CN109610495A - Close to the pile base construction method of Shield-bored tunnels - Google Patents

Close to the pile base construction method of Shield-bored tunnels Download PDF

Info

Publication number
CN109610495A
CN109610495A CN201811508159.9A CN201811508159A CN109610495A CN 109610495 A CN109610495 A CN 109610495A CN 201811508159 A CN201811508159 A CN 201811508159A CN 109610495 A CN109610495 A CN 109610495A
Authority
CN
China
Prior art keywords
steel bushing
conduit
close
steel
reinforcement cage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811508159.9A
Other languages
Chinese (zh)
Inventor
王珂
王立峰
孟胜宾
俞钦钦
陈巧红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Lover Health Science and Technology Development Co Ltd
Zhejiang University of Science and Technology ZUST
Original Assignee
Zhejiang Lover Health Science and Technology Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Lover Health Science and Technology Development Co Ltd filed Critical Zhejiang Lover Health Science and Technology Development Co Ltd
Priority to CN201811508159.9A priority Critical patent/CN109610495A/en
Publication of CN109610495A publication Critical patent/CN109610495A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a kind of pile base construction method of close Shield-bored tunnels, include the following steps: that S1, smooth location, convolution cutter are in place;S2, steel bushing is lifted into scheduled position, is directed at the hole location close to Shield-bored tunnels;S3, steel bushing is pressed into one section of depth of soil layer in a manner of static pressure with convolution cutter;S4, the soil body is cut with convolution cutter, fills the water, the mud in steel bushing in one section of depth is gone out, and be transported to ground with slush pump when cutting is close to 50-60cm depth;S5, step S3 and step S4 is repeated, until steel bushing is reached scheduled depth, forms stake holes;S6, steel reinforcement cage is hung, inserts it into steel bushing and be located at center, the height of the height of steel reinforcement cage close to steel bushing;S7, conduit is hung, be inserted into steel reinforcement cage;S8, concrete pour at the top of conduit, and the bottom of steel bushing and steel reinforcement cage is flowed to from conduit bottom.The present invention has method beneficial effect that is simple, at low cost, easy for construction, preventing Shield-bored tunnels deformation.

Description

Close to the pile base construction method of Shield-bored tunnels
Technical field
The present invention relates to a kind of pile base construction methods of close Shield-bored tunnels.
Background technique
21 century is the century that people develop the underground space, and city space can not be expanded without limitation, and Urban Underground is empty Between be constantly exploited, city tunnel and underground engineering are to deeper spatial spread.
With the development of China's metro construction cause, more and more subway line engineerings build investment.In subway In engineering, the deep foundation that pile foundation is big as a kind of intensity, bearing capacity is high, durability is good is used widely.Traditional pile foundation is applied Work is increased to the head (jump bit) that is redrilled with sword centainly frequently with percussive drilling, using percussive drill by rack, hoist engine Highly, soil layer and cutting broken rock drilling are impacted by the impact force of free-falling, the scope of application is wider, but work progress In, hammering can generate loud noise and vibration, have large effect that need to consider soil compaction effect the periphery soil body.On tunnel underground edge Line, website carry out pile foundation construction can section of jurisdiction to shield tunnel construction and track have an impact, and subway is operated normally to deformation There are strict requirements.Therefore influence of the pile foundation construction to neighbour's tunnel structure is reduced, neighbour's tunnel subsidence and horizontal distortion are controlled Engineering measure, guarantee the safety of tunnel and surrounding building, become urgent need to solve the problem in engineering construction.
Summary of the invention
According to the above deficiency, providing the pile base construction method close to Shield-bored tunnels, this method can solve the present invention The problems such as sedimentation of prior art pile foundation surrounding ground, the displacement of tunnel structure.
The technical scheme is that
A kind of pile base construction method of close Shield-bored tunnels, includes the following steps:
S1 smooth location, convolution cutter are in place;
Steel bushing is lifted into scheduled position by S2, is directed at the hole location close to Shield-bored tunnels;
Steel bushing is pressed into one section of depth of soil layer with convolution cutter by S3 in a manner of static pressure;
S4 cuts the soil body with convolution cutter, fills the water when cutting is close to 50-60cm depth, will be in steel bushing in one section of depth Mud go out, and be transported to ground with slush pump;
S5 repeats step S3 and step S4, until steel bushing is reached scheduled depth, forms stake holes;
S6 hangs steel reinforcement cage, inserts it into steel bushing and be located at center, the height of the height of steel reinforcement cage close to steel bushing;
S7 hangs conduit, is inserted into steel reinforcement cage, and the bottom of conduit is close but does not touch the bottom of steel bushing and steel reinforcement cage;
S8 concrete pours at the top of the conduit, flows to the bottom of steel bushing and steel reinforcement cage from conduit bottom, in casting process Conduit is drawn high when pouring, and the depth for ensuring conduit Transducers Embedded in Concrete during drawing high waits for coagulation quietly close to 2-6m after the completion of pouring Soil solidification forms pile foundation.
It can reduce when steel bushing pushes due to being provided with steel bushing to periphery soil body generation stress and soil compaction phenomenon, steel bushing Interior undisturbed takes soil, and rock drilling without friction can obviously reduce to steel bushing externalities;
It is filled the water into stake holes, so that the hydraulic balance inside and outside steel bushing.After steel bushing complete penetration artesian aquifer, then covered For artesian aquifer part soil excavation to prevent stratum dehydration, hole wall from collapsing, hole quality is high in managing.
In the step S8, during waiting for quietly, when mixed mud reaches the intensity of 20%-30%, steel bushing is extracted.It needs to illustrate , comprehensively considered according to soil layer construction, cost, steel bushing can not be extracted.
The conduit uses preceding carry out closed-water test, it is ensured that the tube wall of conduit is water-tight.
In the step 8, when side filling concrete edge draws high conduit and steel bushing, the bottom of steel bushing will be consistently lower than conduit Bottom.
In the step 7, the distance from bottom steel bushing of conduit and 30~40cm of bottom of steel reinforcement cage.
The present invention has method beneficial effect that is simple, at low cost, easy for construction, preventing Shield-bored tunnels deformation.
Detailed description of the invention
Fig. 1 is overall structure diagram of the invention.
Specific embodiment
Now in conjunction with attached drawing, the present invention is further illustrated:
As shown in Figure 1, a kind of pile base construction method of close Shield-bored tunnels, includes the following steps:
S1 smooth location, convolution cutter are in place;
Steel bushing 2 is lifted into scheduled position by S2, is directed at the hole location close to Shield-bored tunnels;
Steel bushing 2 is pressed into one section of depth of soil layer with convolution cutter by S3 in a manner of static pressure;
S4 cuts the soil body with convolution cutter, fills the water when cutting is close to 50-60cm depth, by one section of depth in steel bushing 2 Interior mud is gone out, and is transported to ground with slush pump;
S5 repeats step S3 and step S4, until steel bushing is reached scheduled depth, forms stake holes;
S6 hangs steel reinforcement cage 3, inserts it into steel bushing 2 and be located at center, the height of the height of steel reinforcement cage 3 close to steel bushing 2 Degree;
S7 hangs conduit 1, is inserted into steel reinforcement cage 3, and the bottom of conduit 1 is close but does not touch steel bushing 2 and steel reinforcement cage 3 Bottom;The distance from bottom steel bushing 2 of conduit 1 and 30~40cm of bottom of steel reinforcement cage 3;
S8 concrete pours at the top of conduit 1, and the bottom of steel bushing 2 and steel reinforcement cage 3 is flowed to from 1 bottom of conduit, was poured Conduit 1 is drawn high when pouring in journey, and the depth for ensuring 1 Transducers Embedded in Concrete of conduit during drawing high is quiet after the completion of pouring close to 2-6m Pile foundation is formed to concrete setting.
In step S8, during waiting for quietly, when mixed mud reaches the intensity of 20%-30%, steel bushing 2 is extracted;Side fills concrete While the bottom of steel bushing 2 will be consistently lower than the bottom of conduit 1 when drawing high conduit 1 and steel bushing 2.
Conduit 1 uses preceding carry out closed-water test, it is ensured that the tube wall of conduit 1 is water-tight.

Claims (5)

1. a kind of pile base construction method of close Shield-bored tunnels, characterized in that include the following steps:
S1 smooth location, convolution cutter are in place;
Steel bushing is lifted into scheduled position by S2, is directed at the hole location close to Shield-bored tunnels;
Steel bushing is pressed into one section of depth of soil layer with convolution cutter by S3 in a manner of static pressure;
S4 cuts the soil body with convolution cutter, fills the water when cutting is close to 50-60cm depth, will be in steel bushing in one section of depth Mud go out, and be transported to ground with slush pump;
S5 repeats step S3 and step S4, until steel bushing is reached scheduled depth, forms stake holes;
S6 hangs steel reinforcement cage, inserts it into steel bushing and be located at center, the height of the height of steel reinforcement cage close to steel bushing;
S7 hangs conduit, is inserted into steel reinforcement cage, and the bottom of conduit is close but does not touch the bottom of steel bushing and steel reinforcement cage;
S8 concrete pours at the top of the conduit, flows to the bottom of steel bushing and steel reinforcement cage from conduit bottom, in casting process Conduit is drawn high when pouring, and the depth for ensuring conduit Transducers Embedded in Concrete during drawing high waits for coagulation quietly close to 2-6m after the completion of pouring Soil solidification forms pile foundation.
2. a kind of pile base construction method of close Shield-bored tunnels as described in claim 1, characterized in that in step S8, During waiting for quietly, when mixed mud reaches the intensity of 20%-30%, steel bushing is extracted.
3. a kind of pile base construction method of close Shield-bored tunnels as described in claim 1, characterized in that the conduit makes With preceding carrying out closed-water test, it is ensured that the tube wall of conduit is water-tight.
4. a kind of pile base construction method of close Shield-bored tunnels as described in claim 1, characterized in that the step 8 In, when side filling concrete edge draws high conduit and steel bushing, the bottom of steel bushing will be consistently lower than the bottom of conduit.
5. a kind of pile base construction method of close Shield-bored tunnels as described in claim 1, characterized in that the step 7 In, the distance from bottom steel bushing of conduit and 30~40cm of bottom of steel reinforcement cage.
CN201811508159.9A 2018-12-11 2018-12-11 Close to the pile base construction method of Shield-bored tunnels Pending CN109610495A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811508159.9A CN109610495A (en) 2018-12-11 2018-12-11 Close to the pile base construction method of Shield-bored tunnels

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811508159.9A CN109610495A (en) 2018-12-11 2018-12-11 Close to the pile base construction method of Shield-bored tunnels

Publications (1)

Publication Number Publication Date
CN109610495A true CN109610495A (en) 2019-04-12

Family

ID=66006969

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811508159.9A Pending CN109610495A (en) 2018-12-11 2018-12-11 Close to the pile base construction method of Shield-bored tunnels

Country Status (1)

Country Link
CN (1) CN109610495A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102926409A (en) * 2011-08-09 2013-02-13 上海建工五建集团有限公司 Construction method for preventing water and soil loss
CN104110028A (en) * 2014-07-07 2014-10-22 河北省水利工程局 Grouting pile construction method for dry operation drilling and waterless pouring of concrete
JP2016089404A (en) * 2014-10-31 2016-05-23 大成建設株式会社 Grout method for cast-in-place concrete pile
CN108130904A (en) * 2017-12-25 2018-06-08 浙江大学城市学院 A kind of construction method of the composite bushing drill-pouring pilework of neighbouring existing subway

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102926409A (en) * 2011-08-09 2013-02-13 上海建工五建集团有限公司 Construction method for preventing water and soil loss
CN104110028A (en) * 2014-07-07 2014-10-22 河北省水利工程局 Grouting pile construction method for dry operation drilling and waterless pouring of concrete
JP2016089404A (en) * 2014-10-31 2016-05-23 大成建設株式会社 Grout method for cast-in-place concrete pile
CN108130904A (en) * 2017-12-25 2018-06-08 浙江大学城市学院 A kind of construction method of the composite bushing drill-pouring pilework of neighbouring existing subway

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
叶新平等: "《土木建筑工程施工工艺标准》", 31 July 2006, 国防科技大学出版社 *
沈保汉等: "捷程(MZ)系列全套管钻机喀斯特地层嵌岩灌注桩施工工法", 《工程机械与维修》 *
闫庆生: "桥梁桩基临近既有地铁线施工技术研究", 《铁道建筑技术》 *
陈林等: "全护筒桩基施工方法在临近构筑物桩基施工中的应用", 《市政技术》 *

Similar Documents

Publication Publication Date Title
CN101139838B (en) Construction method for high artesian area ultra-deep foundation pit
US20210348355A1 (en) Grouting consolidation method for full casing borehole guide prefabricated pile and prefabricated pile therefor
CN105275381B (en) Impact drill drilling construction method in rich water pebble layer
CN105569560B (en) A full set of tubular type long auger stake machine and the method for utilizing the ram machine construction
CN105155516B (en) The method of construction drill bored concrete pile before making an overall screening underground obstacle
CN108166483A (en) Bored pile construction method
CN106545007A (en) The method of pile in stratum of the bottom for hard rock stratum
CN103321244A (en) Construction method for additionally arranged basement in existing building on sand foundation
CN107905236A (en) The construction method of friction pile churning driven fast pore-creating and concrete placings
CN111236216A (en) Construction method of bridge drilled pile
CN105464105B (en) One kind is without friction pile pile making method
CN106677166A (en) Flow construction method for forming cast-in-place bored pile for gravel-decomposed rock stratum in double-machine combined mode
CN110158579A (en) A kind of bored pile construction method
CN111594041A (en) Rapid hole forming construction method for large-diameter deep hole pile foundation under karst geology
CN205382483U (en) Drilling bored concrete pile drilling equipment in deep water sand boulder bed riverbed
CN105862862B (en) A kind of large diameter pile buries hammer Refloatation method
CN104975734B (en) Casting machine casing installation method
CN100523389C (en) Ballastless track steel reinforced concrete pile-net construction method
CN204401612U (en) A kind of super-large diameter all steel casing does operation pore-creating filling pile construction equipment
CN110080779A (en) Tunnel tunnel bottom karst cave treatment construction method
CN107542092A (en) High efficiency honeycomb method broken pile head construction technology
CN207109804U (en) A kind of quick spreading structure configuration of soft soil foundation bored concrete pile
CN109944238A (en) Pile construction method is rammed in full-sleeve full-rotation
CN106498951B (en) A kind of shaft excavation construction method
CN103821137A (en) Construction method and device for long auger drilling, rock embedding, bottom expanding and press-casting pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190412

WD01 Invention patent application deemed withdrawn after publication