CN109707159A - A kind of pipeline that adjustable recycles hangs mould - Google Patents
A kind of pipeline that adjustable recycles hangs mould Download PDFInfo
- Publication number
- CN109707159A CN109707159A CN201910074368.5A CN201910074368A CN109707159A CN 109707159 A CN109707159 A CN 109707159A CN 201910074368 A CN201910074368 A CN 201910074368A CN 109707159 A CN109707159 A CN 109707159A
- Authority
- CN
- China
- Prior art keywords
- half module
- hole
- semicircle orifice
- module
- adjustable
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The invention discloses a kind of pipelines that adjustable recycles to hang mould, including left half module and right half module, and Zuo Banmo or right half module are semi-annular shape;The semicircle orifice both ends of semicircular ring are respectively equipped with fixing seat, and the fixing seat of semicircle orifice one end is equipped with through-hole, is equipped with bolt in through-hole;The fixing seat of the semicircle orifice other end (is equipped with threaded hole, the top wire hole perpendicular to threaded hole is equipped in the middle part of threaded hole;Left half module is fixed with right half module through being bolted, and through jackscrew.The configuration of the present invention is simple is easy production, solves the problems, such as that preformed hole construction is cumbersome, construction quality is not easy to control, higher to reserving hole precision and pitch requirements.The hole of different tube spacing can be used, artificial, reusable save the cost, the reduction wasting of resources are saved.After construction, without manual cleaning chisel mill, upper and lower interlayer reduces the trouble for clearing up fixed iron and steel wire before pouring, is not in infiltration hidden danger without being fixed with iron wire.
Description
Technical field
The present invention relates to a kind of pipelines that adjustable recycles to hang mould, belongs to building pipe mounting technique field.
Background technique
For high-rise civil building water supply and drainage construction engineering, a large amount of pipelines need guiding through the reserving hole of floor, secondary plugging
Larger workload.Partial region (such as caisson and toilet) is more demanding to the tightness of secondary plugging.Pipe traditional at present
There are three types of road through-flooring hole formwork ways: first is that using bamboo clappers support cystosepiment as template, since the intensity of cystosepiment is difficult
Meet blocking concrete and pour requirement, template spillage phenomenon easily occurs, the serious concrete perfusion that may occur is with foam
The case where plate topples together, there is serious potential safety and quality hazards.Therefore this method is very unreliable.Second is that under hole
It pads upper plank and is fixed on above hole with iron wire pulling plank in side;Or plank is held using bolt cross bar under iron wire with steel pipe support.
This method construct at the scene in operation difficulty it is larger, higher building high for layer, there is also no small security risks, and to applying
The specialized capability of worker person is more demanding, and construction quality is not easy control, and template secondary use rate is low.Third is that using old-fashioned primary
Template is hung in molding, after cleaning basal plane is fixed, point front and back two-step pouring.This method disadvantage is mainly to live reserving hole and pipeline
Pitch requirements are higher after installation, using there are limitations.
Summary of the invention
The purpose of the present invention is to provide a kind of pipelines that adjustable recycles to hang mould, can be directed to different pipeline pitch tubes
Hole carries out quickly hanging mould, with overcome prior art construction efficiency is low, operation difficulty is big, easy spillage and to reserved opening spacing and
The higher disadvantage of Pipe installing required precision, thus overcome the deficiencies in the prior art.
To achieve the above object, the present invention adopts the following technical scheme:
The pipeline that a kind of adjustable of the invention recycles hangs mould, including left half module and right half module, and left half module and right half module are equal
For semi-annular shape;The semicircle orifice both ends of the semicircular ring of left half module or right half module are respectively equipped with fixing seat, the fixation of semicircle orifice one end
Seat is equipped with through-hole, is equipped with bolt in through-hole;The fixing seat of semicircle orifice one end is equipped with threaded hole, is equipped in the middle part of threaded hole perpendicular to spiral shell
The top wire hole of pit;Left half module is with right half module through being bolted;And it is fixed through jackscrew.
Aforementioned tubular duct is hung in mould, and the intrados of the semicircle orifice is equipped with semicanal, the extrados and semicircle orifice intrados of semicanal
Connection.
Aforementioned tubular duct is hung in mould, and corresponding left half module or right half module top surface are equipped with reinforcement in the middle part of the circular arc of the semicircle orifice
Muscle.
Aforementioned tubular duct is hung in mould, one of them is primary-secondary module for the left half module or right half module, and primary-secondary module includes submodule;Submodule
It is connected through hinge and master mold rotation.
Aforementioned tubular duct is hung in mould, and the master mold of the primary-secondary module is equipped with a pair of of rotating handle, is connected in the middle part of rotating handle through pin shaft and master mold
It connects.
Aforementioned tubular duct is hung in mould, one of them is small for the width in the middle part of the semicircular ring of primary-secondary module for the left half module or right half module
Width in the middle part of the semicircular ring that another is not primary-secondary module.
By adopting the above-described technical solution, production is easy compared with prior art, the present invention the configuration of the present invention is simple,
Alternative traditional iron wire hangs the method that mould and old-fashioned finished product hang mould, solves that preformed hole construction is cumbersome, construction quality is not easy
It controls, to reserving hole precision and the higher problem of pitch requirements.The hole of different tube spacing can be used, save manually,
Reusable save the cost reduces the wasting of resources.After construction, without later period investment manual cleaning chisel mill, upper and lower interlayer is not necessarily to
It is fixed with iron wire, reduces the trouble for clearing up fixed iron and steel wire before pouring, seep water hidden danger caused by preventing thus.
Detailed description of the invention
Fig. 1 is structural schematic diagram of the invention;
Fig. 2 is the axonometric drawing of Fig. 1.
The label in accompanying drawing is: the left half module of 1-, the right half module of 2-, 3- semicircle orifice, 4- fixing seat, 5- bolt, 6- threaded hole,
7- top wire hole, 8- jackscrew, 9- semicanal, 10- reinforcing rib, 11- submodule, 12- hinge, 13- rotating handle, 14- pin shaft.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawings and examples.
The pipeline that a kind of adjustable of the invention recycles hangs mould, as depicted in figs. 1 and 2, including left half module 1 and right half
Mould 2, Zuo Banmo 1 or right half module 2 are semi-annular shape;3 both ends of semicircle orifice of semicircular ring are respectively equipped with fixing seat 4, semicircle orifice 3 one
The fixing seat 4 at end is equipped with through-hole, is equipped with bolt 5 in through-hole;The fixing seat 4 of 3 one end of semicircle orifice is equipped with threaded hole, threaded hole middle part
Equipped with the top wire hole 7 perpendicular to threaded hole 6;Left half module 1 is connect with right half module 2 through bolt 5;And it is fixed through jackscrew 8.Semicircle orifice 3
Intrados be equipped with semicanal 9, the extrados of semicanal 9 connect with 3 intrados of semicircle orifice.A corresponding left side in the middle part of the circular arc of semicircle orifice 3
Half module 1 or 2 top surface of right half module are equipped with reinforcing rib 10.One of them is primary-secondary module for left half module 1 or right half module 2, and primary-secondary module includes
Submodule 11;Submodule 11 is connected through hinge 12 and master mold rotation.The master mold of primary-secondary module is equipped with a pair of of rotating handle 13, passes through in the middle part of rotating handle 13
Pin shaft 14 is connect with master mold.Width in the middle part of primary-secondary module semicircular ring is less than width in the middle part of the semicircular ring of another non-primary-secondary module.
Embodiment
This example completes basal plane cleaning before hanging hole after the completion of Pipe installing.Pass through hinge according to the spacing between side-by-side tubes
12 adjustment submodules 11 open and close, to meet basic operation space.By two pieces of semicanals 9 of corresponding caliber by bolt 5 and left half module 1 or
Fixing seat 4 on right half module 2 connects;When left half module 1 or right half module 2 are bonded, smeared in the binding face of left half module 1 and right half module 2
A small amount of machine oil and on be pushed into be adjacent to state, adjust two bolts 5 later, left half module 1 and right half module 2 locked, until downward nothing
Subject to method pulls.After completing the above work, conventional plugging operations can be carried out, after putty property is stablized, bolt 5 is unclamped and removes a left side
Half module 1 and right half module 2 clear up remaining putty on left half module 1 and right half module 2 and remain next use.
The configuration of the present invention is simple is easy production, and alternative traditional iron wire hangs the method that mould and old-fashioned finished product hang mould, solves
Preformed hole construction is cumbersome, construction quality is not easy to control, to reserving hole precision and the higher problem of pitch requirements.To difference
The hole of tube spacing can be used, and save artificial, reusable save the cost, the reduction wasting of resources.After construction, it is not necessarily to the later period
Manual cleaning chisel mill is put into, upper and lower interlayer reduces the trouble for clearing up fixed iron and steel wire before pouring, prevent without being fixed with iron wire
Thus seep water hidden danger caused by.
Claims (6)
1. a kind of pipeline that adjustable recycles hangs mould, including left half module (1) and right half module (2), it is characterised in that: Zuo Banmo
(1) or right half module (2) is semi-annular shape;Semicircle orifice (3) both ends of the semicircular ring of left half module (1) or right half module (2) are set respectively
Have fixing seat (4), the fixing seat (4) of semicircle orifice (3) one end is equipped with through-hole, is equipped with bolt (5) in through-hole;Semicircle orifice (3) one end
Fixing seat (4) be equipped with threaded hole (6), the top wire hole (7) perpendicular to threaded hole (6) is equipped in the middle part of threaded hole;Left half module (1) with
Right half module (2) connects through bolt (5), and fixed through jackscrew (8).
2. the pipeline that adjustable recycles according to claim 1 hangs mould, it is characterised in that: the semicircle orifice (3) it is interior
Cambered surface is equipped with semicanal (9), and the extrados of semicanal (9) is connect with semicircle orifice (3) intrados.
3. the pipeline that adjustable recycles according to claim 1 hangs mould, it is characterised in that: the circle of the semicircle orifice (3)
Corresponding left half module (1) or right half module (2) top surface are equipped with reinforcing rib (10) in the middle part of arc.
4. the pipeline that adjustable recycles according to claim 1 hangs mould, it is characterised in that: the left half module (1) or the right side
One of them is primary-secondary module to half module (2), and primary-secondary module includes submodule (11);Submodule (11) is connected through hinge (12) and master mold rotation.
5. the pipeline that adjustable recycles according to claim 4 hangs mould, it is characterised in that: on the master mold of the primary-secondary module
Equipped with a pair of of rotating handle (13), it is connect through pin shaft (14) with master mold in the middle part of rotating handle (13).
6. the pipeline that adjustable recycles according to claim 4 hangs mould, it is characterised in that: the left half module (1) or the right side
Half module (2) one of them be that be less than another be not the width in the middle part of the semicircular ring of primary-secondary module for width in the middle part of the semicircular ring of primary-secondary module
Degree.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910074368.5A CN109707159A (en) | 2019-01-25 | 2019-01-25 | A kind of pipeline that adjustable recycles hangs mould |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910074368.5A CN109707159A (en) | 2019-01-25 | 2019-01-25 | A kind of pipeline that adjustable recycles hangs mould |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109707159A true CN109707159A (en) | 2019-05-03 |
Family
ID=66261867
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910074368.5A Pending CN109707159A (en) | 2019-01-25 | 2019-01-25 | A kind of pipeline that adjustable recycles hangs mould |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109707159A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111441578A (en) * | 2020-04-01 | 2020-07-24 | 中建四局第六建设有限公司 | Hydroelectric circular pipe mold hanging die and construction method thereof |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE29705434U1 (en) * | 1997-03-26 | 1997-05-15 | Babiuch, Jens, 98701 Neustadt | Adjustable formwork, especially for the interior wall areas of a chimney cover plate |
CN203247837U (en) * | 2013-04-26 | 2013-10-23 | 浙江杰立建设集团有限公司 | Device for patching holes of board-penetrating pipeline |
CN204001724U (en) * | 2014-07-30 | 2014-12-10 | 西安市建筑工程总公司 | Mould constructing structure is hung in a kind of drainage pipe preformed hole sizing |
CN204098485U (en) * | 2014-08-26 | 2015-01-14 | 中国二冶集团有限公司 | One hangs hole mould |
CN204225485U (en) * | 2014-10-31 | 2015-03-25 | 屈元特 | A kind of anticreep slip reserved holes of pipes shutoff mould |
CN205100583U (en) * | 2015-11-05 | 2016-03-23 | 中民筑友有限公司 | Floor pipe hole plugging device |
CN206815824U (en) * | 2017-06-23 | 2017-12-29 | 中建八局第三建设有限公司 | Die device is hung in a kind of reserved holes of pipes antiseep closure |
CN209723610U (en) * | 2019-01-25 | 2019-12-03 | 中建四局安装工程有限公司 | A kind of pipeline that adjustable recycles hangs mould |
-
2019
- 2019-01-25 CN CN201910074368.5A patent/CN109707159A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE29705434U1 (en) * | 1997-03-26 | 1997-05-15 | Babiuch, Jens, 98701 Neustadt | Adjustable formwork, especially for the interior wall areas of a chimney cover plate |
CN203247837U (en) * | 2013-04-26 | 2013-10-23 | 浙江杰立建设集团有限公司 | Device for patching holes of board-penetrating pipeline |
CN204001724U (en) * | 2014-07-30 | 2014-12-10 | 西安市建筑工程总公司 | Mould constructing structure is hung in a kind of drainage pipe preformed hole sizing |
CN204098485U (en) * | 2014-08-26 | 2015-01-14 | 中国二冶集团有限公司 | One hangs hole mould |
CN204225485U (en) * | 2014-10-31 | 2015-03-25 | 屈元特 | A kind of anticreep slip reserved holes of pipes shutoff mould |
CN205100583U (en) * | 2015-11-05 | 2016-03-23 | 中民筑友有限公司 | Floor pipe hole plugging device |
CN206815824U (en) * | 2017-06-23 | 2017-12-29 | 中建八局第三建设有限公司 | Die device is hung in a kind of reserved holes of pipes antiseep closure |
CN209723610U (en) * | 2019-01-25 | 2019-12-03 | 中建四局安装工程有限公司 | A kind of pipeline that adjustable recycles hangs mould |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111441578A (en) * | 2020-04-01 | 2020-07-24 | 中建四局第六建设有限公司 | Hydroelectric circular pipe mold hanging die and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206625428U (en) | Pipe shaft post-cast floor slab closed system | |
CN113431333A (en) | Concrete pouring device for building construction and use method thereof | |
CN209723610U (en) | A kind of pipeline that adjustable recycles hangs mould | |
CN204626966U (en) | A kind of deformation joint formwork erection device | |
CN109707159A (en) | A kind of pipeline that adjustable recycles hangs mould | |
CN206784915U (en) | A kind of new steel structure suspension type flooring gang form | |
CN209868938U (en) | Prefabricated piping lane forming die | |
CN204690801U (en) | Formwork erecting structure is hung in basement roof ater-casting | |
CN110424534A (en) | A kind of prefabricated assembled non-reinforced concrete frame and its construction method | |
CN206667756U (en) | Vertical crane span structure built-in fitting | |
CN110629787A (en) | Core mold for pipe gallery pouring and construction method | |
CN110173109A (en) | A kind of reserved opening fast hangs hole structure and construction method | |
CN111236681A (en) | Hanging die for adding laminated slab at bottom of concrete slab and construction method thereof | |
CN212336470U (en) | Anti structure that floats of hollow superstructure of cast in situ concrete jumbo size mandrel | |
CN111119233B (en) | Concrete side wall embedded iron part fixing mechanism and using method thereof | |
CN216949534U (en) | Inclined strut embedded part of aluminum alloy vertical template | |
CN205711982U (en) | Gate dam oil pipe channel forming template | |
CN206054951U (en) | A kind of vertical sleeve fixing device of tool-type | |
CN219825119U (en) | Aqueduct pouring construction template | |
CN206220482U (en) | A kind of cast-in-situ wall template support system | |
CN206233612U (en) | Core Walls Structure cast-in-place concrete wet curing system | |
CN110173113A (en) | A kind of Lin Qiang hangs hole constructing structure and method | |
CN221031466U (en) | Detachable water-stopping bolt reinforcing structure for plugging reserved hole | |
CN216865563U (en) | Penetration type invisible bridge structure | |
CN216505823U (en) | Adjustable standardized punching tool |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |