CN109586285A - Energy consumption mark post value calculating method, energy consumption management method and energy consumption management system - Google Patents
Energy consumption mark post value calculating method, energy consumption management method and energy consumption management system Download PDFInfo
- Publication number
- CN109586285A CN109586285A CN201811484288.9A CN201811484288A CN109586285A CN 109586285 A CN109586285 A CN 109586285A CN 201811484288 A CN201811484288 A CN 201811484288A CN 109586285 A CN109586285 A CN 109586285A
- Authority
- CN
- China
- Prior art keywords
- energy consumption
- information
- place
- mark post
- modification
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2203/00—Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
- H02J2203/20—Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The present invention discloses a kind of energy consumption mark post value calculating method, comprising: obtains energy consumption place asset management table information and energy consumption premise temperature information;Energy consumption mark post value is calculated according to the energy consumption place asset management table information and energy consumption premise temperature information got.The present invention can increase the compactness of calculated energy consumption mark post value and actual conditions, to enhance directive significance when carrying out reducing energy consumption and improvement and optimization to energy consumption place.
Description
Technical field
The present invention relates to managing power consumption fields, and in particular to a kind of energy consumption mark post value calculating method, energy consumption management method and
Energy consumption management system.
Background technique
Energy consumption index is the data target of various reflection energy-output ratios, for describing the size and kind of energy-output ratio
Class.It is the energy consumption place of information technoloy equipment and refrigeration equipment for energy consumption object, energy consumption mark post value is mainly power consumption, by energy consumption
The calculating of mark post value can provide data foundation and guidance when carrying out reducing energy consumption and improvement and optimization to energy consumption place, existing
Energy consumption mark post value calculating method formula it is excessively rough, usually by the way that " (refrigeration equipment energy consumption+IT is set energy consumption mark post value PUE=
Standby energy consumption)/information technoloy equipment energy consumption " for this formula come what is calculated, value of the value of PUE more than or equal to 1, PUE indicates energy benefit closer to 1
With more reasonable.Due to not accounting for the factors such as the building structure of energy consumption place, indoor and outdoor temperature, and these factors can with or directly or
Refrigeration equipment energy consumption and information technoloy equipment energy consumption are influenced indirectly, so also needing to change existing energy consumption mark post value calculating method
Into increasing the compactness of calculated energy consumption mark post value and actual conditions, thus carrying out reducing energy consumption and complete to energy consumption place
Enhance directive significance when kind optimization.
Summary of the invention
In view of this, the application provides a kind of improved energy consumption mark post value calculating method, calculated energy can be increased
The compactness of mark post value and actual conditions is consumed, thus the enhancing guidance meaning when carrying out reducing energy consumption and improvement and optimization to energy consumption place
Justice.In order to solve the above technical problems, technical solution provided by the invention is as follows:
Energy consumption mark post value calculating method, comprising:
Obtain energy consumption place asset management table information and energy consumption premise temperature information;
Energy consumption mark post value is calculated according to the energy consumption place asset management table information and energy consumption premise temperature information got.
Further, the energy consumption place asset management table information includes the specified function of each information technoloy equipment in energy consumption place
Rate, the rated power of each refrigeration equipment, ac-dc conversion equipment transformation efficiency and energy consumption place building coefficient, the energy consumption field
Institute's temperature information includes energy consumption place room temperature-time relationship table and energy consumption place outdoor temperature-time relationship table.
Further, the energy consumption place asset management table information and energy consumption premise temperature information that the basis is got calculate
The step for energy consumption mark post value includes:
Energy consumption basic data P1 is calculated according to formula (1):
P1=P2+P3 (1);
Energy consumption mark post value S is calculated according to formula (2):
S=P1 × R1 × (P2/R2) × T (2);
Wherein, P2 is the total rated power of all information technoloy equipments in energy consumption place, and P3 is all refrigeration equipments in energy consumption place
Total rated power, R1 be energy consumption place building coefficient, R2 be energy consumption place in ac-dc conversion equipment transformation efficiency, T is energy
The difference of consumption place room temperature and outdoor temperature is greater than the duration of the first preset value.
Further, when energy consumption place building is board house, if the difference of energy consumption place room temperature and outdoor temperature is big
In the first preset value, the value of energy consumption place building coefficient is 0.9, if the difference of energy consumption place room temperature and outdoor temperature
Less than the first preset value, the value of energy consumption place building coefficient is 1.05;When energy consumption place building is brick laying structure, if
The difference of energy consumption place room temperature and outdoor temperature is greater than the first preset value, and the value of energy consumption place building coefficient is 0.8, such as
The difference of fruit energy consumption place room temperature and outdoor temperature is 1.2 less than the first preset value, the value of energy consumption place building coefficient.
Energy consumption management method, comprising:
Obtain the electricity consumption data in current energy consumption mark post value and financial statement;
Energy consumption irrelevance is calculated according to the energy consumption mark post value and electricity consumption data;
Energy consumption place is managed according to the energy consumption irrelevance;
Wherein, the current energy consumption mark post value is calculated by above-mentioned energy consumption mark post value calculating method.
Further, described the step for calculating energy consumption irrelevance according to the energy consumption mark post value and electricity consumption data, wraps
It includes:
Energy consumption irrelevance X is calculated by formula (3):
X=abs (S-Q)/S (3);
Wherein, abs is ABS function, and S is current energy consumption mark post value, and Q is the electricity consumption data in financial statement.
Further, described the step for being managed according to the energy consumption irrelevance to energy consumption place, includes:
Judge whether the energy consumption irrelevance X is greater than the second preset value, is preset if the energy consumption irrelevance X is greater than second
Value carries out in next step;
Obtain information verification modification application form;
Obtain energy consumption place asset management table;
Check whether the relevant information in the energy consumption place asset management table is checked in modification application form with the information
The information of application verification modification is consistent, if inconsistent, carries out in next step;
It is checked in modification application form according to the information and applies for asset management table in energy consumption place described in the content modification of modification
In relevant information;
More new energy consumption place asset management table.
Further, described checked in modification application form according to the information applies for energy consumption field described in the content modification of modification
Before the step for relevant information in institute's asset management table further include:
It audits in the information verification modification application form and applies for whether the content of modification is correct, if correctly, described in progress
The correlation applied in asset management table in energy consumption place described in the content modification of modification in modification application form is checked according to the information
The step for information, otherwise, application failure.
Further, described audit applies for that whether correct this of content of modification moves in the information verification modification application form
Work includes:
Obtain equipment photo corresponding with the content of modification is applied in information verification modification application form, the equipment
It include equipment essential information in photo;
It audits in the information verification modification application form and applies for that the content of modification and the equipment in the equipment photo are basic
Whether information is consistent, if unanimously, assert in the information verification modification application form and applying for that the content of modification is correct, otherwise,
Application failure.
Energy consumption management system, comprising:
First acquisition unit: for obtaining energy consumption place asset management table information, energy consumption place indoor temperature information and energy
Consume place outdoor temperature information;
First computing unit: the information for being got according to the first acquisition module calculates energy consumption mark post value;
Second acquisition unit: for obtaining the electricity consumption in the calculated energy consumption mark post value of the first computing module and financial statement
Measure data;
Second computing unit: the information for being got according to the second acquisition module calculates energy consumption irrelevance;
Managing power consumption unit: for being managed according to the calculated energy consumption irrelevance of the second computing module to energy consumption place
Energy consumption mark post value calculating method provided by the invention can increase calculated energy consumption mark post value and actual conditions
Compactness, to enhance directive significance when carrying out reducing energy consumption and improvement and optimization to energy consumption place.
Detailed description of the invention
Fig. 1 is the energy consumption mark post value calculating method flow chart that embodiment 1 provides.
Fig. 2 is the energy consumption management method flow chart that embodiment 2 provides.
Fig. 3 is the energy consumption management system structural block diagram that embodiment 3 provides.
Specific embodiment
It is with reference to the accompanying drawing and specific real in order to make those skilled in the art more fully understand technical solution of the present invention
Applying example, the present invention is described in further detail.
Embodiment 1
As shown in Figure 1, the present embodiment provides a kind of energy consumption mark post value calculating methods, comprising:
S1: energy consumption place asset management table information and energy consumption premise temperature information are obtained;
S2: energy consumption mark post is calculated according to the energy consumption place asset management table information and energy consumption premise temperature information got
Value.
What needs to be explained here is that this method can be applied to energy consumption mark post value computing system, energy consumption also can be applied to
Management system, in actual conditions, energy consumption management system may include energy consumption mark post value computing system, the present embodiment due to consideration that
The temperature conditions in energy consumption place, and the height of temperature or height variation are the heat dissipation that can directly influence energy consumption equipment, energy consumption
The problems such as, so calculation method provided in this embodiment is more scientific, actual conditions are more bonded, are saved to energy consumption place
It can be transformed stronger with directive significance when improvement and optimization.In addition, the energy consumption place asset management table in step S1 can be from enterprise
Financial system in obtain, can also be by financial system and energy consumption mark post value computing system or the interface pair of energy consumption management system
It connects, then asset management table in energy consumption place is imported into energy consumption mark post value computing system or energy consumption management system, being in calculating in this way can
Directly to transfer from energy consumption mark post value computing system or energy consumption management system, energy consumption premise temperature information can be passed by temperature
Sensor obtains.
It should also be noted that, the calculating of energy consumption mark post value is carried out according to facility information, architecture information and temperature information
Theoretical value calculate or suggest that reference value calculates, relatively objective true, the power consumption in the energy consumption place of energy consumption mark post value reaction, meter
The purpose for calculating this value is: (1) rendering an account for the monthly energy consumption place electricity charge and provide comparison data, in particular turn powered base station offer
Reference data can audit the electricity charge in time and render an account data if deviation is excessive, so as to be reduced or avoided the electricity charge more reports,
Disorderly report phenomenon;(2) support data are provided for technical energy saving, cost can be made for energy-saving equipment investment by energy consumption mark post value
And budget return analysis;(3) can targetedly analyze energy saving direction, for example, a computer room power consumption values it is excessive be due to building
Caused by the reasons such as the low efficiency of group unreasonable structure or refrigeration equipment mismanagement or alternating current-direct current converting apparatus;(4) from
Generally carry out the managing power consumption in energy consumption place.
Preferably, asset management table information in energy consumption place described in step S1 includes each information technoloy equipment in energy consumption place
Rated power, the rated power of each refrigeration equipment, ac-dc conversion equipment transformation efficiency and energy consumption place building coefficient, it is described
Energy consumption premise temperature information includes energy consumption place room temperature-time relationship table and energy consumption place outdoor temperature-time relationship table.
What needs to be explained here is that all devices in energy consumption place all can be registered in the asset management of energy consumption place as assets
In table, all essential informations of meeting registering apparatus when equipment is registered, such as building structure (the board house knot of energy consumption place (such as computer room)
Structure or brick laying structure), area etc., for another example the manufacturer of information technoloy equipment or refrigeration equipment (such as air-conditioning), device model, type,
Rated power etc., the alternating current-direct current transformation efficiency of ac-dc conversion equipment, can all register on the books similar to various to convenient for another example
Management.
Preferably, energy consumption place asset management table information and energy consumption premise temperature information that the basis is got calculate
The step for energy consumption mark post value, i.e. step S2 include:
S21: energy consumption basic data P1 is calculated according to formula (1):
P1=P2+P3 (1);
S22: energy consumption mark post value S is calculated according to formula (2):
S=P1 × R1 × (P2/R2) × T (2);
Wherein, P2 is the total rated power of all information technoloy equipments in energy consumption place, and P3 is all refrigeration equipments in energy consumption place
Total rated power, R1 be energy consumption place building coefficient, R2 be energy consumption place in ac-dc conversion equipment transformation efficiency, T is energy
The difference of consumption place room temperature and outdoor temperature is greater than the duration of the first preset value.
When implementing the present embodiment, the first preset value can be set to 5 DEG C, and T is energy consumption place room temperature and outdoor temp
Degree difference be greater than the first preset value duration namely refer to, energy consumption place room temperature differed with outdoor temperature 5 DEG C or more when
It is long, may be 2 hours, it is also possible to be 5 hours, specific duration information according to energy consumption place room temperature-time relationship table and
Energy consumption place outdoor temperature-time relationship table obtains.
Preferably, when energy consumption place building is board house, if the difference of energy consumption place room temperature and outdoor temperature is big
In the first preset value, the value of energy consumption place building coefficient is 0.9, if the difference of energy consumption place room temperature and outdoor temperature
Less than the first preset value, the value of energy consumption place building coefficient is 1.05;When energy consumption place building is brick laying structure, if
The difference of energy consumption place room temperature and outdoor temperature is greater than the first preset value, and the value of energy consumption place building coefficient is 0.8, such as
The difference of fruit energy consumption place room temperature and outdoor temperature is 1.2 less than the first preset value, the value of energy consumption place building coefficient.
The preferred value of these parameters is according to lot of experimental data and summary of experience gained, using the parameter value of the present embodiment
The accuracy of calculated result can be improved.
Embodiment 2
As shown in Fig. 2, the present embodiment provides a kind of energy consumption management methods, comprising:
P1: the electricity consumption data in current energy consumption mark post value and financial statement are obtained;
P2: energy consumption irrelevance is calculated according to the energy consumption mark post value and electricity consumption data;
P3: energy consumption place is managed according to the energy consumption irrelevance;
Wherein, the energy consumption mark post value calculating method that the current energy consumption mark post value can be provided by embodiment 1 is counted
It calculates and obtains.
What needs to be explained here is that the calculating of energy consumption mark post value be according to facility information, architecture information and temperature information into
Capable theoretical value calculates or suggests that reference value calculates, relatively objective true, if according to energy consumption mark post value and electricity consumption data meter
The energy consumption irrelevance of calculating, which has exceeded, receives range, it is necessary to related adjustment is carried out, to facilitate staff or administrative staff
Understand, adjust and manage entire energy consumption place.
Preferably, it described the step for calculating energy consumption irrelevance according to the energy consumption mark post value and electricity consumption data, that is, walks
Suddenly P2 includes:
Energy consumption irrelevance X is calculated by formula (3):
X=abs (S-Q)/S (3);
Wherein, abs is ABS function, and S is current energy consumption mark post value, and Q is the electricity consumption data in financial statement.
Preferably, described the step for being managed according to the energy consumption irrelevance to energy consumption place, i.e. step P3 include:
P31: judging whether the energy consumption irrelevance X is greater than the second preset value, if the energy consumption irrelevance X is greater than second
Preset value carries out in next step;What needs to be explained here is that illustrating financial report if energy consumption irrelevance X is not more than the second preset value
Electricity consumption data and current energy consumption mark post value in table are coincide substantially, then do not need to carry out following verification movement, in this way can be with
Working efficiency is improved, if energy consumption irrelevance is greater than the second preset value, it is understood that there may be both sides reason, on the one hand the reason is that coming
From current energy consumption mark post value, if energy consumption Premises Equipment has update, introduces or eliminate, and the letter in energy consumption place asset management table
Breath does not timely update, and the electricity consumption data that will lead in calculated result and financial statement have relatively large deviation, need this when
The relevant information in energy consumption place asset management table is checked and modifies, on the other hand the reason is that electricity consumption in financial statement
Data also result in the electricity consumption data in calculated result and financial statement if someone makes a false report, lies about or report by mistake related data
There is relatively large deviation, but it is indefinite due to, it needs us first to check the information in asset management table, therefore, needs
Carry out step P32.
P32: information verification modification application form is obtained;What needs to be explained here is that being checked in modification application form according to information
Content, can obtain wish check or verify target device, such as if information verification modification application form in content be
Wish to carry out a certain equipment information verification, or wishes verify in energy consumption place asset management table whether have a certain equipment, this
When just need to carry out step P33.
P33: energy consumption place asset management table is obtained;
P34: it checks the relevant information in the energy consumption place asset management table and whether checks to modify with the information and apply
The information of application verification modification is consistent in table, if inconsistent, carries out in next step;What needs to be explained here is that if information core
Content in modification application form is desirable to carry out information verification to equipment a certain in energy consumption place asset management table, is on the one hand needed
Confirm whether this equipment is registered in energy consumption place asset management table, if registered, carries out essential information verification, such as
Fruit is not registered, then is registered;Likewise, if the content in information verification modification application form is desirable to verify energy consumption place
Whether there is a certain equipment in asset management table, is on the one hand also required to confirm whether this equipment is registered in the asset management of energy consumption place
In table, if registered, essential information verification is carried out, if be not registered, is registered, it is also necessary to explanation, i.e.,
So that energy consumption irrelevance X is greater than the second preset value, also will appear verification unanimous circumstances, this when, it is likely that there have been
Human factor, it may be possible to make a false report, lie about or report by mistake related data, it is also possible to occur mistake when logging data, be arranged
It looks into.
P35: it is checked in modification application form according to the information and applies for energy consumption place Assets Reorganization Taking described in the content modification of modification
Manage the relevant information in table;What needs to be explained here is that including wishing to check or verifying in information verification modification application form
The essential information of equipment, if the register information of relevant device and information verification modification application form in energy consumption place asset management table
The essential information of middle relevant device is inconsistent, then is repaired by the essential information that information checks relevant device in modification application form
Change.
P36: more new energy consumption place asset management table.What needs to be explained here is that may call upon newest energy after update
It consumes place asset management table and carries out the calculating of primary energy consumption mark post value, and it is default to judge whether new energy consumption irrelevance is greater than second
Value, if illustrating correctly, otherwise the electricity consumption data in financial statement are in second preset value value etc, it can be determined that
Power consumption data in financial statement be it is wrong, need further to inquire reason.
Preferably, described checked in modification application form according to the information applies for energy consumption field described in the content modification of modification
The step for relevant information in institute's asset management table, i.e. before step P35 further include:
P350: audit in the information verification modification application form apply for whether the content of modification is correct, if correctly, carried out
Described checked in modification application form according to the information is applied in asset management table in energy consumption place described in the content modification of modification
The step for relevant information, otherwise, application failure.Increase audit step, it can be ensured that apply in information verification modification application form
The content of modification is correct, that is to say, that may insure to wish to check in information verification modification application form a certain setting of can verifying
Standby essential information is correctly, can to guarantee that modified information is also correctly, to improve and calculate reliability in this way.
Preferably, described audit applies for that whether correct this of content of modification moves in the information verification modification application form
Work includes:
P3501: equipment photo corresponding with the content of modification is applied in information verification modification application form, institute are obtained
Stating includes equipment essential information in equipment photo;
P3502: the content for applying for modification in the information verification modification application form and setting in the equipment photo are audited
Whether standby essential information is consistent, if unanimously, assert in the information verification modification application form and applying for that the content of modification is correct,
Otherwise, application failure.
What needs to be explained here is that, in order to improve the accuracy of audit, can be divided into more when the present embodiment is embodied
Grade audit, for example, carrying out two-stage if applying for that the content of modification is level-one different degree content in information verification modification application form
Audit only carries out level-one audit if applying for that the content of modification is second level different degree content in information verification modification application form,
Such mode needs first to carry out different degree classification to the content being related in energy consumption place asset management table, thus according to difference
The content of different degree rank carries out the audit of different stage, for example level-one audits (primary audit) and second level audit is (secondary to examine
Core), to improve review efficiency while improving and auditing accuracy.
Embodiment 3
As shown in figure 3, the present embodiment provides a kind of energy consumption management systems, comprising:
First acquisition unit: for obtaining energy consumption place asset management table information, energy consumption place indoor temperature information and energy
Consume place outdoor temperature information;
First computing unit: the information for being got according to the first acquisition module calculates energy consumption mark post value;
Second acquisition unit: for obtaining the electricity consumption in the calculated energy consumption mark post value of the first computing module and financial statement
Measure data;
Second computing unit: the information for being got according to the second acquisition module calculates energy consumption irrelevance;
Managing power consumption unit: for carrying out pipe to energy consumption place according to the calculated energy consumption irrelevance of the second computing module
Reason.
Energy consumption management system in this present embodiment is closed, each unit executes the concrete mode of operation in the related party
It is described in detail in the embodiment of method, explanation will not be elaborated herein.
The above is only the preferred embodiment of the present invention, it is noted that above-mentioned preferred embodiment is not construed as pair
Limitation of the invention, protection scope of the present invention should be defined by the scope defined by the claims..For the art
For those of ordinary skill, without departing from the spirit and scope of the present invention, several improvements and modifications can also be made, these change
It also should be regarded as protection scope of the present invention into retouching.
Claims (10)
1. energy consumption mark post value calculating method characterized by comprising
Obtain energy consumption place asset management table information and energy consumption premise temperature information;
Energy consumption mark post value is calculated according to the energy consumption place asset management table information and energy consumption premise temperature information got.
2. energy consumption mark post value calculating method according to claim 1, which is characterized in that the energy consumption place asset management table
Information includes the rated power of each information technoloy equipment in energy consumption place, the rated power of each refrigeration equipment, ac-dc conversion equipment
Transformation efficiency and energy consumption place building coefficient, the energy consumption premise temperature information include energy consumption place room temperature-time relationship
Table and energy consumption place outdoor temperature-time relationship table.
3. energy consumption mark post value calculating method according to claim 2, which is characterized in that the energy consumption field that the basis is got
Institute's asset management table information and energy consumption premise temperature information calculate the step for energy consumption mark post value and include:
Energy consumption basic data P1 is calculated according to formula (1):
P1=P2+P3 (1);
Energy consumption mark post value S is calculated according to formula (2):
S=P1 × R1 × (P2/R2) × T (2);
Wherein, P2 is the total rated power of all information technoloy equipments in energy consumption place, and P3 is the total of all refrigeration equipments in energy consumption place
Rated power, R1 are energy consumption place building coefficient, and R2 is ac-dc conversion equipment transformation efficiency in energy consumption place, and T is energy consumption field
The difference of institute's room temperature and outdoor temperature is greater than the duration of the first preset value.
4. energy consumption mark post value calculating method according to claim 3, which is characterized in that when energy consumption place, building is board house
When, if the difference of energy consumption place room temperature and outdoor temperature is greater than the first preset value, the value of energy consumption place building coefficient
Be 0.9, if the difference of energy consumption place room temperature and outdoor temperature less than the first preset value, energy consumption place building coefficient
Value is 1.05;When energy consumption place building is brick laying structure, if the difference of energy consumption place room temperature and outdoor temperature is greater than the
One preset value, the value of energy consumption place building coefficient is 0.8, if the difference of energy consumption place room temperature and outdoor temperature is less than
First preset value, the value of energy consumption place building coefficient are 1.2.
5. energy consumption management method characterized by comprising
Obtain the electricity consumption data in current energy consumption mark post value and financial statement;
Energy consumption irrelevance is calculated according to the energy consumption mark post value and electricity consumption data;
Energy consumption place is managed according to the energy consumption irrelevance;
Wherein, the current energy consumption mark post value is calculated by method described in claim 1-4 any one.
6. energy consumption management method according to claim 5, which is characterized in that described according to the energy consumption mark post value and electricity consumption
Measuring the step for data calculate energy consumption irrelevance includes:
Energy consumption irrelevance X is calculated by formula (3):
X=abs (S-Q)/S (3);
Wherein, abs is ABS function, and S is current energy consumption mark post value, and Q is the electricity consumption data in financial statement.
7. energy consumption management method according to claim 6, which is characterized in that it is described according to the energy consumption irrelevance to energy consumption
The step for place is managed include:
Judge whether the energy consumption irrelevance X is greater than the second preset value, if the energy consumption irrelevance X is greater than the second preset value,
It carries out in next step;
Obtain information verification modification application form;
Obtain energy consumption place asset management table;
It checks the relevant information in the energy consumption place asset management table and whether is checked in modification application form with the information and applied
The information for checking modification is consistent, if inconsistent, carries out in next step;
It is checked in modification application form and is applied in asset management table in energy consumption place described in the content modification of modification according to the information
Relevant information;
More new energy consumption place asset management table.
8. energy consumption management method according to claim 7, which is characterized in that described to check modification application according to the information
Before the step for applying for the relevant information in asset management table in energy consumption place described in the content modification of modification in table further include:
It audits in the information verification modification application form and applies for whether the content of modification is correct, if correctly, carrying out the basis
Apply for the relevant information in asset management table in energy consumption place described in the content modification of modification in the information verification modification application form
The step for, otherwise, application failure.
9. energy consumption management method according to claim 8, which is characterized in that the audit information verification modification application
Apply for that the whether correct This move of content modified includes: in table
Obtain equipment photo corresponding with the content of modification is applied in information verification modification application form, the equipment photo
In include equipment essential information;
Audit the content for applying for modification in the information verification modification application form and the equipment essential information in the equipment photo
It is whether consistent, if unanimously, assert in the information verification modification application form and applying for that the content of modification is correct, otherwise, application
Failure.
10. energy consumption management system characterized by comprising
First acquisition unit: for obtaining energy consumption place asset management table information, energy consumption place indoor temperature information and energy consumption field
Institute's outdoor temperature information;
First computing unit: the information for being got according to the first acquisition module calculates energy consumption mark post value;
Second acquisition unit: for obtaining the electricity consumption number in the calculated energy consumption mark post value of the first computing module and financial statement
According to;
Second computing unit: the information for being got according to the second acquisition module calculates energy consumption irrelevance;
Managing power consumption unit: for being managed according to the calculated energy consumption irrelevance of the second computing module to energy consumption place.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811484288.9A CN109586285A (en) | 2018-12-06 | 2018-12-06 | Energy consumption mark post value calculating method, energy consumption management method and energy consumption management system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811484288.9A CN109586285A (en) | 2018-12-06 | 2018-12-06 | Energy consumption mark post value calculating method, energy consumption management method and energy consumption management system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109586285A true CN109586285A (en) | 2019-04-05 |
Family
ID=65927294
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811484288.9A Pending CN109586285A (en) | 2018-12-06 | 2018-12-06 | Energy consumption mark post value calculating method, energy consumption management method and energy consumption management system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109586285A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113342872A (en) * | 2021-05-26 | 2021-09-03 | 上海蓝色帛缔智能工程有限公司 | PUE energy consumption monitoring-based method and electronic equipment |
CN114049017A (en) * | 2021-11-16 | 2022-02-15 | 重庆瑞盾科技发展有限公司 | Electricity charge cost management method and system based on alternating current-direct current intelligent switch ammeter |
Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101393451A (en) * | 2007-09-19 | 2009-03-25 | 谭雄 | Construction energy-conserving control method and system |
CN102243685A (en) * | 2011-03-30 | 2011-11-16 | 翎零碳建筑科技(上海)有限公司 | Quantizing system and computing method of carbon dioxide emission reduction quantity based on building |
CN102609808A (en) * | 2012-01-17 | 2012-07-25 | 北京百度网讯科技有限公司 | Method and device for performing energy consumption management on data center |
CN102645915A (en) * | 2011-09-17 | 2012-08-22 | 深圳市善能科技有限公司 | Energy-saving method and system for monitoring, diagnosing and controlling energy efficiency |
WO2013040376A2 (en) * | 2011-09-16 | 2013-03-21 | General Electric Company | Data provisioning system and method |
CN103034213A (en) * | 2012-12-20 | 2013-04-10 | 武汉北斗睿华科技有限公司 | Remote monitoring and controlling system |
CN103250169A (en) * | 2010-09-03 | 2013-08-14 | Abb研究有限公司 | A method for energy benchmarking and diagnosis through optimization and a system thereof |
CN103310107A (en) * | 2013-06-24 | 2013-09-18 | 浪潮电子信息产业股份有限公司 | Method for evaluating energy efficiency of data center infrastructure |
CN104680001A (en) * | 2015-02-11 | 2015-06-03 | 西安建筑科技大学 | Method for calculating architectural energy saving rate based on human body thermal adaptive model |
CN105700492A (en) * | 2015-12-03 | 2016-06-22 | 国家电网公司 | Building energy management system |
CN106681964A (en) * | 2016-12-24 | 2017-05-17 | 天津大学 | Public building energy consumption auditing statistics splitting method |
CN106709627A (en) * | 2016-11-21 | 2017-05-24 | 广州远正智能科技股份有限公司 | Benchmark energy consumption management method and device thereof |
CN106768044A (en) * | 2016-12-21 | 2017-05-31 | 潘小胜 | A kind of building energy consumption detection method |
CN107133372A (en) * | 2016-02-26 | 2017-09-05 | 中国移动通信集团公司 | A kind of mobile communication base station energy consumption mark post displaying appraisal procedure and device |
CN108427840A (en) * | 2018-03-09 | 2018-08-21 | 捷通智慧科技股份有限公司 | Data center's air conditioner system energy saving amount computational methods based on the prediction of benchmark efficiency |
-
2018
- 2018-12-06 CN CN201811484288.9A patent/CN109586285A/en active Pending
Patent Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101393451A (en) * | 2007-09-19 | 2009-03-25 | 谭雄 | Construction energy-conserving control method and system |
CN103250169A (en) * | 2010-09-03 | 2013-08-14 | Abb研究有限公司 | A method for energy benchmarking and diagnosis through optimization and a system thereof |
CN102243685A (en) * | 2011-03-30 | 2011-11-16 | 翎零碳建筑科技(上海)有限公司 | Quantizing system and computing method of carbon dioxide emission reduction quantity based on building |
WO2013040376A2 (en) * | 2011-09-16 | 2013-03-21 | General Electric Company | Data provisioning system and method |
CN102645915A (en) * | 2011-09-17 | 2012-08-22 | 深圳市善能科技有限公司 | Energy-saving method and system for monitoring, diagnosing and controlling energy efficiency |
CN102609808A (en) * | 2012-01-17 | 2012-07-25 | 北京百度网讯科技有限公司 | Method and device for performing energy consumption management on data center |
CN103034213A (en) * | 2012-12-20 | 2013-04-10 | 武汉北斗睿华科技有限公司 | Remote monitoring and controlling system |
CN103310107A (en) * | 2013-06-24 | 2013-09-18 | 浪潮电子信息产业股份有限公司 | Method for evaluating energy efficiency of data center infrastructure |
CN104680001A (en) * | 2015-02-11 | 2015-06-03 | 西安建筑科技大学 | Method for calculating architectural energy saving rate based on human body thermal adaptive model |
CN105700492A (en) * | 2015-12-03 | 2016-06-22 | 国家电网公司 | Building energy management system |
CN107133372A (en) * | 2016-02-26 | 2017-09-05 | 中国移动通信集团公司 | A kind of mobile communication base station energy consumption mark post displaying appraisal procedure and device |
CN106709627A (en) * | 2016-11-21 | 2017-05-24 | 广州远正智能科技股份有限公司 | Benchmark energy consumption management method and device thereof |
CN106768044A (en) * | 2016-12-21 | 2017-05-31 | 潘小胜 | A kind of building energy consumption detection method |
CN106681964A (en) * | 2016-12-24 | 2017-05-17 | 天津大学 | Public building energy consumption auditing statistics splitting method |
CN108427840A (en) * | 2018-03-09 | 2018-08-21 | 捷通智慧科技股份有限公司 | Data center's air conditioner system energy saving amount computational methods based on the prediction of benchmark efficiency |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113342872A (en) * | 2021-05-26 | 2021-09-03 | 上海蓝色帛缔智能工程有限公司 | PUE energy consumption monitoring-based method and electronic equipment |
CN113342872B (en) * | 2021-05-26 | 2022-11-18 | 上海蓝色帛缔智能工程有限公司 | PUE energy consumption monitoring-based method and electronic equipment |
CN114049017A (en) * | 2021-11-16 | 2022-02-15 | 重庆瑞盾科技发展有限公司 | Electricity charge cost management method and system based on alternating current-direct current intelligent switch ammeter |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Sendrayaperumal et al. | Energy auditing for efficient planning and implementation in commercial and residential buildings | |
Li et al. | Experimental validation of the simulation module of the water-cooled variable refrigerant flow system under cooling operation | |
CN109586285A (en) | Energy consumption mark post value calculating method, energy consumption management method and energy consumption management system | |
CN108846506B (en) | Energy system planning method, device, equipment and storage medium | |
CN103294041A (en) | Energy management system | |
CN114626643A (en) | Smart city government power supply regulation and control method, Internet of things system, device and medium | |
Li et al. | Predicting HVAC energy consumption in commercial buildings using multiagent systems | |
CN102708259B (en) | Method for modeling generator set excitation system based on frequency-domain method | |
CN106468467A (en) | A kind of air-conditioning refrigeration duty real-time estimate algorithm being applied to embedded control system | |
CN102156227A (en) | Detecting system and detecting method for non-vehicular charging machine | |
CN102620346B (en) | The temperature control-flow stepping of Self-controlled room temperature can regulate household heat metering system | |
Lang et al. | Engineering estimates versus impact evaluation of energy efficiency projects: Regression discontinuity evidence from a case study | |
Deng et al. | Indoor temperature control of cost-effective smart buildings via real-time smart grid communications | |
CN109523174A (en) | A kind of low-voltage platform area family change relationship check method based on data-driven | |
CN109738723A (en) | A kind of electric energy meter three-phase automatic identification method | |
Zhang et al. | Analysis of energy consumption prediction for office buildings based on GA-BP and BP algorithm | |
EP3054437A2 (en) | Digital power meter reader system for remote meter reading, and utilizing method using same | |
CN106646319B (en) | Electronic type voltage transformer exception discrimination method based on combined measurement in standing | |
KR20130122194A (en) | Method for managing energy controlling temperature differential of chilled or hot water and apparatus thereof | |
TWI503780B (en) | Optimizing system for contract demand and optimizing method using for the same | |
CN108427840A (en) | Data center's air conditioner system energy saving amount computational methods based on the prediction of benchmark efficiency | |
CN110514898A (en) | Power grid power supply capacity metering system based on 0.4KV client | |
Akbari et al. | An algorithm to disaggregate commercial whole-building hourly electrical load into end uses | |
Avotins et al. | IoT Solution Approach for Energy Consumption Reduction in Buildings: Part 3. Mathematical Model of Building and Experimental Results | |
Blazek et al. | Data centers revisited: assessment of the energy impact of retrofits and technology trends in a high-density computing facility |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |