CN109629438A - Bridging method in a kind of water - Google Patents

Bridging method in a kind of water Download PDF

Info

Publication number
CN109629438A
CN109629438A CN201910027947.4A CN201910027947A CN109629438A CN 109629438 A CN109629438 A CN 109629438A CN 201910027947 A CN201910027947 A CN 201910027947A CN 109629438 A CN109629438 A CN 109629438A
Authority
CN
China
Prior art keywords
girder
steel
construction
assembled
pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910027947.4A
Other languages
Chinese (zh)
Inventor
李永
梁新礼
宋于褀
雷志春
林凤国
刘正波
宁世凯
张卓健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Original Assignee
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Bridge Engineering Bureau Group Co Ltd filed Critical China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority to CN201910027947.4A priority Critical patent/CN109629438A/en
Publication of CN109629438A publication Critical patent/CN109629438A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • E01D21/105Balanced cantilevered erection

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention provides bridging method in a kind of water, bridging method using main bridge trestle using both ends operation simultaneously, set up with main trestle synchronization job mode by branch trestle in the water.Main bridge girder steel sets up girder steel from original design side, the scheme of arch rib is set up after the completion of girder steel, it is optimized for setting up simultaneously across span centre to two sides symmetric double cantilever erection, continuous truss sliding roadway arch and freely-supported steel truss girder in, girder steel is set up simultaneously with arch rib, the arrangement and method for construction for reaching the "three-synchronims" of girder steel synchronous with freely-supported steel truss girder with lower part engineering synchronism, continuous truss sliding roadway arch, purlin and arch synchronization, thus the Optimizing construction duration significantly.And the optimization of Specific construction scheme is realized in multi-platform construction in water, is made steel suspension bridge, pile foundation, cushion cap, pier shaft, steel truss girder and each construction link overlap joint parallel operations of sliding roadway arch, is reached rapid construction, guarantee quality and the purpose of duration.

Description

Bridging method in a kind of water
Technical field
The present invention relates to bridging methods in bridge formation technical field more particularly to a kind of water.
Background technique
Bridge is generally erected in rivers,lakes and seas, the structures for making traffic etc. that can smoothly pass through.It is modern high to adapt to The transportation industry of speed development, bridge, which also crosses over mountain stream, unfavorable geology or meets other traffic, to be needed and making of setting up is current more It is convenient.It is opposite also more convenient in land construction bridge, but for building bridge in water, due to needing in Ha Noi frame If it is inconvenient to construct, therefore, it is necessary to the longer periods to build bridge.
Summary of the invention
The purpose of the invention is to overcome the deficiencies of the prior art and provide bridging method in a kind of water.
The present invention is achieved through the following technical solutions:
The present invention provides bridging method in a kind of water, bridging method includes: from the both ends on riverbank construction first in the water Main trestle;
In korneforos construction branch trestle;
Cushion cap and bridge pier are set up between two branch trestles;
According to sequence of construction construction bridge pier and bridge pier pier girder steel assembling support;
The builder's road on two branch trestles;
3 internode girder steels between two bridge piers on sidewalk at assembled center on the bracket of assembled second main trestle;
The assembled girder erection crane on 3 assembled internode girder steels;
Utilize the symmetrical assembled girder steel of the double cantilevers of girder erection crane;
Behind girder erection crane respectively assembled girder steel to corresponding bridge pier, assembly girder erection crane carrys out assembled pier at assembling support Between arch rib;
The girder steel of 3 internodes on the first main trestle between the assembled both ends pier for being located at riverbank section on assembling support;And it spells It fills assembly girder erection crane at bracket and carrys out arch rib between assembled pier;
First main trestle and the second main trestle are closed up.
Preferably, described to set up cushion cap and bridge pier between two branch trestles;Specifically:
Drilling platform is set up between two branch trestles;
The construction drill stake on drilling platform;
Drilling platform is removed, steel sheet pile is squeezed into;Steel purlin is installed, inhales mud to back cover absolute altitude;
Cleaning steel sheet pile simultaneously pours bottom concrete, and sets up cushion cap and bridge pier on the bottom concrete poured.
Preferably, further includes:
When according to sequence of construction construction bridge pier and bridge pier pier girder steel assembling support, construct interim Dun.
Preferably, described to set up cushion cap specifically: lower part is supported using more steel pipe bored concrete piles, top laying distribution beam, Bailey beam.
It preferably, further include using girder erection crane multiple bridge piers that assembled girder steel is extremely set respectively;
And using the arch rib between girder erection crane respectively multiple bridge piers of the assembled setting.
The beneficial effects of the present invention are: main bridge trestle is using both ends operation simultaneously, branch trestle and main trestle synchronization job side Formula is set up.Main bridge girder steel sets up girder steel from original design side, and the scheme of arch rib is set up after the completion of girder steel, is optimized in across span centre It is set up simultaneously to two sides symmetric double cantilever erection, continuous truss sliding roadway arch and freely-supported steel truss girder, girder steel is set up simultaneously with arch rib, is reached To girder steel, purlin synchronous with freely-supported steel truss girder with lower part engineering synchronism, the continuous truss sliding roadway arch "three-synchronims" synchronous with arch is applied Work scheme, thus the Optimizing construction duration significantly.
In water it is multi-platform construction realize Specific construction scheme optimization, make steel suspension bridge, pile foundation, cushion cap, pier shaft, steel truss girder and The each construction link of sliding roadway arch overlaps parallel operations, reaches rapid construction, guarantees quality and the purpose of duration.
Detailed description of the invention
Fig. 1 is the flow chart of bridging method in water provided in an embodiment of the present invention;
Fig. 2 is the flow chart of bridging method in water provided in an embodiment of the present invention;
Fig. 3 is the flow chart of bridging method in water provided in an embodiment of the present invention;
Fig. 4 is the flow chart of bridging method in water provided in an embodiment of the present invention;
Fig. 5 is the flow chart of bridging method in water provided in an embodiment of the present invention;
Fig. 6 is the flow chart of bridging method in water provided in an embodiment of the present invention;
Fig. 7 is the flow chart of bridging method in water provided in an embodiment of the present invention.
In figure: branch trestle 1, cushion cap 2, control platform 3, steel pipe stake holes 4, crawler crane 5, support 6, support stake 7, steel-pipe pile 8, support frame 9, XR360 rotary drilling rig 10, steel sheet pile 11, assembling support 12, bridge pier 13, Temporary Piers 14.
Specific embodiment
Hereinafter, certain exemplary embodiments are simply just described.As one skilled in the art will recognize that Like that, without departing from the spirit or scope of the present invention, described embodiment can be modified by various different modes. Therefore, attached drawing and description are considered essentially illustrative rather than restrictive.
The present invention provides bridging methods in a kind of water, and to facilitate understanding of the present embodiment of the invention providing method, says first It is bright once the invention relates to bridge in structure and the equipment that uses.
Firstly, the bridging method of the application is related to as shown in FIG. 1 to FIG. 7: control platform 3, cushion cap 2, branch trestle 1, steel Hole of post 4, support stake 7, support frame 9,13 middle line of bridge pier, crawler crane 5, XR360 rotary drilling rig 10, bridge pier 13, is faced at support 6 When pier 14, assembling support 12, girder erection crane, sidewalk etc..Wherein, as shown in FIG. 1 to FIG. 3, control platform 3 is located at two trestles 1 middle position is laid in 2 top of cushion cap, provides platform for the construction operation of drilling machine, is laid with pier steel plate.And it holds Platform 2 is used to support 6 control platforms 3, and by more steel pipe bored concrete pile supports 6, top is by laying distribution beam, Bailey beam for its underpart The control platform 3 on top provides the support 6 of water vertical force.In addition, the substructure of branch trestle 1 is using the company between steel-pipe pile 8 It connects, increases the stability of stake.Branch trestle 1 provides traffic platform using continuously constructing by cross for construction machinery.Steel pipe stake holes 4: its Aperture size standard is suitble to the construction operation using vibration hammer to two rows of pier steel-pipe piles 8 and steel sheet pile 11.Support 6 Above support stake 7, it is used to support the steady of 6 trestles 1, and the flat work wells of mechanical waters such as crawler crane 5 are mentioned For advantage.It has multiple small standard types number to be intensively laid with, uniform force, realizes full compression area stability under loading.And it supports Stake 7: basis uses 630 × 10mm of φ steel pipe, and the smooth construction of support stake 7 is realized using vibration hammer, supports 6 trestles 1 and branch Steady, the vertical pressures of 6 transmitting of reception support of support 6.
In addition, 9 connecting material bridging of support frame uses 20 channel steels.Horizontal connection uses 20 channel steels, joint steel pipe size Design and code requirement need to be met according to specific size blanking, weldquality.Support stake 7 independent is connected, improves and stablizes Property.
13 middle line of bridge pier among the above: positioned at the center line of control platform 3, effect mainly draws the symmetrical of bridge pier 13 Point, the mark of middle line.
Sidewalk therein be on branch trestle 1, respectively from the starting end of engineering and concluding paragraph inserting piling first across and last Across steel-pipe pile 8, other steel-pipe piles 8 of then gradually constructing.
Fig. 4~Fig. 7 is referred to together;Wherein, XR360 rotary drilling rig 10: above the control platform waterborne 3 of early period, rotation Dig 10 construction drill stake of drilling machine.
Bridge pier 13: bridge pier 13 of constructing is being isolated at a distance according to Bridge Design scheme, is providing support 6, bridge to beam body Pier 13 is removed without the later period, lower support 6 structure of the replacing time as bridge after construction terminates.
Temporary Piers 14: Temporary Piers 14 are constructed in the case where 13 spacing of bridge pier is too big, are mainly auxiliary pier Platform supports the top gravity of 6 work progress, provides support 6.
Assembling support 12: assembling support 12 is 6 structure of Auxiliary support built at the initial stage that platform is built on the water, is Early period, center went out the stress offer support 6 of steel truss girder, prevented deflection deformation.
Girder erection crane 1,4: start to construct to engineering both ends from pier, realize the smooth right of girder steel and engineering both ends It connects, sidewalk is mainly on the branch trestle 1 of girder steel top and two sides.
Girder erection crane 2,3: its engineering is constructed by respective pier, and construction direction is mainly applied to engineering center Work carries out arch rib assembly and engineering closure work after the splicing for completing girder steel.
Girder erection crane 5: its workbench mainly platform on the water mainly carries out the spelling of steel truss girder early period in work Be filled with and later period pier shaft between arch rib it is assembled.
Girder erection crane 7: it is mainly the truss construction of engineering end girder steel, and construction direction is carried out from end to center, Realize the drop-over of truss end structure and the arch rib construction on top.
Crawler crane 5: the assembly and drop-over engineering of girder steel between crawler crane 5 and girder erection crane joint construction end pier.
After having understood the structure of above-mentioned bridge and the equipment that uses, bridging method packet in water provided by the embodiments of the present application It includes:
As shown in Figure 4, from the first main trestle of the both ends on riverbank construction, and in korneforos construction branch trestle 1;While specific Construct main line trestle and branch trestle 1 so that main trestle and branch trestle 1 synchronize build.
As shown in FIG. 1 to 3, cushion cap 2 and bridge pier 13 are set up between two branch trestles 1;
Specifically, using 100t crawler crane 5 on branch trestle 13 steel-pipe pile 8 of inserting piling control platform, in two branch trestles 1 Between set up control platform 3;Steel pile casting construction, construction drill stake.Start vibration hammer, by steel pile casting bottom absolute altitude inserting piling to stake top mark The high following position 6m, the construction drill stake in control platform 3 later, specifically, using 10 construction drill stake of rotary drilling rig.Complete Cheng Hou removes control platform 3, squeezes into steel sheet pile 11;Steel purlin is installed, inhales mud to back cover absolute altitude;Clear up steel sheet pile 11 simultaneously later Bottom concrete is poured, and sets up cushion cap 2 and bridge pier 13 on the bottom concrete poured.
According to sequence of construction construction bridge pier 13 and 13 pier girder steel assembling support 12 of bridge pier;Specifically, according to respective design When sequence of construction construction bridge pier 13 and 13 pier girder steel assembling support 12 of bridge pier, Temporary Piers 14 of also constructing simultaneously.
The builder's road on two branch trestles 1;Specifically, in builder's road, it is synchronous to carry out girder steel construction, girder steel assembly Field construction.
As shown in figure 5,3 sections between two bridge piers 13 on sidewalk at assembled center on the bracket of assembled second main trestle Between girder steel;The assembled girder erection crane on 3 assembled internode girder steels;Utilize the symmetrical assembled girder steel of the double cantilevers of girder erection crane;
Specifically, 3 internodes using 150t crawler crane 5 on sidewalk at assembled center between two piers on assembling support 12 Girder steel utilizes the girder steel of 3 internode of the 150t crawler crane 5 on trestle between the pier of assembled bridge section both ends on assembling support 12;Benefit With 150t crawler crane 5 on 3 assembled internode girder steels assembly 50t girder erection crane;Utilize the double cantilevers pair of girder erection crane Claim assembled girder steel.
Behind the girder erection crane respectively assembled girder steel to corresponding bridge pier 13, assembly girder erection crane is spelled at assembling support 12 Arch rib between dress pier;
Using girder steel between the lifting pier of crawler crane 5, wherein between pier after 3 internodes of assembled completion, utilize crawler crane 5 assembled Girder erection crane continues remaining girder steel between assembled pier.
The girder steel of 3 internodes on the first main trestle between the assembled both ends pier for being located at riverbank section on assembling support 12;And Assembly girder erection crane carrys out arch rib between assembled pier at assembling support 12;
As shown in fig. 6, using girder erection crane multiple bridge piers 13 that assembled girder steel is extremely set respectively;And using girder erection crane point Arch rib between multiple bridge piers 13 of the not assembled setting.Such as the assembled girder steel of girder erection crane difference to 16# pier, 13# pier, 13# Pier, 10# pier top.Meanwhile using girder erection crane difference assembly 16#~15# pier, 13#~14# pier, 13#~12# pier, 10#~11# Arch rib between pier.
First main trestle and the second main trestle are closed up;
As shown in fig. 7, specifically, accurately adjusting girder position;Remove all girder erection cranes, assembling support 12 and Temporary Piers 14, complete full-bridge steel girder erection;Bridge deck construction.
It can be seen from the above description that main bridge trestle is using both ends operation simultaneously, branch trestle 1 and main trestle synchronization job Mode is set up.Main bridge girder steel sets up girder steel from original design side, and the scheme of arch rib is set up after the completion of girder steel, be optimized in across across Middle to set up simultaneously to two sides symmetric double cantilever erection, continuous truss sliding roadway arch and freely-supported steel truss girder, girder steel is set up simultaneously with arch rib, Reach the "three-synchronims" of girder steel synchronous with freely-supported steel truss girder with lower part engineering synchronism, continuous truss sliding roadway arch, purlin and arch synchronization Arrangement and method for construction, thus the Optimizing construction duration significantly.
The optimization of Specific construction scheme is realized in multi-platform construction in water, makes steel suspension bridge, pile foundation, cushion cap 2, pier shaft, steel truss girder Parallel operations are overlapped with each construction link of sliding roadway arch, reaches rapid construction, guarantees quality and the purpose of duration.
The above is merely preferred embodiments of the present invention, be not intended to limit the invention, it is all in spirit of the invention and Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within principle.

Claims (5)

1. bridging method in a kind of water characterized by comprising
From the first main trestle of the both ends on riverbank construction;
In korneforos construction branch trestle;
Cushion cap and bridge pier are set up between two branch trestles;
According to sequence of construction construction bridge pier and bridge pier pier girder steel assembling support;
The builder's road on two branch trestles;
3 internode girder steels between two bridge piers on sidewalk at assembled center on the bracket of assembled second main trestle;It is assembled Assembled girder erection crane on 3 good internode girder steels;
Utilize the symmetrical assembled girder steel of the double cantilevers of girder erection crane;
Behind girder erection crane respectively assembled girder steel to corresponding bridge pier, encircle between the next assembled pier of assembly girder erection crane at assembling support Rib;
The girder steel of 3 internodes on the first main trestle between the assembled both ends pier for being located at riverbank section on assembling support;And
Assembly girder erection crane carrys out arch rib between assembled pier at assembling support;
First main trestle and the second main trestle are closed up.
2. bridging method in water according to claim 1, which is characterized in that described to set up cushion cap between two branch trestles And bridge pier;Specifically:
Drilling platform is set up between two branch trestles;
The construction drill stake on drilling platform;
Drilling platform is removed, steel sheet pile is squeezed into;Steel purlin is installed, inhales mud to back cover absolute altitude;
Cleaning steel sheet pile simultaneously pours bottom concrete, and sets up cushion cap and bridge pier on the bottom concrete poured.
3. bridging method in water according to claim 2, which is characterized in that further include:
When according to sequence of construction construction bridge pier and bridge pier pier girder steel assembling support, construct interim Dun.
4. bridging method in water according to claim 2, which is characterized in that described to set up cushion cap specifically:
Using more steel pipe bored concrete pile supports, top is laid with distribution beam, Bailey beam for lower part.
5. bridging method in water according to claim 1, which is characterized in that further include: it is assembled respectively using girder erection crane Multiple bridge piers of girder steel extremely setting;
And using the arch rib between girder erection crane respectively multiple bridge piers of the assembled setting.
CN201910027947.4A 2019-01-11 2019-01-11 Bridging method in a kind of water Pending CN109629438A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910027947.4A CN109629438A (en) 2019-01-11 2019-01-11 Bridging method in a kind of water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910027947.4A CN109629438A (en) 2019-01-11 2019-01-11 Bridging method in a kind of water

Publications (1)

Publication Number Publication Date
CN109629438A true CN109629438A (en) 2019-04-16

Family

ID=66061750

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910027947.4A Pending CN109629438A (en) 2019-01-11 2019-01-11 Bridging method in a kind of water

Country Status (1)

Country Link
CN (1) CN109629438A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110172922A (en) * 2019-06-17 2019-08-27 中国建筑第六工程局有限公司 A kind of environmentally friendly downlink Self-propelled steel trestle work structure construction method
CN110644363A (en) * 2019-06-24 2020-01-03 高军 Construction method of underwater main tower of cross-river cable-stayed bridge of high-speed railway
CN111119070A (en) * 2019-12-24 2020-05-08 江苏中铁山桥重工有限公司 Method for erecting W-shaped steel truss girder by adopting symmetrical gantry crane suspension assembly
CN111139749A (en) * 2020-01-08 2020-05-12 中铁四局集团有限公司 Large-span bearing type continuous steel truss girder cantilever erection construction method
CN112681135A (en) * 2020-12-14 2021-04-20 中铁二十局集团第三工程有限公司 Construction method of n-shaped sea-crossing temporary steel trestle

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1121822A (en) * 1997-07-03 1999-01-26 Tomoe Kikai Kogyo Kk Overhang erecting device
CN104790297A (en) * 2015-04-20 2015-07-22 中国铁建大桥工程局集团有限公司 Flexible arch splicing method for steel trussed beams
CN105970836A (en) * 2016-03-23 2016-09-28 中铁四局集团钢结构有限公司 Method for erecting large-span lower chord variable truss high continuous steel trussed beam cantilever
CN108360387A (en) * 2018-04-04 2018-08-03 中国铁建大桥工程局集团有限公司 A kind of continuous just trusses sliding roadway arch steel bridge rapid constructing method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1121822A (en) * 1997-07-03 1999-01-26 Tomoe Kikai Kogyo Kk Overhang erecting device
CN104790297A (en) * 2015-04-20 2015-07-22 中国铁建大桥工程局集团有限公司 Flexible arch splicing method for steel trussed beams
CN105970836A (en) * 2016-03-23 2016-09-28 中铁四局集团钢结构有限公司 Method for erecting large-span lower chord variable truss high continuous steel trussed beam cantilever
CN108360387A (en) * 2018-04-04 2018-08-03 中国铁建大桥工程局集团有限公司 A kind of continuous just trusses sliding roadway arch steel bridge rapid constructing method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
卢向勇: "厦深铁路榕江特大桥主桥施工技术方案研究", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 *
彭大文、李国芬、黄小广: "《桥梁工程 下》", 31 January 2007, 北京:人民交通出版社 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110172922A (en) * 2019-06-17 2019-08-27 中国建筑第六工程局有限公司 A kind of environmentally friendly downlink Self-propelled steel trestle work structure construction method
CN110644363A (en) * 2019-06-24 2020-01-03 高军 Construction method of underwater main tower of cross-river cable-stayed bridge of high-speed railway
CN111119070A (en) * 2019-12-24 2020-05-08 江苏中铁山桥重工有限公司 Method for erecting W-shaped steel truss girder by adopting symmetrical gantry crane suspension assembly
CN111119070B (en) * 2019-12-24 2022-02-11 江苏中铁山桥重工有限公司 Method for erecting W-shaped steel truss girder by adopting symmetrical gantry crane suspension assembly
CN111139749A (en) * 2020-01-08 2020-05-12 中铁四局集团有限公司 Large-span bearing type continuous steel truss girder cantilever erection construction method
CN112681135A (en) * 2020-12-14 2021-04-20 中铁二十局集团第三工程有限公司 Construction method of n-shaped sea-crossing temporary steel trestle
CN112681135B (en) * 2020-12-14 2022-10-11 中铁二十局集团第三工程有限公司 Construction method of n-shaped sea-crossing temporary steel trestle

Similar Documents

Publication Publication Date Title
CN109629438A (en) Bridging method in a kind of water
CN111648228A (en) Assembled pier and construction process thereof
CN106065577A (en) The structure of a kind of new pile foundation underpinning and method
CN102287194B (en) Construction method of multi-span gently arc tunnel
CN106939553B (en) A kind of Steel Bridge Deck and steel box arch rib installation method
CN112342917A (en) Combined construction method for pushing beam first and then lifting arch of large-span tied arch bridge
CN106088120B (en) A kind of cofferdam decentralization construction method
CN113863172A (en) Rapid urban bridge dismantling and rebuilding construction method based on gantry crane
CN217580865U (en) Large-diameter steel casing drilling platform under deep water slope bare rock geological condition
CN108797323B (en) Steel trestle suitable for hard stratum
CN109056710B (en) Hard stratum steel pipe pile and construction method thereof
CN113027463B (en) Suspension type reverse wall working well supporting structure and construction method
CN212054725U (en) Cast-in-place reinforced concrete arch-covering formwork system
CN113106833A (en) Special-shaped pedestrian landscape bridge structure and construction method thereof
CN110847047B (en) Open sea bare rock trestle construction method
AU2012313196B2 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
CN216689329U (en) Drilling platform based on marine steel batter pile support pile basis
CN110820519A (en) Tunnel arch bridge convenient for rapid construction and construction method thereof
JP2002364004A (en) Installation method for underwater foundation
CN205276273U (en) Civil engineering construction uses hollow pile body
CN213062061U (en) Sectional type steel pouring jacket cofferdam
CN211172070U (en) Assembled type suspended wall retaining wall structure of reinforced concrete member
CN113073683A (en) Temporary suspension device for existing pipeline and construction method
JP7250302B2 (en) Bridge construction method and unit structure
CN112854293A (en) Structure of wall door opening of subway station auxiliary and main body connecting section and construction process thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190416