (en) 2019-01-17 2019-01-17 A kind of spliced steel arch-shelf and preparation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910043698.8A CN109736857A (en) 2019-01-17 2019-01-17 A kind of spliced steel arch-shelf and preparation method thereof

Publications (1)

Publication Number Publication Date
CN109736857A true CN109736857A (en) 2019-05-10

Family

ID=66365000

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910043698.8A Pending CN109736857A (en) 2019-01-17 2019-01-17 A kind of spliced steel arch-shelf and preparation method thereof

Country Status (1)

Country Link
CN (1) CN109736857A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185478A (en) * 2019-05-31 2019-08-30 中国铁建重工集团股份有限公司 A kind of splicing apparatus, steel arch-shelf section and steel arch-shelf
CN111706368A (en) * 2020-06-30 2020-09-25 中铁二院工程集团有限责任公司 Tunnel inner section steel frame longitudinal connection structure and construction method
CN113503173A (en) * 2021-07-12 2021-10-15 内蒙古工业大学 Mine roadway support steel arch frame and mounting method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105909280A (en) * 2016-06-13 2016-08-31 中铁五局集团有限公司 Installing structure for super-large section tunnel arch wall lining rebar positioning and reinforcing
CN206205908U (en) * 2016-06-22 2017-05-31 中交第一公路勘察设计研究院有限公司 A kind of channel-section steel bow member joist for preventing tunnel subsidence to deform
CN206816279U (en) * 2017-06-23 2017-12-29 中铁十二局集团有限公司 A kind of U-shaped branch of continuous adjustable steel arch-shelf founds device
CN206816278U (en) * 2017-06-28 2017-12-29 中铁四局集团有限公司 The new recyclable supporting steel arch-shelf of horizontal ground settlement and tunnel
CN208010367U (en) * 2018-02-08 2018-10-26 贵州大学 A kind of tunnel shaped steel arch spatial cooperation support system
JP2018178451A (en) * 2017-04-07 2018-11-15 前田建設工業株式会社 Connection structure, connection method and erecting method of steel support
CN108894799A (en) * 2018-08-30 2018-11-27 沈阳建筑大学 The light high type of large cross-section tunnel combines steelframe

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105909280A (en) * 2016-06-13 2016-08-31 中铁五局集团有限公司 Installing structure for super-large section tunnel arch wall lining rebar positioning and reinforcing
CN206205908U (en) * 2016-06-22 2017-05-31 中交第一公路勘察设计研究院有限公司 A kind of channel-section steel bow member joist for preventing tunnel subsidence to deform
JP2018178451A (en) * 2017-04-07 2018-11-15 前田建設工業株式会社 Connection structure, connection method and erecting method of steel support
CN206816279U (en) * 2017-06-23 2017-12-29 中铁十二局集团有限公司 A kind of U-shaped branch of continuous adjustable steel arch-shelf founds device
CN206816278U (en) * 2017-06-28 2017-12-29 中铁四局集团有限公司 The new recyclable supporting steel arch-shelf of horizontal ground settlement and tunnel
CN208010367U (en) * 2018-02-08 2018-10-26 贵州大学 A kind of tunnel shaped steel arch spatial cooperation support system
CN108894799A (en) * 2018-08-30 2018-11-27 沈阳建筑大学 The light high type of large cross-section tunnel combines steelframe

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185478A (en) * 2019-05-31 2019-08-30 中国铁建重工集团股份有限公司 A kind of splicing apparatus, steel arch-shelf section and steel arch-shelf
CN111706368A (en) * 2020-06-30 2020-09-25 中铁二院工程集团有限责任公司 Tunnel inner section steel frame longitudinal connection structure and construction method
CN113503173A (en) * 2021-07-12 2021-10-15 内蒙古工业大学 Mine roadway support steel arch frame and mounting method thereof
CN113503173B (en) * 2021-07-12 2023-07-14 内蒙古工业大学 Mine roadway support steel arch frame and installation method thereof

Similar Documents

Publication Publication Date Title
CN109736857A (en) A kind of spliced steel arch-shelf and preparation method thereof
CN106869329B (en) Splice node and its construction method in assembling steel plate concrete shear force wall scene
CN108442933B (en) Shield starting base and shield starting method
ES2533339T3 (en) Formwork modules, assembled and disposable, to build modular formwork to make concrete foundations
KR101762155B1 (en) Twin wall having detachable truss and the manufacturing method thereof
CN109137720A (en) Prefabricated case beam and construction method
CN210797303U (en) Road and bridge prefabricated component installation positioner
US20090108170A1 (en) Concrete forming system
CN207794090U (en) Inner supporting device for pattern foundation pit supporting structure
CN209724364U (en) A kind of spliced steel arch-shelf
CN206290080U (en) Guardrail
CN106499187A (en) A kind of arm support and concrete spraying machine
CN207841707U (en) Assembled beam making bench
CN105414841A (en) Assembling die
CN109440653A (en) Suitable for the erecting beam construction method and auxiliary shifting beam equipment under special space
CN104695702A (en) Hyperbolic hopper template and support method thereof of coal storage bunker
KR102362712B1 (en) Prefabricated beam formwork
CN212469580U (en) A connect positioning die for processing of bridge steel reinforcement cage
CN209163439U (en) Tool-typed formwork installs structure at a kind of structure drop plate
CN203655136U (en) Foldable vertical ladder used for portal crane
CN208686400U (en) The support unit of branch structure at the beginning of a kind of subsurface excavation method for PBA
CN204738430U (en) Concrete precast slab grade beam fetal membrane supports and positioning tool
CN107366295B (en) The structural assembly of positioning controller
CN205116872U (en) Modularization communication tower
CN107419653B (en) A kind of spliced bridge and bridge jointing method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190510