CN109610449A - 大直径桥桩断桩的施工方法 - Google Patents
大直径桥桩断桩的施工方法 Download PDFInfo
- Publication number
- CN109610449A CN109610449A CN201811508555.1A CN201811508555A CN109610449A CN 109610449 A CN109610449 A CN 109610449A CN 201811508555 A CN201811508555 A CN 201811508555A CN 109610449 A CN109610449 A CN 109610449A
- Authority
- CN
- China
- Prior art keywords
- concrete
- steel pipe
- broken
- stake holes
- level
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/64—Repairing piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
本发明公开了一种大直径桥桩断桩的施工方法,包括如下步骤:S1、在断桩的桩孔内插入新导管,新导管的底部接近首次浇注的混凝土断层面;S2、插入多根钢管到桩孔内,均匀分布,钢管的底孔用混凝土塞密封,钢管内充满泥浆,钢管的底部接近混凝土断层面;S3、从新导管内灌装混凝土到桩孔内,边灌边拉升,直至将再次浇注的混凝土灌装到桩孔顶部;S4、钻芯机的采样管插入钢管内,冲破混凝土塞进入混凝土断层面进行取样;S5、插入注浆机的注浆管到钢管内接近混凝土断层面,对混凝土断层面用泥浆进行高压旋喷清洗;S6、从钢管内灌装混凝土。本发明具有方法简单、成本低、施工质量好、施工时间短的有益效果。
Description
技术领域
本发明涉及一种大直径桥桩断桩的施工方法。
背景技术
现价段我国基础建设不断发展,大型桥梁在各地区不断兴建,大型桥梁建造过程中地下基础中桩的成桩过程尤为重要,当桩的成桩过程中出现问题这是非常严重的,这些问题需要慎重解决。成桩过程中经常出现断桩,以前的处理方法:一是跟设计或检测商量扩大上部直径,以满足承载力要求;二是采用旋喷桩处理,采用这两种方法会出现以下问题:
第一种方法会让设计院花费更多时间来重新设计,让检测单位重新选择测量位置,这花费了大量时间,延误了工期。
第二种方法会花费大量人力物力,如果原来的地下本来就是坚硬土层,再用旋喷桩就要慎重了。
发明内容
本发明根据以上不足,提供了一种大直径桥桩断桩的施工方法,可以继续使用底部的断桩,保持它的性能,保证施工顺利进行。
本发明的技术方案是:
一种大直径桥桩断桩的施工方法,其特征是,包括如下步骤:
S1 在断桩的桩孔内插入新导管,新导管的底部接近首次浇注的混凝土断层面;
S2 插入多根钢管到桩孔内,均匀分布,钢管的底孔用混凝土塞密封,钢管内充满泥浆,钢管的底部接近混凝土断层面;
S3 从新导管内灌装混凝土到桩孔内,边灌边拉升,直至将再次浇注的混凝土灌装到桩孔顶部;
S4 钻芯机的采样管插入钢管内,冲破混凝土塞进入混凝土断层面进行取样,检验样品成分;根据取样获得混凝土断层位置、含量等信息,方便后续施工提供依据;
S5 插入注浆机的注浆管到钢管内接近混凝土断层面,对混凝土断层面用泥浆进行高压旋喷清洗,并将部分混凝土经本身或其它的钢管输送到桩孔外,混凝土断层面形成多个高压旋喷清洗形成的凹腔;
S6 从钢管内灌装混凝土,该混凝土填满该凹腔和钢管;
S7 静置等待混凝土凝固。
所述桩孔直径接近2.5m,所述钢管的数量为6根,中间放置1根钢管,接近桩孔周边放置5根钢管。
所述泥浆的粘度为18~23s、 密度为1.06~1.10g/cm3、含砂率为0.5%。
所述步骤S6中的混凝土,其水泥的等级比浇注的混凝土高一级。
采用“高压旋喷切割、优质泥浆清孔、高强度等级水泥浆置换和灌注混凝土”的处理方案后,经钻芯取样,芯样较完整,混凝土抗压强度平均值达到31.93MPa;采用超声波透射法检测,原断桩部位各剖面的声学参数均无异常,无声速低于低限值。施工前进行了详细测定,水泥浆和混凝土初凝时间分别是20h和16h,由于忽视了大体积水泥浆和混凝土的水化热,实际施工时水泥浆和混凝土初凝时间比试验室提供的缩短很多。
与现有的技术相比本发明具有以下特点和优异效果:
1.在原有的断桩基础上成桩,利于节约材料用量;
2.用高压旋喷清洗高效快捷;
3.两部分间用高强度混凝土浇灌不会降低桩的性能;
4.在本次施工过程中施工安全。
本发明具有方法简单、成本低、施工质量好、施工时间短的有益效果。
附图说明
图1为本发明桩孔内断桩的结构示意图。
图2为本发明桩孔内插入多根钢管的结构示意图。
图3为本发明混凝土填满凹腔的结构示意图。
具体实施方式
现结合附图对本发明作进一步的说明:
如图1-3所示,因混凝土灌注过程中导管拔管拔空,造成桩孔1内导管2断裂,导管2被埋倾斜无法使用,底部混凝土3初凝,一种大直径桥桩断桩的施工方法,包括如下步骤:
S1 在断桩2的桩孔1内插入新导管,新导管的底部接近首次浇注的混凝土断层面;新导管的底部下端距混凝土断层面约1m。
S2 插入多根钢管4到桩孔1内,均匀分布,钢管4的底孔用混凝土塞密封,钢管4内充满泥浆,钢管4的底部接近混凝土断层面;
S3 从新导管内灌装混凝土到桩孔1内,边灌边拉升,直至将再次浇注的混凝土灌装到桩孔1顶部;
S4 钻芯机的采样管插入钢管内,冲破混凝土塞进入混凝土断层面进行取样,检验样品成分;
S5 插入注浆机的注浆管到钢管4内接近混凝土断层面,对混凝土断层面用比桩身高一个等级的泥浆进行高压旋喷清洗,并将部分混凝土经本身或其它的钢管输送到桩孔外,混凝土断层面形成多个高压旋喷清洗形成的凹腔5;可应用伞形测锤、横向测锤检查旋喷后凹腔的纵向和横向空间;泥浆的粘度为18~23s、 密度为1.06~1.10g/cm3、含砂率为0.5%。
S6 从钢管内灌装混凝土,该混凝土填满该凹腔5和钢管;混凝土,其水泥的等级比浇注的混凝土高一级;水泥为p.O42.5,水灰比0.5,初凝时间在20h以上,以保证水泥浆在置换泥浆时和泵送混凝土置换水泥浆过程中,水泥浆不初凝;
S7 静置等待混凝土凝固。
桩孔1直径接近2.5m,钢管4的数量为6根,中间放置1根钢管4,接近桩孔周边放置5根钢管4。
Claims (4)
1.一种大直径桥桩断桩的施工方法,其特征是,包括如下步骤:
S1 在断桩的桩孔内插入新导管,新导管的底部接近首次浇注的混凝土断层面;
S2 插入多根钢管到桩孔内,均匀分布,钢管的底孔用混凝土塞密封,钢管内充满泥浆,钢管的底部接近混凝土断层面;
S3 从新导管内灌装混凝土到桩孔内,边灌边拉升,直至将再次浇注的混凝土灌装到桩孔顶部;
S4 钻芯机的采样管插入钢管内,冲破混凝土塞进入混凝土断层面进行取样,检验样品成分;
S5 插入注浆机的注浆管到钢管内接近混凝土断层面,对混凝土断层面用泥浆进行高压旋喷清洗,并将部分混凝土经本身或其它的钢管输送到桩孔外,混凝土断层面形成多个高压旋喷清洗形成的凹腔;
S6 从钢管内灌装混凝土,该混凝土填满该凹腔和钢管;
S7 静置等待混凝土凝固。
2.如权利要求1所述的一种大直径桥桩断桩的施工方法,其特征是,所述桩孔直径接近2.5m,所述钢管的数量为6根,中间放置1根钢管,接近桩孔周边放置5根钢管。
3. 如权利要求1所述的一种大直径桥桩断桩的施工方法,其特征是,所述泥浆的粘度为18~23s、 密度为1.06~1.10g/cm3、含砂率为0.5%。
4.如权利要求1所述的一种大直径桥桩断桩的施工方法,其特征是,所述步骤S6中的混凝土,其水泥的等级比浇注的混凝土高一级。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811508555.1A CN109610449A (zh) | 2018-12-11 | 2018-12-11 | 大直径桥桩断桩的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811508555.1A CN109610449A (zh) | 2018-12-11 | 2018-12-11 | 大直径桥桩断桩的施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109610449A true CN109610449A (zh) | 2019-04-12 |
Family
ID=66008603
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811508555.1A Pending CN109610449A (zh) | 2018-12-11 | 2018-12-11 | 大直径桥桩断桩的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109610449A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112695754A (zh) * | 2020-12-23 | 2021-04-23 | 北京城建华夏基础建设工程有限公司 | 一种水下锚杆施工方法 |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2012246627A (ja) * | 2011-05-25 | 2012-12-13 | Ohbayashi Corp | 既設構造物の補強構造および補強工法 |
CN106284335A (zh) * | 2016-09-27 | 2017-01-04 | 浙江铁甲建筑设备租赁有限公司 | 灌注桩质量缺陷处理方法 |
-
2018
- 2018-12-11 CN CN201811508555.1A patent/CN109610449A/zh active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2012246627A (ja) * | 2011-05-25 | 2012-12-13 | Ohbayashi Corp | 既設構造物の補強構造および補強工法 |
CN106284335A (zh) * | 2016-09-27 | 2017-01-04 | 浙江铁甲建筑设备租赁有限公司 | 灌注桩质量缺陷处理方法 |
Non-Patent Citations (1)
Title |
---|
崔桂官: "某特大桥大直径钻孔灌注桩断桩处理技术", 《公路与汽运》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112695754A (zh) * | 2020-12-23 | 2021-04-23 | 北京城建华夏基础建设工程有限公司 | 一种水下锚杆施工方法 |
CN112695754B (zh) * | 2020-12-23 | 2022-09-13 | 北京城建华夏基础建设工程有限公司 | 一种水下锚杆施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105604001B (zh) | 劲芯水泥土筒桩及施工方法和筒形旋搅钻具 | |
CN102011399B (zh) | 一种基于phc桩的多重高喷扩底桩施工方法 | |
CN106759297A (zh) | 一种支护桩与三管高压旋喷桩深基坑的施工方法 | |
CN107513995A (zh) | 一种桥梁灌注桩后压浆施工方法 | |
CN109519150B (zh) | 一种针对出水量较大的降水井封堵装置及方法 | |
CN109736303A (zh) | 一种压灌水泥土静压管桩结构及施工方法 | |
CN106759295B (zh) | 静钻挤扩支盘与管桩的组合桩型及其施工方法 | |
CN103147707B (zh) | 桩底沉渣成套处理方法 | |
CN105297710A (zh) | 一种高喷水泥土螺旋钻挤、扩孔钢筋混凝土灌注组合桩及制作方法 | |
CN109610449A (zh) | 大直径桥桩断桩的施工方法 | |
CN113266417A (zh) | 一种溶洞桩基的施工方法 | |
CN110792077A (zh) | 一种适用于淤泥质软土中的支盘桩装置及其施工工艺 | |
CN104452751A (zh) | 钻孔桩二次灌注成桩装置及其成桩方法 | |
CN209243732U (zh) | 一种高效微型钢管桩施工结构 | |
CN209066518U (zh) | 一种截桩迫降纠倾结构及微型钢管桩的施工结构 | |
CN103410529A (zh) | 一种用于软弱围岩的隧道支撑拱脚加固结构及施工方法 | |
CN203891785U (zh) | 水文水井管内投砾专用接头管总成 | |
CN106120714A (zh) | 一种提高空心桩承载力的装置及其使用方法 | |
CN108221948A (zh) | 一种地基处理方法 | |
CN102619223A (zh) | 粘结力增强式刚柔组合桩及施工方法 | |
CN116024963A (zh) | 一种低返浆高压旋喷复合灌浆方法及设备 | |
CN106149726B (zh) | 动态压力水下迁移性沙层基土的充填稳定灌浆方法 | |
CN109881696A (zh) | 一种hppg封底施工方法 | |
CN108677959A (zh) | 一种适于空间受限条件下注浆施工的注浆花管及注浆施工方法 | |
CN104863126B (zh) | 采用压浆技术处理大直径钻孔灌注桩塌孔的方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20190412 |
|
WD01 | Invention patent application deemed withdrawn after publication |