CN109723369A - A kind of pole ascending operation device and its step on bar method - Google Patents

A kind of pole ascending operation device and its step on bar method Download PDF

Info

Publication number
CN109723369A
CN109723369A CN201910010367.4A CN201910010367A CN109723369A CN 109723369 A CN109723369 A CN 109723369A CN 201910010367 A CN201910010367 A CN 201910010367A CN 109723369 A CN109723369 A CN 109723369A
Authority
CN
China
Prior art keywords
bridge
additional
connecting band
pole
keel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910010367.4A
Other languages
Chinese (zh)
Inventor
钱柏贤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Jia Rui Electric Power Engineering Co Ltd
Original Assignee
Henan Jia Rui Electric Power Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Jia Rui Electric Power Engineering Co Ltd filed Critical Henan Jia Rui Electric Power Engineering Co Ltd
Priority to CN201910010367.4A priority Critical patent/CN109723369A/en
Publication of CN109723369A publication Critical patent/CN109723369A/en
Pending legal-status Critical Current

Links

Landscapes

  • Emergency Lowering Means (AREA)

Abstract

The present invention relates to a kind of pole ascending operation device and its bar method is stepped on, including a master steps on bridge and at least one adds and steps on bridge;It includes main joist that master, which steps on bridge, the bottom of main joist is provided with pedestal, the bottom of pedestal is provided with lower margin, connected slot is provided at the top of main joist, additional bridge of stepping on includes additional keel, connected slot is also equipped at the top of additional keel, the bottom of additional keel is provided with the connection plug matched with connected slot, the two sides of main joist and additional keel are provided with several pole for climbing, slideway is provided in the middle part of main joist and additional keel, seat-belt anchorage is arranged in the inside of slideway, it is with stopper that the outside of slideway is provided with the safety matched with seat-belt anchorage, the back side of main joist and additional keel is evenly arranged with snap-gauge along the vertical direction, the both ends of snap-gauge are respectively arranged with the first connecting band and the second connecting band, first connecting band is connect with the free end of the second connecting band by eye-splice.

Description

A kind of pole ascending operation device and its step on bar method
Technical field
The invention belongs to electric operating technical fields, and in particular to a kind of pole ascending operation device and its step on bar method.
Background technique
In 110kV and transmission of electricity below or distribution line, most of routes make full use of city because increasing economic efficiency Occupied area uses cement pole for shaft tower main body, carries transmission pressure, carries out power Transmission.Such route is modern city The core force of electric line.To promote power supply quality, power supply reliability, O&M and service work to such route are improved As the key points and difficulties in power transmission and distribution work.
When overhauling to cement shaft tower, traditional bar mode of stepping on is divided into two kinds, one is climbers are used, is stepped on Bar, another kind are alternately to be climbed using pedal, carried out stepping on bar.Shaft tower surface moisture or winter shaft tower surface freeze after the rain When, danger of falling of skidding is easy using above-mentioned bar mode of stepping on, threatens personal safety, and stepped on using aforesaid way Bar needs to be grasped certain skill, not practical enough.
Summary of the invention
In view of the deficiencies of the prior art, the present invention provides a kind of structurally reasonable, easy to use, safety and firmness steps on bar work Industry device and its step on bar method.
The technical scheme of the present invention is realized as follows: pole ascending operation device, including a master step on bridge and at least one It is additional to step on bridge;It includes main joist that master, which steps on bridge, and the bottom of main joist is provided with pedestal, and the bottom of pedestal is provided with lower margin, main Connected slot is provided at the top of keel, additional bridge of stepping on includes additional keel, is also equipped with connection at the top of additional keel and inserts The bottom of slot, additional keel is provided with the connection plug matched with connected slot, and the two sides of main joist and additional keel are all provided with Several pole for climbing are equipped with, slideway, the fixed dress of inside setting safety belt of slideway are provided in the middle part of main joist and additional keel It sets, the outside of slideway is provided with that the safety matched with seat-belt anchorage is with stopper, main joist and additional keel The back side is evenly arranged with snap-gauge along the vertical direction, and the both ends of snap-gauge are respectively arranged with the first connecting band and the second connecting band, and first Connecting band is connect with the free end of the second connecting band by eye-splice.
The seat-belt anchorage includes the slide plate being arranged in inside slideway, is provided in the middle part of slide plate and extends to cunning Fixed ring outside road is evenly arranged with the ball matched with slideway on slide plate.
The safety with stopper includes the sleeve being fixed at outside slideway, and being internally provided with for sleeve runs through The pull rod of slideway, the pull rod outer sheath of sleeve inner are equipped with spring, are provided on pull rod and match with spring close to slideway one end Snap ring.
The pole for climbing main joist and additional keel two sides interlaced arrangement, between two pole for climbing of the same side Between be divided into 40-80cm.
The two sides of the main joist and additional keel are provided with four pole for climbing, between two pole for climbing of the same side Between be divided into 80cm, the length of main joist and additional keel is 320cm.
The lower margin is square plate body structure, and the top of lower margin and the bottom of pedestal are hinged, and the bottom of lower margin is set It is equipped with non-slip mat.
The snap-gauge is arc plate body, and main joist is structure as a whole with the snap-gauge that its back is arranged in, add keel and The snap-gauge that its back is arranged in is structure as a whole.
The free end of first connecting band is provided with male plug button, and the free end of the second connecting band is provided with female plug button, Female plug button and male plug button are in mating connection.
Tri-glide is provided in first connecting band and/or the second connecting band.
Pole ascending operation device as described above steps on bar method, comprising the following steps:
S1, preparation: the additional quantity n for stepping on bridge of height H selection of climbing shaft tower as needed, wherein the main height for stepping on bridge Degree is h1, the additional height for stepping on bridge is h2, n satisfaction:
The value round of n additional quantity for stepping on bridge needed for being;
S2, master step on bridge and set up: main bridge of stepping on is close to shaft tower, and lower margin is made to keep horizontal positioned, from the bottom to top successively will be on snap-gauge First connecting band of connection is connect around to shaft tower rear side by eye-splice with the second connecting band;
S3, additional to step on bridge and set up: additional bridge of stepping on is close to shaft tower, so that the additional connection plug for stepping on bridge bottom is inserted into master and steps on The first connecting band connected on snap-gauge is successively surround by the inside of the connected slot at the top of bridge with the second connecting band from the bottom to top It is connected on rear side of to shaft tower by eye-splice
If n > 1, continues to insert to add on the mounted additional top for stepping on bridge and step on bridge, and pass through the first connecting band and second Connecting band is fixed;
S4, steps on bar operation: operator's wear safety belt, and safety belt is connected with fixed ring, seat-belt anchorage with The climbing elevated height of operator and upward sliding, while with elevated height, during seat-belt anchorage sliding The fixed device of drag link safety band in the safety caging device for needing that it is pulled to be passed through.
Technical solution of the present invention has following good effect:
1. structure is simple, rationally, it is firm to connect with shaft tower for design, guarantees operator's life safety;
2. it is easy to use convenient for assembly, it can be added according to the different selection different numbers of shaft tower height and step on bridge, be suitable for climbing The shaft tower of different height;
It is combined 3. safety is with stopper with seat-belt anchorage, can effectively protect operator, avoid the mistake in climbing It is fallen in journey due to fault;
4. method provided by through the invention, assembled speed is fast, primary assembled for more people climbing shaft tower use, is obviously improved Working efficiency.
Detailed description of the invention
Fig. 1 is the main structural schematic diagram for stepping on bridge in the present invention.
Fig. 2 is that the structural schematic diagram for stepping on bridge is added in the present invention.
Fig. 3 is the main top view for stepping on bridge in the present invention.
Fig. 4 is that the top view for stepping on bridge is added in the present invention.
Fig. 5 is the structural schematic diagram of seat-belt anchorage in the present invention.
The main safety stepped on bridge structural schematic diagram with stopper in Fig. 6 present invention.
The safety stepped on bridge structural schematic diagram with stopper is added in Fig. 7 present invention.
Specific embodiment
A specific embodiment of the invention is further described with reference to the accompanying drawings and embodiments, following embodiment is used It clearly describes technical solution of the present invention, and cannot be limited the scope of protection of the present invention with this.
Pole ascending operation device as shown in Figures 1 to 4, including a master steps on bridge and at least one adds and steps on bridge;Master steps on Bridge includes main joist 3, and the bottom of main joist 3 is provided with pedestal 2, and the bottom of pedestal 2 is provided with lower margin 1, the top of main joist 3 It is provided with connected slot 15, additional bridge of stepping on includes additional keel 7, and the top of additional keel 7 is also equipped with connected slot 15, attached The bottom of keel 7 is added to be provided with the connection plug 8 matched with connected slot 15, main joist 3 and the two sides of additional keel 7 are all provided with It is equipped with several pole for climbing 4, the middle part of main joist 3 and additional keel 7 is provided with slideway 9, and the inside setting safety belt of slideway 9 is solid Determine device 5, the outside of slideway 9 is provided with the safety matched with seat-belt anchorage 5 with stopper 6, main joist 3 with it is attached Add the back side of keel 7 to be evenly arranged with snap-gauge 10 along the vertical direction, the both ends of snap-gauge 10 be respectively arranged with the first connecting band 11 with Second connecting band 12, the first connecting band 11 are connect with the free end of the second connecting band 12 by eye-splice.
The pole for climbing 4 main joist 3 and additional keel 7 two sides interlaced arrangement, two pole for climbing 4 of the same side it Between between be divided into 40-80cm.The two sides of the main joist 3 and additional keel 7 are provided with four pole for climbing 4, the same side It is divided into 80cm between two pole for climbing 4, the length of main joist 3 and additional keel 7 is 320cm.The lower margin 1 is positive Square plate structure, the top of lower margin 1 and the bottom of pedestal 2 are hinged, and the bottom of lower margin 1 is provided with non-slip mat.Non-slip mat can Using rubber pad, the bottom of lower margin 1 is transferred on by bolt.The snap-gauge 10 is arc plate body, and main joist 3 and setting are at it The snap-gauge 10 at back is structure as a whole, and additional keel 7 are structure as a whole with the snap-gauge 10 that its back is arranged in.The main master for stepping on bridge Two snap-gauges 10 are at least arranged in 3 rear side of keel, and the middle part of main joist 3 is arranged in one of snap-gauge 10, another snap-gauge 10 is set It sets at the top of main joist 3;Two snap-gauges 10, one of snap-gauge 10 is at least arranged in additional 7 rear side of additional keel for stepping on bridge The middle part of additional keel 7 is set, and the top of additional keel 7 is arranged in another snap-gauge 10.First connecting band 11 Free end is provided with male plug button 13, and the free end of the second connecting band 12 is provided with female plug button 14, female plug button 14 and 13 phase of male plug button It is cooperatively connected.It is provided with tri-glide in first connecting band 11 and/or the second connecting band 12, it is adjustable by tri-glide The length of first connecting band 11, the second connecting band 12.
As shown in figure 5, the seat-belt anchorage 5 includes the slide plate 501 being arranged in inside slideway 9, slide plate 501 Middle part is provided with the fixed ring 503 extended to outside slideway 9, is evenly arranged with the ball matched with slideway 9 on slide plate 501 502.Slideway 9 is the T-slot for being provided with 7 side of main joist 3 and additional keel, and slide plate 501 is rectangular plate body, ball 502 Quantity is four, is uniformly provided with four circular through holes on slide plate 501 accordingly, clamps respectively in four circular through-holes One ball 502, ball 502 can be rotated in through-hole inner rotation with movement of the slide plate 501 in slideway 9.Fixed ring 503 be circular ring structure, and one side is fixedly connected by metallic rod with the middle part of slide plate 501.
As shown in Figures 6 and 7, the safety with stopper 6 includes the sleeve 601 being fixed at outside slideway 9, set The pull rod 602 of cylinder 601 being internally provided with through slideway 9,602 outer sheath of pull rod inside sleeve 601 are equipped with spring 603, drawing The snap ring 604 matched with spring 603 close to 9 one end of slideway is provided on bar 602.Pull rod 602 is pulled, pull rod 602, which is located at, to be slided Part inside road 9 is drawn out, and seat-belt anchorage 5 can pass through from this from slideway 9, and releasing lever 602, pull rod 602 is in bullet Under the action of spring 603 inside reduction insertion slideway 9, stops seat-belt anchorage 5 to pass through, can effectively protect operator, keep away Exempt to fall during climbing due to fault.Preferably, the slot matched with pull rod 602 is opened up in the inside of slideway 9, The slot is inserted under 602 reducing condition of pull rod.
Pole ascending operation device as described above steps on bar method, comprising the following steps:
S1, preparation: the additional quantity n for stepping on bridge of height H selection of climbing shaft tower as needed, wherein the main height for stepping on bridge Degree is h1, the additional height for stepping on bridge is h2, n satisfaction:
The value round of n additional quantity for stepping on bridge needed for being;
S2, master step on bridge and set up: main bridge of stepping on is close to shaft tower, so that lower margin 1 is kept horizontal positioned, from the bottom to top successively by snap-gauge 10 First connecting band 11 of upper connection is connect around to shaft tower rear side by eye-splice with the second connecting band 12;
S3, additional to step on bridge and set up: additional bridge of stepping on is close to shaft tower, and the additional connection plug 8 for stepping on bridge bottom is made to be inserted into master The inside of the connected slot 15 at the top of bridge is stepped on, from the bottom to top successively connects the first connecting band 11 and second connected on snap-gauge 10 Tape splicing 12 passes through eye-splice connection around to shaft tower rear side
If n > 1, continue that inserting is additional to step on bridge on the mounted additional top for stepping on bridge, and passes through the first connecting band 11 and the Two connecting bands 12 are fixed;
S4 steps on bar operation: operator's wear safety belt, and safety belt is connected with fixed ring 503, seat-belt anchorage 5 with the climbing elevated height of operator upward sliding, while with elevated height, in the mistake that seat-belt anchorage 5 slides 602 seat-belt anchorage 5 of pull rod in the safety caging device 6 in journey needing that it is pulled to be passed through.

Claims (10)

1. a kind of pole ascending operation device, it is characterised in that: step on bridge including a master and at least one adds and steps on bridge;Master steps on bar Frame includes main joist (3), and the bottom of main joist (3) is provided with pedestal (2), and the bottom of pedestal (2) is provided with lower margin (1), main dragon Connected slot (15) are provided at the top of bone (3), additional bridge of stepping on includes additional keel (7), and the top of additional keel (7) is also set Connected slot (15) are equipped with, the bottom of additional keel (7) is provided with the connection plug (8) matched with connected slot (15), main The two sides of keel (3) and additional keel (7) are provided with several pole for climbing (4), the middle part of main joist (3) and additional keel (7) It is provided with slideway (9), seat-belt anchorage (5) are arranged in the inside of slideway (9), and the outside of slideway (9) is provided with and safety The safety matched with fixed device (5) is (6) with stopper, and the back side of main joist (3) and additional keel (7) is along the vertical direction It being evenly arranged with snap-gauge (10), the both ends of snap-gauge (10) are respectively arranged with the first connecting band (11) and the second connecting band (12), the One connecting band (11) is connect with the free end of the second connecting band (12) by eye-splice.
2. pole ascending operation device according to claim 1, it is characterised in that: the seat-belt anchorage (5) includes The slide plate (501) internal in slideway (9) is set, is provided in the middle part of slide plate (501) and extends to the external fixed ring of slideway (9) (503), the ball (502) matched with slideway (9) is evenly arranged on slide plate (501).
3. pole ascending operation device according to claim 2, it is characterised in that: the safety (6) with stopper includes The sleeve (601) being fixed at outside slideway (9), the pull rod (602) of sleeve (601) being internally provided with through slideway (9), Internal pull rod (602) outer sheath of sleeve (601) is equipped with spring (603), is provided on pull rod (602) close with spring (603) The snap ring (604) that slideway (9) one end matches.
4. pole ascending operation device according to claim 1, it is characterised in that: the pole for climbing (4) in main joist (3) and The two sides interlaced arrangement of additional keel (7), between two pole for climbing (4) of the same side between be divided into 40-80cm.
5. pole ascending operation device according to claim 4, it is characterised in that: the main joist (3) and additional keel (7) Two sides be provided with four pole for climbing (4), between two pole for climbing (4) of the same side between be divided into 80cm, main joist (3) and The length of additional keel (7) is 320cm.
6. pole ascending operation device according to claim 1, it is characterised in that: the lower margin (1) is square plate body knot Structure, the top of lower margin (1) and the bottom of pedestal (2) are hinged, and the bottom of lower margin (1) is provided with non-slip mat.
7. pole ascending operation device according to claim 1, it is characterised in that: the snap-gauge (10) is arc plate body, main Keel (3) are structure as a whole with the snap-gauge (10) that its back is arranged in, additional keel (7) and the snap-gauge (10) that its back is arranged in It is structure as a whole.
8. pole ascending operation device according to claim 1, it is characterised in that: the free end of first connecting band (11) It is provided with male plug button (13), the free end of the second connecting band (12) is provided with female plug button (14), female plug button (14) and male plug button (13) in mating connection.
9. pole ascending operation device according to claim 1, it is characterised in that: first connecting band (11) and/or Two connecting bands are provided with tri-glide on (12).
10. a kind of pole ascending operation device as described in any one of claim 3-9 claim steps on bar method, feature exists In, comprising the following steps:
S1, preparation: the additional quantity n for stepping on bridge of height H selection of climbing shaft tower as needed, wherein the main height for stepping on bridge Degree is h1, the additional height for stepping on bridge is h2, n satisfaction:
The value round of n additional quantity for stepping on bridge needed for being;
S2, master step on bridge and set up: main bridge of stepping on is close to shaft tower, so that lower margin (1) is kept horizontal positioned, from the bottom to top successively by snap-gauge (10) the first connecting band (11) connected on is connect around to shaft tower rear side by eye-splice with the second connecting band (12);
S3, additional to step on bridge and set up: additional bridge of stepping on is close to shaft tower, is inserted into the additional connection plug (8) for stepping on bridge bottom The main inside for stepping on the connected slot (15) at the top of bridge, the first connecting band (11) that will successively be connected on snap-gauge (10) from the bottom to top It is connect around to shaft tower rear side by eye-splice with the second connecting band (12)
If n > 1, continue that inserting is additional to step on bridge on the mounted additional top for stepping on bridge, and by the first connecting band (11) with Second connecting band (12) is fixed;
S4 steps on bar operation: operator's wear safety belt, and safety belt is connected with fixed ring (503), the fixed dress of safety belt Set (5) with the climbing elevated height of operator upward sliding, it is sliding in seat-belt anchorage (5) while with elevated height Pull rod (602) seat-belt anchorage (5) in the safety caging device (6) in dynamic process needing that it is pulled to be passed through.
CN201910010367.4A 2019-01-07 2019-01-07 A kind of pole ascending operation device and its step on bar method Pending CN109723369A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910010367.4A CN109723369A (en) 2019-01-07 2019-01-07 A kind of pole ascending operation device and its step on bar method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910010367.4A CN109723369A (en) 2019-01-07 2019-01-07 A kind of pole ascending operation device and its step on bar method

Publications (1)

Publication Number Publication Date
CN109723369A true CN109723369A (en) 2019-05-07

Family

ID=66298810

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910010367.4A Pending CN109723369A (en) 2019-01-07 2019-01-07 A kind of pole ascending operation device and its step on bar method

Country Status (1)

Country Link
CN (1) CN109723369A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111760319A (en) * 2020-07-22 2020-10-13 王猛猛 Energy-saving hydroxypropyl methyl cellulose production is with chemical industry distillation column

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1997024506A1 (en) * 1995-12-29 1997-07-10 Söll Gmbh Device for connecting two one-rail ladder members
CN101509348A (en) * 2009-03-16 2009-08-19 林昌华 Single-column lean ladder and manufacture and use method thereof
DE202013006652U1 (en) * 2013-07-24 2013-08-23 Schwemmer & Dorn + Co Gmbh mast Head
KR20140005248U (en) * 2013-03-28 2014-10-08 주식회사 선광 엠 파 safety moving spparatus of ladder
US9631428B2 (en) * 2012-07-25 2017-04-25 Cal G. Niemela Tree-mounted supports

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1997024506A1 (en) * 1995-12-29 1997-07-10 Söll Gmbh Device for connecting two one-rail ladder members
CN101509348A (en) * 2009-03-16 2009-08-19 林昌华 Single-column lean ladder and manufacture and use method thereof
US9631428B2 (en) * 2012-07-25 2017-04-25 Cal G. Niemela Tree-mounted supports
KR20140005248U (en) * 2013-03-28 2014-10-08 주식회사 선광 엠 파 safety moving spparatus of ladder
DE202013006652U1 (en) * 2013-07-24 2013-08-23 Schwemmer & Dorn + Co Gmbh mast Head

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111760319A (en) * 2020-07-22 2020-10-13 王猛猛 Energy-saving hydroxypropyl methyl cellulose production is with chemical industry distillation column
CN111760319B (en) * 2020-07-22 2022-02-11 山东赫达股份有限公司 Energy-saving hydroxypropyl methyl cellulose production is with chemical industry distillation column

Similar Documents

Publication Publication Date Title
CN205759484U (en) Novel climbing rod grappler
CN109723369A (en) A kind of pole ascending operation device and its step on bar method
CN108465212B (en) Ascending tool capable of reducing use fatigue
CN209752099U (en) Pole climber
CN203915952U (en) A kind of communication pole climbers
DE202020104257U1 (en) Water inflatable surfboard with two air chambers
CN110005333B (en) Telescopic insulating ladder
CN102160927B (en) Device for tug of war
CN208465104U (en) A kind of electric pole safety climbing climbers
CN207654634U (en) A kind of Skidproof climbers for climbing electric pole
CN206183896U (en) Climbing safety auxiliary device for steel pylons
CN208862471U (en) Anchor support insulator chain overhauls mobile pedal
CN206762170U (en) Antifatigue climber for climbing
CN205516268U (en) Power line overhauls staple bolt with climbing wire pole
CN213347602U (en) Can long bamboo joint rope skipping of quick adjustment rope
CN210404546U (en) Safety wire-routing device
CN209862560U (en) High-altitude welding slag receiving umbrella
CN209618815U (en) Portable lifting machine
CN208877843U (en) A kind of climbers for preventing from falling off from electric pole
CN208426578U (en) A kind of anti-skidding Handle of skipping rope
CN207237185U (en) Power marketing power utility check Portable climbing device
CN218961712U (en) Climbing device for electric power operation and maintenance
CN218205625U (en) Spider man high altitude safety bedplate
CN205516265U (en) Step on pole operation safety hook
CN205586527U (en) Cableway water skiing device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190507