CN109610768A - Panel installation assembly and method - Google Patents

Panel installation assembly and method Download PDF

Info

Publication number
CN109610768A
CN109610768A CN201811558117.6A CN201811558117A CN109610768A CN 109610768 A CN109610768 A CN 109610768A CN 201811558117 A CN201811558117 A CN 201811558117A CN 109610768 A CN109610768 A CN 109610768A
Authority
CN
China
Prior art keywords
plate
installation
keel
panel
flange
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811558117.6A
Other languages
Chinese (zh)
Other versions
CN109610768B (en
Inventor
丁欣欣
丁泽成
王文广
周东珊
钟诚
王东
武鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Yasha Decoration Co Ltd
Original Assignee
Zhejiang Yasha Decoration Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Yasha Decoration Co Ltd filed Critical Zhejiang Yasha Decoration Co Ltd
Priority to CN201811558117.6A priority Critical patent/CN109610768B/en
Publication of CN109610768A publication Critical patent/CN109610768A/en
Application granted granted Critical
Publication of CN109610768B publication Critical patent/CN109610768B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/0801Separate fastening elements
    • E04F13/0803Separate fastening elements with load-supporting elongated furring elements between wall and covering elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/0801Separate fastening elements
    • E04F13/0803Separate fastening elements with load-supporting elongated furring elements between wall and covering elements
    • E04F13/0805Separate fastening elements with load-supporting elongated furring elements between wall and covering elements with additional fastening elements between furring elements and the wall
    • E04F13/0807Separate fastening elements with load-supporting elongated furring elements between wall and covering elements with additional fastening elements between furring elements and the wall adjustable perpendicular to the wall

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Finishing Walls (AREA)
  • Floor Finish (AREA)

Abstract

The embodiment of the invention discloses a kind of panel installation assembly and methods, comprising: install keel, installation profile, the day keel for being fixed on the wall and the ground joist for fixing on the ground for being mounted on panel, inserting groove is provided on the day keel and ground joist, the both ends of the installation keel length direction are plugged on respectively in the inserting groove of the day keel and ground joist, clamping groove is provided on the installation keel, the installation profile and the clamping groove are clamped.The set-up time can be greatlyd save using the embodiment of the present invention, improves installation effectiveness, while can greatly facilitate the replacement of panel, is convenient for later period maintenance, improves maintenance efficiency.

Description

Panel installation assembly and method
Technical field
The present invention relates to decorations technical fields, and in particular to a kind of panel installation assembly and method.
Background technique
Currently, with the improvement of people's living standards, the requirement to finishing is higher and higher, in household wall or office field It decorates and uses baking vanish glass panel more and more.Existing baking vanish glass panel installation method is: by baking vanish glass panel Whole back side gluing, is then bonded on wall, and installation is very inconvenient, and when needing replacing baking vanish glass panel, it is more difficult to Low efficiency is replaced in disassembly.
Summary of the invention
In view of this, the embodiment of the present invention proposes a kind of panel installation assembly and method, to solve the above technical problems.
The embodiment of the present invention proposes a kind of panel installation assembly comprising: installation keel, the peace for being mounted on panel Fill profile, the day keel for being fixed on the wall and the ground joist for fixing on the ground, the day keel and ground joist On be provided with inserting groove, the both ends of the installation keel length direction are plugged on the grafting of the day keel and ground joist respectively In slot, clamping groove is provided on the installation keel, the installation profile and the clamping groove are clamped.
Optionally, the day keel and ground joist include pedestal, the first plugboard and the second plugboard, the pedestal tool There are first side and second side for fixing, first side and second side are oppositely arranged, first plugboard and Two plugboards are vertically disposed in first side, and three constitutes the inserting groove.
It optionally, further include leveling corner brace comprising transverse slat and riser connected vertically are provided with first on the transverse slat Waist-shaped hole, the first waist-shaped hole extend perpendicularly to riser, and the second waist-shaped hole, the second waist type are provided on the riser Hole extends perpendicularly to transverse slat, and the first fastener passes through the first waist-shaped hole and fastens the pedestal of the day keel and transverse slat, Second fastener passes through the second waist-shaped hole and is fixed on the wall riser.
Optionally, the installation profile includes substrate, the first buckle and the second buckle, the first plate face fitting of the substrate On the panel, first buckle and the second buckle are vertically disposed on being oppositely arranged with the first plate face for the substrate The second plate face on, and there is gap between two buckles, first buckle is provided with the in the plate face of the second buckle One lug boss, second buckle are provided with the second lug boss in the plate face of the first buckle, and the installation profile passes through the One lug boss and the second lug boss and the clamping groove are clamped.
Optionally, the installation keel include fixed plate, the first snap-arms and the second snap-arms, first snap-arms, Second snap-arms and fixed plate surround clamping groove, and the fixed plate has inner plate surface and for the outer plate surface with wall connecting, institute It states inner plate surface and outer plate surface is oppositely arranged, first snap-arms include the first side plate and first abuts plate, second clamping Arm includes the second side plate and second abuts plate, and first side plate abuts that plate is vertical connect with inner plate surface and first respectively, described Second side plate abuts that plate is vertical connect with inner plate surface and second respectively, and it is coplanar that the first abutting plate with second abuts plate, and position Between the first side plate and the second side plate, described first abuts side of the plate far from the first side plate towards the direction close to fixed plate Fold forms the first flange, and described second abuts side of the plate far from the second side plate turns down towards the direction close to fixed plate, shape At the second flange, first flange and the second flange are each perpendicular to inner plate surface, plate of first flange towards the second flange It is provided with the first protruding portion on face, is provided with the second protruding portion, the peace in the plate face of the first flange of the second flange direction It fills profile and is inserted into the clamping groove, be clamped by the first lug boss and the first protruding portion, the second lug boss and the second protruding portion.
Optionally, the quantity of the installation keel is at least two, and at least two installation keel are arranged in parallel.
Optionally, further includes: supporting element, the supporting element include the support keel for abutting with panel, the support For keel between adjacent installation keel, the both ends of the support keel length direction are plugged on the day keel and pheretima respectively In the inserting groove of bone.
Optionally, the installation keel further include the first support arm and the second support arm, and the first support arm and second support The clamping groove is divided into the first subcard access slot and the second subcard access slot by arm, and first support arm includes the first support plate and the One mounting plate, first support plate is vertical with the first mounting plate and inner plate surface respectively to be connect, and first mounting plate is located at the Between side plate and the first support plate, and abut with first that plate is coplanar, the side of first mounting plate far from the first support plate It is turned down towards the direction close to fixed plate, forms third flange, be provided in the plate face of the first flange of the third flange direction Third protruding portion, the installation profile are inserted into the first subcard access slot, by the first lug boss and the first protruding portion, second convex The portion of rising and the clamping of third protruding portion;Second support arm includes the second support plate and the second mounting plate, second support plate It is vertical with the second mounting plate and inner plate surface respectively to connect, second mounting plate between the second side plate and the second support plate, And abutting that plate is coplanar with second, side of second mounting plate far from the second support plate is turned over towards the direction close to fixed plate Folding forms the 4th flange, is provided with the 4th protruding portion, the installation profile in the plate face of the second flange of the 4th flange direction It is inserted into the second subcard access slot, is clamped by the first lug boss and the 4th protruding portion, the second lug boss and the second protruding portion, institute It states and is embedded with caulking strip between the first support plate and the second support plate.
It optionally, further include leveling part, the leveling part includes leveling board and rivet nut, and the leveling board has front With the back side for abutting with wall, the front is oppositely arranged with the back side, and the rivet nut is vertically set on front, institute Stating on installation keel has screw hole, and the rivet nut is spirally connected with screw hole.
The embodiment of the present invention also provides a kind of panel installation techniques based on panel installation assembly as described above, packet It includes: by sky dragon bone fixation on wall;Ground joist is fixed on the ground;The both ends for installing keel are plugged on a day keel respectively In the inserting groove of ground joist;Installation profile is mounted on panel;Profile will be installed and be connected to the clamping for installing keel In slot.
Panel installation assembly provided in an embodiment of the present invention and method pass through setting installation profile, installation keel, day keel And ground joist, installation keel are fixed on the wall by day ground joist, the card that panel is connected to installation keel by installing profile In access slot, panel integral installation uses drying hair operation, and all components can be produced in factory industry metaplasia, and scene carries out assembled peace Dress can greatly save the set-up time, improve installation effectiveness, while can greatly facilitate the replacement of panel, be convenient for later period maintenance, mention High maintenance efficiency.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the panel installation assembly of the embodiment of the present invention.
Fig. 2 is the structural schematic diagram of the day keel of the embodiment of the present invention.
Fig. 3 is the structural schematic diagram of the adjusting corner brace of the embodiment of the present invention.
Fig. 4 is the scheme of installation of the day keel of the embodiment of the present invention.
Fig. 5 is the scheme of installation of the ground joist of the embodiment of the present invention.
Fig. 6 is the structural schematic diagram of the installation profile of the embodiment of the present invention.
Fig. 7 is the panel of the embodiment of the present invention and the installation diagram of installation keel.
Fig. 8 is the structural schematic diagram of the supporting element of the embodiment of the present invention.
Fig. 9 is the structural schematic diagram of the caulking strip of the embodiment of the present invention.
Figure 10 is the structural schematic diagram of the installation corner brace of the embodiment of the present invention.
Figure 11 is the flow chart of the panel installation techniques of the embodiment of the present invention.
Specific embodiment
Below in conjunction with attached drawing and specific embodiment, technical solution of the present invention is described in detail.It is wherein identical Components are presented with like reference characters.It should be noted that word "front", "rear" used in the following description, " left side ", " right side ", "up" and "down" refer to that the direction in attached drawing, word "inner" and "outside" are referred respectively to towards or away from particular elements The direction of geometric center.
Fig. 1 shows the structural schematic diagram of the panel installation assembly of the embodiment of the present invention, and as shown in Fig. 1, the present invention is implemented The panel installation assembly that example provides comprising: installation profile, installation keel 2, the day keel 3 for being fixed on wall 6 and use In the ground joist 4 fixed on the ground.
Inserting groove, the both ends difference of installation 2 length direction of keel are provided on the day keel 3 and ground joist 4 It is plugged in the inserting groove of the day keel 34 and ground joist 4.
Clamping groove is provided on the installation keel 2, the installation profile is mounted on the panel 1, the installing tache Item and the clamping groove are clamped.
When assembly, first day keel 3 are fixed on wall 6;Ground joist 4 is fixed on the ground;Then keel 2 will be installed Both ends be plugged in the inserting groove of day keel 3 and ground joist 4 respectively;Installation keel 2 can be slid onto pre-determined bit along inserting groove It sets.
Then installation profile is mounted on panel 1;Profile will be installed to be connected in the clamping groove of the installation keel 2, The installation of panel 1 can be realized.
When replacing panel 1, profile need to will be only installed and extracted out of installation keel 2 clamping groove, such as will by sucker Installation profile is extracted out of installation keel 2 clamping groove.
Then, in the new assembly installation profile of panel 1, then profile will be installed again be caught in the clamping groove of installation keel 2 ?.
Panel installation assembly provided in an embodiment of the present invention passes through setting installation profile, installation keel, day keel and pheretima Bone, installation keel are fixed on the wall by day ground joist, and panel is connected in the clamping groove of installation keel by installing profile, Panel integral installation uses drying hair operation, and all components can be produced in factory industry metaplasia, and scene carries out assembled installation, can be big It is big to save the set-up time, installation effectiveness is improved, while can greatly facilitate the replacement of panel, be convenient for later period maintenance, improves maintenance Efficiency.
In a preferred embodiment of the invention, the day keel 3 are consistent with the structure of ground joist 4, are groove profile knot Structure.
As shown in Fig. 2, day keel 3 and ground joist 4 include pedestal 31, the first plugboard 32 and the second plugboard 33.
The pedestal 31 have first side and the second side for fixing on wall 6 or ground, first side and Second side is oppositely arranged.
First plugboard 32 and the second plugboard 33 are vertically disposed in first side, and described in three's composition Inserting groove.
By the way that day keel 3 and ground joist 4 are disposed as trench structure, the structure of day ground joist can be simplified, reduces weight, Facilitate installation.
Further, the pedestal 31 is hollow, further to reduce self weight.
Preferably, partition 34 is additionally provided with inside the pedestal 31.The partition 34 will be partitioned into first inside pedestal 31 Hollow area and the second hollow area.
By the way that partition 34 is arranged, the intensity of pedestal 31 can be increased.
It is highly preferred that partition 34 is vertical with two inner walls of pedestal respectively, to facilitate the setting of partition 34.
Preferably, as in Figure 2-4, the second hollow area offers through-hole on the side wall of the second plugboard 33, first Fastener is passed through by through-hole, is connect with leveling corner brace 8.
Further, it is provided with locating slot 35 on the side wall of the first plugboard 33 of the first hollow area direction, it is tight convenient for second The assembly of firmware.
As shown in figure 5, expansion bolt sequentially passes through locating slot 35, the first hollow area, second side, ground joist 4 is fixed On the ground.
Further, day keel 3 and ground joist 4 are aluminium alloy extrusions, further to reduce production cost.
Optionally, the second plugboard 33 installs keel 2 towards male part 36 is provided in the plate face of the first plugboard 34 Fixed plate on be provided with and be embedded in inner fovea part with the inner fovea part correspondingly of male part 36, male part 36, can not only increase peace The installation fastness of keel 2 prevents installation keel 2 from moving along its length, can also make to install keel 2 preferably in the world Sliding in keel.
As shown in Fig. 2, the quantity of male part 36 is at least three, the spacing between adjacent male part 36 is equal.
As shown in Figure 3-4, panel installation assembly further includes leveling corner brace 8 comprising transverse slat 81 and riser connected vertically 82。
The first waist-shaped hole 83 is provided on the transverse slat 81, the first waist-shaped hole 83 extends perpendicularly to riser 82.
The second waist-shaped hole 84 is provided on the riser 82, second waist-shaped hole 84 extends perpendicularly to transverse slat 81。
First fastener passes through the first waist-shaped hole 83 and fastens the pedestal of the day keel 3 and transverse slat 81, the second fastener Riser 82 is fixed on the wall across the second waist-shaped hole 84.
By adjusting the first fastener in the position of the first waist-shaped hole 83 and the second fastener in the position of the second waist-shaped hole 84 It sets, realizes the leveling of day keel 3, guarantee that the installation of panel 1 is smooth.In the present embodiment, the first fastener and the second fastener It is all made of bolt.
Preferably, as shown in fig. 6-7, the installation profile 10 includes substrate 101, the first buckle 102 and the second buckle 103。
First plate face of the substrate 101 is fitted on the panel 1, and in the present embodiment, substrate 101 is bonded in panel On 1, such as pass through VBH glue (Very High Bond, superelevation adhesion strength glue) bonding.
First buckle 102 and the second buckle 103 are vertically disposed on the opposite with the first plate face of the substrate 101 In the second plate face being arranged, and there is gap between two buckles.
First buckle 102 is provided with the first lug boss, the second buckle 103 back in the plate face of the second buckle 103 The second lug boss is provided in plate face from the first buckle 102, the installation profile 10 passes through the first lug boss and the second protrusion Portion and the clamping groove are clamped.
It is set as substrate 101, the first buckle 102 and the second buckle 103 by the way that profile 10 will be installed, installation profile can be simplified 10 structure reduces self weight, convenient for assembly.
Preferably, as shown in fig. 7, the installation keel 2 include fixed plate 21, the first snap-arms 22 and the second snap-arms 23, first snap-arms 22, the second snap-arms 23 and fixed plate 21 surround clamping groove.
The fixed plate 21 has inner plate surface and the outer plate surface for connecting with wall 6, the inner plate surface and outer plate surface phase To setting.
First snap-arms 22 include the first side plate 221 and first abuts plate 222, and second snap-arms 23 include the Two side plates 231 and second abut plate 232.
First side plate 221 abuts that plate 222 is vertical connect with inner plate surface and first respectively, and second side plate 231 divides Abut that plate 232 is vertical connect with inner plate surface and second.
It is coplanar that the first abutting plate 222 with second abuts plate 232, and positioned at the first side plate 221 and the second side plate 231 Between.
Described first abuts side of the plate 222 far from the first side plate 221 turns down towards the direction close to fixed plate 21, is formed First flange 223.
Described second abuts side of the plate 232 far from the second side plate 231 turns down towards the direction close to fixed plate 21, is formed Second flange 233.
First flange 223 and the second flange 233 are each perpendicular to inner plate surface, and first flange 223 is turned over towards second The first protruding portion is provided in the plate face on side 233.
Second flange 233 is towards being provided with the second protruding portion, the installation profile 10 in the plate face of the first flange 223 It is inserted into the clamping groove, is clamped by the first lug boss and the first protruding portion, the second lug boss and the second protruding portion.
Fixed plate 21, the first snap-arms 22 and the second snap-arms 23 are set as by the way that keel 2 will be installed, installation can be simplified The structure of keel 2 further mitigates self weight, facilitates installation.
Further, third protrusion portion 104 is provided on substrate 101, third protrusion portion 104 is resisted against the first abutting plate On 222.As shown in fig. 6, third protrusion portion 104 is semi-cylindrical hill.
After panel 1 installs, the frictional force of installation buckle 10 with installation keel 2 can be reduced, facilitate and moved down on panel 1 It is dynamic.Wherein, it is "upper" close to the direction of day keel 3, is "lower" close to the direction of ground joist 4.
Preferably, the quantity of the installation keel 2 is at least two, at least two installation keel 2 are arranged in parallel, can Increase the mounting stability of panel 1.
In the present embodiment, installation keel 2 are two, and two installation keel 2 are located on the opposite two sides of panel 1.
When assembly, first will wherein an installation keel 2 it be fixed on wall 6 by installing corner brace, then by the side of panel 1 It is mounted on the installation keel 2.
Then the position that keel 2 are installed according to the width adjusting of panel 1 another, is mounted on the peace for 1 other side of panel On keel 2, then by the installation keel 2 by install corner brace be fixed on wall 6.
Further, as illustrated in figures 1 and 8, panel installation assembly further include: supporting element 5.The supporting element 5 includes branch Support keel 52.
The support keel 52 between adjacent installation keel 2, distinguish by the both ends of 52 length direction of support keel It is plugged in the inserting groove of the day keel 3 and ground joist 4, the panel 1 is connected on the support keel 52.
By the way that support keel 52 is arranged, support force can be provided to panel 1, preferably to fix panel 1.
Preferably, supporting element 5 further includes buffer layer 51, and the buffer layer 51 is fitted on support keel 52.Pass through setting Buffer layer 51 can avoid panel 1 and collide with support keel 52, and protection panels 1 are not damaged.
In a preferred embodiment of invention, buffer layer 51 uses single card foam, to reduce cost.
Optionally, support keel 52 is hollow, to reduce self weight.
Further, support keel 52 perpendicular to length direction section be it is rectangular, with facilitate processing.
Preferably, as shown in Figure 10, panel installation assembly further includes installation corner brace 9, and installation corner brace 9 includes connected vertically Vertical plate 91 and level board 92 are provided with strip-shaped hole 93 on level board 92, and strip-shaped hole 93 extends perpendicularly to vertical plate 91. Multiple first mounting holes 94 are provided on level board 92.
The first mounting hole 94 is passed through by third fastener to fasten the first side plate for installing keel 2 with vertical plate 91, the Four fasteners pass through strip-shaped hole 93 and are fixed on wall 6.
Wherein, screw can be used in third fastener.Expansion bolt can be used in 4th fastener.
Corner brace 9 is installed by setting, on the one hand can increase the installation fastness of installation keel 2, on the other hand, strip-shaped hole Setting, can reduce the requirement to expansion bolt hole location accuracy, allow the hole location of expansion bolt that certain deviation occurs, avoid repeating Punching.
In a preferred embodiment of invention, strip-shaped hole 93 is waist-shaped hole, to facilitate processing and assembly.
In the embodiment in figure 10, there are three the first mounting holes 94 for setting on vertical plate 91, and three the first mounting holes 94 are not Collinearly, i.e., the hole heart of three the first mounting holes 94 is concyclic, and third fastener passes through the first mounting hole 94 for the first side plate and vertical Plate 91 connects, and can further guarantee the installation fastness for installing keel 2.
Further, the first mounting hole 94 centrally located in three the first mounting holes 94 is waist-shaped hole, in addition two A first mounting hole 94 is round hole.Waist-shaped hole is set by one of them first mounting hole 94, the reality for installing corner brace 9 can be made The function of now leveling corner brace 8 facilitates leveling installation keel 2.
Preferably, the second mounting hole 95 connecting with wall 6 is additionally provided on level board 92, with increase installation corner brace 9 with The installation fastness of wall 6.
Further, the third mounting hole connecting with wall 6, third mounting hole and the second peace are additionally provided on level board 92 Dress hole 95 is symmetricly set on the two sides of strip-shaped hole 93.It not only can further increase firmly installing for installation corner brace 9 and wall 6 Property, it can also facilitate the processing of third mounting hole and the second mounting hole 95, reduce cost.
As shown in Figure 10, third mounting hole and the second mounting hole 95 are round hole, to facilitate processing.
Further, the level board 92 is rectangular slab, and two corners of the rectangular slab far from 92 side of vertical plate are equal It is arranged to chamfering, such as 45 ° of chamferings, 60 ° of chamferings, when to avoid assembly, corner is sharply hurted sb.'s feelings, and is improved operation and is installed coefficient.
Similarly, the vertical plate 91 is rectangular slab, and two corners of the rectangular slab far from 92 side of level board are also equal It is arranged to chamfering.
Further, the installation keel further include the first support arm 25 and the second support arm 24,25 He of the first support arm The clamping groove is divided into the first subcard access slot and the second subcard access slot by the second support arm 24.
First support arm 25 includes the first support plate 251 and the first mounting plate 252, and first support plate 251 is divided Not with the first mounting plate 252 and inner plate surface is vertical connect, first mounting plate 252 is located at the first side plate 221 and the first support Between plate 251, and it is coplanar with first to abut plate 222.
Side of first mounting plate 252 far from the first support plate 251 is turned down towards the direction close to fixed plate 21, Form third flange 253, the third flange 253 is towards being provided with third protruding portion in the plate face of the first flange 223.
The installation profile 10 is inserted into the first subcard access slot, by the first lug boss and the first protruding portion, second convex The portion of rising and the clamping of third protruding portion.
Second support arm 24 includes the second support plate 241 and the second mounting plate 242, and second support plate 241 is divided Not with the second mounting plate 242 and inner plate surface is vertical connect, second mounting plate 242 is located at the second side plate 231 and the second support Between plate 241, and it is coplanar with second to abut plate 232.
Side of second mounting plate 242 far from the second support plate 241 is turned down towards the direction close to fixed plate 21, Form the 4th flange 243.
4th flange 243 is towards being provided with the 4th protruding portion, the installation profile 10 in the plate face of the second flange 233 It is inserted into the second subcard access slot, is clamped by the first lug boss and the 4th protruding portion, the second lug boss and the second protruding portion.
Caulking strip 11 is embedded between first support plate 251 and the second support plate 241.
By the first support arm 25 of setting and the second support arm 24, clamping groove is divided into the first subcard access slot and the second subcard Adjacent panels 1 can be mounted on the same installation keel 2, the equipment for reducing component by access slot, reduce cost, improve assembly effect Rate;Moreover, being embedded with caulking strip 11 in gap between the first support plate 251 and the second support plate 241, decoration effect can be improved Fruit.
Optionally, the first abutting plate 222 abuts plate 232 and the second flange with the junction of the first flange 223, second 233, third flange 253 and junction, the junction of the 4th flange 243 and the second mounting plate 242 of the first mounting plate 252 are equal Chamfered is done, to increase the width of the first subcard access slot and the second clamping groove entrance, facilitates the insertion of installation buckle 10.
Preferably, as Figure 7-8, panel installation assembly further includes leveling part 7, and the leveling part 7 includes leveling board 71 With rivet nut 72.
There is the leveling board 71 front and the back side for abutting with wall 6, the front to be oppositely arranged with the back side, institute It states rivet nut 72 to be vertically set on front, there is screw hole, the rivet nut 72 and screw hole spiral shell on the installation keel 2 It connects.
By spinning in and out of the rivet nut 72 in screw hole, adjusts leveling board 71 and the spacing of keel 2 is installed, with reality The leveling of keel 2 is now installed.
After day keel 3 and ground joist 4 complete leveling, installation keel 2 can not have to leveling, only need to be by leveling board 71 and wall 6 fittings.
As shown in figure 8, bearing keel 5 is towards being also equipped with screw hole, rivet nut 72 and the screw hole spiral shell on the side of wall 6 It connects.The leveling board 71 connecting with bearing keel 5 is plastic material, is fixed on wall 6 by air gun nail.
As shown in figure 9, caulking strip 11 includes ontology 111, clamping plate 112, the first plate 113 and the second plate 114.
The ontology 111 has fitting surface and the decorative cover for decoration, and the clamping plate 112 is vertically set on fitting surface On, the clamping plate 112 has the first clamping plate face and second clamping plate face being oppositely arranged.
First plate 113 is vertically set on the first clamping plate face, and second plate 114 is vertically set on On second clamping plate face, the fitting surface of first plate 113 and ontology 111 forms the first slot, second plate 114 and sheet The fitting surface of body 111 forms the second slot.
Grafting item portion, grafting item point are provided in first support plate 251, two plate faces opposite with the second support plate 241 It is not embedded in the first slot and the second slot, to increase the installation fastness of caulking strip 11.
Further, caulking strip 11 further includes third plate 115, and the third plate 115 is vertically set on first clamping plate On face, the first plate 113 is between third plate 115 and ontology 111.
By the way that third plate 115 is arranged, third plate 115 is clipped between clamping plate 112 and the second support plate 241, it is possible to increase The frictional force of ontology 111 and the second support plate 241 further increases the installation fastness of caulking strip 11.
Similarly, caulking strip 11 further includes the 4th plate 116, and the 4th plate 115 is vertically set on second clamping plate face On, the second plate 114 is between the 4th plate 116 and ontology 111.
Optionally, the first plate 113, the second plate 114, third plate 115 and the 4th plate 116 are perpendicular to length side To section be right-angled trapezium, with facilitate processing.
Preferably, the first plate 113, the second plate 114, third plate 115 and the 4th plate 116 are towards ontology 11 Plate face further facilitates processing each parallel to fitting surface.
Further, the first plate 113 and the second plate 114, third plate 115 and the 4th plate 116 are about clamping plate 112 is symmetrical, can further facilitate processing.
Optionally, the first plate 113, the second plate 114, third plate 115 and the 4th plate 116 protrude from ontology 111, to be preferably embedded between the first support plate 251 and the second support plate 241.
Further, the ontology 111 is rectangular slab, and the two sides edge of rectangular slab length direction is provided with recessed portion 117, recessed portion 117 respectively with the junction of the first support plate 251 and the first mounting plate 252, the second support plate 241 and second The junction of mounting plate 242 cooperates, to improve finishing effect.
Optionally, caulking strip 11 is integrally formed, and further reduces production cost.
Further, the material of caulking strip 11 is soft-hard coextrusion PVC (polyvinyl chloride, Polyvinyl chloride) material Material, further reduces production cost.
Based on above-mentioned panel installation assembly, as shown in figure 11, the embodiment of the present invention also provides a kind of panel installation techniques, Include:
By sky dragon bone fixation on wall;
Ground joist is fixed on the ground;
The both ends for installing keel are plugged on respectively in the inserting groove of day keel and ground joist;
Installation profile is mounted on panel;
Profile will be installed to be connected in the clamping groove of the installation keel.
Panel installation techniques provided in an embodiment of the present invention pass through setting installation profile, installation keel, day keel and pheretima Bone, installation keel are fixed on the wall by day ground joist, and panel is connected in the clamping groove of installation keel by installing profile, Integral installation uses drying hair operation, and all components can be produced in factory industry metaplasia, and scene carries out assembled installation, can save significantly The about set-up time improves installation effectiveness, while can greatly facilitate the replacement of panel, is convenient for later period maintenance, improves maintenance efficiency.
More than, technical solution of the present invention is described in detail in conjunction with specific embodiments, described specific implementation Example is used to help understand thought of the invention.The derivation that those skilled in the art make on the basis of the specific embodiment of the invention It is also belonged within the scope of the present invention with modification.

Claims (10)

1. a kind of panel installation assembly characterized by comprising installation keel, are used the installation profile for being mounted on panel It is provided on the day keel being fixed on the wall and ground joist for fixing on the ground, the day keel and ground joist The both ends of inserting groove, the installation keel length direction are plugged on respectively in the inserting groove of the day keel and ground joist, described Clamping groove is provided on installation keel, the installation profile and the clamping groove are clamped.
2. panel installation assembly as described in claim 1, which is characterized in that the day keel and ground joist include pedestal, First plugboard and the second plugboard, the pedestal have first side and second side for fixing, first side and the Two side faces are oppositely arranged, and first plugboard and the second plugboard are vertically disposed in first side, and three is constituted The inserting groove.
3. panel installation assembly as claimed in claim 2, which is characterized in that further include leveling corner brace comprising vertical connection Transverse slat and riser, be provided with the first waist-shaped hole on the transverse slat, the first waist-shaped hole extends perpendicularly to riser, described perpendicular The second waist-shaped hole is provided on plate, second waist-shaped hole extends perpendicularly to transverse slat, and the first fastener passes through the first waist Type hole fastens the pedestal of the day keel and transverse slat, and the second fastener passes through the second waist-shaped hole and is fixed on the wall riser.
4. panel installation assembly as described in claim 1, which is characterized in that the installation profile includes substrate, the first buckle With the second buckle, on the panel, first buckle and the second buckle are respectively perpendicular for the first plate face fitting of the substrate It is arranged in the second plate face of the substrate being oppositely arranged with the first plate face, and there is gap between two buckles, described the One buckle is provided with the first lug boss in the plate face of the second buckle, and second buckle is set in the plate face of the first buckle It is equipped with the second lug boss, the installation profile is clamped by the first lug boss and the second lug boss and the clamping groove.
5. panel installation assembly as claimed in claim 4, which is characterized in that the installation keel include fixed plate, the first card Arm and the second snap-arms are connect, first snap-arms, the second snap-arms and fixed plate surround clamping groove, and the fixed plate has interior Plate face and for the outer plate surface with wall connecting, the inner plate surface and outer plate surface are oppositely arranged, and first snap-arms include the Side plate and first abut plate, second snap-arms include the second side plate and second abut plate, first side plate respectively with Inner plate surface and the first abutting plate vertically connect, and second side plate abuts that plate is vertical connect with inner plate surface and second respectively, described It is coplanar that first abutting plate with second abuts plate, and between the first side plate and the second side plate, and the first abutting plate is far from the The side of side plate is turned down towards the direction close to fixed plate, forms the first flange, and described second abuts plate far from the second side plate Side turned down towards the direction close to fixed plate, form the second flange, first flange and the second flange are each perpendicular to interior Plate face, towards the first protruding portion is provided in the plate face of the second flange, second flange is turned over towards first for first flange The second protruding portion is provided in the plate face on side, the installation profile is inserted into the clamping groove, prominent by the first lug boss and first Portion, the second lug boss and the clamping of the second protruding portion out.
6. panel installation assembly as claimed in claim 5, which is characterized in that the quantity of the installation keel is at least two, At least two installation keel are arranged in parallel.
7. panel installation assembly as claimed in claim 6, which is characterized in that further include: supporting element, the supporting element include using In the support keel abutted with panel, the support keel is between adjacent installation keel, the support keel length direction Both ends be plugged in the inserting groove of the day keel and ground joist respectively.
8. panel installation assembly as claimed in claim 6, which is characterized in that the installation keel further include the first support arm and The clamping groove is divided into the first subcard access slot and the second subcard access slot by the second support arm, the first support arm and the second support arm, First support arm include the first support plate and the first mounting plate, first support plate respectively with the first mounting plate and inner panel Face vertically connects, and first mounting plate is between the first side plate and the first support plate, and it is coplanar with first to abut plate, described Side of first mounting plate far from the first support plate is turned down towards the direction close to fixed plate, forms third flange, the third It is provided with third protruding portion in the plate face of flange the first flange of direction, the installation profile is inserted into the first subcard access slot, leads to Cross the first lug boss and the first protruding portion, the second lug boss and the clamping of third protruding portion;Second support arm includes second Fagging and the second mounting plate, second support plate is vertical with the second mounting plate and inner plate surface respectively to be connect, second installation Plate is between the second side plate and the second support plate, and it is coplanar with second to abut plate, and second mounting plate is far from the second support The side of plate is turned down towards the direction close to fixed plate, forms the 4th flange, plate face of the 4th flange towards the second flange On be provided with the 4th protruding portion, the installation profile is inserted into the second subcard access slot, passes through the first lug boss and the 4th prominent Portion, the second lug boss and the clamping of the second protruding portion, are embedded with caulking strip between first support plate and the second support plate.
9. panel installation assembly a method as claimed in any one of claims 1-8, which is characterized in that further include leveling part, the leveling part Including leveling board and rivet nut, the leveling board has front and the back side for abutting with wall, the front and the back side It is oppositely arranged, the rivet nut is vertically set on front, has screw hole, the rivet nut and spiral shell on the installation keel Hole is spirally connected.
10. a kind of panel installation techniques based on any panel installation assembly of claim 1-9, which is characterized in that packet It includes:
By sky dragon bone fixation on wall;
Ground joist is fixed on the ground;
The both ends for installing keel are plugged on respectively in the inserting groove of day keel and ground joist;
Installation profile is mounted on panel;
Profile will be installed to be connected in the clamping groove of the installation keel.
CN201811558117.6A 2018-12-19 2018-12-19 Panel mounting assembly and method Active CN109610768B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811558117.6A CN109610768B (en) 2018-12-19 2018-12-19 Panel mounting assembly and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811558117.6A CN109610768B (en) 2018-12-19 2018-12-19 Panel mounting assembly and method

Publications (2)

Publication Number Publication Date
CN109610768A true CN109610768A (en) 2019-04-12
CN109610768B CN109610768B (en) 2024-05-28

Family

ID=66009750

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811558117.6A Active CN109610768B (en) 2018-12-19 2018-12-19 Panel mounting assembly and method

Country Status (1)

Country Link
CN (1) CN109610768B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111255184A (en) * 2019-06-19 2020-06-09 谢顺宗 Wall hanging structure
CN114856114A (en) * 2022-04-19 2022-08-05 北新集团建材股份有限公司 Keel assembly and device plate assembly
CN114856116A (en) * 2022-04-19 2022-08-05 北新集团建材股份有限公司 Leveling structure, decorative board mounting structure and subassembly

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN206844398U (en) * 2017-04-11 2018-01-05 上海旭博建筑装饰工程有限公司 Light steel keel partition backbone attachment structure
CN207846776U (en) * 2017-12-29 2018-09-11 南京富海装饰工程有限公司 A kind of ruggedized construction of light steel keel partition
CN108842982A (en) * 2018-07-31 2018-11-20 浙江亚厦装饰股份有限公司 The levelling assembly of metope and installation method
CN211396412U (en) * 2018-12-19 2020-09-01 浙江亚厦装饰股份有限公司 Panel mounting assembly

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN206844398U (en) * 2017-04-11 2018-01-05 上海旭博建筑装饰工程有限公司 Light steel keel partition backbone attachment structure
CN207846776U (en) * 2017-12-29 2018-09-11 南京富海装饰工程有限公司 A kind of ruggedized construction of light steel keel partition
CN108842982A (en) * 2018-07-31 2018-11-20 浙江亚厦装饰股份有限公司 The levelling assembly of metope and installation method
CN211396412U (en) * 2018-12-19 2020-09-01 浙江亚厦装饰股份有限公司 Panel mounting assembly

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111255184A (en) * 2019-06-19 2020-06-09 谢顺宗 Wall hanging structure
CN114856114A (en) * 2022-04-19 2022-08-05 北新集团建材股份有限公司 Keel assembly and device plate assembly
CN114856116A (en) * 2022-04-19 2022-08-05 北新集团建材股份有限公司 Leveling structure, decorative board mounting structure and subassembly
CN114856114B (en) * 2022-04-19 2023-11-10 北新集团建材股份有限公司 Keel assembly and device plate assembly
CN114856116B (en) * 2022-04-19 2024-04-09 北新集团建材股份有限公司 Leveling structure, decorative board mounting structure and assembly

Also Published As

Publication number Publication date
CN109610768B (en) 2024-05-28

Similar Documents

Publication Publication Date Title
CN109610768A (en) Panel installation assembly and method
US20080066407A1 (en) Panel Installation Set and Method of Installing Panel Using the Same
US3308590A (en) Removable panel fastener
SE1150116A1 (en) Edge strip for wall panel mounting
CN112554385A (en) Internal corner structure of toilet
WO2021097862A1 (en) Wall panel mounting structure
CN110158921A (en) Car coat type closing in skirting component and its installation method
CN105133761A (en) Invisible glass curtain wall and mounting method thereof
CN211396412U (en) Panel mounting assembly
CN114622694A (en) Wall surface leveling mechanism and mounting method thereof
CN112554372A (en) Bathroom shingle assembly
CN210918054U (en) Wallboard interval lines that can assemble
CN211396411U (en) Ceiling keel and panel installation assembly
CN201746955U (en) Aluminium profile component of steel-aluminium structural curtain wall
CN110158904A (en) Metope installation levelling component and its installation method
CN206428997U (en) Container-type flowing fast food room
CN211341552U (en) Leveling supporting component and panel installation assembly
CN215888693U (en) Bathroom shingle assembly
CN217998730U (en) Mounting structure special for calcium silicate decorative plate
CN211899403U (en) Installation corner connector and panel installation assembly
CN211396413U (en) Panel supporting device and panel installation assembly
CA2795942C (en) Construction technique for attaching finishing elements and building structure resulting therefrom
US7832164B2 (en) Concealed reinforcement member and joint reinforcement system for trim molding
CN210622196U (en) Connecting piece and mounting structure with same
CN211647772U (en) Assembled curtain wall window system and building curtain wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant