CN109736634A - Precast concrete earth-retaining enclosure wall - Google Patents

Precast concrete earth-retaining enclosure wall Download PDF

Info

Publication number
CN109736634A
CN109736634A CN201811649888.6A CN201811649888A CN109736634A CN 109736634 A CN109736634 A CN 109736634A CN 201811649888 A CN201811649888 A CN 201811649888A CN 109736634 A CN109736634 A CN 109736634A
Authority
CN
China
Prior art keywords
wall
block
assembling block
convex block
vertical chute
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811649888.6A
Other languages
Chinese (zh)
Other versions
CN109736634B (en
Inventor
邱峰
李懋
梁晨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Luzhou Xingluyuan Architectural Technology Co Ltd
Original Assignee
Luzhou Xingluyuan Architectural Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Luzhou Xingluyuan Architectural Technology Co Ltd filed Critical Luzhou Xingluyuan Architectural Technology Co Ltd
Priority to CN201811649888.6A priority Critical patent/CN109736634B/en
Publication of CN109736634A publication Critical patent/CN109736634A/en
Application granted granted Critical
Publication of CN109736634B publication Critical patent/CN109736634B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)
  • Retaining Walls (AREA)

Abstract

The invention discloses one kind to be assembled at the scene, and structure is simple, and the position of each precast concrete block forms the precast concrete earth-retaining enclosure wall of feature wall to realize to landscape arrangement in adjustable earth-retaining enclosure wall.The precast concrete earth-retaining enclosure wall, including mounting base, installation lateral column, wall assembling block and upper beam;The two sides for the wall that the wall assembling block horizontally and vertically stacks formation are provided with installation lateral column, and the installation lateral column is prefabricated vertical columns;The wall lower end is provided with mounting base;Prefabricated upper beam is provided at the top of the wall.Using the precast concrete earth-retaining enclosure wall, construction is simple is easy to operate, can reduce construction cost;Improve working efficiency.

Description

Precast concrete earth-retaining enclosure wall
Technical field
The present invention relates to a kind of retaining wall, especially a kind of precast concrete earth-retaining enclosure wall.
Background technique
Well-known: retaining wall is generally used for slopes earth-retaining, prevents the native stone in slopes from falling.Gear of the present invention Earthen wall refers to the earth-retaining enclosure wall in cell.Existing retaining wall, it is higher to the intensity requirement of wall, and generally using scene Construction carries out prefabricated.Existing cell enclosure wall is typically also by being built on-site, and therefore, construction period is longer, construction cost compared with It is high.
Summary of the invention
Technical problem to be solved by the invention is to provide one kind to be assembled at the scene, and structure is simple, and can To adjust the position of each precast concrete block in earth-retaining enclosure wall, landscape is arranged to realize, forms the prefabricated mixed of feature wall Solidifying soil earth-retaining enclosure wall.
The technical solution adopted by the present invention to solve the technical problems is: precast concrete earth-retaining enclosure wall, including installation bottom Plate, installation lateral column, wall assembling block and upper beam;
The wall assembling block includes assembling block body;It is described assembling block body four sides in two on side It is provided with the first the vertical chute, one end of first the vertical chute is provided with and matched first convex block of the first the vertical chute;
The another two in four sides of block body is assembled described in the assembling block body to being provided with two on side The second vertical the vertical chute;The lower end of second the vertical chute is provided with and matched second convex block of the second the vertical chute; And first convex block and the second convex block are located at the same end of assembling block body;
The both ends of first the vertical chute and the second the vertical chute are blind head;Have between two the second the vertical chutes There is spacing;
The first the vertical chute and the second the vertical chute of the wall assembling block are horizontal positioned, and the wall assembles block Horizontal and vertical stack forms wall, and the wall assembling block in two neighboring horizontal direction is provided with the first convex block and the second convex block One end it is contrary;
Wall assembling block in two neighboring vertical direction is provided with the first convex block and one end of the second convex block is contrary;
In horizontal direction between two adjacent walls assembling block, the first convex block of a wall assembling block is inserted into another In first the vertical chute of a wall assembling block;
Between wall assembling block in two neighboring vertical direction, the second convex block of the wall assembling block of top is inserted into down In second the vertical chute of the wall assembling block of side;
The two sides for the wall that the wall assembling block horizontally and vertically stacks formation are provided with installation lateral column, the installation Lateral column is prefabricated vertical columns;The wall lower end is provided with mounting base;Prefabricated upper cross is provided at the top of the wall Beam.
Further, the precast concrete earth-retaining enclosure wall, including at least two walls assemble block levels and erect To the wall formed is stacked, engraved structure is provided between two walls.
Further, the both ends of the mounting base are provided with fixing seat;It is provided in the installation floor and wall group Fill the matched slot of the second convex block on block.
Further, fixed convex block is provided with below the fixing seat;It is provided on the lateral surface of the fixed convex block Horizontal-extending fixed steel bars.
The beneficial effects of the present invention are: precast concrete earth-retaining enclosure wall of the present invention, due to setting feature wall to Single wall assembles block, wall assembling block can be carried out by factory it is prefabricated, so as to avoid site operation bring at This increase;Wall is assembled secondly by assembling block, construction is simple is easy to operate, can reduce construction cost;Improve work Make efficiency.
Again, the position of wall assembling block can be adjusted, so that occurring being recessed on wall or protrusion, be passed through Landscape arrangement is carried out in recess, is capable of forming feature wall.
Detailed description of the invention
Fig. 1 is the main view for being provided with engraved structure of precast concrete earth-retaining enclosure wall in the embodiment of the present invention;
Fig. 2 is the main view of precast concrete earth-retaining enclosure wall in the embodiment of the present invention;
Fig. 3 is the perspective view of the explosion when assembled of precast concrete earth-retaining enclosure wall wall assembling block in the embodiment of the present invention;
Fig. 4 is the perspective view in the embodiment of the present invention after precast concrete earth-retaining enclosure wall wall assembling block assembling;
Fig. 5 is the main view in the embodiment of the present invention after precast concrete earth-retaining enclosure wall wall assembling block assembling;
Fig. 6 is the top view in the embodiment of the present invention after precast concrete earth-retaining enclosure wall wall assembling block assembling;
Fig. 7 is the A-A cross-sectional view of Fig. 5;
Fig. 8 is the B-B cross-sectional view of Fig. 6;
Fig. 9 is the perspective view of precast concrete earth-retaining enclosure wall wall assembling block in the embodiment of the present invention;
Figure 10 is the main view of precast concrete earth-retaining enclosure wall wall assembling block in the embodiment of the present invention;
Figure 11 is the side view of precast concrete earth-retaining enclosure wall wall assembling block in the embodiment of the present invention;
Figure 12 is the structural schematic diagram of the mounting base of precast concrete earth-retaining enclosure wall in the embodiment of the present invention;
Indicate in figure: 1- mounting base, 2- install lateral column, and 3- wall assembles block, 4- upper beam, 5- engraved structure.
Specific embodiment
Present invention will be further explained below with reference to the attached drawings and examples.
As shown in Figures 1 to 10, precast concrete earth-retaining enclosure wall of the present invention, including mounting base 1, installation lateral column 2, wall assembling block 3 and upper beam 4;
The wall assembling block 3 includes assembling block body 31;Two in four sides of the assembling block body 31 are right The first the vertical chute 32 is provided on side, one end of first the vertical chute 32 be provided with it is matched with the first the vertical chute First convex block 33;
Another two in four sides of assembling block body 31 described in the assembling block body 31 on side to being provided with Two the second vertical the vertical chutes 35;The lower end of second the vertical chute 35 is provided with matched with the second the vertical chute 35 Second convex block 34;And first convex block 33 and the second convex block 34 are located at the same end of assembling block body 31;
The both ends of first the vertical chute 32 and the second the vertical chute 34 are blind head;Two the second the vertical chutes 34 Between have spacing;
The first the vertical chute 32 and the second the vertical chute 34 of the wall assembling block 3 are horizontal positioned, and the wall Assembling block 3, which horizontally and vertically stacks, forms wall, and the wall assembling block 3 in two neighboring horizontal direction is provided with the first convex block 33 It is contrary with one end of the second convex block 34;
Wall assembling block 3 in two neighboring vertical direction is provided with an extreme direction of the first convex block 33 and the second convex block 34 On the contrary;
In horizontal direction between two adjacent walls assembling block 3, the first convex block 33 of a wall assembling block 3 is inserted into Another wall assembles in the first the vertical chute 32 of block 3;
Between wall assembling block 3 in two neighboring vertical direction, the second convex block 34 insertion of the wall assembling block 3 of top Into the second the vertical chute 34 of the wall assembling block 3 of lower section;
The two sides that the wall assembling block 3 horizontally and vertically stacks the wall formed are provided with installation lateral column 2, the peace Dress lateral column 2 is prefabricated vertical columns;The wall lower end is provided with mounting base 1;It is provided at the top of the wall prefabricated Upper beam 4.
In application process, mounting base 1, installation lateral column 2, wall assembling block 3 and upper beam 4 are passed through coagulation by prime minister Soil progress is prefabricated, then prefabricated finished product is transported to the construction site for needing to install earth-retaining enclosure wall.
At the scene in work progress, mounting base 1 is installed first in ground base, then wall assembling block 3 is installed On mounting base 1, after wall assembling block 3 is stacked into corresponding height, stops assembling wall and assemble block 3;Then in wall group Fill the two sides installation installation lateral column 2 of block 3;The top for the wall being finally stacked into wall assembling block 3 is installed by upper beam 4;To The installation to wall is completed, workload can be effectively reduced, shortens construction period, reduces construction cost.
After wall is completed, the wall assembling block 3 on wall can be pushed to make part wall according to the demand of user Body assembles 3 protrusion of block, another portion concave, so that forming corresponding cavity on wall.
Then corresponding view can be arranged in cavity, form feature wall.
In conclusion precast concrete earth-retaining enclosure wall of the present invention, due to setting single wall for feature wall Assemble block, wall assembling block can be carried out by factory it is prefabricated, so as to avoid site operation bring increased costs;Secondly Wall is assembled by assembling block, construction is simple is easy to operate, can reduce construction cost;Improve working efficiency.
Again, the position of wall assembling block can be adjusted, so that occurring being recessed on wall or protrusion, be passed through Landscape arrangement is carried out in recess, is capable of forming feature wall.
Earth-retaining enclosure wall is used in order to avoid not needing the position of earth-retaining partially, so that the cost for causing earth-retaining enclosure wall to build increases Add, further, the precast concrete earth-retaining enclosure wall, including at least two walls assemble the horizontal and vertical heap of block 3 The wall formed is folded, is provided with engraved structure 5 between two walls.
In order to reduce the installation contact area of installation floor 1 Yu ground base, further, the two of the mounting base 1 End is provided with fixing seat 11;It is provided in the installation floor 1 and the matched slot of the second convex block 34 on wall assembling block 3 13.Therefore fixing seat 11 need to be only fixed in ground base.
In order to increase installation fastness of the fixing seat 11 in ground base, further, the lower section of the fixing seat 11 It is provided with fixed convex block 14;Horizontal-extending fixed steel bars 14 are provided on the lateral surface of the fixed convex block 14.

Claims (4)

1. precast concrete earth-retaining enclosure wall, it is characterised in that: including mounting base (1), installation lateral column (2), wall assembling block (3) And upper beam (4);
Wall assembling block (3) includes assembling block body (31);Two in four sides of assembling block body (31) One end that the first the vertical chute (32), first the vertical chute (32) are provided on side is provided with and the first the vertical chute Matched first convex block (33);
Another two in four sides of assembling block body (31) assembling block body (31) on side to being provided with Two vertical the second the vertical chutes (35);The lower end of second the vertical chute (35) is provided with and the second the vertical chute (35) Matched second convex block (34);And first convex block (33) and the second convex block (34) are located at the same of assembling block body (31) End;
The both ends of first the vertical chute (32) and the second the vertical chute (34) are blind head;Two the second the vertical chutes (34) there is spacing between;
The first the vertical chute (32) and the second the vertical chute (34) of wall assembling block (3) are horizontal positioned, and the wall Body assembling block (3) horizontally and vertically stacks and forms wall, and wall assembling block (3) in two neighboring horizontal direction is provided with first One end of convex block (33) and the second convex block (34) is contrary;
Wall assembling block (3) in two neighboring vertical direction is provided with one end side of the first convex block (33) and the second convex block (34) To opposite;
In horizontal direction between two adjacent walls assembling block (3), the first convex block (33) insertion of wall assembling block (3) Into the first the vertical chute (32) of another wall assembling block (3);
Between wall assembling block (3) in two neighboring vertical direction, the second convex block (34) of wall assembling block (3) of top is inserted Enter into the second the vertical chute (34) of wall assembling block (3) of lower section;
The two sides that wall assembling block (3) horizontally and vertically stacks the wall formed are provided with installation lateral column (2), the peace Filling lateral column (2) is prefabricated vertical columns;The wall lower end is provided with mounting base (1);It is provided at the top of the wall pre- The upper beam (4) of system.
2. precast concrete earth-retaining enclosure wall according to claim 1, it is characterised in that: including at least two wall groups It fills block (3) and horizontally and vertically stacks the wall formed, be provided with engraved structure (5) between two walls.
3. precast concrete earth-retaining enclosure wall according to claim 2, it is characterised in that: the both ends of the mounting base (1) It is provided with fixing seat (11);It is provided on the installation floor (1) matched with the second convex block (34) in wall assembling block (3) Slot (13).
4. precast concrete earth-retaining enclosure wall according to claim 3, it is characterised in that: set below the fixing seat (11) It is equipped with fixed convex block (14);Horizontal-extending fixed steel bars (14) are provided on the lateral surface of the fixed convex block (14).
CN201811649888.6A 2018-12-31 2018-12-31 Precast concrete retaining wall Active CN109736634B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811649888.6A CN109736634B (en) 2018-12-31 2018-12-31 Precast concrete retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811649888.6A CN109736634B (en) 2018-12-31 2018-12-31 Precast concrete retaining wall

Publications (2)

Publication Number Publication Date
CN109736634A true CN109736634A (en) 2019-05-10
CN109736634B CN109736634B (en) 2022-05-06

Family

ID=66362996

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811649888.6A Active CN109736634B (en) 2018-12-31 2018-12-31 Precast concrete retaining wall

Country Status (1)

Country Link
CN (1) CN109736634B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100283022A1 (en) * 2009-02-03 2010-11-11 Warren Delafield Modular Railing Systems with Cellular PVC Panels
CN202220344U (en) * 2011-09-28 2012-05-16 招商局重庆交通科研设计院有限公司 Building module for assembling retaining walls
CN103243739A (en) * 2013-05-15 2013-08-14 招商局重庆交通科研设计院有限公司 Reinforced retaining wall ecological panel structure with self-interlocking function
CN103603370A (en) * 2013-12-07 2014-02-26 黄靓 Spatial crossed and embedded ecological building block retaining wall and construction method thereof
CN205296210U (en) * 2015-12-23 2016-06-08 昆山通海建材科技有限公司 View barricade
CN206681491U (en) * 2017-04-17 2017-11-28 四川建筑职业技术学院 The detachable assembled enclosure wall in building site
CN108487306A (en) * 2018-06-05 2018-09-04 核工业井巷建设集团公司 A kind of Retaining Wall and its construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100283022A1 (en) * 2009-02-03 2010-11-11 Warren Delafield Modular Railing Systems with Cellular PVC Panels
CN202220344U (en) * 2011-09-28 2012-05-16 招商局重庆交通科研设计院有限公司 Building module for assembling retaining walls
CN103243739A (en) * 2013-05-15 2013-08-14 招商局重庆交通科研设计院有限公司 Reinforced retaining wall ecological panel structure with self-interlocking function
CN103603370A (en) * 2013-12-07 2014-02-26 黄靓 Spatial crossed and embedded ecological building block retaining wall and construction method thereof
CN205296210U (en) * 2015-12-23 2016-06-08 昆山通海建材科技有限公司 View barricade
CN206681491U (en) * 2017-04-17 2017-11-28 四川建筑职业技术学院 The detachable assembled enclosure wall in building site
CN108487306A (en) * 2018-06-05 2018-09-04 核工业井巷建设集团公司 A kind of Retaining Wall and its construction method

Also Published As

Publication number Publication date
CN109736634B (en) 2022-05-06

Similar Documents

Publication Publication Date Title
EP1996774B1 (en) Building block
JP4119946B2 (en) Stabilizing element for mechanically stabilized soil structure and mechanically stabilized soil structure
US6168353B1 (en) Retaining wall and method of wall construction
US20100310324A1 (en) Multi-component retaining wall block
CN210767243U (en) Assembled building frame construction
JP6343727B1 (en) Self-supporting retaining wall and connecting block
EP1618266B1 (en) A method for making coating walls
CN103572775A (en) Semi-assembly type retaining wall of soil filling slope and construction method for semi-assembly type retaining wall
EP1711661B1 (en) A bifacial reinforcing unit for earthworks and a method for the production of a reinforced earthwork
JP2001311169A (en) Block for earth retaining wall
CN109736634A (en) Precast concrete earth-retaining enclosure wall
KR100481160B1 (en) The retaining wall for a block
JP5984754B2 (en) Solid foundation method using PC unit and PC unit
US6213689B1 (en) Construction unit for a retaining wall and a method for constructing the retaining wall
CN105714847B (en) A kind of reinforced earth bulkhead concrete modular and combinations thereof method
CN210976179U (en) Keel system rammed earth wall
RU176405U1 (en) SUPPORT WALL UNIT
CN218667871U (en) Floor structure of assembled building
JP3806628B2 (en) Building basic structure and construction method
JP3212647U (en) Concrete block
JP6279892B2 (en) Form for wall construction and construction method of wall using the same
JP2000336677A (en) L-shaped piled block for retaining wall
CN212535319U (en) Prefabricated enclosure wall for upper part of concrete retaining wall
JP2771581B2 (en) Construction method of mating concrete block
KR101331449B1 (en) Precasting block for foundation work and the method of foundation work using it

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant