CN109636064A - Support the Study on Power Grid Planning scheme generation method and device of multi-person synergy operation - Google Patents

Support the Study on Power Grid Planning scheme generation method and device of multi-person synergy operation Download PDF

Info

Publication number
CN109636064A
CN109636064A CN201811602463.XA CN201811602463A CN109636064A CN 109636064 A CN109636064 A CN 109636064A CN 201811602463 A CN201811602463 A CN 201811602463A CN 109636064 A CN109636064 A CN 109636064A
Authority
CN
China
Prior art keywords
planning
power grid
study
scheme
server
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811602463.XA
Other languages
Chinese (zh)
Inventor
郑志伟
邹卫美
周勤勇
裘微江
张彦涛
吴国辉
杨京齐
李亚楼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
Original Assignee
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, China Electric Power Research Institute Co Ltd CEPRI filed Critical State Grid Corp of China SGCC
Priority to CN201811602463.XA priority Critical patent/CN109636064A/en
Publication of CN109636064A publication Critical patent/CN109636064A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Public Health (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention provides the Study on Power Grid Planning scheme generation method and device for supporting multi-person synergy operation.Wherein, for the method for client, comprising: in the case where meeting planning year boundary condition constraint, Electric Power Network Planning benchmark rack is superimposed in the project of transmitting and converting electricity locally saved, forms preliminary Study on Power Grid Planning scheme;Power grid security and stability analysis is carried out for preliminary Study on Power Grid Planning scheme, filters out that meet the Study on Power Grid Planning scheme of power grid security and stability index be Study on Power Grid Planning scheme after check;Economic and technical norms evaluation is carried out for the Study on Power Grid Planning scheme after check, determines that the optimal design scheme of economic and technical norms is Study on Power Grid Planning scheme to be evaluated.Study on Power Grid Planning scheme generation method and device provided by the invention, unified management planning reference net rack data, the Study on Power Grid Planning scheme for realizing that project of transmitting and converting electricity, each stage determine is shared, is convenient for multi-person synergy operation, improves the science and efficiency of Electric Power Network Planning work.

Description

Support the Study on Power Grid Planning scheme generation method and device of multi-person synergy operation
Technical field
The present invention relates to Electric Power Network Planning technical fields, and more particularly, to a kind of electricity for supporting multi-person synergy operation Net planning and designing scheme generation method and device.
Background technique
Because programme designs the research and development lag of analysis tool, many work in Electric Power Network Planning department are also relied at present It is carried out in mode manually.Specifically, according to the requirement of planning process sequential relationship, in planning period, it is related to completing Mass data such as summarizes, copies, integrating, filing at the work, causes the task of planning personnel many and diverse, needing in work will be very big Energy many time spends in the work such as data collection, data preparation.To a certain extent, currently, handling many and diverse rule Data are drawn, so that planning personnel is difficult to concentrate one's energy in the design and analysis of Study on Power Grid Planning scheme.
In addition, extensive use and height in scheme simulation analysis, in view of PSASP, BPA etc. in dispatching of power netwoks operation field Degree of recognition, planning personnel also have imitative by the common electric analog application software progress programme design such as PSASP, BPA, scheme The habit really checked.But after above-mentioned software can only generate determining Study on Power Grid Planning scheme in engineer, the side of execution The process of case simulation analysis, to a science, complete Electric Power Network Planning task is executed, ability is inadequate.
To sum up, currently, in Electric Power Network Planning and its related special studies project, existing answering for planning business demand Back work needed for being not enough to complete planning business with software causes the scientific level of current Electric Power Network Planning work insufficient, work It is relatively low to make efficiency.
Summary of the invention
The present invention provides a kind of Study on Power Grid Planning scheme generation method and device for supporting multi-person synergy operation, to overcome It is scientific insufficient when Electric Power Network Planning at present, the relatively low problem of working efficiency.
In a first aspect, the present invention provides a kind of Study on Power Grid Planning scheme generation method for supporting multi-person synergy operation, For client, include the following steps:
Step S10: meet planning year boundary condition constraint under, by Electric Power Network Planning benchmark rack with it is defeated what is locally saved The superposition of power transformation engineering set, forms preliminary Study on Power Grid Planning scheme;
The Electric Power Network Planning benchmark rack is requested and is obtained to server-side;
The planning year boundary condition is requested and is obtained to server-side;
It include: benchmark rack information, planning year power information, planning year load letter in the Study on Power Grid Planning scheme Breath, planning substation information, planning line information;
Step S20: carrying out security and stability analysis for preliminary Study on Power Grid Planning scheme, filters out and meets power grid peace The Study on Power Grid Planning scheme of total stability index is the Study on Power Grid Planning scheme after checking.
Specifically, after step S20, further includes:
Step S30: economic and technical norms analysis is carried out for the Study on Power Grid Planning scheme after check, determines electrical network economy The optimal Study on Power Grid Planning scheme of technical indicator is Study on Power Grid Planning scheme to be evaluated;
Wherein, the Study on Power Grid Planning scheme after check is locally generated, or request and get to server-side.
Specifically, after step S30, further includes:
Step S40: requesting to server-side and obtains Study on Power Grid Planning scheme to be evaluated;
It determines review comment corresponding with the Study on Power Grid Planning scheme to be evaluated, and the review comment is uploaded To server-side, so that the review comment is increased to the description of corresponding Study on Power Grid Planning scheme to be evaluated by server-side In information.
Specifically, before step S10, further includes:
According to the planning year obtained from server-side or planning horizon, electricity corresponding with the planning year or planning horizon is determined Network planning draws benchmark rack;
The Electric Power Network Planning benchmark rack includes: the installation of status power supply and force data, status electric network data, load number out According to, operation of power networks supplemental characteristic.
Specifically, before step S10, further includes:
According to the planning year obtained from server-side or planning horizon, rule corresponding with the planning year or planning horizon are determined Draw scene, power sources construction programme data, load protocol;
According to the power sources construction programme data and the load protocol, the electricity met under the planning scene is determined The planning year boundary condition that power electric quantity balancing requires;
The planning year boundary condition is uploaded to server-side.
Specifically, in step slo, further includes:
Based on the Electric Power Network Planning benchmark rack and the planning boundary condition, at least one project of transmitting and converting electricity is generated, often A project of transmitting and converting electricity includes: substation information, line information;
The project of transmitting and converting electricity is uploaded to server-side.
Specifically, in step S20, when carrying out security and stability analysis for preliminary Study on Power Grid Planning scheme, Server-side is requested to carry out security and stability analysis to the preliminary Study on Power Grid Planning scheme.
Specifically, in step slo, after forming preliminary Study on Power Grid Planning scheme, preliminary Electric Power Network Planning is set Meter scheme is uploaded to server-side;
Correspondingly,
It is that the preliminary Study on Power Grid Planning scheme is locally generated or request and obtain to server-side in step S20 It gets.
Specifically, in step S20, determining that the Study on Power Grid Planning scheme for meeting power grid security and stability index is school After Study on Power Grid Planning scheme after core,
Study on Power Grid Planning scheme after the check is uploaded to server-side;
Correspondingly,
In step s 30, the Study on Power Grid Planning scheme after the check be locally generated or to server-side request simultaneously It gets.
Second aspect, the present invention provides a kind of Study on Power Grid Planning scheme generation method for supporting multi-person synergy operation, For server-side, comprising the following steps:
Step S100: according to current planning tasks, planning year or planning horizon are determined;
Step S200: it is sent to the first client and the Electric Power Network Planning for corresponding to the foundation of planning year or planning horizon is provided The request of benchmark rack;Or
It is sent to the second client and the planning year boundary condition for corresponding to the foundation of planning year or planning horizon is provided Request;
Step S300: the Electric Power Network Planning benchmark rack that first client uploads is received;Or
Receive the planning year boundary condition that second client uploads.
Specifically, further includes:
According to the data acquisition request that any client is submitted, Xiang Suoshu any client sends data acquisition request middle finger Fixed data;
The data specified in the data acquisition request include: Electric Power Network Planning benchmark rack, planning year boundary condition, defeated change Study on Power Grid Planning scheme, Study on Power Grid Planning side to be evaluated after electrical engineering, preliminary Study on Power Grid Planning scheme, check Case.
Specifically, further includes:
After the review comment for the Study on Power Grid Planning scheme wait evaluate for receiving client upload, according to whole Review comment, determine check and approve after Study on Power Grid Planning scheme.
The third aspect, the present invention provides a kind of Study on Power Grid Planning schemes generation device for supporting multi-person synergy operation, For executing the Study on Power Grid Planning scheme generation method of the support multi-person synergy operation illustrated in the first aspect.
Fourth aspect, the present invention provides a kind of Study on Power Grid Planning schemes generation device for supporting multi-person synergy operation, For executing the Study on Power Grid Planning scheme generation method of the support multi-person synergy operation illustrated in second aspect.
Compared with prior art, the Study on Power Grid Planning scheme generation method provided by the invention for supporting multi-person synergy operation And device is managed collectively Electric Power Network Planning reference net rack data, when multi-person synergy plans operation, it is ensured that different planning and designing Personnel use consistent planning reference net rack data;It realizes the collaborative design of Electric Power Network Planning alternative collection and shares;Realize each stage electricity Net planning and design scheme is shared, and the science and working efficiency of Electric Power Network Planning work are improved.
Detailed description of the invention
By reference to the following drawings, exemplary embodiments of the present invention can be more fully understood by:
Fig. 1 is the Study on Power Grid Planning scheme generation method of the support multi-person synergy operation of the preferred embodiment for the present invention Flow diagram;
Fig. 2 is the Study on Power Grid Planning schemes generation side of the support multi-person synergy operation of another preferred embodiment of the present invention The flow diagram of method;
Fig. 3 is filled using the Study on Power Grid Planning schemes generation of the support multi-person synergy operation of the preferred embodiment for the present invention Set schematic diagram when determining Study on Power Grid Planning scheme.
Specific embodiment
Exemplary embodiments of the present invention are introduced referring now to the drawings, however, the present invention can use many different shapes Formula is implemented, and is not limited to the embodiment described herein, and to provide these embodiments be at large and fully disclose The present invention, and the scope of the present invention is sufficiently conveyed to person of ordinary skill in the field.Show for what is be illustrated in the accompanying drawings Term in example property embodiment is not limitation of the invention.In the accompanying drawings, identical cells/elements use identical attached Icon note.
Unless otherwise indicated, term (including scientific and technical terminology) used herein has person of ordinary skill in the field It is common to understand meaning.Further it will be understood that with the term that usually used dictionary limits, should be understood as and its The context of related fields has consistent meaning, and is not construed as Utopian or too formal meaning.
In general, the old process of Electric Power Network Planning work includes determining plan objects, the generation of planning boundary condition, quantity of electricity Multiple links such as balance, planning alternative collection generation, conceptual design, grid structure demonstration, the evaluation of solution technique economic indicator.One In secondary complete Electric Power Network Planning work, logically relationship the work of each section in above-mentioned process successively need to be executed, until final Generate Study on Power Grid Planning scheme.Meanwhile Electric Power Network Planning is also the work of a multi-person synergy, in view of the complexity of planning process, Entire planning process needs different planning personnels to cooperate with completion, this also further increases the difficulty of Electric Power Network Planning work.
For the science and working efficiency for improving Electric Power Network Planning, set firstly, carrying out Electric Power Network Planning for some planning tasks The process of meter conceptual design optimizes, and specifically, includes the following steps:
1) Net Frame of Electric Network of certain base year is chosen as planning benchmark rack.In an Electric Power Network Planning operation, it should keep Reference net rack data is constant.
2) edge-restraint condition of Electric Power Network Planning is established, comprising: plan the power sources construction programme in year, plan the load side in year Case.Usually the power sources construction programme in planning year is usually and has determined when doing Electric Power Network Planning, and as Electric Power Network Planning operation Power constraints condition;It plans that the load level in year can execute load prediction based on regional economic level etc. and obtain, can also lead to It crosses in some research reports and directly acquires, and as Electric Power Network Planning load constraint condition.
3) design planning project of transmitting and converting electricity, the collection of multiple projects of transmitting and converting electricity are combined into Electric Power Network Planning alternative collection.One defeated change Electrical engineering is made of substation and route, only comprising substation or can also only include route;Pass through bus in substation It can connect the equipment such as transformer, load, shunt capacitance reactance.In Study on Power Grid Planning conceptual design, each power transmission and transformation work Journey as a whole, is set as the state of putting into operation or the state that do not put into operation;Usually, Electric Power Network Planning alternative collection is the bigger the better.
4) design Study on Power Grid Planning scheme, i.e., select project of transmitting and converting electricity from Electric Power Network Planning alternative collection, and with planning base Quasi- rack superposition, establishes the channel of planning power grid, determines alternative Study on Power Grid Planning scheme.Planning and designing personnel can build Multiple Study on Power Grid Planning schemes are found, alternately Study on Power Grid Planning scheme.
5) Study on Power Grid Planning scheme simulation analysis, i.e., the alternative Study on Power Grid Planning scheme established to step 4) are imitated Whether true analysis, such as Load flow calculation, temporarily steady calculating, short circuit calculation, meet electricity net safety stable requirement with check scheme.
6) 5) Study on Power Grid Planning scheme evaluation is executing the step later to meeting the standby of electricity net safety stable requirement It selects Study on Power Grid Planning scheme to continue to execute scheme evaluation calculating, obtains every economic and technical norms of scheme.
7) scheme comparison is invited expert later, is cared for that is, to the optimal scheme of technical-economic index is selected in the alternative It asks and is evaluated, be finally approval scheme by the Study on Power Grid Planning solution tab selected and externally issue.
The above-mentioned process for establishing Electric Power Network Planning is scientific, but inefficient.Specifically, in above method, each planning is set Meter personnel organize work each independently, that is, the several planning and designing personnel in entire seminar are that single machine works independently Mode, data transmitting is carried out between different planning and designing personnel can only be by similar point-to-point such as " export → copy → importing " The consistency of mode, data transmitting not can guarantee;Even if multiple personnel carry out Electric Power Network Planning work jointly, it is also difficult to it is more to embody people The big advantage of strength increases the extra work expense of data distribution, transmitting, merger instead.
It is that people more than one, too many levels are worked in coordination the complex work of progress in view of Electric Power Network Planning, is executing a power grid rule Draw project task when, the role of participant can substantially be divided into: Electric Power Network Planning project person in overall, several planning and designing personnel, Several leading bodys at a higher level and expert advisor etc..Specifically, Electric Power Network Planning project person in overall is responsible for the standard of entire foundation of planning data It is standby, comprising: foundation of planning year power grid facilities network rack data and planning year power supply, load data;Planning and designing personnel are based on total negative The data information that duty people provides carries out planning project of transmitting and converting electricity design, forms Electric Power Network Planning alternative collection;Planning and designing personnel simultaneously It needs based on planning benchmark rack and plans that alternative collection completes the design and analysis of Study on Power Grid Planning scheme;Planning and designing personnel After tentatively completing Study on Power Grid Planning conceptual design and analysis than choosing, needs to submit to leading body at a higher level and expert advisor carries out Evaluation, and according to review comment and suggest modifying to scheme, it so repeats, until the final Electric Power Network Planning determined after checking and approving Design scheme.
Further, it is the efficiency for improving Electric Power Network Planning work, proposes a kind of Electric Power Network Planning for supporting multi-person synergy operation Design scheme generating means, method and system.
As shown in Figure 1, the Study on Power Grid Planning scheme generation method of the support multi-person synergy operation, is used for client, packet Include following steps:
Step S10: meet planning year boundary condition constraint under, by Electric Power Network Planning benchmark rack with it is defeated what is locally saved The superposition of power transformation engineering set, forms preliminary Study on Power Grid Planning scheme;
The Electric Power Network Planning benchmark rack is requested and is obtained to server-side;
The planning year boundary condition is requested and is obtained to server-side;
It include: benchmark rack information, planning year power information, planning year load letter in the Study on Power Grid Planning scheme Breath, planning substation information, planning line information;
Step S20: carrying out security and stability analysis for preliminary Study on Power Grid Planning scheme, filters out and meets power grid peace The Study on Power Grid Planning scheme of total stability index is the Study on Power Grid Planning scheme after checking.
Specifically, after step S20, further includes:
Step S30: economic and technical norms analysis is carried out for the Study on Power Grid Planning scheme after check, determines electrical network economy The optimal Study on Power Grid Planning scheme of technical indicator is Study on Power Grid Planning scheme to be evaluated;
Wherein, the Study on Power Grid Planning scheme after check is locally generated, or request and get to server-side.
It is construed as, includes at least one power transmission and transformation work in the project of transmitting and converting electricity set of client locally saved Journey;Each project of transmitting and converting electricity is generated according to Electric Power Network Planning benchmark rack and planning year boundary condition.
When planning typing, it (includes: to become that the information or data for needing typing, which includes: newly-built substation, newly-built station equipment, Depressor, bus, load, shunt capacitance reactor, series capacitance reactor), new route etc.;Based on the above planning information, into Row combination, can establish project of transmitting and converting electricity.
It is construed as, includes: Electric Power Network Planning reference net rack data, planning in each Study on Power Grid Planning scheme Power data, planning load data, project of transmitting and converting electricity data (including planning substation, planning route), the physics ginseng being related to Number includes the objects such as bus, generator, transformer, load, AC line, AC line, shunt capacitance reactor, series capacitance reactor Manage all kinds of parameters of equipment.
It is construed as, the Study on Power Grid Planning scheme after check is some preliminary Study on Power Grid Planning scheme;? During security and stability is checked, may still strategy parameter be adjusted by not being related to modification Study on Power Grid Planning scheme Section.
When carrying out security and stability analysis for each preliminary Study on Power Grid Planning scheme, various electricity can be used Network simulation software or other emulation modes.Such as, the format arranged by Current protocols, can be using PSASP, PSD-BPA (China Electric Power Research Institute's independent research) it is emulated.Or other emulation modes or emulation tool.
Preferably, electricity net safety stable index includes reliability and safety indexes, and such as: voltage level cannot be beyond regulation Value, short circuit current level overrate, reactive compensation capacity cannot be less than specified value, and power backup capacity cannot be less than regulation Value etc..It is selected according to " guiding rules of power system safety and stability " when specific embodiment.
It is construed as, carries out economic and technical norms analysis for the Study on Power Grid Planning scheme after check, including to electricity Net programme carries out assessment calculating.
Scheme evaluating is carried out online for the ease of organizes expert, specifically, after step S30, further includes:
Step S40: requesting to server-side and obtains Study on Power Grid Planning scheme to be evaluated;
It determines review comment corresponding with the Study on Power Grid Planning scheme to be evaluated, and the review comment is uploaded To server-side, so that the review comment is increased to the description of corresponding Study on Power Grid Planning scheme to be evaluated by server-side In information.
Be construed as, these Study on Power Grid Planning schemes to be evaluated be completed by different planning and designing personnel and on Pass to server-side.Evaluation expert downloads whole Study on Power Grid Planning schemes to be evaluated for some planning tasks To after local, the check that carries into execution a plan, scheme evaluation, scheme comparison, from the design scheme that these planning and designing personnel recommend It selects excellent in excellent, and provides review comment.After these review comments are uploaded to server-side, these review comments can be used as design The remark information of scheme is summarized and is used by planning person in overall.
Specifically, before step S10, further includes:
According to the planning year obtained from server-side or planning horizon, electricity corresponding with the planning year or planning horizon is determined Network planning draws benchmark rack;
The Electric Power Network Planning benchmark rack includes: the installation of status power supply and force data, status electric network data, load number out According to, operation of power networks supplemental characteristic.
Specifically, before step S10, further includes:
According to the planning year obtained from server-side or planning horizon, rule corresponding with the planning year or planning horizon are determined Draw scene, power sources construction programme data, load protocol;
According to the power sources construction programme data and the load protocol, the electricity met under the planning scene is determined The planning year boundary condition that power electric quantity balancing requires;
The planning year boundary condition is uploaded to server-side.
Specifically, in step slo, further includes:
Based on the Electric Power Network Planning benchmark rack and the planning boundary condition, at least one project of transmitting and converting electricity is generated, often A project of transmitting and converting electricity includes: substation information, line information;
The project of transmitting and converting electricity is uploaded to server-side.
Specifically, in step S20, when carrying out security and stability analysis for preliminary Study on Power Grid Planning scheme, Server-side is requested to carry out security and stability analysis to the preliminary Study on Power Grid Planning scheme.
Specifically, in step slo, after forming preliminary Study on Power Grid Planning scheme, preliminary Electric Power Network Planning is set Meter scheme is uploaded to server-side;
Correspondingly,
It is that the preliminary Study on Power Grid Planning scheme is locally generated or request and obtain to server-side in step S20 It gets.
Specifically, in step S20, determining that the Study on Power Grid Planning scheme for meeting power grid security and stability index is school After Study on Power Grid Planning scheme after core,
Study on Power Grid Planning scheme after the check is uploaded to server-side;
Correspondingly,
In step s 30, the Study on Power Grid Planning scheme after the check be locally generated or to server-side request simultaneously It gets.
It is construed as, after which uploads to server-side, is safeguarded by server-side is unified, and by the electricity Net facilities network rack data is shared to client, to guarantee the consistency of reference net rack data when multi-person synergy planning.
It is construed as, which can also be generated and be safeguarded by server-side.
Specifically, Electric Power Network Planning benchmark rack includes: the installation of status power supply and force data, status electric network data, load out The data such as data, operation of power networks supplemental characteristic.
It should be noted that the power data in planning year is usually by obtaining in power source planning report;Plan the negative of year Lotus protocol is usually to pass through load prediction to be calculated or by obtaining in report and being manually entered system;Boundary condition It is determining then need to calculate by balance of electric power and ener and carry out abundant intensity verification, and power source design is adjusted until meeting abundant intensity and wanting It asks.
It is construed as, in client by single project of transmitting and converting electricity data by one or more project of transmitting and converting electricity batch datas After reaching server-side, shared from server-side to each client.
It specifically, is after Share Permissions are arranged in the project of transmitting and converting electricity in server-side, it is defeated that other clients just may browse through this Power transformation engineering simultaneously sends acquisition request to server-side.
It is construed as, specified data can be locally created in the data acquisition request;Or in other planning After personnel share to server-side, the local of client is requested and downloaded to server-side.
