Summary of the invention
This application provides the method for attaching of middle box culvert caulking strip, close for not carrying out in the related technology to filleting to solve
The problem of sealing in the presence of then may result in construction.
According to the one aspect of the application, a kind of method of attaching of middle box culvert caulking strip is provided, comprising: centering box culvert
The location for paste of filleting is dried, and makes the location for paste of the filleting is dry to make an uproar, wherein the location for paste includes;Middle box culvert ring contact
Face, the reserved groove for pasting caulking strip;Alite paste is smeared in the location for paste of the middle box culvert, and inspection after alite paste is smeared in day
Whether the area of the location for paste of the alite paste covering is more than threshold value;In the case where being less than as the threshold value, again
It carries out smearing the alite paste;In the case where being more than the threshold value, scheduled duration is placed, wherein the scheduled duration is root
It is determined according to the temperature and humidity being previously obtained with the corresponding table for placing duration;After placing scheduled duration, by caulking strip
It is inserted in the groove of filleting, wherein unified by the caulking strip when being inserted in caulking strip in the reserved groove of the middle box culvert
The outer arc side of outer edge and the reserved groove of the middle box culvert is close to, and first fixes corner when being inserted in caulking strip, then to corner
Both sides push;The tight caulking strip is successively struck, makes the caulking strip docile on the middle box culvert.
Further, before the location for paste of the filleting to the middle box culvert is dried, the method also includes:
The location for paste is cleared up, so that the location for paste is without attachment.
Further, before being dried to the location for paste of the filleting of the middle box culvert, the method also includes: sentence
The filleting that breaks then repairs the defect if there is defect with the presence or absence of defect.
Further, the predetermined time is 10 to 30 minutes.
Further, carrying out drying to the location for paste of the filleting of the middle box culvert includes: using blowtorch to the middle box culvert
The location for paste of filleting dried.
Further, successively strike the tight caulking strip make the caulking strip docile on the middle box culvert after, it is described
Method further include: by the middle static placement of box culvert more than 12 hours.
Further, by the static placement of the middle box culvert more than 12 hours after, which comprises in institute to be installed
State the position installation connecting bolt gasket of middle box culvert;By the raising middle flask cable case under the connecting bolt gasket.
Further, after by the raising middle flask cable case under the connecting bolt gasket, which comprises check
Whether the caulking strip pasted falls off, and in the case where falling off, is pasted again.
It further, included: by the middle box culvert surface covering waterproof more than 12 hours by the middle static placement of box culvert
The static placement of measure was more than 12 hours.
Further, before the caulking strip is inserted in the groove of the filleting, the method also includes: to described
Caulking strip smears waterproofing agent.
By the application, using following steps: the location for paste of the filleting of centering box culvert is dried, and makes the viscous of the filleting
It is dry at patch to make an uproar, wherein the location for paste includes;Middle box culvert loop interface, the reserved groove for pasting caulking strip;In the middle box culvert
Location for paste smear alite paste, and day smear check after alite paste the location for paste of alite paste covering area whether
More than threshold value;In the case where being less than as the threshold value, re-starts and smear the alite paste;It is being more than the feelings of the threshold value
Under condition, scheduled duration is placed, wherein the scheduled duration is corresponding with placement duration according to the temperature and humidity being previously obtained
What table determined;After placing scheduled duration, caulking strip is inserted in the groove of filleting, wherein be inserted in caulking strip described
It is unified to lean on the outer arc side of the outer edge and the reserved groove of the middle box culvert of the caulking strip when in the reserved groove of middle box culvert
Tightly, first corner is fixed when being inserted in caulking strip, then is pushed to corner both sides;The tight caulking strip is successively struck, the filleting is made
Docile is on the middle box culvert.It solves and filleting is not sealed in the related technology, in the presence of may result in construction
The problem of, improve middle box culvert construction technology.
Specific embodiment
It should be noted that in the absence of conflict, the features in the embodiments and the embodiments of the present application can phase
Mutually combination.The application is described in detail below with reference to the accompanying drawings and in conjunction with the embodiments.
In order to make those skilled in the art more fully understand application scheme, below in conjunction in the embodiment of the present application
Attached drawing, the technical scheme in the embodiment of the application is clearly and completely described, it is clear that described embodiment is only
The embodiment of the application a part, instead of all the embodiments.Based on the embodiment in the application, ordinary skill people
Member's every other embodiment obtained without making creative work, all should belong to the model of the application protection
It encloses.
It should be noted that the description and claims of this application and term " first " in above-mentioned attached drawing, "
Two " etc. be to be used to distinguish similar objects, without being used to describe a particular order or precedence order.It should be understood that using in this way
Data be interchangeable under appropriate circumstances, so as to embodiments herein described herein.In addition, term " includes " and " tool
Have " and their any deformation, it is intended that cover it is non-exclusive include, for example, containing a series of steps or units
Process, method, system, product or equipment those of are not necessarily limited to be clearly listed step or unit, but may include without clear
Other step or units listing to Chu or intrinsic for these process, methods, product or equipment.
In the present embodiment, a kind of method of attaching of middle box culvert caulking strip is provided, Fig. 1 is mentioned according to the embodiment of the present application
The flow chart of the method for attaching of the middle box culvert caulking strip supplied, as shown in Figure 1, the process includes the following steps:
The location for paste of step S101, the filleting of centering box culvert are dried, and make the location for paste of filleting is dry to make an uproar, wherein are pasted
Place includes;Middle box culvert loop interface, the reserved groove for pasting caulking strip;
Step S102 smears alite paste in the location for paste of middle box culvert, and inspection alite paste covering after alite paste is smeared in day
The area of location for paste whether be more than threshold value;
Step S103 re-starts smearing alite paste in the case where being less than as threshold value;Be more than threshold value the case where
Under, place scheduled duration, wherein scheduled duration is true according to the temperature and humidity that are previously obtained and the corresponding table for placing duration
Fixed;
Caulking strip is inserted in the groove of filleting by step S104 after placing scheduled duration, wherein by caulking strip set
It is unified to be close to the outer arc side of the reserved groove of the outer edge and middle box culvert of caulking strip when entering in the reserved groove of box culvert, it covers
First corner is fixed when entering caulking strip, then is pushed to corner both sides;
Step S105 successively strikes tight caulking strip, makes caulking strip docile on middle box culvert.
It solves and filleting is not sealed in the related technology through the above steps, in the presence of may result in construction
The problem of, improve middle box culvert construction technology.
Optionally, before the location for paste of the filleting to middle box culvert is dried, the above method further include: to location for paste into
Row cleaning, so that location for paste is without attachment.
Optionally, before the location for paste of the filleting of centering box culvert is dried, the above method further include: whether judge filleting
Existing defects then repair defect if there is defect.
Optionally, the predetermined time is 10 to 30 minutes;Preferably 10 to 15 minutes.
Optionally, the location for paste of the filleting of centering box culvert carry out drying include: using blowtorch centering box culvert filleting it is viscous
It is dried at patch.
Optionally, successively strike tight caulking strip make caulking strip docile on middle box culvert after, the above method further include: will in
The static placement of box culvert was more than 12 hours.
Optionally, after placement that middle box culvert is static was more than 12 hours, the above method includes: in middle box culvert to be installed
Position is installed by connecting bolt gasket;By raising middle flask cable case under connecting bolt gasket.
Optionally, after by raising middle flask cable case under connecting bolt gasket, the above method includes: the filleting for checking and pasting
Whether item falls off, and in the case where falling off, is pasted again.
It optionally, included: that middle box culvert surface covers to waterproof measure is static to be put more than 12 hours by the static placement of middle box culvert
It sets more than 12 hours.
Optionally, before in the groove that caulking strip is inserted in filleting, the above method further include: waterproof is smeared to caulking strip
Agent.
It is illustrated below with reference to an alternative embodiment.
Preparation before caulking strip stickup
After middle box culvert reaches building site, preferably by the side of inspecting for acceptance of quality inspection engineer and management carry out again in box culvert stickup
Preparation.Box culvert all carries out presentation quality inspection in every piece, middle box culvert surface answer it is bright and clean smooth, no honeycomb, dew muscle, flawless,
Unfilled corner.If finding light defects in filleting attachment, light defects are modified, filleting is nearby not allow for defect, hole
Position should be complete, the sundries such as no cement slurry.Middle box culvert there are mass defect is repaired, according to middle box culvert after passed examination
Box culvert in category classification stacking.
The filleting of box culvert in judgement can be sentenced with the presence or absence of the mode of defect by the way of artificial intelligence
Disconnected: the filleting of centering box culvert is taken pictures, and the photo taken pictures then is carried out binary conversion treatment, obtains black and white figure
Picture.Using black and white image as input data, it is input in preparatory trained model.The model is by multiple groups training number
It is obtained according to training, training data includes two classes, includes flawless middle box culvert filleting in every group of first kind training data
Black-and-white photograph and identify the black-and-white photograph be flawless middle box culvert photo identification information;In second every group of class training data
It include the black-and-white photograph of defective middle box culvert filleting and the identification information for identifying the black-and-white photograph defective locations.Pass through this
The filleting that the model that sample training obtains can just obtain box culvert in this after the photo for inputting a middle box culvert filleting whether there is
The conclusion of defect.Narrow in the situation using big data quantity training, judging can be more accurate with the increasing of amount of training data,
Efficiency and accuracy are improved compared to manual identified.
Middle box culvert caulking strip is pasted
Before caulking strip is pasted, box culvert need to prepare following material in each piece:
Serial number |
Project |
Type |
Unit |
Quantity |
Remarks |
1 |
Caulking strip |
Circumferential weld |
Set |
1 |
|
2 |
Adhesive glue |
|
Bucket |
1 |
|
3 |
Brush |
|
? |
5 |
|
4 |
Glue scraping cutter |
|
? |
2 |
|
5 |
Wooden mallet |
|
It is a |
2 |
|
6 |
Glue bucket |
|
It is a |
2 |
|
1. box culvert cleaning should ensure that filleting portion faces without attachment, free from dust in, and centering box culvert is made when not allowing to clear up
At damage, it is smooth clean and tidy to clear up rear surface.
2. material preparation will rationally be prepared sticking construction tool and middle box culvert caulking strip etc., the material used by technical instruction
It needs to use after the assay was approved as required.
3. dry cleansing is answered on box culvert surface in when pasting, when necessary using the portion for pasting caulking strip on box culvert in blowtorch drying
Position.
4. smearing alite paste on middle box culvert loop interface, the reserved groove for pasting caulking strip with brush, smears and wants uniformly,
Do not allow to leak brush phenomenon to occur.
5. cool after being painted with alite paste set a period of time (10-15 minutes general, different with gas epidemic disaster), contacted to finger
When not viscous, then the frame shape caulking strip processed is inserted in filleting groove.
It is unified that the outer edge of caulking strip and middle box culvert are reserved into groove 6. caulking strip is inserted in the reserved groove of middle box culvert
Outer arc side be close to, first corner is fixed when being inserted in caulking strip, then to corner both sides push.
7. successively striking tight caulking strip with wooden mallet, make caulking strip docile on middle box culvert, be careful not to crack caulking strip, glues
Caulking strip after patch answers that secured, smooth, tight, position is accurate, must not have heave, overlength and phenomena such as notch.The institute of middle box culvert
There is corner there is not allowed that shrugging, sunken shoulder phenomenon.Middle box culvert is being pasted in installing caulking strip 12h, and underground must not be sent assembled.
8. connection bolt elastic packing washer is gone into the well by quantity with middle box culvert bolt matching, in the progress of underground when box culvert installation
It is sleeved under connecting bolt gasket.
9. wet weather or rainy day, surface covered Lock gate it is noted that protecting to the caulking strip pasted.
10. to smear waterproofing agent to caulking strip when the ponding of underground.
The caulking strip that posted must not be caused to damage when box culvert is gone into the well and transported in 11..
Construction lofting
It is tested in batches to box culvert in finished product according to construction speed and assembled quality condition, survey engineer, simultaneously
Construction lofting is carried out to box culvert in i.e. assembly.Every batch of is 5~10 pieces, and measures interval and be not more than 3 days;If multiple batches of middle box culvert
Assembled quality is preferable, then can suitably increase box culvert quantity in every batch of;Conversely, should then increase measurement frequency, every batch of is reduced
Quantity.
Construction lofting content include two aspect contents: first is that in finished product box culvert inspection, inspection content includes: the gradient, height
Faulting of slab ends and seam situation between journey, mileage and adjacent section of jurisdiction.Second is that the setting-out of middle box culvert to be assembled, includes mileage, two sides
The contents such as boundary, design and actual measurement end face elevation.
After survey engineer completes measurement, is formed measurement report (this work should be completed in 1h), in time propose report
Give shield driver.Shield driver is according to measurement report as a result, determining the assembling scheme of next step.If box culvert is spelled in report display
Dress error transfinites, then should link up in time with supervision control engineering teacher and chief technology officer, determines handling suggestion and provides assembly side in next step
Case.
It should also be noted that, the terms "include", "comprise" or its any other variant are intended to nonexcludability
It include so that the process, method, commodity or the equipment that include a series of elements not only include those elements, but also to wrap
Include other elements that are not explicitly listed, or further include for this process, method, commodity or equipment intrinsic want
Element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including element
There is also other identical elements in process, method, commodity or equipment.
The above is only embodiments herein, are not intended to limit this application.To those skilled in the art,
Various changes and changes are possible in this application.It is all within the spirit and principles of the present application made by any modification, equivalent replacement,
Improve etc., it should be included within the scope of the claims of this application.