CN109610814A - A kind of installation of deep-well garage sliding formwork and construction method - Google Patents

A kind of installation of deep-well garage sliding formwork and construction method Download PDF

Info

Publication number
CN109610814A
CN109610814A CN201811256520.3A CN201811256520A CN109610814A CN 109610814 A CN109610814 A CN 109610814A CN 201811256520 A CN201811256520 A CN 201811256520A CN 109610814 A CN109610814 A CN 109610814A
Authority
CN
China
Prior art keywords
deep
template
well
operation platform
sliding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811256520.3A
Other languages
Chinese (zh)
Inventor
庄建军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Yi Po Intelligent Technology Co Ltd
Original Assignee
Hangzhou Yi Po Intelligent Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Yi Po Intelligent Technology Co Ltd filed Critical Hangzhou Yi Po Intelligent Technology Co Ltd
Priority to CN201811256520.3A priority Critical patent/CN109610814A/en
Publication of CN109610814A publication Critical patent/CN109610814A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/22Sliding forms raised continuously or step-by-step and being in contact with the poured concrete during raising and which are not anchored in the hardened concrete; Arrangements of lifting means therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/22Sliding forms raised continuously or step-by-step and being in contact with the poured concrete during raising and which are not anchored in the hardened concrete; Arrangements of lifting means therefor
    • E04G11/24Construction of lifting jacks or climbing rods for sliding forms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/002Workplatforms, railings; Arrangements for pouring concrete, attached to the form

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

A kind of installation of deep-well garage sliding formwork and construction method, including template system, operation platform system, hydraulic lifting system;The template system includes template, enclosure, open type hoisting frame;The operation platform system includes main operation platform, auxiliary operation platform;The hydraulic lifting system includes hydraulic jack, hydraulic control panel, oil piping system, support rod, Yi Jishui, electric corollary system;The borehole wall applied to deep-well garage is poured, and is reduced equipment investment and is reduced the wasting of resources.

Description

A kind of installation of deep-well garage sliding formwork and construction method
Technical field
The present invention relates to Slip Form Construction Technique field, specially a kind of deep-well garage sliding formwork installation and construction method.
Background technique
Sliding formwork is the slow moving structure molding of template, and usually fixed-size typified form is drawn by pulling equipment.It is sliding Mould engineering technology is that China's Cast-in-situ Concrete Structural Engineering construction machinery degree is high, speed of application is fast, live place occupancy Less, structural integrity is strong, anti-seismic performance is good, safety work is secure, the significant a kind of construction skill of environment and economical synthesis benefit Art, often referred to simply as " sliding formwork ".But sliding formwork not only includes common or dedicated equal tool-typed formworks, further include the sliding equipment of power and The complex arts such as matching operation technique, at present mainly with hydraulic jack for sliding power, in the synchronous effect of jack in groups Under, drive the tool-typed formwork of 1 meter Duo Gao or sliding sash to slide along rigid molding concrete surface or template surface, concrete by The layering suitable for reading of template is poured into grooving, and every layer is usually no more than 30cm thickness, when concrete undermost in template reaches one After determining intensity, template grooving relies on the effect of lifting machinery, along the concrete surface sliding poured or sliding sash along mould The sliding of plate outer surface, slides about 30cm or so again upwards, so so continuous cycle operation, until reaching design height, completes Entire construction.Although slding form operation in civil construction project all trades and professions, is all widely used, in deep-well vehicle In the construction building in library or rarely known by the people, since the building in deep-well garage is under earth's surface, traditional sliding formwork is applied Work applicability is poor, according to the difficulty that our long-term construction experiences encounter, is even built using traditional sliding formwork, but its Labor and materials needed for needing to set scaffold using a large amount of formwork, Large-scale Hoisting equipment, tower, template quantity greatly increase, resource Waste is serious.
Summary of the invention
The purpose of the invention is to provide a kind of installation of deep-well garage sliding formwork and construction method, it is applied to deep-well garage The borehole wall casting, reduce equipment investment and reduce the wasting of resources.
In order to achieve the above-mentioned object of the invention, the invention adopts the following technical scheme: a kind of deep-well garage sliding formwork installation with And construction method, including template system, operation platform system, hydraulic lifting system;The template system include template, enclosure, Open type hoisting frame;The operation platform system includes main operation platform, auxiliary operation platform;The hydraulic lifting system includes liquid Press jack, hydraulic control panel, oil piping system, support rod, Yi Jishui, electric corollary system;Slding form operation specific method includes such as Lower step:
Step is 1.: after the completion of deep-well ground settlement and tunnel, positioned at deep-well the bottom of the channel along deep-well channel wall according to pouring permanent well Wall requires wiretie cage, and steel reinforcement cage is located between inner template and the former borehole wall, highly pre- embedded according to deep-well channel depth;
Step is 2.: it is 1. described according to step, open type hoisting frame and enclosure be installed, enclosure annular is around being arranged in open type hoisting frame On periphery, template is installed between deep-well channel wall and open type hoisting frame, and template is inner template, and inner template is installed in advance to opening Formula hoisting frame side forms confined space with former borehole wall supporting surface;
Step is 3.: it is 2. described according to step, main operation platform is installed, main operation platform include including steel truss, stupefied wood, bed board, Steel truss support forms entirety in enclosure, for connecting open type hoisting frame and enclosure;
Step is 4.: it is 3. described according to step, auxiliary operation platform is installed, auxiliary operation platform include choose outside tripod, stupefied wood and Bed board composition;
Step is 5.: it is 4. described according to step, it installs on hydraulic jack to the lower beam of open type hoisting frame, hydraulic control panel peace It is filled on bed board and is connect with oil piping system and water, electric corollary system;Hydraulic control panel controls high-voltage oil liquid and passes through oil fuel tube, divides Oil pipe and branch oil pipe are transported in each hydraulic jack, hydraulic jack lifting motion;The first layer concrete is poured to internal model Between plate and former borehole wall supporting surface, concrete casting height is once 30-40cm, with a thickness of 40-80cm, is poured second layer coagulation Soil is about 2 hours with the first layer concrete interval, continuous alternately with 2 hours for a duration, until reaching required deep-well Structure height;
Step is 6.: 5. described according to step, hydraulic jack elevator belt moving template is sliding by track of support rod;One layer of casting mixed The solidifying soil sliding 30-40cm of rear pattern plate, continuous was alternately a duration climbing form 30-40cm until reaching required depth with 2 hours The structure height of well.
Preferably, the step 6. in, deep-well channel reaches the structure height of required deep-well, continues empty sliding template 50- 60cm height is until be higher by ground level, form removal system, operation platform system, hydraulic lifting system.
Preferably, the step 2. in, template is fixed form combined steel mould.
Preferably, the step 3. in, enclosure forms integrally molded with open type hoisting frame.
Preferably, the step 2. in, open type hoisting frame pillar construction using steel pipe make, hydraulic jack promoted when, Drive enclosure, template and operation platform system to synchronize by open type hoisting frame sliding upwards, and will be sliding when generate it is vertical In load transmission to hydraulic jack and support rod.
Preferably, the step 3. with step 4. in, main operation platform for wiretie cage, casting concrete, template Sliding control, main operation platform are tiled using thick steel plate;Auxiliary operation platform disk thick steel plate Mi Pu, disk width are 70- 80cm, and major-minor operating platform is designed with anti-fall be caught.
Preferably, the step 5. in, borehole wall internal layer surface add waterproof filler and second pouring concrete it Between bury water-stopping steel band.
Preferably, the step 6. in, high-voltage oil liquid is delivered in hydraulic jack, and continuous oil supply oil return makes hydraulic thousand Jin top piston constantly compressed, resetted, by hydraulic jack withstand on it is sliding on support rod keep template sliding upwards, the template Climbing verticality is controlled with laser orientation.
Preferably, the step 6. in, support rod be rigid material, using bushing type support rod, added on the outside of support rod in Diameter is greater than the casing of its 2-5cm, and sleeve upper end is fixed with open type hoisting frame crossbeam, and lower end is connect with template;And it supports Joggle, snapping also can be used in bar.
Compared with prior art, using above-mentioned technical proposal a kind of deep-well garage sliding formwork installation and construction method, Having the following beneficial effects: can be applied in deep-well garage borehole wall building, avoid that equipment is more in traditional slding form operation, resource is unrestrained The problem of taking, the deep-well passage construction speed for being becomes faster, save formwork and tower sets labor and materials required for scaffold, saves disposable The dosage for putting into template more can be dismantled easily and flexible assembling and be may be reused.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of sliding formwork installation in a kind of deep-well garage of the invention and construction method embodiment;
Fig. 2 is the structural schematic diagram in the present embodiment middle-deep well channel;
Fig. 3 is support rod sleeve type structure schematic diagram in the present embodiment;
Fig. 4 is support rod tenon joint type structural schematic diagram in the present embodiment;
Fig. 5 is the buckled structural schematic diagram of support rod in the present embodiment.
Specific embodiment
The present invention is described further with reference to the accompanying drawing.
A kind of installation of deep-well garage sliding formwork as shown in Fig. 1 to 5 and construction method, including template system, operating platform System, hydraulic lifting system;The template system includes template, enclosure, open type hoisting frame;The operation platform system includes master Operating platform, auxiliary operation platform;The hydraulic lifting system includes hydraulic jack, hydraulic control panel, oil piping system, support Bar, Yi Jishui, electric corollary system;Slding form operation specific method includes the following steps:
Step is 1.: after the completion of deep-well ground settlement and tunnel, positioned at deep-well the bottom of the channel along deep-well channel wall according to pouring permanent well Wall requires wiretie cage, and steel reinforcement cage is located between inner template and the former borehole wall, highly pre- embedded according to deep-well channel depth;
Step is 2.: it is 1. described according to step, open type hoisting frame and enclosure be installed, enclosure annular is around being arranged in open type hoisting frame On periphery, template is installed between deep-well channel wall and open type hoisting frame, and template is inner template, and inner template is installed in advance to opening Formula hoisting frame side forms confined space with former borehole wall supporting surface;
Step is 3.: it is 2. described according to step, main operation platform is installed, main operation platform include including steel truss, stupefied wood, bed board, Steel truss support forms entirety in enclosure, for connecting open type hoisting frame and enclosure;
Step is 4.: it is 3. described according to step, auxiliary operation platform is installed, auxiliary operation platform include choose outside tripod, stupefied wood and Bed board composition;
Step is 5.: it is 4. described according to step, it installs on hydraulic jack to the lower beam of open type hoisting frame, hydraulic control panel peace It is filled on bed board and is connect with oil piping system and water, electric corollary system;Hydraulic control panel controls high-voltage oil liquid and passes through oil fuel tube, divides Oil pipe and branch oil pipe are transported in each hydraulic jack, hydraulic jack lifting motion;The first layer concrete is poured to internal model Between plate and former borehole wall supporting surface, concrete casting height is once 30-40cm, with a thickness of 40-80cm, is poured second layer coagulation Soil is about 2 hours with the first layer concrete interval, continuous alternately with 2 hours for a duration, until reaching required deep-well Structure height;
Step is 6.: 5. described according to step, hydraulic jack elevator belt moving template is sliding by track of support rod;One layer of casting mixed The solidifying soil sliding 30-40cm of rear pattern plate, continuous was alternately a duration climbing form 30-40cm until reaching required depth with 2 hours The structure height of well;It can be applied to that it is more, the wasting of resources to avoid equipment in traditional slding form operation in deep-well garage borehole wall building Problem, the deep-well passage construction speed for being becomes faster, save formwork and tower sets labor and materials required for scaffold, saves disposable investment The dosage of template more can be dismantled easily and flexible assembling and be may be reused.
Consider the stability of support rod and the stability of whole operation platform, at least 24 hydraulic jacks are set altogether along barrel Top, support rod are with 48 × 3.5 steel pipe of Ф, inner template 900 × 200.Main operation platform is set as space truss form, platform bed board 30~50 thickness about 135m2, weight about 9.0t of thickness;Support rod permitted bearing capacity calculates:
Wherein: the permitted bearing capacity of P- support rod;A- service factor, takes 0.7;E- support rod elasticity modulus, E= 2.06×10^5/mm2;J- support rod cross sectional moment of inertia, J=12.16cm4;K- safety coefficient, takes 3.0;LO- support rod It comes to nothing length, takes 1.2m;Therefore: consider engineering practice, there are certain bearing capacity leeway, support rod bearing capacity presses 3.0t It chooses.
Sliding form apparatus design load calculates as follows:
1, the self weight of template system, operation platform system: consider by 9t; 
2, the construction loads on main operation platform: 135 ㎡ × 100kg/m^2=13.5t;Frictional resistance when 4 templates are promoted: because It is steel form, frictional resistance takes 3kN/m^2. 
The kN/m^2=21t of 70 ㎡ × 3;1.2 N=43.5 × 1.2 of 9+13.5+21=43.5t load factor=52.2t n=N/P =52.2/3=17 platform, less than selected 24;Therefore: support rod is fully able to meet the promotion requirement of main operation platform.Support The calculating of bar:
Hydraulic jack is climbed with support rod using 48 × 3.5 steel pipe of φ;Load P=N1/n=169.1/84 that every bar is born= 20.13KN。
The allowable load of support rod calculates, formula [P]=0.7 × 40EI/K (L0+95) 2;In formula: support rod in E-formula Elasticity modulus=2.1 × 104KN/cm^2.
I-support rod cross sectional moment of inertia=12.296cm4;K-safety coefficient=2.
L0-support rod drift, by least favorable state computation when being promoted.
The high 120cm of template, template is suitable for reading to arrive the high 50cm of mouth under hoisting frame crossbeam, under hoisting frame lower beam under mouth to jack Bayonet distance 25cm, bottom plate is thick temporarily to take 1.0M;L0=120+50+25+100=295cm.
Substitute into data: [P]=0.7 × 40 × 2.1 × 104 × 12.296/ { 2 × (295+95) ^2 }=23.7 > 20.13KN (safety).
Step 6. in, deep-well channel reaches the structure height of required deep-well, continues empty sliding template 50-60cm height until high Ground level out, form removal system, operation platform system, hydraulic lifting system.
Step 2. in, template is fixed form combined steel mould, and concrete sizing, casting effect are good, is not easy to leak outside.
Step 3. in, enclosure and open type hoisting frame weld;Structural strength is high, convenient when dismantling after the completion of construction.
Step 2. in, open type hoisting frame pillar construction using steel pipe make, hydraulic jack promoted when, promoted by open type It is sliding upwards that frame drives enclosure, template and operation platform system to synchronize, and will be sliding when the vertical load that generates be transmitted to liquid It presses on jack and support rod.
Step 3. with step 4. in, main operation platform for wiretie, casting concrete, template sliding lifting control, main behaviour Make platform to tile using thick steel plate;Auxiliary operation platform disk thick steel plate Mi Pu, disk width are 70-80cm, and major-minor Operating platform is equipped with anti-fall be caught;Preventing dropped material, structural strength is high, stationarity is good, and disk must be tight, prevents from collapsing, fall apart, and pacifies Full operation.
Step 5. in, borehole wall internal layer surface, which is added, buries water-stopping steel between waterproof filler and the concrete of second pouring Band, since deep-well channel is under, ponding is easily infiltrated on the outside of the borehole wall, and addition waterproof filler avoids infiltration inside the borehole wall, It can be the pond special-purpose water-proof anticorrosive paint layer of model PHA103, PHA105.
Step 6. in, high-voltage oil liquid is delivered in hydraulic jack, and continuous oil supply oil return makes the piston of hydraulic jack It constantly compressed, resetted, being withstood on by hydraulic jack sliding on support rod keeps template sliding upwards;Template sliding lifting verticality is by swashing Light oriented control, for control casting after concrete verticality.
Step 6. in, support rod is rigid material, and using bushing type support rod, internal diameter is added on the outside of support rod greater than its 2- The casing of 5cm, sleeve upper end are fixed with open type hoisting frame crossbeam, and lower end is connect with template;And support rod also can be used Joggle, snapping.
Make the preferred embodiment of the present invention above, does not depart from original of the invention for those of ordinary skill in the art Under the premise of reason, several variations and modifications can also be made, these also should be regarded as protection scope of the present invention.

Claims (9)

1. a kind of deep-well garage sliding formwork installation and construction method, it is characterised in that: including template system, operation platform system, Hydraulic lifting system;The template system includes template, enclosure, open type hoisting frame;The operation platform system includes main operation Platform, auxiliary operation platform;The hydraulic lifting system include hydraulic jack, hydraulic control panel, oil piping system, support rod, And water, electric corollary system;Slding form operation specific method includes the following steps:
Step is 1.: after the completion of deep-well ground settlement and tunnel, positioned at deep-well the bottom of the channel along deep-well channel wall according to pouring permanent well Wall requires wiretie cage, and steel reinforcement cage is located between inner template and the former borehole wall, highly pre- embedded according to deep-well channel depth;
Step is 2.: it is 1. described according to step, open type hoisting frame and enclosure be installed, enclosure annular is around being arranged in open type hoisting frame On periphery, template is installed between deep-well channel wall and open type hoisting frame, and template is inner template, and inner template is installed in advance to opening Formula hoisting frame side forms confined space with former borehole wall supporting surface;
Step is 3.: it is 2. described according to step, main operation platform is installed, main operation platform include including steel truss, stupefied wood, bed board, Steel truss support forms entirety in enclosure, for connecting open type hoisting frame and enclosure;
Step is 4.: it is 3. described according to step, auxiliary operation platform is installed, auxiliary operation platform include choose outside tripod, stupefied wood and Bed board composition;
Step is 5.: it is 4. described according to step, it installs on hydraulic jack to the lower beam of open type hoisting frame, hydraulic control panel peace It is filled on bed board and is connect with oil piping system and water, electric corollary system;Hydraulic control panel controls high-voltage oil liquid and passes through oil fuel tube, divides Oil pipe and branch oil pipe are transported in each hydraulic jack, hydraulic jack lifting motion;The first layer concrete is poured to internal model Between plate and former borehole wall supporting surface, concrete casting height is once 30-40cm, with a thickness of 40-80cm, is poured second layer coagulation Soil,It is about 2 hours with the first layer concrete interval, it is continuous alternately with 2 hours for a duration, until reaching required deep-well Structure height;
Step is 6.: 5. described according to step, hydraulic jack elevator belt moving template is sliding by track of support rod;One layer of casting mixed The solidifying soil sliding 30-40cm of rear pattern plate, continuous was alternately a duration climbing form 30-40cm until reaching required depth with 2 hours The structure height of well.
2. sliding formwork installation in a kind of deep-well garage according to claim 1 and construction method, it is characterised in that: the step 6. in, deep-well channel reaches the structure height of required deep-well, continues empty sliding template 50-60cm height until being higher by ground level, tears open Removing template system, operation platform system, hydraulic lifting system.
3. sliding formwork installation in a kind of deep-well garage according to claim 1 and construction method, it is characterised in that: the step 2. in, template is fixed form combined steel mould.
4. a kind of deep-well garage slding form operation method according to claim 1, it is characterised in that: the step 3. in, enclose Circle forms integrally molded with open type hoisting frame.
5. sliding formwork installation in a kind of deep-well garage according to claim 1 and construction method, it is characterised in that: the step In 2., open type hoisting frame pillar construction using steel pipe make, hydraulic jack promoted when, by open type hoisting frame drive enclosure, Template and operation platform system synchronize it is sliding upwards, and will be sliding when the vertical load that generates be transmitted to hydraulic jack and branch On strut.
6. sliding formwork installation in a kind of deep-well garage according to claim 1 and construction method, it is characterised in that: the step 3. with step 4. in, main operation platform is for wiretie, casting concrete, template sliding lifting control, and main operation platform is using thick Steel plate tiling;Auxiliary operation platform disk thick steel plate Mi Pu, disk width is 70-80cm, and major-minor operating platform is equipped with It is anti-fall to be caught.
7. sliding formwork installation in a kind of deep-well garage according to claim 1 and construction method, it is characterised in that: the step 5. in, borehole wall internal layer surface, which is added, buries water-stopping steel band between waterproof filler and the concrete of second pouring.
8. sliding formwork installation in a kind of deep-well garage according to claim 1 and construction method, it is characterised in that: the step 6. in, high-voltage oil liquid is delivered in hydraulic jack, and continuous oil supply oil return compresses the piston of hydraulic jack constantly, is multiple Position, by hydraulic jack withstand on it is sliding on support rod keep template sliding upwards, the template sliding lifting verticality is by laser orientation control System.
9. sliding formwork installation in a kind of deep-well garage according to claim 1 and construction method, it is characterised in that: the step 6. in, support rod is rigid material, and using bushing type support rod, the casing that internal diameter is greater than its 2-5cm, casing are added on the outside of support rod Upper end is fixed with open type hoisting frame crossbeam, and lower end is connect with template;And joggle, snapping also can be used in support rod.
CN201811256520.3A 2018-10-26 2018-10-26 A kind of installation of deep-well garage sliding formwork and construction method Pending CN109610814A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811256520.3A CN109610814A (en) 2018-10-26 2018-10-26 A kind of installation of deep-well garage sliding formwork and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811256520.3A CN109610814A (en) 2018-10-26 2018-10-26 A kind of installation of deep-well garage sliding formwork and construction method

Publications (1)

Publication Number Publication Date
CN109610814A true CN109610814A (en) 2019-04-12

Family

ID=66002548

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811256520.3A Pending CN109610814A (en) 2018-10-26 2018-10-26 A kind of installation of deep-well garage sliding formwork and construction method

Country Status (1)

Country Link
CN (1) CN109610814A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116023118A (en) * 2022-12-12 2023-04-28 中国建筑第五工程局有限公司 Red layer soft rock similar material simulating progressive disintegration and preparation method and device thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201377326Y (en) * 2009-04-08 2010-01-06 中交隧道工程局有限公司 Hydraulic formwork device with integration of lining and middle partition board
CN203050716U (en) * 2013-01-11 2013-07-10 成都市新筑路桥机械股份有限公司 Hydraulic slip form for vertical shaft tunnel lining
CN103362108A (en) * 2012-03-26 2013-10-23 中国水利水电第十四工程局有限公司 Composite-structure porous shaft slip form construction device and method
CN105134220A (en) * 2015-08-25 2015-12-09 三峡大学 Hydraulic sliding formwork for vertical shaft lining

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201377326Y (en) * 2009-04-08 2010-01-06 中交隧道工程局有限公司 Hydraulic formwork device with integration of lining and middle partition board
CN103362108A (en) * 2012-03-26 2013-10-23 中国水利水电第十四工程局有限公司 Composite-structure porous shaft slip form construction device and method
CN203050716U (en) * 2013-01-11 2013-07-10 成都市新筑路桥机械股份有限公司 Hydraulic slip form for vertical shaft tunnel lining
CN105134220A (en) * 2015-08-25 2015-12-09 三峡大学 Hydraulic sliding formwork for vertical shaft lining

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
无: ""竖井滑模施工组织设计"", 《HTTPS://WENKU.BAIDU.COM/VIEW/C91D278EA1C7AA00B52ACBA1.HTML?FR=SEARCH》 *
郭爱云: "《混凝土工实用技术手册》", 31 January 2011 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116023118A (en) * 2022-12-12 2023-04-28 中国建筑第五工程局有限公司 Red layer soft rock similar material simulating progressive disintegration and preparation method and device thereof
CN116023118B (en) * 2022-12-12 2023-09-15 中国建筑第五工程局有限公司 Red layer soft rock similar material simulating progressive disintegration and preparation method and device thereof

Similar Documents

Publication Publication Date Title
CN104631512B (en) Hang modulus method after-pouring band beam-slab construction method
CN106638940B (en) A kind of assembled high residential building concrete prefabricated element construction
CN104790302B (en) A kind of high pier continuous rigid frame bridge end bay straightway Hanging Basket coordinates bent cap support integral construction method
CN107059920B (en) Loess formation piping lane construction technology
CN209227580U (en) The tower-crane foundation structure of raft foundation is placed under a kind of
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN108193608A (en) The cast-in-place road gully of mobile moldbase and construction method
CN112376589A (en) Landslide belt pile plate type comprehensive protection construction system and construction method
CN104563503A (en) Cast-in-place reinforced concrete high-altitude automatic building method of high-rise and ultra high-rise residential buildings
CN102587416A (en) Basement attached lane structure and construction method thereof
CN108005118A (en) Underground pipe gallery agent structure integrates construction method
CN105133575A (en) Suspended formwork supporting device for casting lining on surface of underground continuous wall and construction method
CN210066671U (en) Novel rectangular gallery structure
CN103061508A (en) Triangular slip form device and construction method for the same triangular slip form
CN202466623U (en) Basement attached lane structure
CN104963348B (en) A kind of soft clay area tower crane construction supporting structure and its construction method
CN106988319A (en) A kind of rapid constructing method of large deep foundation pit agent structure side wall
CN109610814A (en) A kind of installation of deep-well garage sliding formwork and construction method
CN103122642A (en) Construction method of vertical post support change
CN203452375U (en) Hydraulic self-jacking oblique creeping formwork
CN108222656A (en) The construction method of Prefabricated enclosure wall
CN104846745A (en) Urban high-pier support-free formwork turnover construction method
CN209293068U (en) A kind of open trench tunnel falsework system
CN109339067B (en) Concrete dam facing heightening structure and construction method
CN204715764U (en) The structure that a kind of constructional column and agent structure are constructed simultaneously

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190412

RJ01 Rejection of invention patent application after publication