CN109653334A - A kind of anti-clogging engineering sewage discharge pipeline configuration - Google Patents
A kind of anti-clogging engineering sewage discharge pipeline configuration Download PDFInfo
- Publication number
- CN109653334A CN109653334A CN201811492947.3A CN201811492947A CN109653334A CN 109653334 A CN109653334 A CN 109653334A CN 201811492947 A CN201811492947 A CN 201811492947A CN 109653334 A CN109653334 A CN 109653334A
- Authority
- CN
- China
- Prior art keywords
- pipe
- water
- storage box
- water storage
- sewage
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F3/00—Sewer pipe-line systems
- E03F3/04—Pipes or fittings specially adapted to sewers
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F9/00—Arrangements or fixed installations methods or devices for cleaning or clearing sewer pipes, e.g. by flushing
- E03F9/007—Devices providing a flushing surge
Landscapes
- Health & Medical Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Hydrology & Water Resources (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Sewage (AREA)
Abstract
The present invention provides a kind of anti-clogging engineering sewage discharge pipeline configuration, it further include isocon, water storage box and flushing pipe, one end of the isocon and the water inlet end of plumbing for waste water are connected to shunt the sewage of plumbing for waste water, the other end of isocon is set in water storage box, water storage box is set to above sewage pipe, the flushing pipe is connected between water storage box and the water outlet of plumbing for waste water, flushing pipe is equipped with the solenoid valve for being connected to or blocking with sewage pipe for controlling water storage box, the bottom of the water storage box is equipped with the first liquid level gauge for detecting water level information in water storage box, the first liquid level gauge is electrically connected with the solenoid valve the connection of the water level information control water storage box and sewage pipe that detect so as to solenoid valve according to first liquid level gauge or blocks with flushing pollution discharge pipe.The present invention can effectively prevent blowdown blockage, improve contaminant removal effectiveness, prevent sludgd deposition in sewage pipe, realize auto-flushing, automatic blocking-proof.
Description
Technical field
The present invention relates to blow-off line technical fields, and in particular to a kind of anti-clogging engineering sewage discharge pipeline configuration.
Background technique
Existing sewage is typically all to pass through pipeline sewage is directly concentrated progress sewage treatment by source discharge to terminal,
Sewage pipe is usually to be laid in ground end, connects sewage source by plumbing for waste water and sewage pipe, plumbing for waste water are usually all with gradient
To compensate the difference in height between sewage source and sewage pipe, and contain more sludge in sewage, the tile arrangement of sewage pipe determines
Drainage flow speed is gentle in managing, therefore sludge is not easy to be washed, and easily causes the blocking of blowdown pipeline, to influence
Contaminant removal effectiveness, also, the flowmeter being arranged in sewage pipe also can not can normally measure use because of the presence of mud.
Summary of the invention
The first purpose of this invention be against the above deficiency place, provide one kind can periodically big flow to sewage pipe into
Row washes away the anti-clogging engineering sewage discharge pipeline configuration for preventing blowdown blockage.
The present invention solves the first scheme used by technical problem: a kind of anti-clogging engineering sewage discharge pipeline configuration, packet
Include the sewage pipe at plumbing for waste water peace floor file bottom, plumbing for waste water is tilted down extended by eminence, and plumbing for waste water is located at one end of eminence
For water inlet end, one end that plumbing for waste water is located at lower is water outlet, and it further includes isocon, water storage box that water outlet is connect with sewage pipe
And flushing pipe, the water inlet end of one end of the isocon and plumbing for waste water are connected to shunt the sewage of plumbing for waste water, isocon it is another
One end is set in water storage box, and water storage box is set to above sewage pipe, and the flushing pipe is connected to water storage box and plumbing for waste water and sewage pipe
Junction between, flushing pipe is equipped with the solenoid valve that is connected to or blocks with sewage pipe for controlling water storage box, the water storage box
Bottom be equipped with first liquid level gauge for detecting water level information in water storage box, the first liquid level gauge be electrically connected with the solenoid valve with
Just the connection of solenoid valve is detected according to first liquid level gauge water level information control water storage box and sewage pipe is blocked with flushing pollution discharge
Pipe.
Further, the blocking of sewage pipe caused by sludge retention in order to prevent;The anti-clogging engineering sewage discharge pipeline knot
Structure further includes the giant with the removable connection of flushing pipe.
Further, the water in order to prevent in plumbing for waste water flows in water storage box;The flushing pipe be equipped with for prevent into
Water in dirty pipe flows into the first check valve in flushing pipe.
Further, in order to control the circulation of sewage in plumbing for waste water;The sewage pipe is equipped with flange expansion joint and position
Electromagnetic valve II in flange expansion joint front end.
Further, hydraulically full in the sewage pipe where electromagnetic flowmeter in order to guarantee, to ensure electromagnetic flowmeter
Normal measurement uses;The end of the sewage pipe is equipped with inverted U-shaped curved tube, is additionally provided with the electromagnetism positioned at curved tube front end on sewage pipe
Flowmeter.
Further, in order to will guarantee water storage box in water flowed into flushing pipe;The water storage box is square structure, stores
The bottom surface of water tank is the cone structure that setting is extended obliquely downward by four circumferential flushing pipe junctions.
For the prior art, the invention has the following advantages that the present invention can effectively prevent blowdown blockage, the row of avoiding
Dirty pipe causes mud to be accumulated because the water flows gently, improves contaminant removal effectiveness, by the way that isocon is arranged, sewage separation is gone out a part and is concentrated
It is stored in reservoir, when the water accumulation in reservoir is to setting height, first liquid level gauge sends signal, solenoid valve
It automatically opens, the water in the reservoir above sewage pipe carries out big yield flushing to sewage pipe by flushing pipe, prevents dirt
Mud is deposited in sewage pipe, is periodically washed away and is avoided mud product solid in sewage pipe, realizes regular auto-flushing, automatic blocking-proof,
To guarantee the precise measurement of electromagnetic flowmeter, and the setting of curved tube, it is ensured that be full of liquid where electromagnetic flowmeter in pipeline
Body is further ensured that the normal measurement of electromagnetic flowmeter uses.
Detailed description of the invention
The invention will be further described in conjunction with the embodiments with reference to the accompanying drawings:
Fig. 1 is the structural diagram of the present invention;
Fig. 2 is overlooking structure diagram of the invention.
In figure: 1- first liquid level gauge;2- water storage box;3- isocon;4- plumbing for waste water;5- flushing pipe;6- solenoid valve;7- first
Check valve;8- electromagnetic valve II;9- flange expansion joint;10- electromagnetic flowmeter;11- curved tube;12- sewage pipe.
Specific embodiment
The content of present invention is described in detail with specific embodiment with reference to the accompanying drawings of the specification:
Specific embodiment: as shown in Figs. 1-2, the present embodiment provides a kind of anti-clogging engineering sewage discharge pipeline configurations, including into
The sewage pipe 12 at the peaceful floor file of dirty pipe 4 bottom, plumbing for waste water 4 are tilted down extended by eminence, and plumbing for waste water 4 is located at one end of eminence
For water inlet end, one end that plumbing for waste water 4 is located at lower is water outlet, and water outlet is connect with sewage pipe 12, further includes isocon 3, stores
Water tank 2 and flushing pipe 5, one end of the isocon 3 are connect to shunt the sewage of plumbing for waste water 4 with the water inlet end of plumbing for waste water 4, point
The other end of flow tube 3 is set in water storage box 2, and water storage box 2 is set to the top of sewage pipe 12, the flushing pipe 5 be connected to water storage box 2 with
Between plumbing for waste water 4 and the junction of sewage pipe 12, flushing pipe 5 is the straight tube that root is vertically arranged here, to keep enough to mud
Impulse force, flushing pipe 5 is equipped with the solenoid valve 6 that is connected to or blocks with sewage pipe 12 for controlling water storage box 2, the water storage box 2
Bottom be equipped with first liquid level gauge 1 for detecting water level information in water storage box 2, the first liquid level gauge 1 is electrically connected with solenoid valve 6
Connect the connection of the water level information control water storage box 2 and sewage pipe 12 that are detected so as to solenoid valve 6 according to first liquid level gauge 1 or block with
Flushing pollution discharge pipe 12.
In the present embodiment, the blocking of sewage pipe 12 caused by sludge retention in order to prevent;The anti-clogging engineering sewage discharge
12 structure of pipe further includes the giant with the removable connection of flushing pipe 5.
In the present embodiment, the water in order to prevent in plumbing for waste water 4 flows in water storage box 2;The flushing pipe 5 is equipped with and is used for
Prevent the first check valve 7 that the water in plumbing for waste water 4 flows into flushing pipe 5.
In the present embodiment, in order to control the circulation of sewage in plumbing for waste water 4;The sewage pipe 12 is equipped with flange expansion joint
9 and the electromagnetic valve II 8 positioned at 9 front end of flange expansion joint.
In the present embodiment, hydraulically full in the sewage pipe 12 where electromagnetic flowmeter 10 in order to guarantee, to ensure electromagnetism
The normal measurement of flowmeter 10 uses;The end of the sewage pipe 12 is equipped with inverted U-shaped curved tube 11, is additionally provided with position on sewage pipe 12
Electromagnetic flowmeter 10 in 11 front end of curved tube, the height of the horizontal plane where 11 bottom surface of curved tube is higher than bottom on sewage pipe 12 here
The height of horizontal plane where face.
In the present embodiment, in order to will guarantee water storage box 2 in water flowed into flushing pipe 5;The water storage box 2 is square
Structure, the bottom surface of water storage box 2 are the cone structure that setting is extended obliquely downward by four 5 junctions of circumferential flushing pipe.
Inspection shaft is that municipal works are arranged for convenience of repairing and installing, and is generally located in pipeline intersection, turning, pipe
Locate at a certain distance at diameter or gradient change and on straight line pipeline section, and the blowoff line at inspection shaft is curved because of pipeline generation
Folding, easily accumulation sludge cause the blocking of blowoff line, therefore the present invention is usually to be arranged in inspection shaft, in the present invention, also
Second liquid level gauge and drinking-water pipe for detecting water level information in inspection shaft can be set in the bottom of inspection shaft, drinking-water pipe
One end is set to the bottom of inspection shaft, and the other end of drinking-water pipe is set in water storage box 2, and suction pump is arranged on drinking-water pipe and takes out for controlling
The water for checking bottom is drawn into water storage box 2 by water pipe, and second liquid level gauge and suction pump are electrically connected to suction pump according to the
Water in the water level information control drinking-water pipe suction inspection shaft of one liquidometer 1 detection;The water of water storage box 2 flows back into inspection in order to prevent
It looks into well body;The drinking-water pipe is equipped with for preventing the water of water storage box 2 from flowing back into the intracorporal second one-way valve of inspection shaft.
The present invention can effectively prevent sewage pipe 12 to block, and improve contaminant removal effectiveness, by the way that isocon 3 is arranged, by sewage separation
A part is focused in reservoir and is stored out, and when the water accumulation in reservoir is to setting height, first liquid level gauge 1 is sent
Signal, solenoid valve 6 automatically open, and the water in reservoir is rinsed sewage pipe 12 by flushing pipe 5, prevent sludgd deposition from existing
In sewage pipe 12, auto-flushing, automatic blocking-proof are realized;Whether the setting of second liquid level gauge, can monitor in real time has sewage infiltration
Sewage is drawn into water storage box 2 once leaking by suction pump by the case where leakage, prevents in inspection shaft that there are ponding shadows
Ring the normal work for arriving electrical component, the setting of curved tube 11, it is ensured that the normal measurement work of electromagnetic flowmeter 10.
The above description is only an embodiment of the present invention, is not intended to limit scope of patent protection of the invention, all utilizations
Equivalent structure or equivalent flow shift made by description of the invention and accompanying drawing content is applied directly or indirectly in other correlations
Technical field, be included within the scope of the present invention.
Claims (6)
1. a kind of anti-clogging engineering sewage discharge pipeline configuration, the sewage pipe including plumbing for waste water peace floor file bottom, plumbing for waste water from eminence to
Lower inclination is extended, and one end that plumbing for waste water is located at eminence is water inlet end, and one end that plumbing for waste water is located at lower is water outlet, water outlet
End is connect with sewage pipe, it is characterised in that: further include isocon, water storage box and flushing pipe, one end of the isocon and into
The water inlet end of dirty pipe is connected to shunt the sewage of plumbing for waste water, and the other end of isocon is set in water storage box, and water storage box is set to blowdown
Above pipe, the flushing pipe is connected between water storage box and plumbing for waste water and the junction of sewage pipe, and flushing pipe is equipped with for controlling
The solenoid valve that water storage box processed is connected to or blocks with sewage pipe, the bottom of the water storage box is equipped with believes for detecting water level in water storage box
The first liquid level gauge of breath, the first liquid level gauge are electrically connected with the solenoid valve the water level detected so as to solenoid valve according to first liquid level gauge
Information controls the connection of water storage box and sewage pipe or blocks with flushing pollution discharge pipe.
2. anti-clogging engineering sewage discharge pipeline configuration according to claim 1, it is characterised in that: the anti-clogging engineering sewage discharge
Pipeline configuration further includes the giant with the removable connection of flushing pipe.
3. anti-clogging engineering sewage discharge pipeline configuration according to claim 1, it is characterised in that: the flushing pipe, which is equipped with, to be used
In the first check valve for preventing the water in plumbing for waste water from flowing into flushing pipe.
4. anti-clogging engineering sewage discharge pipeline configuration according to claim 1, it is characterised in that: the sewage pipe is equipped with method
Blue telescopic joint and electromagnetic valve II positioned at flange expansion joint front end.
5. anti-clogging engineering sewage discharge pipeline configuration according to claim 1, it is characterised in that: the end of the sewage pipe is set
There is inverted U-shaped curved tube, the electromagnetic flowmeter positioned at curved tube front end is additionally provided on sewage pipe.
6. anti-clogging engineering sewage discharge pipeline configuration according to claim 1, it is characterised in that: the water storage box is square knot
Structure, the bottom surface of water storage box are the cone structure that setting is extended obliquely downward by four circumferential flushing pipe junctions.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811492947.3A CN109653334A (en) | 2018-12-07 | 2018-12-07 | A kind of anti-clogging engineering sewage discharge pipeline configuration |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811492947.3A CN109653334A (en) | 2018-12-07 | 2018-12-07 | A kind of anti-clogging engineering sewage discharge pipeline configuration |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109653334A true CN109653334A (en) | 2019-04-19 |
Family
ID=66112905
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811492947.3A Pending CN109653334A (en) | 2018-12-07 | 2018-12-07 | A kind of anti-clogging engineering sewage discharge pipeline configuration |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109653334A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110585830A (en) * | 2019-10-10 | 2019-12-20 | 攀钢集团钒钛资源股份有限公司 | System for wet dust removal of tail gas of rotary kiln |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104790515A (en) * | 2015-04-23 | 2015-07-22 | 南通百海新型材料制造有限公司 | Back washing and sewage discharge device |
CN206859397U (en) * | 2017-06-28 | 2018-01-09 | 中冶南方城市建设工程技术有限公司 | The flushing desilting system of gravity stream sewage pipe in pipe gallery |
CN107700633A (en) * | 2017-10-16 | 2018-02-16 | 贺州市瑞程科技有限公司 | A kind of auto-flushing blowdown apparatus |
US20180111174A1 (en) * | 2015-06-26 | 2018-04-26 | Dyteqta Limited | Drain pipe cleaning device and method of cleaning |
-
2018
- 2018-12-07 CN CN201811492947.3A patent/CN109653334A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104790515A (en) * | 2015-04-23 | 2015-07-22 | 南通百海新型材料制造有限公司 | Back washing and sewage discharge device |
US20180111174A1 (en) * | 2015-06-26 | 2018-04-26 | Dyteqta Limited | Drain pipe cleaning device and method of cleaning |
CN206859397U (en) * | 2017-06-28 | 2018-01-09 | 中冶南方城市建设工程技术有限公司 | The flushing desilting system of gravity stream sewage pipe in pipe gallery |
CN107700633A (en) * | 2017-10-16 | 2018-02-16 | 贺州市瑞程科技有限公司 | A kind of auto-flushing blowdown apparatus |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110585830A (en) * | 2019-10-10 | 2019-12-20 | 攀钢集团钒钛资源股份有限公司 | System for wet dust removal of tail gas of rotary kiln |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100441267B1 (en) | Circulating drainage system for sewage pipe installation work | |
JP4851358B2 (en) | 厨 芥 Wastewater transfer system | |
JP2007262766A (en) | Recharge method and underground water recharge system used for the same | |
JP5716123B1 (en) | Sewage discharge system | |
CN205760144U (en) | Deep basal pit Yield rainfall relation recycling processing means | |
KR100959373B1 (en) | A scale exhausting apparatus of a water supply pipe | |
JP3690547B2 (en) | Circulating drainage device for sewage pipe work | |
CN109653334A (en) | A kind of anti-clogging engineering sewage discharge pipeline configuration | |
CN208009590U (en) | A kind of discharge pipe line fault location monitoring device based on architecture information | |
CN207714475U (en) | Cope with the blowdown pipe fitting of surface subsidence | |
CN214116966U (en) | Urban rainwater and sewage diversion pipe network silt flushing device | |
CN203684387U (en) | Special double-water-tank integrated sewage lifting equipment for subway | |
KR20160128003A (en) | filter cleansing method of apparatus for draining ground water | |
CN204456414U (en) | From the flushing system of falling rainbow | |
CN208056242U (en) | A kind of anti-clogging blow-off line component | |
CN205712445U (en) | A kind of underground garage built-in oil removal sand-catching apparatus | |
CN205875373U (en) | Two box sewage lifting device of integration | |
CN110792134A (en) | Siphon drainage system | |
CN206090804U (en) | Novel sewage promotes drainage equipment | |
CN109736424A (en) | A kind of engineering sewage discharge integration unit | |
CN202865987U (en) | Empty type sewage hoisting equipment | |
CN202248125U (en) | Blocking prevention water drainage elbow | |
CN208183937U (en) | It is a kind of with the sustainable closed sewage water lifter of double casees used of crushing function | |
CN102966175A (en) | Empty-type sewage hoisting equipment | |
JP6412732B2 (en) | Sewage discharge system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190419 |