When it is implemented, Study on Power Grid Planning scheme (namely the preliminary Study on Power Grid Planning determined for different phase Study on Power Grid Planning scheme after scheme, check, Study on Power Grid Planning scheme to be evaluated), it can be believed by the remarks of file Breath or filename distinguish.
Second aspect, as shown in Fig. 2, the Study on Power Grid Planning side of the support multi-person synergy operation of one embodiment of the invention Case generation method is used for server-side, comprising the following steps:
Step S100: according to current planning tasks, planning year or planning horizon are determined;
Step S200: it is sent to the first client and the Electric Power Network Planning for corresponding to the foundation of planning year or planning horizon is provided The request of benchmark rack;Or
It is sent to the second client and the planning year boundary condition for corresponding to the foundation of planning year or planning horizon is provided Request;
Step S300: the Electric Power Network Planning benchmark rack that first client uploads is received;Or
Receive the planning year boundary condition that second client uploads.
Specifically, further includes:
According to the data acquisition request that any client is submitted, Xiang Suoshu any client sends data acquisition request middle finger Fixed data;
The data specified in the data acquisition request include: Electric Power Network Planning benchmark rack, planning year boundary condition, defeated change Study on Power Grid Planning scheme, Study on Power Grid Planning side to be evaluated after electrical engineering, preliminary Study on Power Grid Planning scheme, check Case.
Specifically, further includes:
After the review comment for the Study on Power Grid Planning scheme wait evaluate for receiving client upload, according to whole Review comment, determine check and approve after Study on Power Grid Planning scheme.
When it is implemented, for the Study on Power Grid Planning scheme generation method of the support multi-person synergy operation for server-side Making software is distinguished with the Study on Power Grid Planning scheme generation method of the support multi-person synergy operation for client, realizes the branch Hold the Study on Power Grid Planning scheme generation method of multi-person synergy operation.
As shown in figure 3, for the Study on Power Grid Planning scheme generation method of the support multi-person synergy operation for client The software of establishment, be denoted as the support multi-person synergy operation for client Study on Power Grid Planning schemes generation device 1000 ( That is client-side program);The generating means 1000 are deployed on office computer, then each office computer and a set of generating means 1000 one client device of composition;
For the support multi-person synergy operation for server-side Study on Power Grid Planning scheme generation method establishment software, It is denoted as (namely the objective server-side journey of Study on Power Grid Planning schemes generation device 2000 of the support multi-person synergy operation for server-side Sequence);The generating means 2000 are deployed on a high-performance computer or on office computer, a server device is formed.
More client devices and a server device form the Study on Power Grid Planning of a support multi-person synergy operation Scheme generation system can execute arbitrary Electric Power Network Planning project task.
Determine that system carries out Electric Power Network Planning using the Study on Power Grid Planning scheme of support multi-person synergy operation as shown in Figure 3 When operation, including following operation:
1), serve end program is deployed on a high-performance computer, people's management is always blamed by planning and designing or is used and is somebody's turn to do Server-side and the serve end program.
Planning and designing always blame people using the server-side and the serve end program, execute following operation:
◆ user management and rights management, that is, organize the planning and designing personnel being related in each Electric Power Network Planning operation, The projects such as Electric Power Network Planning expert advisor, person in charge group membership simultaneously establishes account, while being responsible for setting project group membership to all kinds of Plan the access authority of file;
◆ report push function is notified and ground, such as Electric Power Network Planning project task scheduling, data etc. are pushed to each planning and set Meter personnel;
◆ the management of Electric Power Network Planning facilities network rack data, maintenance are supported to carry out pipe to Electric Power Network Planning basic data in server-side Reason and maintenance;
◆ the management of Electric Power Network Planning boundary condition, maintenance, usually according to the planning power source design of planning project foundation and rule Draw load scheme.When it is implemented, can be established by specified planning and designing personnel at given client end, and it is pushed to service End, the sets of data safeguarded by server-side;
◆ the management of Electric Power Network Planning alternative collection, maintenance e.g., receive the project of transmitting and converting electricity in any client push, and examine Core;To the settable Share Permissions of single project of transmitting and converting electricity, the project of transmitting and converting electricity for being provided with Share Permissions can be passed through by other users Client browse and downloading;
◆ Study on Power Grid Planning project management, maintenance, e.g., the alternative Electric Power Network Planning received in any client push is set Meter scheme;Share Permissions can be arranged to single scheme respectively, the alternative Study on Power Grid Planning scheme provided with Share Permissions can Pass through Client browse and downloading by other users.
◆ execute simulation calculation.When executing simulation calculation, server-side and client have the consistent simulation calculation of precision Function.Can choose and locally execute calculating in client, client calculate the time it is longer or calculate operation it is more when, client It can choose and calculating task is pushed to server-side, the simulation efficiency of client is improved by the high-performance calculation of server-side, After calculating, client fetches result from server-side and continues subsequent operation in client, to realize that computing capability is shared.
2), dispose client-side program on each respective office computer of planning and designing personnel, by each planning and designing personnel ( That is the user of client device) manage and use client and the client-side program.
Each planning and designing personnel utilize the client and the client-side program, execute following operation:
◆ by client-side program provide establish the function of connection with server-side and serve end program establishes connection, and lead to Cross pre-assigned user name, password carries out proof of identity, acquirement data access authority;
◆ the list of reference net rack data is obtained from server-side, and downloads corresponding reference net rack data extremely by planning project task It is local to use.Each planning and designing personnel in the reference net rack data list for checking server-side, only browse and download permission; This Permission Design, it is ensured that when executing the same planning tasks, benchmark rack number that different planning and designing personnel use According to consistent.
◆ typing planning boundary condition is responsible for specially by some planning and designing personnel, specifically, according to server-side push Report and notice are ground, specified some planning and designing personnel complete planning power supply, planning load level typing in its client, and lead to Balance of electric power and ener calculating is crossed, confirmation is able to satisfy the planning boundary condition data of Energy adequacy requirement under planning scene.And Before other planning and designing personnel carry out Study on Power Grid Planning conceptual design, by the boundary condition data-pushing to server-side, by taking Business device end shares to other planning and designing personnel use, repeats maintenance perimeter strip number of packages so as to avoid other planning and designing personnel According to.
◆ planning and designing personnel are independently engineered project of transmitting and converting electricity in its client, and can be by designed power transmission and transformation work Server-side is pushed to after Cheng Tianjia description to be shared;After server-side audit passes through and authorizes Share Permissions, the power transmission and transformation work Journey can be browsed and be downloaded by other planning and designing personnel;Each planning and designing personnel can also check whether server-side has other designers The shared project of transmitting and converting electricity of member, can be directly downloaded to local use.To realize in multi-person synergy planning, build quickly Vertical one very big and unduplicated planning alternative collection each other.
◆ planning and designing personnel are able to satisfy Study on Power Grid Planning conceptual design analysis needs in the local project of transmitting and converting electricity of confirmation, And after obtaining planning boundary condition data, it can start to carry out Study on Power Grid Planning conceptual design.Planning and designing personnel can To be independently engineered multiple alternative Study on Power Grid Planning schemes, and the simulation analysis that carries into execution a plan in the machine, referred to by economic technology Mark is than selecting optimal alternative.It is also possible to push to clothes after selecting the optimal alternative addition description by the machine It is shared at business end;The optimal alternative of the machine after being granted Share Permissions can by other designers browse and Downloading.In addition, planning and designing personnel can also after the optimal alternative of target that the machine has been determined, select by server-side other The design scheme that people shares is locally downloading, carries out with the machine scheme again than choosing, to realize alternative Study on Power Grid Planning side Case it is excellent in select excellent, and additional to the secret sharing of server-side can describe.
◆ when carrying out simulation analysis to alternative Study on Power Grid Planning scheme, such as Load flow calculation, temporarily steady batch fault scanning, Long term dynamics whole process simulation etc., because of the limitation of the machine computing capability, local computing kimonos is may be selected in planning and designing personnel Business end calculates both simulation calculation modes.Calculating task is committed to server-side by server-side if selection server-side calculates Multicore computing capability improves simulation efficiency.
3), on the power grid schemes such as Electric Power Network Planning expert advisor, the person in charge audit respective office computer of participant Deploying client program.
By power grid scheme audit participant (namely reviewer and user of client device) management and use visitor Family end and the client-side program.When Electric Power Network Planning project task execution is to material time node, can by server-side or other people The method that work participates in notifies above-mentioned power grid scheme audit participant to evaluate design scheme, can also be divided with centralized review Dissipate evaluation.When dispersion evaluation, each expert, person in charge are recommended by pre-assigned user name, the downloading of code entry server-side Target grid planning and design scheme checked to local, and can refer to scheme description and provide further evaluation and suggest;Tool Body, directly additional evaluation is suggested in scheme description.
4), after completing scheme evaluating, Electric Power Network Planning person in overall can be based on each expert, person in charge to target grid The evaluation suggestion of planning and design scheme arranges each planning and designing personnel further modification, until ultimately generating and issuing Study on Power Grid Planning scheme report after approval.
To sum up, Electric Power Network Planning work is carried out based on the above method, apparatus and system, realizes planning design analysis work Multi-person synergy, the efficiency of significant increase programme design.
In the specific implementation, the Study on Power Grid Planning schemes generation device of the support multi-person synergy operation includes server-side journey Sequence and client-side program, wherein serve end program is deployed in server-side, and responsible data management, data sharing, computing capability are shared Deng;Client-side program is deployed in client, is responsible for completing specific project of transmitting and converting electricity design and Study on Power Grid Planning conceptual design.
Specifically, server-side is one or more high-performance computer;Client have it is multiple, specifically, each client End is the Taiwan Affairs Office's unility computer;Server-side and client are connected with each other by local area network or wide area network, realize that information and data pass It is defeated.
The layout data management function that this method and device are provided in server-side, ensure that in planning process should remain unchanged Data it is controlled, also ensure that the multi-user of uncertain data generates and audit is shared.
This method and device follow strictly Electric Power Network Planning work in the process for the electrical reticulation design programme that client provides Timing, so that the Study on Power Grid Planning scheme generated is more scientific, cooperation serve end program makes programme generating process have evidence It can follow.
This method and device support more people of planning alternative collection in server-side offer project of transmitting and converting electricity data sharing function Collaborative design allows planning alternative collection quickly and efficiently to have enough project of transmitting and converting electricity schemes.
The Study on Power Grid Planning scheme sharing functionality that this method and device are provided in server-side supports Study on Power Grid Planning side More people of case are shared, realize Electric Power Network Planning alternative it is excellent in select it is excellent.Meanwhile realizing target grid planning and design scheme Expert disperses evaluation, so that scheme evaluating mode is more flexible.
The computing capability sharing functionality that this method and device are provided in server-side, support emulate Study on Power Grid Planning scheme Analytical calculation is committed to server-side execution, can be further improved the working efficiency of Electric Power Network Planning.
The Electric Power Network Planning of the support multi-person synergy operation determines method and apparatus, is able to achieve multi-person synergy and carries out Electric Power Network Planning Design scheme design analysis, greatly improves the efficiency of Electric Power Network Planning work.
Specifically, it is based on this method and device, planning reference net rack data can be managed collectively, plan and make in multi-person synergy When industry, it is ensured that different planning and designing personnel use consistent planning reference net rack data.
Specifically, it is based on this method and device, the project of transmitting and converting electricity that may be implemented to establish when planning typing state is whole In a planning process share, greatly mitigate project of transmitting and converting electricity design the duplication of labour, multi-person synergy planning when, put into per capita compared with Few workload can construct a sufficiently large planning alternative collection, to meet the requirement of Electric Power Network Planning alternative collection.
Specifically, it is based on this method and device, the shared of Study on Power Grid Planning scheme may be implemented;By supporting different rule The design scheme of the machine is shared to server-side by the personnel of drawing, and after Share Permissions are awarded, allows other people locally downloading and this Machine scheme is carried out together than choosing;Compared to one conceptual design and scheme comparison, multiple planning personnel's result of design are realized It is selected in excellent excellent.
Specifically, it is based on this method and device, it is shared that computing capability may be implemented;Planning and designing personnel can be by service The computing capability provided is provided, planning calculating task is committed to server-side execution calculating and obtains calculated result from server-side, from And promote programme simulation analysis computational efficiency.
Preferably, in deployment, hardware only needs a high-performance computer+working environment for this method and device;It is soft Part is windows executable program, and easy configuration after need to only installing is implemented simply, conveniently.
To sum up, Electric Power Network Planning work is carried out based on the above method, apparatus and system, realizes planning design analysis work Multi-person synergy, the efficiency of significant increase programme design.
The present invention is described by reference to a small amount of embodiment above.However, it is known in those skilled in the art, As defined by subsidiary Patent right requirement, in addition to the present invention other embodiments disclosed above equally fall in this hair In bright range.
Normally, all terms used in the claims are all solved according to them in the common meaning of technical field It releases, unless in addition clearly being defined wherein.All references " one/described/be somebody's turn to do [device, component etc.] " are all opened ground At least one example being construed in described device, component etc., unless otherwise expressly specified.Any method disclosed herein Step need not all be run with disclosed accurate sequence, unless explicitly stated otherwise.

Claims (14)

1. a kind of Study on Power Grid Planning scheme generation method for supporting multi-person synergy operation, which is characterized in that be used for client, packet Include following steps:
Step S10: in the case where meeting planning year boundary condition constraint, by Electric Power Network Planning benchmark rack and in the power transmission and transformation locally saved The superposition of engineering set, forms preliminary Study on Power Grid Planning scheme;
The Electric Power Network Planning benchmark rack is requested and is obtained to server-side;
The planning year boundary condition is requested and is obtained to server-side;
It include: benchmark rack information, planning year power information, planning year information on load, rule in the Study on Power Grid Planning scheme Wipe power station information, planning line information;
Step S20: carrying out security and stability analysis for preliminary Study on Power Grid Planning scheme, filters out that meet power grid security steady The Study on Power Grid Planning scheme of qualitative index is the Study on Power Grid Planning scheme after checking.
2. the method according to claim 1, wherein
After step S20, further includes:
Step S30: economic and technical norms analysis is carried out for the Study on Power Grid Planning scheme after check, determines electrical network economy technology The optimal Study on Power Grid Planning scheme of index is Study on Power Grid Planning scheme to be evaluated;
Wherein, the Study on Power Grid Planning scheme after check is locally generated, or request and get to server-side.
3. according to the method described in claim 2, it is characterized in that,
After step S30, further includes:
Step S40: requesting to server-side and obtains Study on Power Grid Planning scheme to be evaluated;
It determines review comment corresponding with the Study on Power Grid Planning scheme to be evaluated, and the review comment is uploaded to clothes Business end, so that believing the description that the review comment increases to corresponding Study on Power Grid Planning scheme to be evaluated in server-side In breath.
4. the method according to claim 1, wherein
Before step S10, further includes:
According to the planning year obtained from server-side or planning horizon, power grid rule corresponding with the planning year or planning horizon are determined Draw benchmark rack;
The Electric Power Network Planning benchmark rack includes: the installation of status power supply and force data, status electric network data, load data, electricity out Net operational parameter data.
5. the method according to claim 1, wherein
Before step S10, further includes:
According to the planning year obtained from server-side or planning horizon, planning field corresponding with the planning year or planning horizon is determined Scape, power sources construction programme data, load protocol;
According to the power sources construction programme data and the load protocol, the electric power electricity met under the planning scene is determined The planning year boundary condition that amount balance requires;
The planning year boundary condition is uploaded to server-side.
6. the method according to claim 1, wherein
In step slo, further includes:
Based on the Electric Power Network Planning benchmark rack and the planning boundary condition, at least one project of transmitting and converting electricity, Mei Gesuo are generated Stating project of transmitting and converting electricity includes: substation information, line information;
The project of transmitting and converting electricity is uploaded to server-side.
7. the method according to claim 1, wherein
In step S20, when carrying out security and stability analysis for preliminary Study on Power Grid Planning scheme, server-side pair is requested The preliminary Study on Power Grid Planning scheme carries out security and stability analysis.
8. the method according to claim 1, wherein
In step slo, after forming preliminary Study on Power Grid Planning scheme, preliminary Study on Power Grid Planning scheme is uploaded to Server-side;
Correspondingly,
It is that the preliminary Study on Power Grid Planning scheme is locally generated or request and get to server-side in step S20 's.
9. according to the method described in claim 2, it is characterized in that,
In step S20, determining that the Study on Power Grid Planning scheme for meeting power grid security and stability index is the power grid after checking After planning and design scheme,
Study on Power Grid Planning scheme after the check is uploaded to server-side;
Correspondingly,
In step s 30, the Study on Power Grid Planning scheme after the check be locally generated or request and obtain to server-side It arrives.
10. a kind of Study on Power Grid Planning scheme generation method for supporting multi-person synergy operation, which is characterized in that it is used for server-side, The following steps are included:
Step S100: according to current planning tasks, planning year or planning horizon are determined;
Step S200: it is sent to the first client and the Electric Power Network Planning benchmark for corresponding to the foundation of planning year or planning horizon is provided The request of rack;Or
It is sent to the second client and the request for the planning year boundary condition for corresponding to the foundation of planning year or planning horizon is provided;
Step S300: the Electric Power Network Planning benchmark rack that first client uploads is received;Or
Receive the planning year boundary condition that second client uploads.
11. according to the method described in claim 10, it is characterized by further comprising:
According to the data acquisition request that any client is submitted, specified in Xiang Suoshu any client transmission data acquisition request Data;
The data specified in the data acquisition request include: Electric Power Network Planning benchmark rack, planning year boundary condition, power transmission and transformation work Study on Power Grid Planning scheme, Study on Power Grid Planning scheme to be evaluated after journey, preliminary Study on Power Grid Planning scheme, check.
12. according to the method described in claim 10, it is characterized by further comprising:
After the review comment for the Study on Power Grid Planning scheme wait evaluate for receiving client upload, commented according to whole Opinion is examined, determines the Study on Power Grid Planning scheme after checking and approving.
13. a kind of Study on Power Grid Planning schemes generation device for supporting multi-person synergy operation, which is characterized in that be used for perform claim It is required that any one of 1-9.
14. a kind of Study on Power Grid Planning schemes generation device for supporting multi-person synergy operation, which is characterized in that be used for perform claim It is required that any one of 10-12.
CN201811602463.XA 2018-12-26 2018-12-26 Support the Study on Power Grid Planning scheme generation method and device of multi-person synergy operation Pending CN109636064A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811602463.XA CN109636064A (en) 2018-12-26 2018-12-26 Support the Study on Power Grid Planning scheme generation method and device of multi-person synergy operation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811602463.XA CN109636064A (en) 2018-12-26 2018-12-26 Support the Study on Power Grid Planning scheme generation method and device of multi-person synergy operation

Publications (1)

Publication Number Publication Date
CN109636064A true CN109636064A (en) 2019-04-16

Family

ID=66077952

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811602463.XA Pending CN109636064A (en) 2018-12-26 2018-12-26 Support the Study on Power Grid Planning scheme generation method and device of multi-person synergy operation

Country Status (1)

Country Link
CN (1) CN109636064A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101567561A (en) * 2009-05-27 2009-10-28 国网北京经济技术研究院 Comparing and selecting system of power transmission network planning scheme
CN101986331A (en) * 2010-10-25 2011-03-16 中国电力科学研究院 Power grid simulation calculation cooperative work system
CN103489139A (en) * 2013-10-18 2014-01-01 国家电网公司 Comprehensive analysis and management system for urban distribution network planning
CN104239957A (en) * 2013-06-17 2014-12-24 国家电网公司 Optimal power network planning method based on reliability contract
CN106056272A (en) * 2016-05-18 2016-10-26 国网山东省电力公司经济技术研究院 Power grid programming, management and controlling method and system based on mobile GIS
EP3098935A1 (en) * 2008-05-09 2016-11-30 Accenture Global Services Limited Method and system for managing a power grid
KR101722393B1 (en) * 2016-02-19 2017-04-05 숭실대학교산학협력단 Method of selecting position for offshore substation in the wind power plant and method of designing for power grid design in the wind power plant
CN109034458A (en) * 2018-06-29 2018-12-18 国家电网有限公司 It is a kind of to guarantee to permit taking in acquired electric grid investment planing method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3098935A1 (en) * 2008-05-09 2016-11-30 Accenture Global Services Limited Method and system for managing a power grid
CN101567561A (en) * 2009-05-27 2009-10-28 国网北京经济技术研究院 Comparing and selecting system of power transmission network planning scheme
CN101986331A (en) * 2010-10-25 2011-03-16 中国电力科学研究院 Power grid simulation calculation cooperative work system
CN104239957A (en) * 2013-06-17 2014-12-24 国家电网公司 Optimal power network planning method based on reliability contract
CN103489139A (en) * 2013-10-18 2014-01-01 国家电网公司 Comprehensive analysis and management system for urban distribution network planning
KR101722393B1 (en) * 2016-02-19 2017-04-05 숭실대학교산학협력단 Method of selecting position for offshore substation in the wind power plant and method of designing for power grid design in the wind power plant
CN106056272A (en) * 2016-05-18 2016-10-26 国网山东省电力公司经济技术研究院 Power grid programming, management and controlling method and system based on mobile GIS
CN109034458A (en) * 2018-06-29 2018-12-18 国家电网有限公司 It is a kind of to guarantee to permit taking in acquired electric grid investment planing method

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
乔新辉等: "省域电网布局规划三维大数据平台开发与应用研究", 《北京测绘》 *
罗庆等: "基于CIM的电网规划管理决策辅助系统", 《电力系统保护与控制》 *
覃智君等: "综合规划软件的体系结构和关键技术研究", 《华北电力大学学报》 *
魏威等: "基于统一数据平台的电网规划软件", 《继电器》 *

Similar Documents

Publication Publication Date Title
Papavasiliou et al. Applying high performance computing to transmission-constrained stochastic unit commitment for renewable energy integration
Haack et al. VOLTTRON™: An agent platform for integrating electric vehicles and Smart Grid
Skarvelis-Kazakos et al. Implementing agent-based emissions trading for controlling Virtual Power Plant emissions
CN105406459B (en) Utilize the method for the optimal load flow estimated based on uniformity distributed treatment in power network
Mazzini et al. Minimisation of active power losses and number of control adjustments in the optimal reactive dispatch problem
Silva et al. An IoT-based energy management system for AC microgrids with grid and security constraints
Johnson et al. Evaluation of interoperable distributed energy resources to ieee 1547.1 using sunspec modbus, ieee 1815, and ieee 2030.5
Zhang et al. Distributed optimal active power dispatch under constraints for smart grids
El-Sayed et al. A real pilot-platform implementation for blockchain-based peer-to-peer energy trading
Wiegel et al. Smart Energy System Control Laboratory–a fully-automated and user-oriented research infrastructure for controlling and operating smart energy systems
Du et al. Efficient forecasting scheme and optimal delivery approach of energy for the energy Internet
CN109782724A (en) The control method and terminal device of anti-misoperation locking
Ranganathan et al. Distributed Linear Programming Models in a Smart Grid
Sarstedt et al. Standardized evaluation of multi-level grid control strategies for future converter-dominated electric energy systems
Reiman et al. App deconfliction: Orchestrating distributed, multi-agent, multi-objective operations for power systems
CN104346756A (en) Method and system for constructing power grid planning platform
CN109636064A (en) Support the Study on Power Grid Planning scheme generation method and device of multi-person synergy operation
CN104243218B (en) A kind of communication of power system mode list preparation method based on more schedule constraints
CN107169180A (en) A kind of power grid regulation model center system of two-stage deployment
CN103745025B (en) Integrated EMTDC (electromagnetic transient DC) comprehensive application platform of high-voltage direct current system
Syed et al. Laboratory infrastructure driven key performance indicator development using the smart grid architecture model
Finke et al. Transition towards a full self-sufficiency through PV systems integration for sub-Saharan Africa: a technical approach for a smart blockchain-based mini-grid
CN114119278A (en) Multi-station fusion power resource management system based on block chain technology
Roche Agent-Based Architectures and Algorithms for Energy Management in Smart Grids. Application to Smart Power Generation and Residential Demand Response
Nikolopoulos Designing a platform for smart electric vehicle charging-a case study in Uppsala, Sweden

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190416

RJ01 Rejection of invention patent application after publication