CN109695250A - A kind of deep soft soil layer major diameter open caisson construction method - Google Patents
A kind of deep soft soil layer major diameter open caisson construction method Download PDFInfo
- Publication number
- CN109695250A CN109695250A CN201910128322.7A CN201910128322A CN109695250A CN 109695250 A CN109695250 A CN 109695250A CN 201910128322 A CN201910128322 A CN 201910128322A CN 109695250 A CN109695250 A CN 109695250A
- Authority
- CN
- China
- Prior art keywords
- open caisson
- caisson
- construction
- mixing pile
- soft soil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/46—Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The invention discloses a kind of deep soft soil layer major diameter open caisson construction methods, including construction procedure below: preparation of construction, including material prepares and equipment prepares;Cement mixing pile is set, along caisson wall injection deep cement-mixed pile, so that deep soft soil layer form compound foundation;Injected hole is set, opens up injected hole in cement mixing pile peripheral hardware;Excavation of foundation pit, according to drawing on composite foundation excavation pit;Make open caisson;Open caisson excavates, and open caisson is segmented sinking by the way of two sequences excavation;Back cover construction after open caisson stabilization sinks down into designed elevation, carries out back cover construction to open caisson bottom.This kind of deep soft soil layer major diameter open caisson construction method can place the generation of situations such as open caisson super heavy, inclination of open caisson, have the advantages that not available for the prior arts such as implementation cost is low, enforcement difficulty is low, safe and reliable, construction quality is good.
Description
Technical field
The present invention relates to a kind of engineering construction method, especially a kind of deep soft soil layer major diameter open caisson construction method.
Background technique
Open caisson is the underground structure of pit shaft shape, and when construction is general to be first fabricated to the works of a pit shaft shape in earth's surface,
Then caisson structure self weight (or under imposed load effect) is borrowed to overcome and soil by constantly cutting the earth out of well under the going along with sb. to guard him of the borehole wall
Resistance native under frictional force and blade foot, makes open caisson gradually sink between wall;After reaching predetermined design absolute altitude, then carry out back cover, structure
Build internal structure.Open caisson is usually in foundation pit, sewage pumping station, the large equipment base, people's air defense shelter, shield of construction Bridge Piers
It is used when assembled well, upper pipe working well or received well, underground driveway and station water conservancy project foundation construction enclosure device.This method is not only
Have the characteristics that construction is simple, speed are fast, safe and reliable, also with small to surrounding constructure influence, occupied area is small, shoveling amount
The advantages that few.
When open caisson is constructed under the conditions of the Soft Clays such as mud, muck soil, peat, cumulosol, since Soft Soil Layer mentions
The frictional force and Lack of support of confession are easy to appear that well sinking amplitude is excessive, open caisson in the case where caisson structure size is big
The problems such as inclination correction is difficult, influences construction quality.
In view of this, the purpose of the present invention is to provide a kind of new technical solutions to solve existing technological deficiency.
Summary of the invention
For overcome the deficiencies in the prior art, the present invention provides a kind of deep soft soil layer major diameter open caisson construction method,
It solves open caisson in the prior art and is easy to appear that sinking control difficulty is big, sinking amplitude is excessive in deep soft soil layer construction,
And the technical problems such as Deviation Rectification for Open Caisson difficulty.
The technical solution adopted by the present invention to solve the technical problems is:
A kind of deep soft soil layer major diameter open caisson construction method, including construction procedure below:
Step 1: preparation of construction, including material prepares and equipment prepares;
Step 2: setting cement mixing pile, along caisson wall injection deep cement-mixed pile, so that deep soft soil layer shape
At composite foundation;
Step 3: setting injected hole opens up injected hole in cement mixing pile peripheral hardware;
Step 4: excavation of foundation pit, according to drawing on composite foundation excavation pit;
Step 5: production open caisson;
Step 6: open caisson excavates, and open caisson is segmented sinking by the way of two sequences excavation;
Step 7: back cover construction after open caisson stabilization sinks down into designed elevation, carries out back cover construction to open caisson bottom.
As an improvement of the above technical solution, in implementation steps two, if being equably arranged in caisson cutting edge bottom in advance
Dry deep cement-mixed pile increases caisson cutting edge end Bearing Capacity of Composite Foundation, improves the end resistance and the borehole wall of caisson cutting edge
Side friction;Upper soil horizon can be used as empty stake, lower part soft soil layer Duan Weishi, cement mixing pile in cement mixing pile driving construction
Stake bottom absolute altitude is more than that Sinking Well Design bottom absolute altitude is no less than 2m;Cement mixing pile stake diameter can select diameter 500 according to open caisson wall thickness
Or 600mm.
As a further improvement of the above technical scheme, in implementation steps three, injected hole is abutted along caisson wall outer rim
The setting of open caisson outer wall, increases open caisson external wall friction power, to play the role of controlling well sinking speed;Injected hole aperture is
About 1.0~1.5m is arranged in 50mm, pitch of holes, and bored grouting depth is consistent with cement mixing pile stake bottom depth.
As a further improvement of the above technical scheme, in implementation steps four, the excavation of foundation pit depth about 1 of open caisson operation
~2m, the slope gradient are 1:1, and bottom of foundation ditch sideline is from open caisson outer wall 2m or so;Pit earthwork can be used backhoe and be excavated, and match
It closes and manually repairs slope and smooth side slope and hole bottom, reuse dump truck for the soil dug out and transport to the stacking of specified spoir receiving place;
When excavation of foundation pit is close to designed elevation, ground at blade foot is handled well, desurfacing loosens the soil, and the granulated slag that rockfills is changed, in mountain flour slag
It is laid with chock in upper blade foot, prevents that differential settlement occurs during next step open caisson manufacture.
As a further improvement of the above technical scheme, in implementation steps five, including working procedure below:
5.1, it determines that open caisson pours number: according to site condition live after excavation of foundation pit, determining that merogenesis pours open caisson in advance
Number;
5.2, blade foot plain concrete cushion layer pours: carrying out plain concrete cushion layer formwork in boundary of works area and pours;
5.3, blade foot construct: according to drawing or check determine blade foot be arranged type, according to drawing and mat surface mark into
The binding of row blade foot reinforcing bar, formwork and concreting;
5.4, open caisson scaffold building: double ground steel pipe scaffold is arranged in open caisson periphery, needs to be expired on the inside of open caisson
Hall scaffold building;
5.5, open caisson template is installed: before the installation of open caisson template, being checked according to specification, installs open caisson mould after checking computations are qualified
Plate;
5.6, the borehole wall pours: borehole wall placement layer by layer is carried out after template is checked and accepted, every layer pours 30~50cm, can basis
Casting concrete amount is poured using more pump trucks simultaneously, and is vibrated.
As a further improvement of the above technical scheme, in implementation steps six, each section of well sinking is all made of two sequences
Mixing pile is divided into 12 sections by open caisson circumferencial direction by digging mode, and in a sequence, successively interval abolishes 12 sections to uniform intervals paragraph by paragraph
6 sections of cement mixing piles in cement mixing pile, and the synchronous sand pocket displacement support top in position is abolished at cement mixing pile interval;Two
In sequence, 6 sections of this layer of residue of cement mixing pile is abolished, while abolishing the sand pocket that a tagmeme is set, open caisson bottom relies on border at this time
Sand pocket support top;Finally, the sandbox using sand pocket acts on, realizes safe, uniform, the controlled sinking of open caisson, prevent from substantially sinking and inclining
Tiltedly;When filling sand pocket, sand pocket should be fitted closely with blade foot and mixing pile;The cement mixing pile is abolished thickness every time and is no more than
0.5m;The above process is repeated several times and makes well sinking to designed elevation.
The beneficial effects of the present invention are: the present invention provides a kind of deep soft soil layer major diameter open caisson construction method, it should
Kind deep soft soil layer major diameter open caisson construction method is provided with cement mixing pile and injected hole in construction, can provide for open caisson
The resistance of group structure, avoids well sinking position super heavy;It is set during well sinking using second order alternation excavation and pre-buried sandbag
The mode changed carries out segmentation sinking, it can be ensured that open caisson guarantees that within the scope of the vertical missing of control, open caisson is not in sinking watching
It will appear inclination of open caisson bias phenomenon, effectively promote the construction quality of open caisson.
In short, this kind of deep soft soil layer major diameter open caisson construction method, solve in the prior art open caisson deep soft
It is easy to appear that sinking control difficulty is big, sinking amplitude is excessive in the construction of soil layer and the technologies such as Deviation Rectification for Open Caisson difficulty is asked
Topic.
Detailed description of the invention
Present invention will be further explained below with reference to the attached drawings and examples.
Fig. 1 is method and step flow chart of the invention;
Fig. 2 is working procedure flow chart of the invention;
Fig. 3 is the plane figure schematic diagram of cement mixing pile in the present invention;
Fig. 4 is the sectional elevation structural schematic diagram of cement mixing pile in the present invention;
Fig. 5 is the plane figure schematic diagram of injected hole in the present invention;
Fig. 6 is the sectional elevation structural schematic diagram of injected hole in the present invention;
Sectional elevation structural schematic diagram when Fig. 7 is excavation pit in the present invention;
Fig. 8 is the planar structure schematic diagram in the present invention after the completion of open caisson manufacture;
Fig. 9 is the sectional elevation structural schematic diagram in the present invention after the completion of open caisson manufacture;
Figure 10 is planar structure schematic diagram when carrying out sequence construction in the present invention in caisson sinking construction;
Figure 11 is sectional elevation structural schematic diagram when carrying out sequence construction in the present invention in caisson sinking construction;
Figure 12 is planar structure schematic diagram when carrying out the construction of two sequences in the present invention in caisson sinking construction;
Figure 13 is sectional elevation structural schematic diagram when carrying out the construction of two sequences in the present invention in caisson sinking construction;
Figure 14 is that open caisson uniformly sinks the sectional elevation structural schematic diagram after one section in caisson sinking construction in the present invention;
Figure 15 is the sectional elevation structural schematic diagram in the present invention after well sinking to designed elevation.
Specific embodiment
It is carried out below with reference to technical effect of the embodiment and attached drawing to design of the invention, specific structure and generation clear
Chu is fully described by, to be completely understood by the purpose of the present invention, feature and effect.Obviously, described embodiment is this hair
Bright a part of the embodiment, rather than whole embodiments, based on the embodiment of the present invention, those skilled in the art are not being paid
Other embodiments obtained, belong to the scope of protection of the invention under the premise of creative work.In addition, being related in patent
All connection/connection relationships, not singly refer to that component directly connects, and refer to can according to specific implementation situation, by addition or
Reduce couple auxiliary, Lai Zucheng more preferably coupling structure.Each technical characteristic in the invention, in not conflicting conflict
Under the premise of can with combination of interactions, referring to Fig.1-15.
A kind of deep soft soil layer major diameter open caisson construction method, including construction procedure below:
Step 1: preparation of construction, including material prepares and equipment prepares;
Step 2: setting cement mixing pile, along caisson wall injection deep cement-mixed pile, so that deep soft soil layer shape
At composite foundation;
Step 3: setting injected hole opens up injected hole in cement mixing pile peripheral hardware;
Step 4: excavation of foundation pit, according to drawing on composite foundation excavation pit;
Step 5: production open caisson;
Step 6: open caisson excavates, and open caisson is segmented sinking by the way of two sequences excavation;
Step 7: back cover construction after open caisson stabilization sinks down into designed elevation, carries out back cover construction to open caisson bottom.
Preferably, in implementation steps two, several deep-cement stirrings is equably set in caisson cutting edge bottom in advance
Stake increases caisson cutting edge end Bearing Capacity of Composite Foundation, improves the end resistance of caisson cutting edge and the side friction of the borehole wall;Cement stirs
Mixing pile driving construction can be used upper soil horizon as empty stake, and lower part soft soil layer Duan Weishi, cement mixing pile stake bottom absolute altitude is more than open caisson
Design bottom absolute altitude is no less than 2m;Cement mixing pile stake diameter can select diameter 500 or 600mm according to open caisson wall thickness.
Preferably, in implementation steps three, injected hole is arranged along caisson wall outer rim against open caisson outer wall, increases outside open caisson
Wall friction power, to play the role of controlling well sinking speed;Injected hole aperture is 50mm, and about 1.0~1.5m is arranged in pitch of holes,
Bored grouting depth is consistent with cement mixing pile stake bottom depth.
Preferably, in implementation steps four, excavation of foundation pit depth about 1~2m of open caisson operation, the slope gradient is 1:1, base
Bottom sideline is cheated from open caisson outer wall 2m or so;Pit earthwork can be used backhoe and be excavated, and slope and smooth side slope are manually repaired in cooperation
With hole bottom, dump truck is reused by the soil dug out and transports to the stacking of specified spoir receiving place;It is close to design in excavation of foundation pit
When absolute altitude, ground at blade foot is handled well, desurfacing loosens the soil, and changes the granulated slag that rockfills, and is laid with chock in blade foot on mountain flour slag, prevents
Differential settlement occurs during next step open caisson manufacture.
Preferably, in implementation steps five, including working procedure below:
5.1, it determines that open caisson pours number: according to site condition live after excavation of foundation pit, determining that merogenesis pours open caisson in advance
Number;
5.2, blade foot plain concrete cushion layer pours: carrying out plain concrete cushion layer formwork in boundary of works area and pours;
5.3, blade foot construct: according to drawing or check determine blade foot be arranged type, according to drawing and mat surface mark into
The binding of row blade foot reinforcing bar, formwork and concreting;
5.4, open caisson scaffold building: double ground steel pipe scaffold is arranged in open caisson periphery, needs to be expired on the inside of open caisson
Hall scaffold building;
5.5, open caisson template is installed: before the installation of open caisson template, being checked according to specification, installs open caisson mould after checking computations are qualified
Plate;
5.6, the borehole wall pours: borehole wall placement layer by layer is carried out after template is checked and accepted, every layer pours 30~50cm, can basis
Casting concrete amount is poured using more pump trucks simultaneously, and is vibrated.
Preferably, in implementation steps six, each section of well sinking is all made of two sequence digging modes, by open caisson circumferencial direction
Mixing pile is divided into 12 sections, in a sequence, uniform intervals 6 sections of cement that successively interval is abolished in 12 sections of cement mixing piles paragraph by paragraph are stirred
Stake is mixed, and abolishes the synchronous sand pocket displacement support top in position at cement mixing pile interval;In two sequences, 6 sections of this layer of residue are abolished
Cement mixing pile, while the sand pocket that a tagmeme is set is abolished, open caisson bottom relies on border sand pocket support top at this time;Finally, utilizing sand pocket
Sandbox effect, realize safe, uniform, the controlled sinking of open caisson, prevent from substantially sinking and tilting;When filling sand pocket, sand pocket should be with
Blade foot and mixing pile fit closely;The cement mixing pile abolishes thickness no more than 0.5m every time;The above process is repeated several times simultaneously
So that well sinking is to designed elevation.
When the present invention is embodied:
One, along open caisson wall injection deep cement-mixed pile, referring in particular to Fig. 3, Fig. 4.
1, a certain number of deep cement-mixed piles 1 are equably set in caisson cutting edge bottom in advance, increase caisson cutting edge
End Bearing Capacity of Composite Foundation improves the end resistance of caisson cutting edge and the side friction of the borehole wall, prevents open caisson super heavy.
2, to save construction cost, upper soil horizon is can be used as empty stake in the construction of cement mixing pile 1, and lower part soft soil layer section is
Real stake, 1 stake bottom absolute altitude of cement mixing should be more than that Sinking Well Design bottom absolute altitude is no less than 2m.
3,1 diameter of cement mixing pile can select diameter 500 or 600mm according to open caisson wall thickness.
Two, 1 outside bored grouting of cement mixing pile forms injected hole 2, referring in particular to Fig. 5, Fig. 6.
1, injected hole 2 is arranged along open caisson wall outer rim against open caisson outer wall, it is therefore an objective to improve caisson wall periphery weak soil body
Mechanical property increases open caisson external wall friction power, to play the role of controlling well sinking speed.
2,2 aperture of injected hole is 50mm, and about 1.0~1.5m is arranged in pitch of holes, and bored grouting depth is the same as 1 bottom depth of mixing pile
Degree.
Three, excavation of foundation pit, referring in particular to Fig. 7.
1, foundation pit 3 cutting depth about 1~2m of open caisson operation, the slope gradient are 1:1, and bottom of foundation ditch sideline is from open caisson outer wall
2m or so.
2, it backhoe can be used is excavated for 3 cubic metres of earth of foundation pit, slope and smooth side slope and hole bottom are manually repaired in cooperation, reuse self-unloading
The soil dug out is transported to specified spoir receiving place and stacked by automobile.
3, when foundation pit 3 is excavated close to designed elevation 31, ground at blade foot is handled well, desurfacing loosens the soil, and changes and rockfills
Granulated slag is laid with chock in blade foot on mountain flour slag, prevents that differential settlement occurs during next step open caisson manufacture.
Four, open caisson is made, referring in particular to Fig. 8, Fig. 9.
1, open caisson 4 pours number: live site condition after being excavated according to foundation pit 3 determines that merogenesis pours time of open caisson in advance
Number.
2, blade foot plain concrete cushion layer pours: carrying out plain concrete cushion layer formwork in boundary of works area, pours.
3, blade foot is constructed: according to drawing or being checked determining blade foot setting type, is carried out according to drawing and mat surface label
The binding of blade foot reinforcing bar, formwork and concreting.
4, open caisson scaffold building: double ground steel pipe scaffold is arranged in open caisson periphery, needs to carry out full hall on the inside of open caisson
Scaffold building.
5, open caisson template is installed: before the installation of open caisson template, it is necessary to be checked according to relevant regulations specification.
6, the borehole wall pours: borehole wall placement layer by layer is carried out after template is checked and accepted, every layer pours 30~50cm, can be according to pouring
It builds amount of concrete while being poured using more pump trucks, and vibrate.
Five, 4 inner excavation of open caisson takes soil, and at pleasure 1 two sequence of mixing pile is excavated under open caisson 4, referring in particular to Figure 10, Figure 11, figure
12, Figure 13.
1, each section of open caisson 4 sinks to using two sequence digging modes, and dividing cement mixing pile 1 by 4 circumference of open caisson is 12 sections, and one
Successively 6 sections of cement mixing pile 1 in 12 sections is abolished at interval to sequence uniform intervals paragraph by paragraph, and abolishes position at the interval of cement mixing pile 1
Set the synchronous displacement support top of sand pocket 5;Two sequences abolish 6 sections of this layer of residue of cement mixing pile 1, while abolishing the sand pocket that a tagmeme is set
5, open caisson bottom relies on 5 support top of border sand pocket at this time;Finally, the sandbox using sand pocket 5 acts on, realize the safety of open caisson 4, uniformly,
Controlled sinking prevents from substantially sinking and tilting.
2, when filling sand pocket 5, sand pocket 5 should be fitted closely with blade foot and cement mixing pile.
3, cement mixing pile 1 abolishes thickness no more than 0.5m every time, prevents open caisson from abolishing unevenly because of cement mixing pile
And it tilts.
Six, support top sand pocket 5 uniformly is abolished, completes the uniform sinking of one section of open caisson 4, and repeat the construction of the five, the six steps, until
Open caisson 4 sinks down into designed elevation 31, referring in particular to Figure 14, Figure 15.
Seven, after open caisson 4 sinks down into designed elevation 31, back cover construction is carried out to 4 shaft bottom of open caisson.
It is to be illustrated to preferable implementation of the invention, but the invention is not limited to the implementation above
Example, those skilled in the art can also make various equivalent variations on the premise of without prejudice to spirit of the invention or replace
It changes, these equivalent deformations or replacement are all included in the scope defined by the claims of the present application.
Claims (6)
1. a kind of deep soft soil layer major diameter open caisson construction method, it is characterised in that: including construction procedure below:
Step 1: preparation of construction, including material prepares and equipment prepares;
Step 2: setting cement mixing pile, along caisson wall injection deep cement-mixed pile, so that deep soft soil layer is formed again
Close ground;
Step 3: setting injected hole opens up injected hole in cement mixing pile peripheral hardware;
Step 4: excavation of foundation pit, according to drawing on composite foundation excavation pit;
Step 5: production open caisson;
Step 6: open caisson excavates, and open caisson is segmented sinking by the way of two sequences excavation;
Step 7: back cover construction after open caisson stabilization sinks down into designed elevation, carries out back cover construction to open caisson bottom.
2. a kind of deep soft soil layer major diameter open caisson construction method according to claim 1, it is characterised in that: implementing
When step 2, several deep cement-mixed piles is equably set in caisson cutting edge bottom in advance, it is multiple to increase caisson cutting edge end
Foundation bearing capacity is closed, the end resistance of caisson cutting edge and the side friction of the borehole wall are improved;Top soil can be used in cement mixing pile driving construction
Layer is empty stake, and lower part soft soil layer Duan Weishi, cement mixing pile stake bottom absolute altitude is more than that Sinking Well Design bottom absolute altitude is no less than 2m;Water
Mud mixing pile stake diameter can select diameter 500 or 600mm according to open caisson wall thickness.
3. a kind of deep soft soil layer major diameter open caisson construction method according to claim 1, it is characterised in that: implementing
When step 3, injected hole is arranged along caisson wall outer rim against open caisson outer wall, increases open caisson external wall friction power, heavy to play control
The effect of well subsidence velocity;Injected hole aperture is 50mm, and 1.0~1.5m, bored grouting depth and cement mixing is arranged in pitch of holes
Stake stake bottom depth is consistent.
4. according to a kind of deep soft soil layer major diameter open caisson construction method described in claim 1, it is characterised in that: implementing to walk
When rapid four, excavation of foundation pit depth about 1~2m of open caisson operation, the slope gradient is 1:1, and bottom of foundation ditch sideline is left from open caisson outer wall 2m
It is right;Pit earthwork can be used backhoe and be excavated, and slope and smooth side slope and hole bottom are manually repaired in cooperation, and reusing dump truck will dig
Soil out transports to the stacking of specified spoir receiving place;When excavation of foundation pit is close to designed elevation, ground at blade foot is handled well, clearly
Skim-coat loosens the soil, and changes the granulated slag that rockfills, and is laid with chock in blade foot on mountain flour slag, prevents from occurring not during next step open caisson manufacture
Uniform settlement.
5. according to a kind of deep soft soil layer major diameter open caisson construction method described in claim 1, it is characterised in that: implementing to walk
When rapid five, including working procedure below:
5.1, it determines that open caisson pours number: according to site condition live after excavation of foundation pit, determining that merogenesis pours time of open caisson in advance
Number;
5.2, blade foot plain concrete cushion layer pours: carrying out plain concrete cushion layer formwork in boundary of works area and pours;
5.3, blade foot is constructed: according to drawing or being checked determining blade foot setting type, is carried out sword according to drawing and mat surface label
The binding of foot reinforcing bar, formwork and concreting;
5.4, open caisson scaffold building: double ground steel pipe scaffold is arranged in open caisson periphery, needs to carry out full hall foot on the inside of open caisson
Hand cradle is set up;
5.5, open caisson template is installed: before the installation of open caisson template, being checked according to specification, installs open caisson template after checking computations are qualified;
5.6, the borehole wall pours: borehole wall placement layer by layer is carried out after template is checked and accepted, every layer pours 30~50cm, can be according to pouring
Amount of concrete is poured using more pump trucks simultaneously, and is vibrated.
6. according to a kind of deep soft soil layer major diameter open caisson construction method described in claim 1, it is characterised in that: implementing to walk
When rapid six, each section of well sinking is all made of two sequence digging modes, mixing pile is divided into 12 sections by open caisson circumferencial direction, in a sequence
In, successively 6 sections of cement mixing piles in 12 sections of cement mixing piles are abolished at interval to uniform intervals paragraph by paragraph, and at cement mixing pile interval
Abolish the synchronous sand pocket displacement support top in position;In two sequences, 6 sections of this layer of residue of cement mixing pile is abolished, while abolishing a sequence
The sand pocket of position, open caisson bottom relies on border sand pocket support top at this time;Finally, the sandbox using sand pocket acts on, realization open caisson safety,
Uniformly, controlled sinking prevents from substantially sinking and tilting;When filling sand pocket, sand pocket should be fitted closely with blade foot and mixing pile;It is described
Cement mixing pile abolishes thickness no more than 0.5m every time;The above process is repeated several times and makes well sinking to designed elevation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910128322.7A CN109695250A (en) | 2019-02-21 | 2019-02-21 | A kind of deep soft soil layer major diameter open caisson construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910128322.7A CN109695250A (en) | 2019-02-21 | 2019-02-21 | A kind of deep soft soil layer major diameter open caisson construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109695250A true CN109695250A (en) | 2019-04-30 |
Family
ID=66233473
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910128322.7A Pending CN109695250A (en) | 2019-02-21 | 2019-02-21 | A kind of deep soft soil layer major diameter open caisson construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109695250A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111042171A (en) * | 2019-12-26 | 2020-04-21 | 天津市赛英工程技术咨询有限公司 | Open caisson construction method suitable for silt soft soil foundation and high underground water level |
CN112176806A (en) * | 2020-10-16 | 2021-01-05 | 于胜泉 | Stable road soft foundation treatment method and matched soft foundation treatment construction system |
CN115492144A (en) * | 2022-09-15 | 2022-12-20 | 中国一冶集团有限公司 | Construction method of pipe jacking and open caisson in sandbank area |
WO2023020161A1 (en) * | 2021-11-22 | 2023-02-23 | 中铁四局集团第三建设有限公司 | Method for preventing open caisson from suddenly sinking in soft foundation |
CN117513349A (en) * | 2023-12-20 | 2024-02-06 | 兰州交通大学 | Pit excavation method combining open caisson with slope releasing |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102493367A (en) * | 2011-12-06 | 2012-06-13 | 中铁六局集团有限公司 | Non-blasting construction method for dismantling pier to land bridge |
CN102587401A (en) * | 2012-03-26 | 2012-07-18 | 上海亚同环保实业股份有限公司 | Sinking construction method for open caisson in geological sludge layer under saturated water condition |
CN106958256A (en) * | 2017-03-22 | 2017-07-18 | 中建四局第五建筑工程有限公司 | A kind of placement layer by layer, the open caisson construction technique repeatedly sunk |
-
2019
- 2019-02-21 CN CN201910128322.7A patent/CN109695250A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102493367A (en) * | 2011-12-06 | 2012-06-13 | 中铁六局集团有限公司 | Non-blasting construction method for dismantling pier to land bridge |
CN102587401A (en) * | 2012-03-26 | 2012-07-18 | 上海亚同环保实业股份有限公司 | Sinking construction method for open caisson in geological sludge layer under saturated water condition |
CN106958256A (en) * | 2017-03-22 | 2017-07-18 | 中建四局第五建筑工程有限公司 | A kind of placement layer by layer, the open caisson construction technique repeatedly sunk |
Non-Patent Citations (1)
Title |
---|
黄文贺等: ""泵房沉井在淤泥质土层中的地基处理及施工方法"", 《中外建筑》 * |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111042171A (en) * | 2019-12-26 | 2020-04-21 | 天津市赛英工程技术咨询有限公司 | Open caisson construction method suitable for silt soft soil foundation and high underground water level |
CN112176806A (en) * | 2020-10-16 | 2021-01-05 | 于胜泉 | Stable road soft foundation treatment method and matched soft foundation treatment construction system |
CN112176806B (en) * | 2020-10-16 | 2021-10-29 | 于胜泉 | Stable road soft foundation treatment method and matched soft foundation treatment construction system |
WO2023020161A1 (en) * | 2021-11-22 | 2023-02-23 | 中铁四局集团第三建设有限公司 | Method for preventing open caisson from suddenly sinking in soft foundation |
CN115492144A (en) * | 2022-09-15 | 2022-12-20 | 中国一冶集团有限公司 | Construction method of pipe jacking and open caisson in sandbank area |
CN115492144B (en) * | 2022-09-15 | 2023-08-29 | 中国一冶集团有限公司 | Construction method of pipe-jacking open caisson in sand area |
CN117513349A (en) * | 2023-12-20 | 2024-02-06 | 兰州交通大学 | Pit excavation method combining open caisson with slope releasing |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109695250A (en) | A kind of deep soft soil layer major diameter open caisson construction method | |
CN107059667B (en) | Door shape assembled armored concrete box culvert and its construction method | |
CN102094425B (en) | Foundation pit construction method adopting shallow buried depth Larsen steel plate pile as protective cofferdam | |
CN108560542B (en) | Waste tire coated building slag bidirectional reinforcement and construction method thereof | |
CN106088127A (en) | Open caisson construction method | |
CN108824445A (en) | A kind of foundation pit construction engineering method with enclosure-type mud equilibrium function building enclosure | |
CN108560536A (en) | The continuous piling wall construction method of Soil-cement | |
CN106284365A (en) | A kind of WATER-WASHING METHOD of building foundation pit excavation | |
US4496268A (en) | Method and apparatus for constructing reinforced concrete walls in the earth | |
CN106869138A (en) | A kind of load retaining wall Retaining Structure with Double-row Piles and its foundation ditch excavation method | |
CN104264683A (en) | Concave ultra-deep foundation pit zoned supporting method for three-side surrounded cultural protection building | |
JP2024037138A (en) | Construction method of large-span station with open wings and semi-top-down excavation and semi-reverse drilling | |
CN110158602A (en) | A kind of Soft Clay deep foundation pit support excavation construction structure and construction method | |
CN107059904A (en) | A kind of underground pipe gallery ponding well excavation method | |
CN109056804B (en) | Comprehensive pipe rack foundation pit supporting structure and implementation method thereof | |
CN218346137U (en) | Foundation with strong bearing capacity | |
CN111021378A (en) | Highway subgrade slope broken line type anchoring pile retaining structure and construction method thereof | |
Nonveiller | Open caissons for deep foundations | |
CN109440781A (en) | Active inclination foundation pit supporting method with double rows of piles | |
CN115506382A (en) | Construction method for pile plate wall of island building platform | |
CN211948552U (en) | Construction platform for underground space development of dense existing building group | |
CN110792440B (en) | Construction method of water-rich loess tunnel penetrating through loess towards valley | |
CN209620034U (en) | Active X-shaped double-row pile foundation pit support structure | |
CN109440778A (en) | Active inclined in two-way method for supporting and protecting row pile pit | |
CN109440779A (en) | Active X-shaped foundation pit supporting method with double rows of piles |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190430 |