CN109638742A CN201910003738.6A CN201910003738A CN109638742A CN 109638742 A CN109638742 A CN 109638742A CN 201910003738 A CN201910003738 A CN 201910003738A CN 109638742 A CN109638742 A CN 109638742A
Authority
CN
China
Prior art keywords
cable
testing bridge
hole
air cushion
crosspiece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910003738.6A
Other languages
Chinese (zh)
Other versions
CN109638742B (en
Inventor
张文亮
周驰
程旎
席志成
李海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Marine Machinery Plant Co Ltd
Original Assignee
Wuhan Marine Machinery Plant Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Marine Machinery Plant Co Ltd filed Critical Wuhan Marine Machinery Plant Co Ltd
Priority to CN201910003738.6A priority Critical patent/CN109638742B/en
Publication of CN109638742A publication Critical patent/CN109638742A/en
Application granted granted Critical
Publication of CN109638742B publication Critical patent/CN109638742B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G3/00Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
    • H02G3/02Details
    • H02G3/04Protective tubing or conduits, e.g. cable ladders or cable troughs
    • H02G3/0456Ladders or other supports
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16FSPRINGS; SHOCK-ABSORBERS; MEANS FOR DAMPING VIBRATION
    • F16F15/00Suppression of vibrations in systems; Means or arrangements for avoiding or reducing out-of-balance forces, e.g. due to motion
    • F16F15/02Suppression of vibrations of non-rotating, e.g. reciprocating systems; Suppression of vibrations of rotating systems by use of members not moving with the rotating systems
    • F16F15/023Suppression of vibrations of non-rotating, e.g. reciprocating systems; Suppression of vibrations of rotating systems by use of members not moving with the rotating systems using fluid means
    • F16F15/0232Suppression of vibrations of non-rotating, e.g. reciprocating systems; Suppression of vibrations of rotating systems by use of members not moving with the rotating systems using fluid means with at least one gas spring
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G3/00Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
    • H02G3/02Details
    • H02G3/04Protective tubing or conduits, e.g. cable ladders or cable troughs
    • H02G3/0406Details thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Acoustics & Sound (AREA)
  • Aviation & Aerospace Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Tables And Desks Characterized By Structural Shape (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of cable testing bridges, belong to cable installing area.Cable testing bridge includes two terraced sides and multiple crosspieces, two terraced sides are arranged parallel, one end of each crosspiece is fixedly mounted on a terraced side, the other end of each crosspiece is fixed on another terraced side, and successively arranged for interval, cable testing bridge further include air cushion to length direction of each crosspiece along terraced side, air cushion is fixedly mounted on multiple crosspieces, length direction of the air cushion along terraced side extends, and multiple first fixation holes are provided on air cushion, and all first fixation holes are used to inserting band.The vibration of cable can be absorbed in the present invention, prevents cable because vibration causes the band of fixed cable to loosen.

Description

A kind of cable testing bridge
Technical field
The invention belongs to cable installing area, in particular to a kind of cable testing bridge.
Background technique
Cable testing bridge is a kind of device for cabling, and common cable testing bridge generally includes: two terraced sides and more A crosspiece, two terraced sides are arranged parallel, and one end of each crosspiece is fixedly mounted on a terraced side, and the other end of each crosspiece is solid It is scheduled on another terraced side, and each crosspiece is along the length direction successively arranged for interval on terraced side.
When passing through above-mentioned cable testing bridge cabling, generally cable is directly strapped on crosspiece by band, so that Length direction arrangement of the cable along terraced side.
In the implementation of the present invention, the inventor finds that the existing technology has at least the following problems:
When cable circulates high current, under the action of electromagnetic induction phenomenon, cable can generate vibration relative to crosspiece, and Due to being only fixedly connected by band between cable and crosspiece, so under prolonged vibration, it, will once band loosens There are the risks that cable falls off.
Summary of the invention
The embodiment of the invention provides a kind of cable testing bridge, can slow down when cable circulates high current, in electromagnetic induction Under the action of phenomenon, cable can be relative to the vibration of crosspiece generation.The technical solution is as follows:
The embodiment of the invention provides a kind of cable testing bridge, the cable testing bridge includes: two terraced sides and multiple crosspieces, and two A terraced side is arranged parallel, and one end of each crosspiece is fixedly mounted on the terraced side, each crosspiece The other end is fixed on another described terraced side, and each crosspiece is along the length direction successively arranged for interval on the terraced side, institute Stating cable testing bridge further includes air cushion, and the air cushion is fixedly mounted on multiple crosspieces, length of the air cushion along the terraced side It spends direction to extend, multiple first fixation holes is provided on the air cushion, all first fixation holes are used to inserting band.
In a kind of implementation of the invention, multiple first cable-through holes, each first mistake are provided on the air cushion Length direction successively arranged for interval of the string holes along the terraced side.
In another implementation of the invention, it is provided with described at least two between crosspiece described in each adjacent two First cable-through hole.
In another implementation of the invention, the cable testing bridge further includes insulation board, the fixed peace of the insulation board On each crosspiece, length direction of the insulation board along the terraced side extends, and the insulation board is folded in the cross Between shelves and the air cushion.
In another implementation of the invention, bond together between the insulation board and the air cushion.
In another implementation of the invention, multiple and first fixation hole is provided on the insulation board one by one Second fixation hole of corresponding arrangement, all second fixation holes are used to insert the band.
In another implementation of the invention, multiple and each first cable-through hole one is provided on the insulation board Second cable-through hole of one corresponding arrangement, length direction successively arranged for interval of each second cable-through hole along the terraced side.
In another implementation of the invention, it is provided with described at least two between crosspiece described in each adjacent two Second cable-through hole.
In another implementation of the invention, multiple lateral mounting holes, the crosspiece are provided on the insulation board On be provided with the longitudinally mounted hole that arrangement is corresponded with each lateral mounting hole, each described lateral mounting hole and correspondence The longitudinally mounted Kong Zhongjun be fitted with the same bolt.
In another implementation of the invention, the insulation board is epoxy resin board.
Technical solution provided in an embodiment of the present invention has the benefit that
By configuring air cushion in cable testing bridge, air cushion is fixedly mounted on multiple crosspieces, to realize air cushion in cross Fixed installation on shelves.Also, the length direction due to air cushion along terraced side extends, so utilizing cable testing bridge cabling When, cable can be arranged along the length direction of air cushion.In addition, more after cable laying, then by being arranged on air cushion A first fixation hole inserts band, so that cable is capable of fixing bind on air cushion, to be generated using air cushion absorbing cable Vibration, avoid band and loosened because of strum, and then improve the mounting stability of cable.
Detailed description of the invention
To describe the technical solutions in the embodiments of the present invention more clearly, make required in being described below to embodiment Attached drawing is briefly described, it should be apparent that, drawings in the following description are only some embodiments of the invention, for For those of ordinary skill in the art, without creative efforts, it can also be obtained according to these attached drawings other Attached drawing.
Fig. 1 is the top view on terraced side provided in an embodiment of the present invention;
Fig. 2 is cable testing bridge top view provided in an embodiment of the present invention;
Fig. 3 is air cushion structure schematic diagram provided in an embodiment of the present invention;
Fig. 4 is cable testing bridge sectional view provided in an embodiment of the present invention;
Fig. 5 is panel structure schematic diagram provided in an embodiment of the present invention;
Fig. 6 is the enlarged drawing at cable testing bridge top view A provided in an embodiment of the present invention;
Fig. 7 is the enlarged drawing at cable testing bridge sectional view B provided in an embodiment of the present invention;
Each symbol indicates that meaning is as follows in figure:
1- ladder side, 11- band, 2- crosspiece, the longitudinally mounted hole 21-, 3- air cushion, the first fixation hole of 31-, 32- first cross line Hole, 33- aeration aperture, 4- gantry, 5- glue, 6- insulation board, the second fixation hole of 61-, the second cable-through hole of 62-, 63- are transversely mounted Hole, 7- bolt, 8- plain cushion, 9- spring washer, 10- nut, 100- cable.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, below in conjunction with attached drawing to embodiment party of the present invention Formula is described in further detail.
The embodiment of the invention provides a kind of cable testing bridges, as shown in Figure 1, the cable testing bridge includes: two terraced sides 1 and more A crosspiece 2, two terraced sides 1 are arranged parallel, and one end of each crosspiece 2 is fixedly mounted on a terraced side 1, each crosspiece 2 it is another One end is fixed on another terraced side 1, and each crosspiece 2 is along the length direction successively arranged for interval on terraced side 1.
Fig. 2 is cable testing bridge top view provided in an embodiment of the present invention, and in conjunction with Fig. 2, in the present embodiment, cable testing bridge is also Including air cushion 3, air cushion 3 is fixedly mounted on multiple crosspieces 2, and length direction of the air cushion 3 along terraced side 1 extends.
Fig. 3 is that air cushion structure schematic diagram provided in an embodiment of the present invention specifically, is provided with more in conjunction with Fig. 3 on air cushion 3 A first fixation hole 31, all first fixation holes 31 are used to inserting band 11.
By configuring air cushion 3 in cable testing bridge, air cushion 3 is fixedly mounted on multiple crosspieces 2, to realize air cushion 3 Fixed installation on crosspiece 2.Also, the length direction due to air cushion 3 along terraced side 1 extends, so applying using cable testing bridge If when cable 100, cable 100 can be arranged along the length direction of air cushion 3.In addition, after cable 100 is laid, then lead to The multiple first fixation holes 31 inserting band 11 being arranged on air cushion 3 is crossed, so that cable 100 is capable of fixing bind on air cushion 3, It to the vibration generated using 3 absorbing cable 100 of air cushion, avoids band 11 and is loosened because cable 100 vibrates, and then improve The mounting stability of cable 100.
In the present embodiment, multiple first cable-through holes 32, length of each first cable-through hole 32 along terraced side 1 are provided on air cushion 3 Spend direction successively arranged for interval.
In above-mentioned implementation, when need to be laid in 100 external electrical equipment of cable on cable testing bridge when, Ke Yixuan The first cable-through hole 32 for selecting suitable position, by cable 100 there through, and with corresponding electrical equipment be electrically connected.It needs to illustrate , the first cable-through hole 32 of suitable position can be one first mistake line being most electrically connected with electrical equipment convenient for cable 100 Hole 32.
Preferably, at least two first cable-through holes 32 are provided between each adjacent two crosspiece 2.
In above-mentioned implementation, when more electrical equipments at a distance of it is closer when, and more electrical equipments require to connect When cable 100, because there are at least two first cable-through holes 32 between two adjacent rungs 2, more electrical equipment connections are avoided Cable 100 causes cable 100 in the crowded of some the first cable-through hole 32.And have multiple first cable-through holes 32 available, it can To select most convenient according to the position of electrical equipment, electrical equipment is connect by most suitable first cable-through hole 32 with cable 100.
Optionally, the shape of the first cable-through hole 32 is round rectangle, and round rectangle is the shape that four right angles are fillet.
In above-mentioned implementation, by setting round rectangle for the first cable-through hole 32, cable 100 can be prevented even It is cut off because of pullling by sharp rectangle right angle when connecing.
Optionally, air cushion 3 is inflatable air cushion, and air cushion 3 is equipped with aeration aperture 33, and aeration aperture 33 is located at the side of inflatable air cushion 3 Edge, close to the position of the first cable-through hole 32.
In above-mentioned implementation, because air cushion 3 is inflatable air cushion, it is mounted on cable testing bridge convenient for air cushion 3.When by dress It only needs for the air cushion 3 of unaerated to be fixed on cable testing bridge, after air cushion 3 fixes, then passing through aeration aperture 33 again is air cushion 3 Inflation.
Preferably, the material of air cushion 3 can be class TPU material, so as to make to bring about the desired sensation using the characteristic of class TPU material Pad 3 is wear-resisting and elasticity is good, so that air cushion 3 has good bearing capacity, enables 3 shock resistance of air cushion and damping performance is prominent Out.
Fig. 4 is cable testing bridge sectional view provided in an embodiment of the present invention, and referring to fig. 4, in the present embodiment, cable testing bridge is also Including insulation board 6, insulation board 6 is fixedly mounted on each crosspiece 2, and length direction of the insulation board 6 along terraced side 1 extends (referring to fig. 2), And insulation board 6 is folded between crosspiece 2 and air cushion 3.
In above-mentioned implementation, because can be produced because of electromagnetic induction phenomenon on gantry 4 when cable flows through high current Induced voltage is given birth to, between the crosspiece 2 on gantry 4 is the electric loop of closure, so just will form inductance loop stream between crosspiece 2, Circulation can generate heat, when insulation board 6 is folded between crosspiece 2 and air cushion 3, can upper surface to cable 100 and crosspiece 2 into The isolation of row physical insulation avoids generating electromagnetic induction, to reduce the fever of crosspiece 2.
Preferably, insulation board 6 can be epoxy resin board.
It should be noted that in other embodiments, the material of insulation board 6 can be selected according to actual needs, example Such as organic glass, nylon, the invention is not limited in this regard.
Optionally, it bonds together between insulation board 6 and air cushion 3.
It preferably, is by 5 adhesion of glue in the implementation case, between insulation board 6 and air cushion 3, glue is AB glue.
It should be noted that in other embodiments, glue 5 can be selected according to actual needs, such as UV glue, 407 glue etc., the invention is not limited in this regard.
Fig. 5 is panel structure schematic diagram provided in an embodiment of the present invention, in conjunction with Fig. 5, in the present embodiment, insulation board 6 On be provided with multiple the second fixation holes 61 that arrangement is corresponded with the first fixation hole 31, all second fixation holes 61 are used to insert Fill band 11.
In above-mentioned implementation, after cable 100 is laid, because multiple second be arranged on insulation board 6 are fixed The first fixation hole 31 on hole 61 and air cushion 3, which corresponds, to be arranged, can be used by the second fixation hole 61 and the first fixation hole 31 Cable 100 is fixed bind in 6 Adhesion formation of air cushion 3 and insulation board on the whole (referring to Fig. 4), to utilize air cushion by band 11 The vibration that 3 absorbing cables 100 generate avoids band 11 and loosens because cable 100 vibrates, and then improves the peace of cable 100 Fill stability.
With continued reference to Fig. 5, in the present embodiment, multiple second cable-through holes 62, each second cable-through hole are provided on insulation board 6 62 along terraced side 1 length direction successively arranged for interval.
In above-mentioned implementation, when need to be laid in 100 external electrical equipment of cable on cable testing bridge when, Ke Yixuan The second cable-through hole 62 for selecting suitable position, by cable 100 there through, and with corresponding electrical equipment be electrically connected.It needs to illustrate , the second cable-through hole 62 of suitable position can be one second mistake line being most electrically connected with electrical equipment convenient for cable 100 Hole 62.
Preferably, at least two second cable-through holes 62 are provided between each adjacent two crosspiece 2.
In above-mentioned implementation, when more electrical equipments at a distance of it is closer when, and more electrical equipments require to connect When cable 100, because there are at least two second cable-through holes 62 between two adjacent rungs 2, more electrical equipment connections are avoided Cable 100 causes cable 100 in the crowded of some the second cable-through hole 62.And have multiple second cable-through holes 62 available, it can To select most convenient according to the position of electrical equipment, electrical equipment is connect by most suitable second cable-through hole 62 with cable 100.
Optionally, the shape of the second cable-through hole 62 is round rectangle, and round rectangle is the shape that four right angles are fillet.
In above-mentioned implementation, by setting round rectangle for the second cable-through hole 62, cable 100 can be prevented even It is cut off because of pullling by sharp rectangle right angle when connecing.
Fig. 6 is the enlarged drawing at cable testing bridge top view A provided in an embodiment of the present invention, in conjunction with Fig. 6, in the present embodiment In, it is provided with multiple lateral mounting holes 63 on insulation board 6, is provided with to correspond with each lateral mounting hole 63 on crosspiece 2 and arrange Longitudinally mounted hole 21, be fitted with the same bolt 7 in each lateral mounting hole 63 and corresponding longitudinally mounted hole 21.
In above-mentioned implementation, because lateral mounting hole 63 and the shape in longitudinally mounted hole 21 are strip, bolt 7 It can be moved in strip hole, have deviation when insulation board 6 and the installation of crosspiece 2, bolt 7 can be moved, to insulation board 6 and crosspiece 2 position is adjusted, and then insulation board 6 is fastened on crosspiece 2, can reduce in this way insulation board 6 installed with crosspiece 2 it is inclined Difference, and it is applied widely.
Enlarged drawing at Fig. 7 cable testing bridge sectional view B provided in an embodiment of the present invention, in conjunction with Fig. 7, insulation board 6 and crosspiece 2 By the way that bolt 7 is sequentially passed through insulation board 6, crosspiece 2, plain cushion 8, spring washer 9, nut 10 from top to bottom, and bolt 7 is fastened.
In above-mentioned implementation, insulation board 6 and crosspiece 2 tighten together, and prevent cable 100 from being drawn by electronic force vibration Insulation board 6 is played to loosen with the crosspiece 2 on gantry 4.
Optionally, in the embodiment of the present invention, bolt 7 can be interior hexagonal flat round hook bolt.
It should be noted that in other embodiments, can be selected according to actual needs, for example, interior hexagonal semicircle Hook bolt and interior hexagonal flower pattern pan bolt, the invention is not limited in this regard.
Referring to Fig. 7, in embodiments of the present invention, the two sides that air cushion 3 extends along its length are with insulation board 6 along length side To the two sides arranged for interval of extension, air cushion 3 is less than the projection of insulation board 6 and air cushion 3 on insulation board 6 and is located at insulation board 6 Interior (referring to Fig. 4).
In above-mentioned implementation, because air cushion 3 is less than insulation board 6, position is provided for the installation of bolt 7, and avoid In heat transfer to air cushion 3 on bolt 7.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, it is all in spirit of the invention and Within principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of cable testing bridge, the cable testing bridge includes: two terraced sides (1) and multiple crosspieces (2), two terraced sides (1) Be arranged parallel, one end of each crosspiece (2) is fixedly mounted on the terraced side (1), each crosspiece (2) it is another One end is fixed on another described terraced side (1), and each crosspiece (2) is successively spaced along the length direction of the terraced side (1) Arrangement, which is characterized in that the cable testing bridge further includes air cushion (3), and the air cushion (3) is fixedly mounted on multiple crosspieces (2) on, the air cushion (3) extends along the length direction of the terraced side (1), and it is fixed that multiple first are provided on the air cushion (3) Hole (31), all first fixation holes (31) are used to inserting band (12).
2. cable testing bridge according to claim 1, which is characterized in that be provided with multiple first on the air cushion (3) and cross line Hole (32), length direction successively arranged for interval of each first cable-through hole (32) along the terraced side (1).
3. cable testing bridge according to claim 2, which is characterized in that crosspiece described in each adjacent two is respectively provided between (2) There are at least two first cable-through holes (32).
4. cable testing bridge according to claim 2, which is characterized in that the cable testing bridge further includes insulation board (6), described Insulation board (6) is fixedly mounted on each crosspiece (2), and the insulation board (6) extends along the length direction of the terraced side (1), And the insulation board (6) is folded between the crosspiece (2) and the air cushion (3).
5. cable testing bridge according to claim 4, which is characterized in that glued between the insulation board (6) and the air cushion (3) It is connected together.
6. cable testing bridge according to claim 4, which is characterized in that be provided on the insulation board (6) it is multiple with it is described First fixation hole (31) corresponds the second fixation hole (61) of arrangement, and all second fixation holes (61) are used to inserting institute State band (12).
7. cable testing bridge according to claim 4, which is characterized in that be provided with multiple and each institute on the insulation board (6) The second cable-through hole (62) that the first cable-through hole (32) correspond arrangement is stated, each second cable-through hole (62) is along the terraced side (1) length direction successively arranged for interval.
8. cable testing bridge according to claim 7, which is characterized in that crosspiece described in each adjacent two is respectively provided between (2) There are at least two second cable-through holes (62).
9. cable testing bridge according to claim 4, which is characterized in that be provided with multiple laterally peaces on the insulation board (6) It fills hole (63), the longitudinally mounted hole for corresponding arrangement with each lateral mounting hole (63) is provided on the crosspiece (2) (21), the same bolt is fitted in each described lateral mounting hole (63) and the corresponding longitudinally mounted hole (21) (7)。
10. cable testing bridge according to claim 4, which is characterized in that the insulation board (6) is epoxy resin board.
CN201910003738.6A 2019-01-03 2019-01-03 Cable bridge Active CN109638742B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910003738.6A CN109638742B (en) 2019-01-03 2019-01-03 Cable bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910003738.6A CN109638742B (en) 2019-01-03 2019-01-03 Cable bridge

Publications (2)

Publication Number Publication Date
CN109638742A true CN109638742A (en) 2019-04-16
CN109638742B CN109638742B (en) 2020-08-11

Family

ID=66056659

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910003738.6A Active CN109638742B (en) 2019-01-03 2019-01-03 Cable bridge

Country Status (1)

Country Link
CN (1) CN109638742B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110556755A (en) * 2019-07-23 2019-12-10 武汉船用机械有限责任公司 Cable bridge
CN113572091A (en) * 2021-07-16 2021-10-29 宋孝军 Cable bridge for power engineering
CN114552505A (en) * 2022-01-20 2022-05-27 北京航天发射技术研究所 Carrier rocket pulls out cable protector

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004120955A (en) * 2002-09-27 2004-04-15 Kono Denki Kk Cable bundle holder
CN202432121U (en) * 2011-11-29 2012-09-12 重庆通用工业(集团)有限责任公司 Pipe clamp bracket
CN105591333A (en) * 2016-03-10 2016-05-18 重庆星特龙实业有限公司 Cable bridge
CN206595661U (en) * 2017-03-10 2017-10-27 浙江吉利控股集团有限公司 One kind can crushing type protective cradle
CN107359575A (en) * 2017-09-08 2017-11-17 扬州市天海滑线电气有限公司 A kind of ladder type bus bridge frame with heat sinking function
CN107565463A (en) * 2017-09-12 2018-01-09 武汉船用机械有限责任公司 Cable isolating device
CN207910399U (en) * 2018-03-26 2018-09-25 广东金来电气有限公司 A kind of reinforced ladder-type bridge frame
CN109066511A (en) * 2018-09-04 2018-12-21 广东电网有限责任公司 Cable bearer and cable-laying gear

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004120955A (en) * 2002-09-27 2004-04-15 Kono Denki Kk Cable bundle holder
CN202432121U (en) * 2011-11-29 2012-09-12 重庆通用工业(集团)有限责任公司 Pipe clamp bracket
CN105591333A (en) * 2016-03-10 2016-05-18 重庆星特龙实业有限公司 Cable bridge
CN206595661U (en) * 2017-03-10 2017-10-27 浙江吉利控股集团有限公司 One kind can crushing type protective cradle
CN107359575A (en) * 2017-09-08 2017-11-17 扬州市天海滑线电气有限公司 A kind of ladder type bus bridge frame with heat sinking function
CN107565463A (en) * 2017-09-12 2018-01-09 武汉船用机械有限责任公司 Cable isolating device
CN207910399U (en) * 2018-03-26 2018-09-25 广东金来电气有限公司 A kind of reinforced ladder-type bridge frame
CN109066511A (en) * 2018-09-04 2018-12-21 广东电网有限责任公司 Cable bearer and cable-laying gear

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110556755A (en) * 2019-07-23 2019-12-10 武汉船用机械有限责任公司 Cable bridge
CN110556755B (en) * 2019-07-23 2021-05-28 武汉船用机械有限责任公司 Cable bridge
CN113572091A (en) * 2021-07-16 2021-10-29 宋孝军 Cable bridge for power engineering
CN113572091B (en) * 2021-07-16 2022-12-09 任丘市天马通讯器材有限公司 Cable bridge for power engineering
CN114552505A (en) * 2022-01-20 2022-05-27 北京航天发射技术研究所 Carrier rocket pulls out cable protector
CN114552505B (en) * 2022-01-20 2024-02-02 北京航天发射技术研究所 Carrier rocket cable removing and pulling protection device

Also Published As

Publication number Publication date
CN109638742B (en) 2020-08-11

Similar Documents

Publication Publication Date Title
CN109638742A (en) A kind of cable testing bridge
CN201181826Y (en) 10KV overhead conductor insulation support fixer
EP1845620A3 (en) Integrated protective circuit component using semiconductors for load relief, voltage limitation and oscillation damping
DE112014001175B4 (en) Electric compressor with integrated inverter
US20140124018A1 (en) Photovoltaic Panel Racking System
CN102044982A (en) Modularization thyristor rectifying unit
CN206856640U (en) A kind of reason line fixing device for battery bag
US10364863B2 (en) Arrangement for fastening a power electronic device such as a frequency converter
CN210041189U (en) Novel cable bridge
CN209353837U (en) High voltage power transmission stringer
CN206602725U (en) Wire-management device and rack
CN203883424U (en) Vibration damper of power transmission line
CN107492801A (en) A kind of support mounting seat of distribution box
US10224703B2 (en) Suspension arrangement for electrical operating components
CN208316033U (en) Switchgear tier
US9755414B2 (en) Overhead electrical grounding mesh and mechanical grid structure
CN106771386A (en) A kind of electrical test thread guide devices for making somebody a mere figurehead electrical equipment
CN107863731B (en) cable fixing device
CN207234679U (en) Anti- vortex stent and cabinet
JP2007028884A (en) Straining device equipped with line-side fixed yoke for three or more conductors
CN206364216U (en) Flexible structure of copper bar in a kind of controller
JP2006012852A (en) Straining device equipped with line side fixed yoke for three or more conductors
WO1999004180A2 (en) Tunable shape memory alloy/elastic damper
CN108668430B (en) Conductor bundle heat dissipation method for satellite single-unit machine
CN217405247U (en) Wire group fixing device and insulating solid-state transformer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant