CN109569140A - A kind of construction site environmental protection device for reducing dust - Google Patents

A kind of construction site environmental protection device for reducing dust Download PDF

Info

Publication number
CN109569140A
CN109569140A CN201811259519.6A CN201811259519A CN109569140A CN 109569140 A CN109569140 A CN 109569140A CN 201811259519 A CN201811259519 A CN 201811259519A CN 109569140 A CN109569140 A CN 109569140A
Authority
CN
China
Prior art keywords
wall
bolted
pipe
water
storage box
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811259519.6A
Other languages
Chinese (zh)
Other versions
CN109569140B (en
Inventor
赵智慧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuancheng Conscience Intellectual Property Service Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201811259519.6A priority Critical patent/CN109569140B/en
Publication of CN109569140A publication Critical patent/CN109569140A/en
Application granted granted Critical
Publication of CN109569140B publication Critical patent/CN109569140B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D47/00Separating dispersed particles from gases, air or vapours by liquid as separating agent
    • B01D47/06Spray cleaning
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D2247/00Details relating to the separation of dispersed particles from gases, air or vapours by liquid as separating agent
    • B01D2247/10Means for removing the washing fluid dispersed in the gas or vapours
    • B01D2247/101Means for removing the washing fluid dispersed in the gas or vapours using a cyclone

Landscapes

  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Prevention Of Fouling (AREA)
  • Separation Of Particles Using Liquids (AREA)

Abstract

The invention belongs to technical field of buildings, especially a kind of construction site environmental protection device for reducing dust, aiming at the problem that existing device for reducing dust can not achieve comprehensive effective dust removing effects, now propose following scheme, including water storage box, the top side outer wall of the water storage box is provided with the first opening, and first opening inner wall the first aqueduct being vertically arranged is bolted, distributive pipe has been bolted in the top exterior walls of first aqueduct, the center of top outer wall of the distributive pipe is provided with first through hole, and the gas-guide tube being vertically arranged is bolted in the inner wall of first through hole.In the present invention, the construction site environmental protection device for reducing dust is provided with the second aqueduct by the peripheral top outer wall in gas-guide tube, during pumping and draining, water flow can enter the inside of gas-guide tube by the second aqueduct, and then realize the spraying and dedusting effect to gas-guide tube inner air.

Description

A kind of construction site environmental protection device for reducing dust
Technical field
The present invention relates to technical field of buildings more particularly to a kind of construction site environmental protection device for reducing dust.
Background technique
With industrialization, the acceleration of urbanization process, construction industry is also fast-developing simultaneously, during construction, Since concrete, sand and cement etc. largely use, construction site can generate a large amount of dust, and construction worker's long-term work is inhaled After receiving the largely air with dust, huge harm can be caused to its body, it is therefore desirable to carry out to construction site effective Depositing dust processing.
Through retrieving, Chinese Patent Application No. is the patent of CN201210239691.1, discloses a kind of drop of pneumatic membrane building Dirt device, the dust absorbing including the guide duct connecting with pneumatic membrane building air-valve air outlet and positioned at the guide duct downstream fill It sets, the guide duct exit normal of the guide duct is downward, and the dust absorbing device is that guide duct described in opening face exports The water surface in pond, the guide duct outlet and the pond keeps suitable distance.The depositing dust of pneumatic membrane building in above-mentioned patent fills Set: 1 during dedusting, and the mode of atomized water spray has been used to be dusted, but can not improve water mist and ash well The contact area of dirt, and then the effect of atomized water spray dedusting is poor;2 in dust removal process, does not lead to the air with dust Enter in clear water, and then the air with dust cannot be made to come into full contact with clear water, and then can not achieve adequately dedusting comprehensively Effect.
Summary of the invention
The technical issues of can not achieve comprehensive effective dust removing effects based on existing device for reducing dust, the invention proposes one kind Construction site environmental protection device for reducing dust.
A kind of construction site environmental protection device for reducing dust proposed by the present invention, including water storage box, the top of the water storage box Portion side outer wall is provided with the first opening, and the first aqueduct being vertically arranged is bolted in the inner wall of the first opening, Distributive pipe has been bolted in the top exterior walls of first aqueduct, and the center of top outer wall of the distributive pipe is provided with One through-hole, and the gas-guide tube being vertically arranged is bolted in the inner wall of first through hole, the outer circumferential walls of the distributive pipe are logical Cross the sparge pipe for being bolted annular array distribution, and sparge pipe tilts upward setting, the peripheral top of the sparge pipe with Oblique block has been bolted in bottom interior wall, there are two the inner wall that the sparge pipe is located remotely from each other one end is bolted The support rod of adjacent upright setting, and same second rotation axis is connected with by bearing between two support rods, described second Support plate has been bolted in the outer circumferential walls of rotation axis, and the top exterior walls of support plate and bottom outer wall pass through bolt It is connected with the first hemisphere protrusion being equidistantly positioned, wind gathering pipe has been bolted in the top exterior walls of the gas-guide tube, and poly- Horizontally disposed first screen pack, the bottom of first screen pack has been bolted in the peripheral top inner wall of air hose The first support column being vertically arranged is bolted in central outer wall, and the circumference bottom interior wall of the gas-guide tube is connected by bolt It is connected to horizontally disposed second support column, and the circumference bottom outer wall of the first support column passes through the top of bearing and the second support column The second screw blade has been bolted in central outer wall connection, the outer circumferential walls of first support column.
Preferably, outer wall offers the water-guiding hole being equidistantly positioned, and the inner wall of water-guiding hole in the middle part of the gas-guide tube circumference The second aqueduct is bolted, the section of second aqueduct is trapezoidal, the circumference phase of second aqueduct Adjacent one end inner wall passes through bearing and is connected with the first rotation axis, and annular has been bolted in the outer circumferential walls of the first rotation axis The curved baffle of array distribution.
Preferably, the flabellum that draws water of annular array distribution is bolted in the circumference bottom outer wall of the gas-guide tube, The first screw blade, and the first screw blade and the second propeller has been bolted in the peripheral top outer wall of the gas-guide tube The leaf hand of spiral is opposite.
Preferably, rotation electricity has been bolted close to the side outer wall of the first aqueduct in the top of the water storage box Machine, and the third rotation axis being vertically arranged, the bottom of the third rotation axis is bolted in the output shaft of rotary electric machine Outer wall is socketed with the second tooth by bolt by being connected with horizontally disposed first gear, the circumference bottom outer wall of the gas-guide tube Wheel, and second gear and the mutual toe joint of first gear, the circumference side bottom outer wall of first aqueduct are provided with second and open Mouthful, and first gear is located at the inside of the second opening, the second gear is located at the top for the flabellum that draws water.
Preferably, dust leg, the top of the dust leg has been bolted in the bottom center inner wall of the water storage box Side outer wall is provided with third opening, and the inner wall of third opening is connected by the circumference bottom outer wall of bearing and gas-guide tube, institute The top other side outer wall for stating dust leg is bolted there are four the equidistant air jet pipe being vertically arranged, and the top of air jet pipe Check valve has been bolted in portion's outer wall.
Preferably, the second hemisphere being equidistantly positioned is bolted in the top and bottom outer wall of the dust leg The second drainpipe being vertically arranged, and the second drainpipe is bolted in protrusion, the bottom side outer wall of the dust leg Circumference bottom interior wall water discharging valve has been bolted.
Preferably, horizontally disposed first drainpipe has been bolted in the side bottom outer wall of the water storage box, and Circumference one end outer wall of first drainpipe has been connected through a screw thread the first drain-pipe cover.
Preferably, the screen pack being vertically arranged is bolted in the top other side inner wall of the water storage box, and The bottom outer wall of screen pack is connected by the bottom other side inner wall of bolt and water storage box.
Preferably, the other side top exterior walls of the water storage box are bolted the water inlet pipe being vertically arranged, and into The peripheral top outer wall of water pipe has been connected through a screw thread water inlet pipe lid, and the other side bottom outer wall of the water storage box is connected by bolt It is connected to horizontally disposed scum pipe, and scum pipe other side top exterior walls are connected by a hinge scum pipe lid, the water storage box Top the exhaust pipe being vertically arranged, and the peripheral top of exhaust pipe is bolted close to the other side outer wall of water inlet pipe Horizontally disposed drain tap has been bolted in inner wall, and the bottom four corners outer wall of the water storage box has been bolted Rubber pad.
Preferably, the rotary electric machine is connected with switch by conducting wire, and switchs and be connected with power supply by conducting wire.
Compared with prior art, the present invention provides a kind of construction site environmental protection device for reducing dust, having following has Beneficial effect:
1, construction site environmental protection device for reducing dust, by being provided with rotary electric machine, first gear and second gear, by turning Dynamic motor drives first gear rotation, and then drives the second gear rotation on gas-guide tube, so that gas-guide tube passes through with rotation It is provided with the second screw blade in gas-guide tube, air guide pipe outer wall is provided with the first screw blade, and by the first screw blade It is arranged to the opposite hand of spiral with the second screw blade, may be implemented to draw water upwards while to lower pumping, in turn Realize very convenient and fast operating effect.
2, the construction site environmental protection device for reducing dust, is provided with second by the peripheral top outer wall in gas-guide tube and leads Water pipe, during pumping and draining, water flow can enter the inside of gas-guide tube by the second aqueduct, and then realize to air guide The spraying and dedusting effect of pipe inner air.
3, the construction site environmental protection device for reducing dust, it is trapezoidal by the way that the section of the second aqueduct to be arranged to, make it Water flow can be improved in the pressure at the second aqueduct osculum end towards the inside of downtake in osculum end, and then improves water flow Spraying effect, while rotary curved baffle is provided at the osculum end of the second aqueduct, water flow will drive arc gear Plate rotation, the curved baffle of rotation can break up water flow, and then improve the contact area of droplet Yu air guide inner air tube, into The effect for improving spraying and dedusting of one step, the in addition setting of curved baffle can be with the contact area of itself and water flow, and then improves Its effect rotated.
4, construction site environmental protection device for reducing dust, by being provided with dust leg, and at the top of dust inside pipe wall It is provided with the second hemisphere protrusion with bottom, when the air with droplet enters the inside of dust leg, the second hemisphere protrusion can To improve the contact area of dust leg and air, so that the air with droplet is attached to the inner wall of dust leg, and then realize to sky The effect of the further dedusting of gas mixes in addition, the air in dust leg can be entered in water storage box by air jet pipe with clear water, and by Exhaust pipe discharge, and then realize final sufficient dust removing effects.
5, the construction site environmental protection device for reducing dust, by being provided with distributive pipe at the top of the first aqueduct, and The outer wall of distributive pipe is provided with sparge pipe, and sparge pipe tilts upward, and then improves the range of water spray, in addition in sparge pipe Be internally provided with oblique block and rotary support plate, and it is convex to be provided at the top and bottom of support plate the first hemisphere It rises, when water flow is passed through between oblique block and support plate, due to the difference of gap size, water flow can be made to generate current difference, in turn It drives support plate constantly to swing, and then improves the range of water spray, more comprehensive dust-laying effect is realized to air.
Detailed description of the invention
Fig. 1 is a kind of the schematic diagram of the section structure of construction site environmental protection device for reducing dust proposed by the present invention;
Fig. 2 is a kind of sparge pipe structural schematic diagram of construction site environmental protection device for reducing dust proposed by the present invention;
Fig. 3 is a kind of second aqueduct structure schematic diagram of construction site environmental protection device for reducing dust proposed by the present invention;
Fig. 4 is that a kind of gas-guide tube of construction site environmental protection device for reducing dust proposed by the present invention and the first aqueduct look up knot Structure schematic diagram;
Fig. 5 is a kind of overlooking structure diagram of construction site environmental protection device for reducing dust proposed by the present invention;
Fig. 6 be a kind of construction site environmental protection device for reducing dust proposed by the present invention and dirt pipe structural schematic diagram.
In figure: 1 first drainpipe, 2 first drain-pipe covers, 3 water storage boxes, 4 draw water flabellum, 5 first aqueducts, 6 gas-guide tubes, 7 first screw blades, 8 second aqueducts, 801 first rotation axis, 802 curved baffles, 9 second screw blades, 10 distributive pipes, 11 Sparge pipe, 1101 oblique blocks, 1,102 second rotation axis, 1103 support plates, 1,104 first hemisphere protrusion, 1105 support rods, 12 are gathered Air hose, 13 first screen packs, 14 first support columns, 15 second support columns, 16 rotary electric machines, 17 third rotation axis, 18 exhausts Pipe, 19 drain taps, 20 water inlet pipe lids, 21 water inlet pipes, 22 scum pipes, 23 scum pipe lids, 24 screen packs, 25 air jet pipes, 26 Dust leg, 2,601 second hemisphere protrusion, 27 first gears, 28 second gears, 29 second drainpipes, 30 rubber pads.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.
In the description of the present invention, it is to be understood that, term " on ", "lower", "front", "rear", "left", "right", "top", The orientation or positional relationship of the instructions such as "bottom", "inner", "outside" is to be based on the orientation or positional relationship shown in the drawings, merely to just In description the present invention and simplify description, rather than the device or element of indication or suggestion meaning must have a particular orientation, with Specific orientation construction and operation, therefore be not considered as limiting the invention.
Referring to Fig.1-6, a kind of construction site environmental protection device for reducing dust, including water storage box 3, the top one of water storage box 3 Side outer wall is provided with the first opening, and the inner wall of the first opening is bolted the first aqueduct 5 being vertically arranged, and first Distributive pipe 10 has been bolted in the top exterior walls of aqueduct 5, and the center of top outer wall of distributive pipe 10 is provided with first through hole, And the gas-guide tube 6 being vertically arranged is bolted in the inner wall of first through hole, the outer circumferential walls of distributive pipe 10 are connected by bolt It is connected to the sparge pipe 11 of annular array distribution, and sparge pipe 11 tilts upward setting, in the peripheral top and bottom of sparge pipe 11 Wall has been bolted oblique block 1101, and the inner wall that sparge pipe 11 is located remotely from each other one end is bolted that there are two adjacent The support rod 1105 being vertically arranged, and same second rotation axis 1102 is connected with by bearing between two support rods 1105, Support plate 1103, and the top exterior walls of support plate 1103 and bottom has been bolted in the outer circumferential walls of second rotation axis 1102 The first hemisphere protrusion 1104 being equidistantly positioned is bolted in portion's outer wall, is internally provided with oblique gear in sparge pipe 11 Block 1101 and rotary support plate 1103, and the first hemisphere protrusion is provided in the top and bottom of support plate 1103 1104, when water flow is passed through between oblique block 1101 and support plate 1103, due to the difference of gap size, water flow can be made to generate stream Speed difference, and then drive support plate 1103 constantly to swing, and then improve the range of water spray, more comprehensive drop is realized to air Dirt effect, wind gathering pipe 12 has been bolted in the top exterior walls of gas-guide tube 6, and the peripheral top inner wall of wind gathering pipe 12 passes through spiral shell It tethers and is connected to horizontally disposed first screen pack 13, the bottom center outer wall of the first screen pack 13 has been bolted perpendicular Horizontally disposed second support column has been bolted in the first support column 14 being directly arranged, the circumference bottom interior wall of gas-guide tube 6 15, and the circumference bottom outer wall of the first support column 14 is connect by bearing with the center of top outer wall of the second support column 15, first The second screw blade 9 has been bolted in the outer circumferential walls of support column 14.
In the present invention, outer wall offers the water-guiding hole being equidistantly positioned in the middle part of 6 circumference of gas-guide tube, and the inner wall of water-guiding hole is equal Be bolted the second aqueduct 8, the section of the second aqueduct 8 be it is trapezoidal, the section of the second aqueduct 8 is arranged to ladder Shape makes its osculum end towards the inside of downtake 6, water flow can be improved in the pressure at 8 osculum end of the second aqueduct, and then improves The spraying effect of water flow, the adjacent one end inner wall of the circumference of the second aqueduct 8 pass through bearing and are connected with the first rotation axis 801, And first rotation axis 801 outer circumferential walls be bolted annular array distribution curved baffle 802, curved baffle 802 Setting, can with the contact area of itself and water flow, and then improve its rotation effect;
The flabellum 4 that draws water of annular array distribution, the circumference of gas-guide tube 6 is bolted in the circumference bottom outer wall of gas-guide tube 6 The first screw blade 7, and 9 hand of spiral phase of the first screw blade 7 and the second screw blade has been bolted in top exterior walls Instead;
Rotary electric machine 16, and rotary electric machine has been bolted close to the side outer wall of the first aqueduct 5 in the top of water storage box 3 The third rotation axis 17 being vertically arranged is bolted in 16 output shaft, and the bottom outer wall of third rotation axis 17 passes through connection There is horizontally disposed first gear 27, the circumference bottom outer wall of gas-guide tube 6 is socketed with second gear 28, and the second tooth by bolt Wheel 28 and the mutual toe joint of first gear 27, the circumference side bottom outer wall of the first aqueduct 5 are provided with the second opening, and the first tooth Wheel 27 is located at the inside of the second opening, and second gear 28 is located at the top for the flabellum 4 that draws water;
Dust leg 26 has been bolted in the bottom center inner wall of water storage box 3, and the top side outer wall of dust leg 26 is provided with Third opening, and the inner wall of third opening is connect by bearing with the circumference bottom outer wall of gas-guide tube 6, the top of dust leg 26 is another Side outer wall is bolted there are four the equidistant air jet pipe 25 being vertically arranged, and the top exterior walls of air jet pipe 25 pass through It is bolted check valve, the conducting direction of check valve is from bottom to up;
The second hemisphere protrusion 2601 being equidistantly positioned, dust is bolted in the top and bottom outer wall of dust leg 26 The second drainpipe 29 being vertically arranged, and the circumference bottom of the second drainpipe 29 is bolted in the bottom side outer wall of pipe 26 Water discharging valve has been bolted in portion's inner wall;
The side bottom outer wall of water storage box 3 has been bolted horizontally disposed first drainpipe 1, and the first drainpipe 1 Circumference one end outer wall has been connected through a screw thread the first drain-pipe cover 2;
The top other side inner wall of water storage box 3 is bolted the screen pack 24 being vertically arranged, and screen pack 24 Bottom outer wall is connect by bolt with the bottom other side inner wall of water storage box 3;
The water inlet pipe 21 being vertically arranged, and the circumference of water inlet pipe 21 is bolted in the other side top exterior walls of water storage box 3 Top exterior walls have been connected through a screw thread water inlet pipe lid 20, and the other side bottom outer wall of water storage box 3 has been bolted level and has set The scum pipe 22 set, and 22 other side top exterior walls of scum pipe are connected by a hinge scum pipe lid 23, the top of water storage box 3 is leaned on The exhaust pipe 18 being vertically arranged is bolted in the other side outer wall of nearly water inlet pipe 21, and in the peripheral top of exhaust pipe 18 Horizontally disposed drain tap 19 has been bolted in wall, and rubber has been bolted in the bottom four corners outer wall of water storage box 3 Rubber mat 30;
Rotary electric machine 16 is connected with switch by conducting wire, and switchs and be connected with power supply by conducting wire.
In use, user is injected firstly the need of by the waste water generated in building or directly by clear water by water inlet pipe 21 In water storage box 3, by waste residue in 24 filtered wastewater of the second screen pack, after water storage box 3 is filled with water, start rotary electric machine 16, drive first gear 27 to rotate by rotary electric machine 16, and then the second gear 28 on gas-guide tube 6 is driven to rotate, so that air guide Pipe 6 is with rotation, and by being provided with 9 leaf of the second propeller in gas-guide tube 6,6 outer wall of gas-guide tube is provided with the first propeller Leaf 7, and the first screw blade 7 and the second screw blade 9 are arranged to the opposite hand of spiral may be implemented to lower pumping Meanwhile drawing water upwards, air of the higher position with dust is pumped into gas-guide tube 6, during pumping and draining, water Stream can enter the inside of gas-guide tube 6 by the second aqueduct 8, and then realize the spraying and dedusting effect to 6 inner air of gas-guide tube, Then the air with droplet can enter the inside of dust leg 26, and dust leg 26 and air can be improved in the second hemisphere protrusion 2601 Contact area so that the air with droplet is attached to the inner wall of dust leg 26, and then realize the effect to the further dedusting of air Fruit, then, the air in dust leg 26 can be entered in water storage box by air jet pipe 25 to be mixed with clear water, and by 18 row of exhaust pipe Out, and then realize on the other hand final sufficient dust removing effects can pass through spray by the water being drawn upwardly out inside the first aqueduct 5 Water pipe 11 sprays, and further realizes to the comprehensive atomizing de-dusting of air.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto, Anyone skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its Inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.

Claims (10)

1. a kind of construction site environmental protection device for reducing dust, including water storage box (3), which is characterized in that the water storage box (3) Top side outer wall is provided with the first opening, and the first aqueduct being vertically arranged is bolted in the inner wall of the first opening (5), the top exterior walls of first aqueduct (5) have been bolted distributive pipe (10), the top of the distributive pipe (10) Central outer wall is provided with first through hole, and the gas-guide tube (6) being vertically arranged is bolted in the inner wall of first through hole, described The sparge pipe (11) of annular array distribution is bolted in the outer circumferential walls of distributive pipe (10), and sparge pipe (11) is tilted towards Oblique block (1101), the spray has been bolted in upper setting, the peripheral top and bottom interior wall of the sparge pipe (11) The inner wall that water pipe (11) is located remotely from each other one end is bolted there are two the support rod (1105) of adjacent upright setting, and two Same second rotation axis (1102), the circle of second rotation axis (1102) are connected with by bearing between support rod (1105) All outer walls have been bolted support plate (1103), and the top exterior walls of support plate (1103) and bottom outer wall pass through spiral shell The the first hemisphere protrusion (1104) for being connected to and being equidistantly positioned is tethered, the top exterior walls of the gas-guide tube (6) have been bolted Wind gathering pipe (12), and horizontally disposed first screen pack has been bolted in the peripheral top inner wall of wind gathering pipe (12) (13), the first support column being vertically arranged is bolted in the bottom center outer wall of first screen pack (13) (14), horizontally disposed second support column (15), and first has been bolted in the circumference bottom interior wall of the gas-guide tube (6) The circumference bottom outer wall of support column (14) is connect by bearing with the center of top outer wall of the second support column (15), and described first The second screw blade (9) have been bolted in the outer circumferential walls of dagger (14).
2. a kind of construction site environmental protection device for reducing dust according to claim 1, which is characterized in that the gas-guide tube (6) outer wall offers the water-guiding hole being equidistantly positioned in the middle part of circumference, and the inner wall of water-guiding hole has been bolted second and has led Water pipe (8), the section of second aqueduct (8) be it is trapezoidal, the adjacent one end inner wall of circumference of second aqueduct (8) is logical It crosses bearing to be connected with the first rotation axis (801), and annular array has been bolted in the outer circumferential walls of the first rotation axis (801) The curved baffle (802) of distribution.
3. a kind of construction site environmental protection device for reducing dust according to claim 2, which is characterized in that the gas-guide tube (6) flabellum that draws water (4) of annular array distribution, the circumference of the gas-guide tube (6) is bolted in circumference bottom outer wall Top exterior walls have been bolted the first screw blade (7), and the first screw blade (7) and the second screw blade (9) spiral It is contrary.
4. a kind of construction site environmental protection device for reducing dust according to claim 3, which is characterized in that the water storage box (3) top has been bolted rotary electric machine (16) close to the side outer wall of the first aqueduct (5), and rotary electric machine (16) Output shaft be bolted the third rotation axis (17) being vertically arranged, the bottom outer wall of the third rotation axis (17) is logical It crosses and is connected with horizontally disposed first gear (27), the circumference bottom outer wall of the gas-guide tube (6) is socketed with second by bolt Gear (28), and second gear (28) and first gear (27) mutual toe joint, one side bottom of circumference of first aqueduct (5) Outer wall is provided with the second opening, and first gear (27) is located at the inside of the second opening, and the second gear (28), which is located at, to be drawn water The top of flabellum (4).
5. a kind of construction site environmental protection device for reducing dust according to claim 4, which is characterized in that the water storage box (3) bottom center inner wall has been bolted dust leg (26), and the top side outer wall of the dust leg (26) is provided with Third opening, and the inner wall of third opening is connect by bearing with the circumference bottom outer wall of gas-guide tube (6), the dust leg (26) Top other side outer wall be bolted there are four the equidistant air jet pipe (25) being vertically arranged, and the top of air jet pipe (25) Check valve has been bolted in portion's outer wall.
6. a kind of construction site environmental protection device for reducing dust according to claim 5, which is characterized in that the dust leg (26) the second hemisphere protrusion (2601) being equidistantly positioned, the dust leg is bolted in top and bottom outer wall (26) the second drainpipe (29) being vertically arranged, and the circle of the second drainpipe (29) is bolted in bottom side outer wall Water discharging valve has been bolted in all bottom interior walls.
7. a kind of construction site environmental protection device for reducing dust according to claim 6, which is characterized in that the water storage box (3) horizontally disposed first drainpipe (1), and the circumference of the first drainpipe (1) has been bolted in side bottom outer wall One end outer wall has been connected through a screw thread the first drain-pipe cover (2).
8. a kind of construction site environmental protection device for reducing dust according to claim 7, which is characterized in that the water storage box (3) screen pack (24) being vertically arranged, and the bottom of screen pack (24) is bolted in top other side inner wall Outer wall is connect by bolt with the bottom other side inner wall of water storage box (3).
9. a kind of construction site environmental protection device for reducing dust according to claim 8, which is characterized in that the water storage box (3) water inlet pipe (21) being vertically arranged, and the peripheral top of water inlet pipe (21) is bolted in other side top exterior walls Outer wall has been connected through a screw thread water inlet pipe lid (20), and water has been bolted in the other side bottom outer wall of the water storage box (3) The scum pipe (22) of flat setting, and scum pipe (22) other side top exterior walls are connected by a hinge and have scum pipe lid (23), it is described The exhaust pipe (18) being vertically arranged is bolted close to the other side outer wall of water inlet pipe (21) for the top of water storage box (3), And the peripheral top inner wall of exhaust pipe (18) has been bolted horizontally disposed drain tap (19), the water storage box (3) Bottom four corners outer wall rubber pad (30) have been bolted.
10. a kind of construction site environmental protection device for reducing dust according to claim 9, which is characterized in that the rotation Motor (16) is connected with switch by conducting wire, and switchs and be connected with power supply by conducting wire.
CN201811259519.6A 2018-10-26 2018-10-26 Dust device is used in building site environmental protection Active CN109569140B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811259519.6A CN109569140B (en) 2018-10-26 2018-10-26 Dust device is used in building site environmental protection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811259519.6A CN109569140B (en) 2018-10-26 2018-10-26 Dust device is used in building site environmental protection

Publications (2)

Publication Number Publication Date
CN109569140A true CN109569140A (en) 2019-04-05
CN109569140B CN109569140B (en) 2020-11-24

Family

ID=65921008

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811259519.6A Active CN109569140B (en) 2018-10-26 2018-10-26 Dust device is used in building site environmental protection

Country Status (1)

Country Link
CN (1) CN109569140B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111637063A (en) * 2020-06-12 2020-09-08 周燕玲 Taste formula show integrated device based on landscape
CN112482291A (en) * 2020-12-28 2021-03-12 德州贯科通风设备有限公司 Dust device for construction
CN113731074A (en) * 2021-08-30 2021-12-03 安徽燚诚环保科技有限公司 Dust fall atomizer and dust fall water-spraying system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3800513A (en) * 1973-02-14 1974-04-02 F Lappin Anti-air pollution device
CN105880057A (en) * 2016-06-24 2016-08-24 中国灌溉排水发展中心 Open flow passage type rotating nozzle capable of being applied to ground covering
CN206762538U (en) * 2017-02-27 2017-12-19 重庆交通大学 A kind of sewage disposal waste gas purification apparatus
CN108554064A (en) * 2018-05-04 2018-09-21 佘峰 A kind of a wide range of dust-extraction unit in construction site

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3800513A (en) * 1973-02-14 1974-04-02 F Lappin Anti-air pollution device
CN105880057A (en) * 2016-06-24 2016-08-24 中国灌溉排水发展中心 Open flow passage type rotating nozzle capable of being applied to ground covering
CN206762538U (en) * 2017-02-27 2017-12-19 重庆交通大学 A kind of sewage disposal waste gas purification apparatus
CN108554064A (en) * 2018-05-04 2018-09-21 佘峰 A kind of a wide range of dust-extraction unit in construction site

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111637063A (en) * 2020-06-12 2020-09-08 周燕玲 Taste formula show integrated device based on landscape
CN111637063B (en) * 2020-06-12 2021-07-06 周燕玲 Taste formula show integrated device based on landscape
CN112482291A (en) * 2020-12-28 2021-03-12 德州贯科通风设备有限公司 Dust device for construction
CN113731074A (en) * 2021-08-30 2021-12-03 安徽燚诚环保科技有限公司 Dust fall atomizer and dust fall water-spraying system

Also Published As

Publication number Publication date
CN109569140B (en) 2020-11-24

Similar Documents

Publication Publication Date Title
CN109569140A (en) A kind of construction site environmental protection device for reducing dust
CN111111347B (en) Waste gas purification tower
CN108554523A (en) A kind of waste material grinding device for building reducing dust
CN107812749A (en) A kind of ground rice processing rice-washing device
CN110833737B (en) Multistage filtering wet dust removal fan
CN109966903B (en) Flue gas processing apparatus that thermal power plant used
CN107376515A (en) A kind of air conditioner filter screen cleaning device
CN108057297A (en) A kind of efficient device for reducing dust in construction site
CN216259988U (en) Anti-blocking device for desulfurizing tower of desulfurizing system
CN114984701B (en) Energy-concerving and environment-protective dust collecting equipment of construction
CN215654536U (en) Environment-friendly dust removal equipment
CN208771070U (en) Dynamic screw sieve liquid film dust pelletizing system
CN208407170U (en) A kind of waste material grinding device for building reducing dust
CN2477284Y (en) Centrifugal wetting fume purifier
CN206867927U (en) A kind of deduster
CN220937896U (en) Precession type dust collector
CN205995202U (en) A kind of Horizontal dedusting equipment
CN205164372U (en) Do benefit to water film deduster who improves rate of gathering dust
CN213790715U (en) Air purification equipment for construction site
CN214552183U (en) Self-cleaning centrifugal water mist-proof multi-stage energy-saving water curtain dust removal device
CN216879639U (en) Novel ball-milling jar device of making an uproar falls easily collects material, gives sound insulation
CN216812214U (en) Centrifugal blower is used in mine
CN211069334U (en) Building site dust collector
CN2400169Y (en) Ball dust remover
CN211635809U (en) Absorption tower defroster with self-cleaning function

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20201105

Address after: 242100 No. 21-5 Zhonggang West Road, Jianping Town, Langxi County, Xuancheng City, Anhui Province

Applicant after: Xuancheng Conscience Intellectual Property Service Co.,Ltd.

Address before: 233500 Room 2509, Room 2, 13 Building, Jiulong International Area A, Mengcheng County, Bozhou City, Anhui Province

Applicant before: Zhao Zhihui

GR01 Patent grant