CN109650227A - A kind of quickly assembling installation elevator hoistway with steel structure - Google Patents

A kind of quickly assembling installation elevator hoistway with steel structure Download PDF

Info

Publication number
CN109650227A
CN109650227A CN201910010355.1A CN201910010355A CN109650227A CN 109650227 A CN109650227 A CN 109650227A CN 201910010355 A CN201910010355 A CN 201910010355A CN 109650227 A CN109650227 A CN 109650227A
Authority
CN
China
Prior art keywords
frame
steel structure
elevator hoistway
chassis
groups
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910010355.1A
Other languages
Chinese (zh)
Other versions
CN109650227B (en
Inventor
王东华
沈林峰
王学建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG EXXON ELEVATOR CO Ltd
Original Assignee
ZHEJIANG EXXON ELEVATOR CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG EXXON ELEVATOR CO Ltd filed Critical ZHEJIANG EXXON ELEVATOR CO Ltd
Priority to CN201910010355.1A priority Critical patent/CN109650227B/en
Publication of CN109650227A publication Critical patent/CN109650227A/en
Application granted granted Critical
Publication of CN109650227B publication Critical patent/CN109650227B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B11/00Main component parts of lifts in, or associated with, buildings or other structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Structural Engineering (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

The invention discloses a kind of quickly assemblings to install elevator hoistway with steel structure additional, including two groups or so side frames disposed in parallel, front end between two groups of side frames is equipped with multiple frame members, and the rear end between two groups of side frames is equipped with more support beams, is equipped with hound between adjacent support beam;The side frame includes top frame and under(-)chassis, and 4 double columns for connecting top frame and under(-)chassis, double columns include 2 columns being set side by side, and the U-shaped mounting plate between column, form longitudinal slot on the flange of the U-shaped mounting plate two sides.The present invention is able to solve the shortcomings of the prior art, facilitates installation, and integral installation efficiency greatly improves.

Description

A kind of quickly assembling installation elevator hoistway with steel structure
Technical field
The present invention relates to a kind of quickly assemblings to install elevator hoistway with steel structure additional.
Background technique
For more and more old residential areas since inhabitation crowd is tending to aging, the elderly is more and more, and existing at present Old residential area is multiple field building, is all fitted without elevator when building, and causes resident's stair activity inconvenient, installs outside aging blocks Elevator can solve this problem.Therefore, fluctuation of service after existing hoistway with steel structure installation, while whole structural strength Do not cause the service life short very much, is unfavorable for long-run development.So the applicant proposes further to improve on this basis, one kind is designed Quickly elevator hoistway with steel structure is installed in assembling additional, to meet the needs of existing market.
Summary of the invention
The technical problem to be solved by the present invention is to overcome the existing defects, provides a kind of quickly assembling installation elevator steel construction Hoistway facilitates installation, and integral installation efficiency greatly improves.
In order to solve the above-mentioned technical problems, the present invention provides the following technical solutions:
Elevator hoistway with steel structure is installed in a kind of quickly assembling additional, it is characterised in that: including two groups or so side frames disposed in parallel, two Front end between group side frame is equipped with multiple frame members, and the rear end between two groups of side frames is equipped with more support beams, adjacent Support beam between be equipped with hound;The side frame includes top frame and under(-)chassis, and for connecting top frame 4 double columns of frame and under(-)chassis, double columns include 2 columns being set side by side, and U-shaped between column Mounting plate forms longitudinal slot on the flange of the U-shaped mounting plate two sides.
The present invention is done further preferably, multiple dual connecting rods are equipped between adjacent double columns, the dual connecting rod includes 2 A connecting rod, the T-type snap-gauge between the connecting rod.
The present invention is done further preferably, the top frame forms multiple support rods, is equipped on the upside of the support rod Protective cover.
The present invention is done further preferably, the under(-)chassis includes bottom plate, forms cavity in the bottom plate.
The present invention is done further preferably, above the under(-)chassis be equipped with fixed frame, the fixed frame with it is described X-type bracket is formed between under(-)chassis to be fixed, and forms powerful support construction.
Compared with prior art the beneficial effects obtained by the present invention are as follows being:
The present invention includes two groups or so side frames disposed in parallel, and the front end between two groups of side frames is equipped with multiple frame members, Rear end between two groups of side frames is equipped with more support beams, is equipped with hound between adjacent support beam;The side frame 4 double columns including top frame and under(-)chassis, and for connecting top frame and under(-)chassis, double column packets 2 columns being set side by side are included, and the U-shaped mounting plate between column, is formed on the flange of the U-shaped mounting plate two sides Longitudinal slot.The present invention can be by prefabricated tailor-made by side frame, it is only necessary to is attached by support beam, and by oblique branch Support is reinforced, and powerful hoistway is formed, and in order to improve stability, the column in side frame uses double columns, and the two Between U-shaped mounting plate is set, form longitudinal slot on the flange of the U-shaped mounting plate two sides, thus substantially increase carriage and lead The sliding of wheel, no longer needs to setting car guide rail, and whole stability also greatly improves.
From the foregoing, it will be observed that the present invention is able to solve the shortcomings of the prior art, facilitate installation, and integral installation is imitated Rate greatly improves.
Detailed description of the invention
Attached drawing is used to provide further understanding of the present invention, and constitutes part of specification, with reality of the invention It applies example to be used to explain the present invention together, not be construed as limiting the invention.
In the accompanying drawings:
Fig. 1 is the schematic diagram of apparent direction after hoistway in the present invention.
Fig. 2 is the schematic diagram of hoistway side-looking direction in the present invention.
Fig. 3 is the schematic diagram of double columns in hoistway of the present invention.
Fig. 4 is the schematic diagram of dual connecting rod in hoistway of the present invention.
Fig. 5 is the schematic diagram of under(-)chassis in hoistway of the present invention.
Specific embodiment
Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings, it should be understood that preferred reality described herein Apply example only for the purpose of illustrating and explaining the present invention and is not intended to limit the present invention.
As shown in Figs. 1-5, the present invention relates to a kind of quickly assemble to install elevator hoistway with steel structure additional, including two groups or so parallel The side frame 101 of setting, the front end between two groups of side frames 101 are equipped with multiple frame members, the rear end between two groups of side frames Equipped with more support beams 102, hound 103 is equipped between adjacent support beam 102, the side frame 101 includes top Frame 11 and under(-)chassis 12, and 4 double columns 13 for connecting top frame 11 and under(-)chassis 12, double columns 13 include 2 columns 131 being set side by side, and the U-shaped mounting plate 132 between column 131, the U-shaped mounting plate 132 Longitudinal slot 133 is formed on the flange of two sides;Car guide rail therein and U-shaped mounting plate 132, which match, to be installed, the longitudinal slot of two sides 133 match with the small guide wheels of guide rail two sides, descend operation stability height on the whole.
Multiple dual connecting rods 14 are equipped in the present invention between adjacent double columns 13, the dual connecting rod 14 includes 2 connections Two lateral flanges of bar 141, the T-type snap-gauge 142 between the connecting rod 141, the T-type snap-gauge are fixed in connecting rod 141, and Each other using welding.Top frame 11 forms multiple support rods, and the fixation for putting machine beam in the present invention;In the support rod 11 upsides are equipped with protective cover 111, play a protective role.
Heretofore described under(-)chassis 12 includes bottom plate 121, and cavity 122 is formed in the bottom plate 121, described Cavity 122 is fixed for pedestal 71;Be equipped with fixed frame 15 above the under(-)chassis 12, the fixed frame 15 and pedestal 71 it Between it is mated with one another, and fixed each other by bolt, form X-type bracket 16 between the fixed frame 15 and the under(-)chassis 12 It is fixed, forms powerful support construction.
Finally, it should be noted that the foregoing is only a preferred embodiment of the present invention, it is not intended to restrict the invention, Although the present invention is described in detail referring to the foregoing embodiments, for those skilled in the art, still may be used To modify the technical solutions described in the foregoing embodiments or equivalent replacement of some of the technical features. All within the spirits and principles of the present invention, any modification, equivalent replacement, improvement and so on should be included in of the invention Within protection scope.

Claims (5)

1. elevator hoistway with steel structure is installed in a kind of quickly assembling additional, it is characterised in that: including two groups or so side frames disposed in parallel, Front end between two groups of side frames is equipped with multiple frame members, and the rear end between two groups of side frames is equipped with more support beams, phase Hound is equipped between adjacent support beam;The side frame includes top frame and under(-)chassis, and for connecting top 4 double columns of frame and under(-)chassis, double columns include 2 columns being set side by side, and the U between column Type mounting plate forms longitudinal slot on the flange of the U-shaped mounting plate two sides.
2. elevator hoistway with steel structure is installed in a kind of quickly assembling according to claim 1 additional, it is characterised in that: adjacent double columns Between be equipped with multiple dual connecting rods, the dual connecting rod include 2 connecting rods, the T-type snap-gauge between the connecting rod.
3. elevator hoistway with steel structure is installed in a kind of quickly assembling according to claim 1 additional, it is characterised in that: the top frame Frame forms multiple support rods, and protective cover is equipped on the upside of the support rod.
4. elevator hoistway with steel structure is installed in a kind of quickly assembling according to claim 1 additional, it is characterised in that: the bottom frame Frame includes bottom plate, forms cavity in the bottom plate.
5. elevator hoistway with steel structure is installed in a kind of quickly assembling according to claim 1 additional, it is characterised in that: in the bottom Be equipped with fixed frame above frame, form X-type bracket between the fixed frame and the under(-)chassis and be fixed, formed it is strong and Strong support construction.
CN201910010355.1A 2019-01-07 2019-01-07 Fast assembly installs elevator steel construction well additional Active CN109650227B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910010355.1A CN109650227B (en) 2019-01-07 2019-01-07 Fast assembly installs elevator steel construction well additional

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910010355.1A CN109650227B (en) 2019-01-07 2019-01-07 Fast assembly installs elevator steel construction well additional

Publications (2)

Publication Number Publication Date
CN109650227A true CN109650227A (en) 2019-04-19
CN109650227B CN109650227B (en) 2021-03-02

Family

ID=66118643

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910010355.1A Active CN109650227B (en) 2019-01-07 2019-01-07 Fast assembly installs elevator steel construction well additional

Country Status (1)

Country Link
CN (1) CN109650227B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111719817A (en) * 2020-05-25 2020-09-29 杭州西奥电梯有限公司 Frame-type steel construction elevator well

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6425463B1 (en) * 2000-03-15 2002-07-30 Frederick Kenneth Broyan Non-personnel lifting device
CN202729526U (en) * 2012-05-31 2013-02-13 深圳市南钜物流设备有限公司 Directly-pushed type lifting table
CN203428694U (en) * 2013-09-05 2014-02-12 杨志宏 Household trackless lifting platform
CN105883549A (en) * 2014-11-21 2016-08-24 宁波谷达机电有限公司 Novel lift well
CN106564806A (en) * 2016-10-27 2017-04-19 深圳市科陆电子科技股份有限公司 Cargo hoister
CN107253652A (en) * 2017-07-13 2017-10-17 黄业华 A kind of existing building installs ladder additional
CN107399656A (en) * 2017-08-31 2017-11-28 西继迅达(许昌)电梯有限公司 Outdoor installation elevator and its construction method
CN107902523A (en) * 2017-12-20 2018-04-13 森赫电梯股份有限公司 A kind of piece-shape type aging blocks install elevator additional
CN207792414U (en) * 2017-12-20 2018-08-31 森赫电梯股份有限公司 Piece-shape type aging blocks install the steel structure derrick of elevator additional

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6425463B1 (en) * 2000-03-15 2002-07-30 Frederick Kenneth Broyan Non-personnel lifting device
CN202729526U (en) * 2012-05-31 2013-02-13 深圳市南钜物流设备有限公司 Directly-pushed type lifting table
CN203428694U (en) * 2013-09-05 2014-02-12 杨志宏 Household trackless lifting platform
CN105883549A (en) * 2014-11-21 2016-08-24 宁波谷达机电有限公司 Novel lift well
CN106564806A (en) * 2016-10-27 2017-04-19 深圳市科陆电子科技股份有限公司 Cargo hoister
CN107253652A (en) * 2017-07-13 2017-10-17 黄业华 A kind of existing building installs ladder additional
CN107399656A (en) * 2017-08-31 2017-11-28 西继迅达(许昌)电梯有限公司 Outdoor installation elevator and its construction method
CN107902523A (en) * 2017-12-20 2018-04-13 森赫电梯股份有限公司 A kind of piece-shape type aging blocks install elevator additional
CN207792414U (en) * 2017-12-20 2018-08-31 森赫电梯股份有限公司 Piece-shape type aging blocks install the steel structure derrick of elevator additional

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111719817A (en) * 2020-05-25 2020-09-29 杭州西奥电梯有限公司 Frame-type steel construction elevator well
CN111719817B (en) * 2020-05-25 2021-08-24 杭州西奥电梯有限公司 Frame-type steel construction elevator well

Also Published As

Publication number Publication date
CN109650227B (en) 2021-03-02

Similar Documents

Publication Publication Date Title
CN209667085U (en) Floor of railway vehicle mounting structure and rail vehicle
CN101624068A (en) Rear vehicle body structure
CN109178009A (en) 100% low-floor rail vehicle chassis of one kind and 100% low-floor rail vehicle
CN109650227A (en) A kind of quickly assembling installation elevator hoistway with steel structure
CN207671507U (en) Visiting elevator car sedan-chair frame and its carriage bracket
CN110539601A (en) Combined type air suspension system of unmatched thrust rod
CN105712168A (en) Truss supporting structure
CN207792414U (en) Piece-shape type aging blocks install the steel structure derrick of elevator additional
CN219525969U (en) Telescopic cage bottom plate frame for construction lifter
CN205131381U (en) Commodity circulation car sub vehicle puts up assembly
CN210562911U (en) Steel bar truss floor board that security performance is high
CN211395393U (en) Firm in structure's bent cap end shield
CN110080540B (en) Large-span steel structure sliding device and construction method thereof
CN203782619U (en) Construction trolley
CN207360424U (en) A kind of small-sized equation motorcycle race vehicle frame
CN208831016U (en) A kind of novel portal-framed structure for two lining trolleys
CN203428765U (en) Hoist trolley and crane using same
CN207314941U (en) A kind of frame structure of multi-storied garage
CN210713922U (en) Add elevator well and former building connection structure
CN207077967U (en) A kind of air suspension trailing arm
CN107651540A (en) A kind of vertical beam component
CN217975531U (en) Reinforced structure of building beam body
CN205973668U (en) Lift platform subassembly
CN210214489U (en) Passenger elevator car bottom bracket
CN219710929U (en) Suspension type operation platform for steel beam welding construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant