A kind of gas treatment equipment and the method to polluted gas progress purified treatment Download PDFInfo
- Publication number
- CN109603416A CN109603416A CN201811625756.XA CN201811625756A CN109603416A CN 109603416 A CN109603416 A CN 109603416A CN 201811625756 A CN201811625756 A CN 201811625756A CN 109603416 A CN109603416 A CN 109603416A
- Authority
- CN
- China
- Prior art keywords
- filler
- filler chamber
- chamber
- partition
- gas
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 12
- 239000000945 filler Substances 0.000 claims abstract description 243
- 238000005192 partition Methods 0.000 claims abstract description 68
- 241000883990 Flabellum Species 0.000 claims abstract description 32
- 239000000463 material Substances 0.000 claims abstract description 17
- 238000001514 detection method Methods 0.000 claims description 30
- 239000003344 environmental pollutant Substances 0.000 claims description 9
- 231100000719 pollutant Toxicity 0.000 claims description 9
- 239000002699 waste material Substances 0.000 claims description 9
- 238000000746 purification Methods 0.000 claims description 7
- 239000007789 gas Substances 0.000 description 82
- 230000000505 pernicious effect Effects 0.000 description 4
- 238000010521 absorption reaction Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 3
- 238000012545 processing Methods 0.000 description 3
- 206010053615 Thermal burn Diseases 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 239000011148 porous material Substances 0.000 description 2
- 238000003672 processing method Methods 0.000 description 2
- 238000001179 sorption measurement Methods 0.000 description 2
- 239000013589 supplement Substances 0.000 description 2
- 238000009825 accumulation Methods 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 239000004035 construction material Substances 0.000 description 1
- 238000011109 contamination Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000007599 discharging Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 230000001788 irregular Effects 0.000 description 1
- 238000010943 off-gassing Methods 0.000 description 1
- 239000002957 persistent organic pollutant Substances 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 229920006395 saturated elastomer Polymers 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
- B01D—SEPARATION
- B01D53/00—Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols
- B01D53/02—Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols by adsorption, e.g. preparative gas chromatography
- B01D53/04—Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols by adsorption, e.g. preparative gas chromatography with stationary adsorbents
- B01D53/0407—Constructional details of adsorbing systems
- B01D53/0423—Beds in columns
Landscapes
- Chemical & Material Sciences (AREA)
- Engineering & Computer Science (AREA)
- Analytical Chemistry (AREA)
- General Chemical & Material Sciences (AREA)
- Oil, Petroleum & Natural Gas (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Treating Waste Gases (AREA)
Abstract
The invention discloses a kind of gas treatment equipment and the methods for carrying out purified treatment to polluted gas, the gas treatment equipment includes tower body, tower body is equipped with air inlet, air outlet, the inner cavity of tower body is separated by porous movable partition and is stacked multiple filler chamber up and down, into, the location arrangements of air outlet make gas pass sequentially through each filler chamber from the bottom to top, the movable partition that partition is arranged to make the filler in the filler chamber on upper layer to fall into the filler chamber of lower layer, the partition can be the more flabellum compoboards that can pull and push movable mode clapboard or rotary type, the method that two different pairs of polluted gas carry out purified treatment can be derived based on two kinds of different type partitions.Technical solution of the present invention has many advantages, such as to save material, at low cost, the convenient, exhaust-gas treatment of operation stablize it is thorough.
Description
Technical field
The present invention relates to gas purification technique fields, and in particular to a kind of gas treatment equipment and carries out to polluted gas net
Change the method for processing.
Background technique
With the economic development of society, air quality becomes us and does not allow the problem of avoiding.The all types of industries continued to increase
Volatile class organic pollutant given out in exhaust gas, ever-increasing vehicle exhaust and all kinds of construction materials etc., seriously
Threaten our health.In order to improve the quality of living, people can select gas cleaning plant to improve the gas of surrounding
Environment.
Current chemical industry exhaust gas processing device is many kinds of, is located again with chemical reaction handling and porous material absorption mostly
Based on reason, the generally operation of current porous material absorption equipment is irregular replacement absorption material, certainly will there is adsorption material in this way
Matter does not reach the problem that saturation may be discarded, and causes the waste of material and the increase of cost;It is also likely to be present adsorption material
Matter supersaturation is but still using, and causes exhaust-gas treatment to be not thorough, unstable problem.
Summary of the invention
The technical problem to be solved in the present invention is to overcome the shortcomings of the prior art, provide one kind can save material, at
This is low, operation is convenient, exhaust-gas treatment stablizes thorough gas treatment equipment.
The technical solution of the present invention is as follows:
A kind of gas treatment equipment, including tower body, the tower body are equipped with air inlet and outlet, batching hole and discharge port,
The inner cavity of the tower body is separated at least two stacked up and down filler chamber by partition, is filled at gas in the filler chamber
Reason filler, the partition are equipped with multiple through-holes;The location arrangements of the air inlet and air outlet make gas from the bottom to top
It passes sequentially through stacked each filler chamber up and down and is discharged, the partition is arranged to make the filler in the filler chamber on upper layer to fall into
Movable partition in the filler chamber of lower layer.Gas flows from bottom to top in tower body, as gas is net by the intracorporal filler of tower
Change, more up, gas pollutant concentration is lower, and the gas pollutant concentration positioned at tower body lower part is higher, therefore is located under tower body
The filler loss in portion is very fast, and the filler than being located at tower body lower part first reaches saturation, at this time if by the intracorporal filler of entire tower
It changes, the filler for not reaching saturation positioned at tower body top is not efficiently used, and causes to waste;If being changed without filler, position
The filler that filler chamber in tower body lower part is saturated cannot play the effect of processing gas, and the treatment effect of gas treatment equipment is just not
It is ideal.Tower body is separated into multiple filler chamber using the partition with through-hole by gas treatment equipment of the invention, and partition be can
Movable, when the filler of undermost filler chamber reaches saturation, by the partition of movable lowest level filler chamber, by lowest level
The filler of filler chamber is discharged from discharge port, respectively the partition of each layer filler chamber of activity, and the filler of upper layer filler chamber is due to gravity original
It is continued to use because dropping into filler chamber, lower layer, makes full use of the intracorporal filler of tower;New filler is replenished in time in tower body most
Upper layer filler chamber, tower body is interior to keep sufficient unsaturated filler, and gas treatment is more stable thoroughly.
Preferably, in above-mentioned gas treatment equipment, the air inlet is arranged in the bottom of the tower body, the air outlet
It is arranged in the top of the tower body, discharge pipe is connected at the air outlet, the discharge pipe is equipped with air-introduced machine.In air-introduced machine
Drainage under, gas enters tower body from the air inlet of tower body bottom, and the partition of tower body inner cavity is equipped with through-hole, and gas is from the bottom to top
It passes sequentially through each filler chamber stacked up and down and is discharged from exit.
Preferably, in above-mentioned gas treatment equipment, the filler chamber is at least provided with three, and at least one filler chamber
It is interior to be equipped with detection device.When filler chamber is multiple, detection device is installed, is reloaded the time by detection device prompt, tower is intracorporal
Waste material is timely discharged, and new filler adds to tower body, and the gas treatment stability of gas treatment equipment is more preferable.
It is furthermore preferred that being equipped in second filler chamber of the tower body bottom-up in above-mentioned gas treatment equipment
For detecting the detection device of second filler chamber's outgassing pollution object concentration, the detection device is specifically located at second filler
In cavity between room and third filler chamber above it.It can preferably be detected by the specific location of optimizing detection device
The residual concentration of gas pollutant out, due to there is enough outlets in cavity, so that testing result is more acurrate, detection device is changed
Expect that reminder time is more acurrate.
Preferably, in above-mentioned gas treatment equipment, the discharge outlet is additionally provided with discharge baffle, and the discharge baffle will
Discharge port is separated into waste from stacking area and Efflux District.Discharge baffle can keep the airtightness of tower body, and waste material is in waste from stacking area
Interior accumulation all handles the waste material of discharge port without reloading every time, saves the working time.
Preferably, in above-mentioned gas treatment equipment, the movable partition can pull and push movable mode clapboard for one, should
Movable mode clapboard can be pulled and pushed by pulling out the filler chamber or the discharging that so that the filler in the filler chamber on upper layer is fallen into lower layer outside tower body
In mouthful, and separate neighbouring two layers of filler chamber again by being inserted into.Movable mode clapboard can be pulled and pushed, structure is simple, surely
Qualitative good, easy to operate, work of reloading is more convenient.
Preferably, in above-mentioned gas treatment equipment, the movable partition can also be more fans of a rotary type
Leaf compoboard, more flabellum compoboards fall into the partial filler in the filler chamber on upper layer by rotating part flabellum first in tower
In the filler chamber of lower layer or discharge port, then by rotate rest part flabellum fall the rest part filler in the filler chamber on upper layer
Enter in the filler chamber or discharge port of lower layer, separates neighbouring two layers of filler chamber again finally by restoring.In filler chamber
Gas be mostly pernicious gas, these pernicious gases may damage personnel, use more flabellum compoboards of rotary type
As partition, work of reloading is completed in tower body, is avoided the intracorporal pernicious gas of tower from flowing to outside tower body and is damaged and pollute ring
Border.The indoor filler temperature of filler is higher, if being brought to outside tower body, personnel is easily caused to scald, and uses more fans of rotary type
Leaf compoboard is as partition, and work of reloading is completed in tower body, and personnel is avoided to be burned, and work of reloading is safer.
The inventive concept total as one, the present invention also provide it is a kind of using above-mentioned gas treatment equipment to contamination gas
The method of body progress purified treatment, comprising the following steps:
S1: the filler of purification gas will be filled in all filler chamber of the gas treatment equipment by batching hole;
S2: the filler chamber that air-introduced machine makes gas pass sequentially through all layers from lower to upper is opened, and is finally arranged from air outlet
Out;
S3: continuously running gas treatment equipment, and detects the gas pollutant concentration in filler chamber by detection device;
S4: it is reminded after the data of detection device feedback reach given threshold and starts to replace filler;
S5: undermost partition is first pulled out into the tower body when replacement filler, makes the filler in undermost filler chamber
It falls into discharge port, then reinserting partition makes undermost filler chamber keep cavity;
S6: upper one layer of partition is pulled out into the tower body again, the filler in one layer of filler chamber is made to fall into lowest level
Filler chamber in, then reinsert this layer partition make this layer filler chamber keep cavity;
S7: and so on, until cavity is kept in the filler chamber of top layer, then by batching hole supplement virgin material to most upper
In the filler chamber of layer, then seals batching hole and start to operate again.
Gas is purified using the above method, the partition of movable using can draw and insert-type partition, structure is simple, surely
Qualitative good, easy to operate, work of reloading is more convenient.Can draw and insert-type partition tower body is separated into multiple filler chamber, work as lowest level
The filler of filler chamber when reaching saturation, only need that first the filler of lowest level filler chamber is discharged, then successively by upper layer filler chamber
Filler fill up next layer of adjacent filler chamber and continue to use, improve the utilization rate of filler;Tower is replenished in time in new filler
Filler chamber, internal top layer, tower body is interior to keep sufficient unsaturated filler, and gas treatment is more stable thoroughly.
The inventive concept total as one, the present invention also provide another kind using above-mentioned gas treatment equipment to pollution
The method of gas progress purified treatment, comprising the following steps:
S1: the filler of purification gas will be filled in all filler chamber of the gas treatment equipment by batching hole;
S2: the filler chamber that air-introduced machine makes gas pass sequentially through all layers from lower to upper is opened, and is finally arranged from air outlet
Out;
S3: continuously running gas treatment equipment, and detects the gas pollutant concentration in filler chamber by detection device;
S4: it is reminded after the data of detection device feedback reach given threshold and starts to replace filler;
S5: flabellum rotation in part in undermost partition is first made into a partition first side opening when replacement filler, and is made most
Partial filler in filler chamber, lower layer is fallen into discharge port by the opening, and the preceding sections flabellum that then circles round simultaneously rotates it simultaneously
Remaining part divides flabellum to make another side opening, and the rest part filler in lowest level filler chamber is fallen by another side opening
In discharge port, then convolution makes lowest level filler chamber keep cavity;
S6: flabellum rotation in part in upper one layer of partition is made into a partition first side opening again, and makes one layer of filler chamber
In partial filler fallen into undermost filler chamber by the opening, then circle round preceding sections flabellum and simultaneously rotate remaining
Part flabellum makes another side opening, and the rest part filler in one layer of filler chamber is fallen by another side opening
In undermost filler chamber, then convolution makes one layer of filler chamber keep cavity;
S7: and so on, until cavity is kept in the filler chamber of top layer, then by batching hole supplement virgin material to most upper
In the filler chamber of layer, then seals batching hole and start to operate again.
Gas is purified using the above method, uses more flabellum compoboards of rotary type as partition, work of reloading
Work is completed in tower body, is avoided the intracorporal pernicious gas of tower from flowing to outside tower body and is damaged and pollute environment.Filler is indoor to be filled out
Material temperature degree may be higher, if being brought to outside tower body, personnel is easily caused to scald, use more flabellum compoboards of rotary type as
Partition, work of reloading are completed in tower body, and work of reloading is safer.Tower body is separated into multiple fillers by the partition of rotary type
Room only needs that first the filler of lowest level filler chamber is discharged, then successively will when the filler of undermost filler chamber reaches saturation
The next layer of filler chamber that the filler of upper layer filler chamber fills up adjacent continues to use, and improves the utilization rate of filler;New filler and
When add to filler chamber, top layer in tower body, sufficient unsaturated filler is kept in tower body, gas treatment is more stable thoroughly.
Compared with the prior art, the advantages of the present invention are as follows:
Tower body is separated into multiple filler chamber using the partition of movable by gas treatment equipment of the invention, works as lowest level
The filler of filler chamber when reaching saturation, only need that first the filler of lowest level filler chamber is discharged, then successively by upper layer filler chamber
Filler fill up next layer of adjacent filler chamber and continue to use, improve the utilization rate of filler;Tower is replenished in time in new filler
Filler chamber, internal top layer, tower body is interior to keep sufficient unsaturated filler, and gas treatment is more stable thoroughly.
Detailed description of the invention
Fig. 1 is cross-sectional view of the gas treatment equipment in middle section of Example 1 and Example 2 of the present invention.
Fig. 2 is the top view of the gas treatment equipment of the embodiment of the present invention 1.
Fig. 3 is the structural schematic diagram of the partition of the gas treatment equipment of the embodiment of the present invention 1.
Fig. 4 is the top view of the gas treatment equipment of the embodiment of the present invention 2.
Fig. 5 is the structural schematic diagram of the partition of the gas treatment equipment of the embodiment of the present invention 2.
Marginal data:
1, tower body;11, filler chamber;2, partition;3, detection device;4, air inlet;5, discharge pipe;6, batching hole;7, it discharges
Mouthful;8, discharge baffle;9, air-introduced machine.
Specific embodiment
To facilitate the understanding of the present invention, the present invention is made below in conjunction with Figure of description and preferred embodiment more complete
Face meticulously describes, but the protection scope of the present invention is not limited to the following specific embodiments.
Unless otherwise defined, all technical terms used hereinafter and the normally understood meaning of those skilled in the art
It is identical.The similar word of "one" or " one " etc. used in present patent application specification and claims does not indicate
Quantity limitation, but indicate that there are at least one.The similar word such as " connection " or " connected " be not limited to physics or
The connection of person's machinery, but may include electrical connection, it is either direct or indirect."upper", "lower", " left side ",
" right side " etc. is only used for indicating relative positional relationship, after the absolute position for being described object changes, then the relative positional relationship
Correspondingly change.
Embodiment 1:
As shown in Figure 1 to Figure 3, the gas treatment equipment of the present embodiment, including tower body 1, tower body 1 are equipped with air inlet 4, go out
The inner cavity of air port, batching hole 6 and discharge port 7, tower body 1 is separated at least two stacked up and down filler chamber 11 by partition 2, fills out
Expect to be filled with gas treatment filler in room 11, partition 2 is equipped with multiple through-holes;The location arrangements of air inlet 4 and air outlet make
It obtains gas to pass sequentially through stacked each filler chamber 11 up and down from the bottom to top and be discharged, partition 2 is arranged to make the filler on upper layer
Filler in room 11 falls into the movable partition in the filler chamber 11 of lower layer.
In the present embodiment, air inlet 4 is arranged in the bottom of tower body 1, and air outlet is arranged in the top of tower body 1, at air outlet
It is connected with discharge pipe 5, discharge pipe 5 is equipped with air-introduced machine 9.
In the present embodiment, there are three filler chamber 11 sets, and has and be equipped with detection device 3 in a filler chamber 11.
In the present embodiment, it is equipped in second filler chamber 11 of tower body 1 bottom-up for detecting second filler chamber
11 go out the detection device 3 of gas concentration, and detection device 3 is specifically located at second filler chamber 11 and the third filler chamber above it
In cavity between 11.
In the present embodiment, discharge baffle 8 is additionally provided at discharge port 7, discharge port 7 is separated into waste from stacking by discharge baffle 8
Area and Efflux District.
In the present embodiment, movable partition can pull and push movable mode clapboard for one, this can pull and push movable mode clapboard and pass through pumping
Separating out falls into the filler in the filler chamber 11 on upper layer in the filler chamber 11 or discharge port 7 of lower layer outside tower body 1, and by being inserted into
Separate neighbouring two layers of filler chamber 11 again.Specifically, partition 2 is equipped with handle, 1 inner wall of tower body is equipped with slot, every
In 2 insertion groove of plate, slot supporting clapboard 2, partition 2 can slide in slot, convenient for extracting out partition 2 out of tower body 1 and inserting partition 2
Enter in tower body 1.
The gas treatment equipment processing method of the present embodiment is as follows:
S1: filling out for purification gas will be filled in all filler chamber 11 of the gas treatment equipment by batching hole 6
Material;
S2: the filler chamber 11 that air-introduced machine 9 makes gas pass sequentially through all layers from lower to upper is opened, and finally from air outlet
Discharge;
S3: continuously running gas treatment equipment, and dense by the gas pollutant in the detection of detection device 3 filler chamber 11
Degree;
S4: it is reminded after the data that detection device 3 is fed back reach given threshold and starts to replace filler;
S5: undermost partition 2 is first pulled out into the tower body 1 when replacement filler, is made in undermost filler chamber 11
Filler is fallen into discharge port 7, and then reinserting partition 2 makes undermost filler chamber 11 keep cavity;
S6: pulling out the tower body 1 for upper one layer of partition 2 again, falls into the filler in one layer of filler chamber 11 most
In the filler chamber 11 of lower layer, the partition 2 for then reinserting this layer makes the filler chamber 11 of this layer keep cavity;
S7: and so on, until keeping cavity in the filler chamber 11 of top layer, virgin material is then supplemented extremely by batching hole 6
In the filler chamber 11 of top layer, then seals the beginning of batching hole 6 and operate again.
Embodiment 2:
As shown in Figure 1, Figure 4 and Figure 5, the gas treatment equipment of the present embodiment is substantially the same manner as Example 1, main difference it
Be in: in the present embodiment, the cross section of gas treatment equipment is circle, and movable partition is more flabellums of a rotary type
Compoboard, more flabellum compoboards fall into the partial filler in the filler chamber 11 on upper layer by rotating part flabellum first in tower
In the filler chamber 11 of lower layer or discharge port 7, then by rotate rest part flabellum make the rest part in the filler chamber 11 on upper layer
Filler is fallen into the filler chamber 11 or discharge port 7 of lower layer, finally by restore make neighbouring two layers of filler chamber 11 again every
It opens.
The processing method of the gas treatment equipment of the present embodiment is as follows:
S1: filling out for purification gas will be filled in all filler chamber 11 of the gas treatment equipment by batching hole 6
Material;
S2: the filler chamber 11 that air-introduced machine 9 makes gas pass sequentially through all layers from lower to upper is opened, and finally from air outlet
Discharge;
S3: continuously running gas treatment equipment, and dense by the gas pollutant in the detection of detection device 3 filler chamber 11
Degree;
S4: it is reminded after the data that detection device 3 is fed back reach given threshold and starts to replace filler;
S5: flabellum rotation in part in undermost partition 2 is first made into the first side opening of partition 2 when replacement filler, and is made
Partial filler in lowest level filler chamber 11 is fallen into discharge port 7 by the opening, and then circle round preceding sections flabellum and simultaneously
Rotation rest part flabellum makes another side opening, and the rest part filler in lowest level filler chamber 11 is made to pass through the other side
Opening is fallen into discharge port 7, and then convolution makes lowest level filler chamber 11 keep cavity;
S6: flabellum rotation in part in upper one layer of partition 2 is made into the first side opening of partition 2 again, and makes one layer of filler
Partial filler in room 11 is fallen into undermost filler chamber 11 by the opening, and the preceding sections flabellum that then circles round simultaneously revolves simultaneously
Turning rest part flabellum makes another side opening, and the rest part filler in one layer of filler chamber 11 is made to pass through the other side
Opening is fallen into undermost filler chamber 11, and then convolution makes one layer of filler chamber 11 keep cavity;
S7: and so on, until keeping cavity in the filler chamber 11 of top layer, virgin material is then supplemented extremely by batching hole 6
In the filler chamber 11 of top layer, then seals the beginning of batching hole 6 and operate again.
The above is only a preferred embodiment of the present invention, protection scope of the present invention is not limited merely to above-mentioned implementation
Example.To those of ordinary skill in the art, obtained improvement and change in the case where not departing from the technology of the present invention concept thereof
It changes and also should be regarded as protection scope of the present invention.
Claims (9)
1. a kind of gas treatment equipment, including tower body (1), the tower body (1) is equipped with air inlet (4), air outlet, batching hole
(6) and discharge port (7), the inner cavity of the tower body (1) are separated at least two stacked up and down filler chamber by partition (2)
(11), gas treatment filler is filled in the filler chamber (11), it is characterised in that: the partition (2) is equipped with multiple logical
Hole;The location arrangements of the air inlet (4) and air outlet make gas pass sequentially through each filler stacked up and down from the bottom to top
Room (11) is simultaneously discharged, and the partition (2) is arranged to make the filler in the filler chamber (11) on upper layer to fall into the filler chamber of lower layer
(11) the movable partition in.
2. gas treatment equipment according to claim 1, it is characterised in that: the air inlet (4) is arranged in the tower body
(1) bottom, the air outlet are arranged in the top of the tower body (1), are connected at the air outlet discharge pipe (5), described
Discharge pipe (5) is equipped with air-introduced machine (9).
3. gas treatment equipment according to claim 1, it is characterised in that: the filler chamber (11) at least provided with three,
And detection device (3) are equipped at least one filler chamber (11).
4. gas treatment equipment according to claim 3, it is characterised in that: the tower body (1) bottom-up second
It is equipped in a filler chamber (11) for detecting the detection device (3) that second filler chamber (11) goes out gas concentration, the detection device
(3) it is specifically located in the cavity between second filler chamber (11) and third filler chamber (11) above it.
5. gas treatment equipment according to claim 1, it is characterised in that: be additionally provided with discharge gear at the discharge port (7)
Discharge port (7) is separated into waste from stacking area and Efflux District by plate (8), the discharge baffle (8).
6. gas treatment equipment according to any one of claims 1-5, it is characterised in that: the movable partition
Movable mode clapboard can be pulled and pushed for one, this, which can pull and push movable mode clapboard, makes the filler chamber (11) on upper layer by pulling out outside tower body (1)
In filler fall into the filler chamber (11) or discharge port (7) of lower layer, and make neighbouring two layers of filler chamber by being inserted into
(11) it separates again.
7. gas treatment equipment according to any one of claims 1-5, it is characterised in that: the movable partition
For more flabellum compoboards of a rotary type, which makes the filler on upper layer by rotating part flabellum first in tower
Partial filler in room (11) is fallen into the filler chamber (11) or discharge port (7) of lower layer, then is made by rotating rest part flabellum
Rest part filler in the filler chamber (11) on upper layer is fallen into the filler chamber (11) or discharge port (7) of lower layer, finally by multiple
Original separates neighbouring two layers of filler chamber (11) again.
8. a kind of method for carrying out purified treatment to polluted gas using gas treatment equipment as claimed in claim 6, feature
It is, comprising the following steps:
S1: filling out for purification gas will be filled in all filler chamber (11) of the gas treatment equipment by batching hole (6)
Material;
S2: the filler chamber (11) that air-introduced machine (9) make gas pass sequentially through all layers from lower to upper is opened, and finally from air outlet
Discharge;
S3: continuously running gas treatment equipment, and dense by the gas pollutant in detection device (3) detection filler chamber (11)
Degree;
S4: it is reminded after the data of detection device (3) feedback reach given threshold and starts to replace filler;
S5: undermost partition (2) is first pulled out into the tower body (1) when replacement filler, is made in undermost filler chamber (11)
Filler fall into discharge port (7), then reinsert partition (2) make undermost filler chamber (11) keep cavity;
S6: pulling out the tower body (1) for upper one layer of partition (2) again, falls into the filler in one layer of filler chamber (11)
In undermost filler chamber (11), the partition (2) for then reinserting this layer makes the filler chamber (11) of this layer keep cavity;
S7: and so on, until keeping cavity in the filler chamber (11) of top layer, virgin material then is supplemented extremely by batching hole (6)
In the filler chamber (11) of top layer, then seals batching hole (6) and start to operate again.
9. a kind of method for carrying out purified treatment to polluted gas using gas treatment equipment as claimed in claim 7, feature
It is, comprising the following steps:
S1: filling out for purification gas will be filled in all filler chamber (11) of the gas treatment equipment by batching hole (6)
Material;
S2: the filler chamber (11) that air-introduced machine (9) make gas pass sequentially through all layers from lower to upper is opened, and finally from air outlet
Discharge;
S3: continuously running gas treatment equipment, and dense by the gas pollutant in detection device (3) detection filler chamber (11)
Degree;
S4: it is reminded after the data of detection device (3) feedback reach given threshold and starts to replace filler;
S5: flabellum rotation in part in undermost partition (2) is first made into partition (2) first side opening when replacement filler, and is made
Partial filler in lowest level filler chamber (11) is fallen into discharge port (7) by the opening, then circles round preceding sections flabellum simultaneously
Rotating rest part flabellum makes another side opening simultaneously, and makes the rest part filler in lowest level filler chamber (11) by being somebody's turn to do
Another side opening is fallen into discharge port (7), and then convolution makes lowest level filler chamber (11) to keep cavity;
S6: flabellum rotation in part in upper one layer of partition (2) is made into partition (2) first side opening again, and makes one layer of filler
Partial filler in room (11) is fallen into undermost filler chamber (11) by the opening, and then circle round preceding sections flabellum and same
Shi Xuanzhuan rest part flabellum makes another side opening, and makes rest part filler in one layer of filler chamber (11) by should
Another side opening is fallen into undermost filler chamber (11), and then convolution makes one layer of filler chamber (11) keep cavity;
S7: and so on, until keeping cavity in the filler chamber (11) of top layer, virgin material then is supplemented extremely by batching hole (6)
In the filler chamber (11) of top layer, then seals batching hole (6) and start to operate again.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811625756.XA CN109603416A (en) | 2018-12-28 | 2018-12-28 | A kind of gas treatment equipment and the method to polluted gas progress purified treatment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811625756.XA CN109603416A (en) | 2018-12-28 | 2018-12-28 | A kind of gas treatment equipment and the method to polluted gas progress purified treatment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109603416A true CN109603416A (en) | 2019-04-12 |
Family
ID=66012852
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811625756.XA Pending CN109603416A (en) | 2018-12-28 | 2018-12-28 | A kind of gas treatment equipment and the method to polluted gas progress purified treatment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109603416A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110237707A (en) * | 2019-07-09 | 2019-09-17 | 华南理工大学 | A kind of low energy consumption device for catalyzing and oxidating ozone |
CN112516750A (en) * | 2020-12-16 | 2021-03-19 | 吴廷贵 | A environment-friendly device for gas cleaning |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203229399U (en) * | 2013-04-27 | 2013-10-09 | 广州氨氮水污染治理有限公司 | Device for treating ultrahigh-concentration ammonia-nitrogen wastewater and recovering ammonia |
CN204637977U (en) * | 2015-02-06 | 2015-09-16 | 中山大学 | The movable waste gas biological purifying device of a kind of filler |
CN205570084U (en) * | 2016-03-07 | 2016-09-14 | 重庆交通大学 | Novel filtration formula exhaust -gas treatment device |
CN207745710U (en) * | 2017-12-27 | 2018-08-21 | 内蒙古华蒙科创环保科技工程有限公司 | Desulfurizing tower |
CN209451576U (en) * | 2018-12-28 | 2019-10-01 | 贵州大龙汇成新材料有限公司 | A kind of gas treatment equipment |
-
2018
- 2018-12-28 CN CN201811625756.XA patent/CN109603416A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203229399U (en) * | 2013-04-27 | 2013-10-09 | 广州氨氮水污染治理有限公司 | Device for treating ultrahigh-concentration ammonia-nitrogen wastewater and recovering ammonia |
CN204637977U (en) * | 2015-02-06 | 2015-09-16 | 中山大学 | The movable waste gas biological purifying device of a kind of filler |
CN205570084U (en) * | 2016-03-07 | 2016-09-14 | 重庆交通大学 | Novel filtration formula exhaust -gas treatment device |
CN207745710U (en) * | 2017-12-27 | 2018-08-21 | 内蒙古华蒙科创环保科技工程有限公司 | Desulfurizing tower |
CN209451576U (en) * | 2018-12-28 | 2019-10-01 | 贵州大龙汇成新材料有限公司 | A kind of gas treatment equipment |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110237707A (en) * | 2019-07-09 | 2019-09-17 | 华南理工大学 | A kind of low energy consumption device for catalyzing and oxidating ozone |
CN112516750A (en) * | 2020-12-16 | 2021-03-19 | 吴廷贵 | A environment-friendly device for gas cleaning |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109603416A (en) | A kind of gas treatment equipment and the method to polluted gas progress purified treatment | |
RU2141914C1 (en) | Method of and device for filling containers | |
CN209451576U (en) | A kind of gas treatment equipment | |
CN105152393B (en) | A kind of laboratory simulation device repaired for underground water pollution and its application method | |
CN101264406A (en) | Rotating filter cartridge type air dust remover | |
CN101067506A (en) | Purifying sterilizing device for central air conditioner | |
KR102251712B1 (en) | Dust collection and waste heat recovery apparatus of exhaust gas after tenter | |
CN208320376U (en) | Dioxin adsorption plant | |
EP1677108B1 (en) | Apparatus for measuring mercury contained in gaseous medium | |
CN201244422Y (en) | Rotating filter cartridge type air dust remover | |
CN104879760B (en) | A kind of cylindrical shape heat-storage catalytic burner | |
CN209109819U (en) | A kind of prosthetic device for soil and groundwater | |
CN205323481U (en) | Vertical waste gas adsorber | |
CN107126927A (en) | A kind of preparation method of architecture indoor particulate matter and gas recombination scavenging material | |
CN107042084A (en) | Liquid handling device | |
CN209317366U (en) | Cellular activated carbon adsorption box | |
CN209060827U (en) | A kind of exhaust-gas treatment activated carbon adsorption device | |
JP2009150606A (en) | Device for removing salt content in air | |
CN111289315A (en) | Dust sampling device suitable for different level | |
JP2001129345A (en) | Activated carbon adsorbing column | |
CN215828517U (en) | Industrial sewage treatment equipment based on filtering membrane | |
CN216367337U (en) | Low-temperature plasma waste gas treatment device | |
CN218901354U (en) | Waste gas treatment device for chloroform | |
CN103418215A (en) | Gas spiral separation and continuous molecular weight emission control device | |
AU2013388102B2 (en) | Systems and methods for multi-celled gas processing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |