CN109523042A - Shorten the method for Substation secondary circuit corrective maintenance time using planar bar code technology - Google Patents

Shorten the method for Substation secondary circuit corrective maintenance time using planar bar code technology Download PDF

Info

Publication number
CN109523042A
CN109523042A CN201811475891.0A CN201811475891A CN109523042A CN 109523042 A CN109523042 A CN 109523042A CN 201811475891 A CN201811475891 A CN 201811475891A CN 109523042 A CN109523042 A CN 109523042A
Authority
CN
China
Prior art keywords
secondary circuit
substation secondary
file
pdf format
dimensional code
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811475891.0A
Other languages
Chinese (zh)
Inventor
王汝强
郑灿涛
徐辉
郭玉峰
蔚科
郭兵
董聪
欧庆满
王正顺
张超
张爽
朱本功
郭宗耀
徐昊琨
郭庆军
马萧萧
赵琦
郭丹丹
邵维廷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wenshang Power Supply Co Of State Grid Shandong Electric Power Co
State Grid Corp of China SGCC
Original Assignee
Wenshang Power Supply Co Of State Grid Shandong Electric Power Co
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wenshang Power Supply Co Of State Grid Shandong Electric Power Co, State Grid Corp of China SGCC filed Critical Wenshang Power Supply Co Of State Grid Shandong Electric Power Co
Priority to CN201811475891.0A priority Critical patent/CN109523042A/en
Publication of CN109523042A publication Critical patent/CN109523042A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/20Administration of product repair or maintenance
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06KGRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
    • G06K17/00Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations
    • G06K17/0022Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations arrangements or provisious for transferring data to distant stations, e.g. from a sensing device
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Health & Medical Sciences (AREA)
  • General Business, Economics & Management (AREA)
  • General Engineering & Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses the methods for shortening Substation secondary circuit corrective maintenance time using planar bar code technology, the following steps are included: the corresponding paper drawing of Substation secondary circuit to be converted to the file of PDF format, the corresponding paper drawing of Substation secondary circuit includes second loop return wiring figure, the file of PDF format is subjected to classification storage so that the file of PDF format carried out with actual Substation secondary circuit it is corresponding;The file of each PDF format is converted into corresponding two dimensional code, includes all information of the file of the PDF format in the two dimensional code, can be obtained electric hookup corresponding to Substation secondary circuit by scanning the two dimensional code.The technical solution of the disclosure converts paper document to the electronic document of pdf format, and pdf file is converted into corresponding two dimensional code, service personnel is in maintenance, it is only necessary to scan the two-dimensional code and maintenance can be realized, it is omitted to take much time and searches the time of paper document, improve work efficiency.

Description

Shorten the method for Substation secondary circuit corrective maintenance time using planar bar code technology
Technical field
This disclosure relates to which troubleshooting technical field, shortens Substation secondary circuit more particularly to using planar bar code technology The method of corrective maintenance time.
Background technique
With the development of electric power network technique, the increase of power consumer, Substation secondary circuit failure occurs often, in substation When secondary circuit failure occurs, need substation equipment maintenance and repair personnel guarantee safety, on time, the completion of high quality maintenance task, according to wanting It asks and eliminates related defects in time, Substation secondary circuit corrective maintenance time is the weight for determining Substation secondary circuit and working normally Factor is wanted, Substation secondary circuit corrective maintenance time is up to two hours, seriously affects and be timely completed Substation secondary circuit Maintenance task and timely defect elimination.
Substation secondary circuit corrective maintenance time is too long, it will the normal confession for the current supply circuit for causing substation to connect Electricity, and the length of power-off time has biggish conflict to electricity consumption user in economic benefit, under normal circumstances, if electricity consumption user is Enterprise, wherein the time of relevant device stopped is too long, and a large amount of time and energy will be consumed by being again turned on.Therefore, how to contract Short Substation secondary circuit corrective maintenance time is the main technical problems to be solved of technical scheme institute.
Mode by existing Substation secondary circuit trouble hunting carries out investigation discovery, and current substation secondary returns When the trouble hunting of road, usually station personnel search corresponding secondary circuit paper for the secondary circuit of the substation Matter wiring diagram is proofreaded one by one according to secondary circuit of the wiring diagram to actual substation, is checked, and secondary circuit papery Wiring diagram is generally stored in individual file cabinet, search get up it is very troublesome, and according to papery wiring diagram carry out secondary circuit There is also the problems such as checking is inconvenient to when maintenance, Substation secondary circuit corrective maintenance time is seriously affected, substation is caused The secondary circuit failure repair time is too long.
In conclusion causing in the prior art for searching corresponding paper document when Substation secondary circuit trouble hunting Repair time too long problem, still shortage effective solution scheme.
Summary of the invention
In order to solve the deficiencies in the prior art, embodiment of the disclosure, which is provided, shortens substation using planar bar code technology The method of secondary circuit failure repair time, this method utilize planar bar code technology by the corresponding paper drawing of Substation secondary circuit The two dimensional code checked can be scanned by being changed into mobile terminal, substantially increase the overhaul efficiency of Substation secondary circuit, shorten inspection Repair the time.
To achieve the goals above, the application uses following technical scheme:
Shorten the method for Substation secondary circuit corrective maintenance time using planar bar code technology, comprising the following steps:
The corresponding paper drawing of Substation secondary circuit is converted to the file of PDF format, Substation secondary circuit is corresponding Paper drawing include second loop return wiring figure, the file of PDF format is subjected to classification storage so that the file of PDF format with Actual Substation secondary circuit is corresponded to;
The file of each PDF format is converted into corresponding two dimensional code, includes the PDF format in the two dimensional code All information of file can be obtained electric hookup corresponding to Substation secondary circuit by scanning the two dimensional code.
Further technical solution, when the corresponding paper drawing of Substation secondary circuit is converted to the file of PDF format, It is realized by way of scanning, paper document is converted to the file of PDF format in the way of scanning, and the file after conversion is clear It is clear, and occupancy memory space is small, is easy to save.
The file of each PDF format is converted into corresponding two dimensional code, the two dimensional code by further technical solution For invisible two-dimensional codes, invisible two-dimensional codes are visible under ultraviolet light or infrared light.
In the technical scheme, invisible two-dimensional codes visible light is not as it can be seen that invisible two-dimensional codes are pasted onto the cabinet body of substation On, in this way, the invisible two-dimensional codes can not be seen on cabinet body, just can be used when only meeting particular light condition, Invisible two-dimensional codes concealment is strong, avoids any a possibility that capable of scanning the two dimensional code per capita, while being also avoided that inoperative people Malicious operation of the member to Substation secondary circuit.
Further technical solution is scanned two dimensional code using mobile terminal, and it is right to obtain Substation secondary circuit institute The electric hookup answered;Or
Ultraviolet lamp and infrared lamp are set on mobile terminal, realize invisible two-dimensional codes as it can be seen that then for issuing corresponding light Mobile terminal scans the two dimensional code using camera, obtains electric hookup corresponding to Substation secondary circuit.
Through the above technical solutions, ultraviolet lamp and infrared lamp are arranged only on mobile terminal or purple light or red can be issued The equipment of light could scan invisible two-dimensional codes, realize to scan the two-dimensional code and need special-purpose terminal that could complete, and increase and check Permission and safety.
Further technical solution, is provided with electrical quantity acquisition unit in Substation secondary circuit, and the electrical quantity is adopted Collection unit is used to acquire the electric data of Substation secondary circuit and by communication port transfers to Cloud Server;
In Cloud Server, corresponding Substation secondary circuit topology is established according to actual Substation secondary circuit Figure, while electrical quantity acquisition unit electric quantity information collected being transmitted in Substation secondary circuit topological diagram, realize electricity Tolerance is associated with Substation secondary circuit topological diagram;
The electrical quantity range that should have when the electrical quantity of acquisition is worked normally with the Substation secondary circuit is sentenced It is disconnected, if no longer in range, carrying out alarm in Substation secondary circuit topological diagram and showing, while warning information is sent to scene Mobile terminal informs that service personnel carries out in time targetedly maintenance.
Further technical solution, the electrical quantity acquisition unit information collected include voltage data and electric current number There is corresponding sample circuit to obtain respectively according to, voltage data and current data, obtains data and be filtered, amplify and A/D first Conversion process, data that treated are being transmitted to Cloud Server, and wired mode or wireless mode can be used when transmitting in data, works as cloud When acquisition data are sufficiently complete in server, the supplement of data can be carried out, the supplement of data can refer to historical data progress herein Supplement.
Embodiment of the disclosure, which is also disclosed, shortens Substation secondary circuit corrective maintenance time using planar bar code technology System, comprising:
Electronic document obtains module, for the corresponding paper drawing of Substation secondary circuit to be converted to the text of PDF format Part, the corresponding paper drawing of Substation secondary circuit include second loop return wiring figure, and the file of PDF format is carried out classification and is deposited Storage so that the file of PDF format carried out with actual Substation secondary circuit it is corresponding;
Two dimensional code conversion module, for the file of each PDF format to be converted into corresponding two dimensional code, the two dimensional code In include the PDF format file all information, by scan the two dimensional code can be obtained Substation secondary circuit institute it is right The electric hookup answered.
Embodiment of the disclosure also discloses a kind of utilization planar bar code technology shortening Substation secondary circuit trouble hunting The cloud platform of time, including Cloud Server, the Cloud Server obtain electronic document, and the electronic document is by substation secondary The corresponding paper drawing in circuit is converted to the file of PDF format, and the corresponding paper drawing of Substation secondary circuit includes secondary returning The file of PDF format is carried out classification storage by road wiring diagram, so that the file of PDF format and actual Substation secondary circuit It is corresponded to;
In Cloud Server, including two dimensional code conversion module, it is corresponding for the file of each PDF format to be converted into Two dimensional code, include all information of the file of the PDF format in the two dimensional code;
Mobile terminal device can be obtained electrical wiring corresponding to Substation secondary circuit by scanning the two dimensional code Figure, the mobile terminal device are also communicated with Cloud Server, the information issued for receiving Cloud Server.
Embodiment of the disclosure also discloses a kind of computer readable storage medium, wherein it is stored with a plurality of instruction, institute It states instruction and is suitable for load by the processor of terminal device and being executed and described utilize planar bar code technology shortening Substation secondary circuit The method of corrective maintenance time.
Embodiment of the disclosure also discloses a kind of terminal device, including processor and computer readable storage medium, Processor is for realizing each instruction;Computer readable storage medium is suitable for for storing a plurality of instruction, described instruction by processor It loads and executes the method for shortening Substation secondary circuit corrective maintenance time using planar bar code technology.
Compared with prior art, the beneficial effect of the disclosure is:
1, the technical solution of the disclosure converts paper document to the electronic document of pdf format, and pdf file is converted to Corresponding two dimensional code, service personnel is in maintenance, it is only necessary to scan the two-dimensional code and maintenance can be realized, be omitted and take much time It the time for removing lookup paper document, improves work efficiency.
2, the two dimensional code in the technical solution of the disclosure may be configured as invisible two-dimensional codes, in this way, only service personnel is equipped with Special equipment could scan the two dimensional code, enhance the permission that two dimensional code uses, and improve the peace of Substation secondary circuit maintenance Full property and professional.
3, it is additionally arranged the corresponding circuit topology figure of Substation secondary circuit in Cloud Server, can be checked on the topological diagram The electric information of secondary circuit can carry out alarm and show when electric information is not in normal data area, while will alarm letter Breath is issued to live mobile terminal, is convenient for on-call maintenance.
Detailed description of the invention
The accompanying drawings constituting a part of this application is used to provide further understanding of the present application, and the application's shows Meaning property embodiment and its explanation are not constituted an undue limitation on the present application for explaining the application.
Fig. 1 is the method flow diagram of some examples of implementation of the disclosure;
Fig. 2 is the tension measuring circuit figure of some examples of implementation of the disclosure;
Fig. 3 is the current measurement circuit figure of some examples of implementation of the disclosure;
Fig. 4 is the system block diagram of some examples of implementation of the disclosure;
Fig. 5 is that the scene of some examples of implementation of the disclosure uses figure.
Specific embodiment
It is noted that following detailed description is all illustrative, it is intended to provide further instruction to the application.Unless another It indicates, all technical and scientific terms used herein has usual with the application person of an ordinary skill in the technical field The identical meanings of understanding.
It should be noted that term used herein above is merely to describe specific embodiment, and be not intended to restricted root According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singular Also it is intended to include plural form, additionally, it should be understood that, when in the present specification using term "comprising" and/or " packet Include " when, indicate existing characteristics, step, operation, device, component and/or their combination.
In a kind of typical embodiment of the application, shorten substation using planar bar code technology as shown in Figure 1, providing The method of secondary circuit failure repair time, comprising the following steps:
The corresponding paper drawing of Substation secondary circuit is converted to the file of PDF format, Substation secondary circuit is corresponding Paper drawing include second loop return wiring figure, the file of PDF format is subjected to classification storage so that the file of PDF format with Actual Substation secondary circuit is corresponded to;
The file of each PDF format is converted into corresponding two dimensional code, includes the PDF format in the two dimensional code All information of file can be obtained electric hookup corresponding to Substation secondary circuit by scanning the two dimensional code.
In specific embodiment, the above-mentioned text that the corresponding paper drawing of Substation secondary circuit is converted to PDF format When part, since paper document quantity is larger, large scale scanner can be used and be scanned.
It is real by way of scanning when the corresponding paper drawing of Substation secondary circuit is converted to the file of PDF format It is existing, paper document is converted to the file of PDF format in the way of scanning, the file after conversion is clear, and it is empty to occupy storage Between it is small, be easy to save.
The file of each PDF format is converted into corresponding two dimensional code, the two dimensional code is invisible two-dimensional codes, stealthy Two dimensional code is visible under ultraviolet light or infrared light.Invisible two-dimensional codes are made of fineness of 10-20 μm of special printing ink, special The ingredient for printing ink includes black ink, red fluorescence powder, blue colour fluorescent powder and green emitting phosphor.Covering above invisible two-dimensional codes There is transparent protective layer, is equipped with hydrophilic layer on the surface of transparent protective layer.
It for above-mentioned invisible two-dimensional codes, is identified using image recognition acquisition equipment, image recognition acquisition equipment includes One of ultraviolet lamp and infrared lamp are whole, keep two dimensional code aobvious invisible two-dimensional codes irradiation by ultraviolet lamp or infrared lamp Shape.
In the technical scheme, invisible two-dimensional codes visible light is not as it can be seen that invisible two-dimensional codes are pasted onto the cabinet body of substation On, in this way, the invisible two-dimensional codes can not be seen on cabinet body, just can be used when only meeting particular light condition, Invisible two-dimensional codes concealment is strong, avoids any a possibility that capable of scanning the two dimensional code per capita, while being also avoided that inoperative people Malicious operation of the member to Substation secondary circuit.
Two dimensional code is scanned using mobile terminal, obtains electric hookup corresponding to Substation secondary circuit;Or Person
Ultraviolet lamp and infrared lamp are set on mobile terminal, realize invisible two-dimensional codes as it can be seen that then for issuing corresponding light Mobile terminal scans the two dimensional code using camera, obtains electric hookup corresponding to Substation secondary circuit.
Through the above technical solutions, ultraviolet lamp and infrared lamp are arranged only on mobile terminal or purple light or red can be issued The equipment of light could scan invisible two-dimensional codes, realize to scan the two-dimensional code and need special-purpose terminal that could complete, and increase and check Permission and safety.
Electrical quantity acquisition unit is provided in Substation secondary circuit, the electrical quantity acquisition unit is for acquiring power transformation Stand secondary circuit electric data and by communication port transfers to Cloud Server;
In Cloud Server, corresponding Substation secondary circuit topology is established according to actual Substation secondary circuit Figure, while electrical quantity acquisition unit electric quantity information collected being transmitted in Substation secondary circuit topological diagram, realize electricity Tolerance is associated with Substation secondary circuit topological diagram;
The electrical quantity range that should have when the electrical quantity of acquisition is worked normally with the Substation secondary circuit is sentenced It is disconnected, if no longer in range, carrying out alarm in Substation secondary circuit topological diagram and showing, while warning information is sent to scene Mobile terminal informs that service personnel carries out in time targetedly maintenance.
The electrical quantity acquisition unit information collected includes voltage data and current data, voltage data and electric current number According to there is corresponding sample circuit to obtain respectively, obtains data and be filtered, amplify and A/D conversion process first, treated number According to Cloud Server is being transmitted to, wired mode or wireless mode is can be used when transmitting in data, when obtaining data not in Cloud Server When enough complete, the supplement of data can be carried out, the supplement of data can refer to historical data and be supplemented herein.
In specific embodiment, as shown in Fig. 2, in voltage detecting circuit, R9, R21 form resistance pressure-dividing network, at than Example reduces input voltage.Operational amplifier LM1B, R11, R13, R10, R12 form differential type subtracter.For calculating partial pressure net The voltage difference of network.Thus, it is possible to directly measure the DC voltage of system.The particular advantages of the circuit are, are transported using LM1B It puts and devises differential type circuit, which can offset the signal of Transfer pipe simultaneously, and interference is made the difference, and substantially increase measurement Precision.
As shown in figure 3, current detection circuit U3 is Hall current sensor.When a current passes through, what is be positively correlated is defeated Voltage out.R16, R17, R18, LM2B form differential type subtracter.For by the output voltage of Hall current sensor carry out into The amplification of one step.The characteristics of circuit, is, using Hall element, without destroying original main circuit, only cable need to be passed through Hall Element can be detected electric current.In addition, the circuit can be supported using LM2B operational amplifier design differential type sample detection, difference channel Disappear the interference of Transfer pipe, improves measurement accuracy.
Embodiment of the disclosure, which is also disclosed, shortens Substation secondary circuit corrective maintenance time using planar bar code technology System, comprising:
Electronic document obtains module, for the corresponding paper drawing of Substation secondary circuit to be converted to the text of PDF format Part, the corresponding paper drawing of Substation secondary circuit include second loop return wiring figure, and the file of PDF format is carried out classification and is deposited Storage so that the file of PDF format carried out with actual Substation secondary circuit it is corresponding;
Two dimensional code conversion module, for the file of each PDF format to be converted into corresponding two dimensional code, the two dimensional code In include the PDF format file all information, by scan the two dimensional code can be obtained Substation secondary circuit institute it is right The electric hookup answered.
In specific embodiment, the two dimensional code of papery is printed on the cabinet body for being pasted onto Substation secondary circuit, As shown in Figure 5.
Embodiment of the disclosure also discloses a kind of utilization planar bar code technology shortening Substation secondary circuit trouble hunting The cloud platform of time, as shown in figure 4, including Cloud Server, the Cloud Server obtains electronic document, and the electronic document is will The corresponding paper drawing of Substation secondary circuit is converted to the file of PDF format, the corresponding paper drawing of Substation secondary circuit Including second loop return wiring figure, the file of PDF format is subjected to classification storage, so that the file of PDF format and actual power transformation Secondary circuit of standing is corresponded to;
In Cloud Server, including two dimensional code conversion module, it is corresponding for the file of each PDF format to be converted into Two dimensional code, include all information of the file of the PDF format in the two dimensional code;
Mobile terminal device can be obtained electrical wiring corresponding to Substation secondary circuit by scanning the two dimensional code Figure, the mobile terminal device are also communicated with Cloud Server, the information issued for receiving Cloud Server.
Embodiment of the disclosure also discloses a kind of computer readable storage medium, wherein it is stored with a plurality of instruction, institute It states instruction and is suitable for load by the processor of terminal device and being executed and described utilize planar bar code technology shortening Substation secondary circuit The method of corrective maintenance time.
Embodiment of the disclosure also discloses a kind of terminal device, including processor and computer readable storage medium, Processor is for realizing each instruction;Computer readable storage medium is suitable for for storing a plurality of instruction, described instruction by processor It loads and executes the method for shortening Substation secondary circuit corrective maintenance time using planar bar code technology.
It should be noted that flowcharts and block diagrams in the drawings show according to various embodiments of the present disclosure method and The architecture, function and operation in the cards of system.It should be noted that each box in flowchart or block diagram can represent A part of one module, program segment or code, a part of the module, program segment or code may include one or more A executable instruction for realizing the logic function of defined in each embodiment.It should also be noted that some alternately Realization in, function marked in the box can also occur according to the sequence that is marked in attached drawing is different from.For example, two connect The box even indicated can actually be basically executed in parallel or they can also be executed in a reverse order sometimes, This depends on related function.It should also be noted that each box and flow chart in flowchart and or block diagram And/or the combination of the box in block diagram, the dedicated hardware based system that functions or operations as defined in executing can be used are come It realizes, or the combination of specialized hardware and computer instruction can be used to realize.
The foregoing is merely preferred embodiment of the present application, are not intended to limit this application, for the skill of this field For art personnel, various changes and changes are possible in this application.Within the spirit and principles of this application, made any to repair Change, equivalent replacement, improvement etc., should be included within the scope of protection of this application.

Claims (10)

1. shortening the method for Substation secondary circuit corrective maintenance time using planar bar code technology, characterized in that including following step It is rapid:
The corresponding paper drawing of Substation secondary circuit is converted to the file of PDF format, the corresponding paper of Substation secondary circuit Matter drawing includes second loop return wiring figure, the file of PDF format is carried out classification storage, so that the file and reality of PDF format Substation secondary circuit corresponded to;
The file of each PDF format is converted into corresponding two dimensional code, includes the file of the PDF format in the two dimensional code All information, can be obtained electric hookup corresponding to Substation secondary circuit by scanning the two dimensional code.
2. shorten the method for Substation secondary circuit corrective maintenance time using planar bar code technology as described in claim 1, It is characterized in, it is real by way of scanning when the corresponding paper drawing of Substation secondary circuit is converted to the file of PDF format It is existing, paper document is converted to the file of PDF format in the way of scanning.
3. shorten the method for Substation secondary circuit corrective maintenance time using planar bar code technology as described in claim 1, It is characterized in, the file of each PDF format is converted into corresponding two dimensional code, the two dimensional code is invisible two-dimensional codes, stealthy Two dimensional code is visible under ultraviolet light or infrared light.
4. shorten the method for Substation secondary circuit corrective maintenance time using planar bar code technology as described in claim 1, It is characterized in, two dimensional code is scanned using mobile terminal, obtains electric hookup corresponding to Substation secondary circuit;Or
Ultraviolet lamp and infrared lamp are set on mobile terminal, realize invisible two-dimensional codes as it can be seen that then moving for issuing corresponding light Terminal scans the two dimensional code using camera, obtains electric hookup corresponding to Substation secondary circuit.
5. shorten the method for Substation secondary circuit corrective maintenance time using planar bar code technology as described in claim 1, It is characterized in, electrical quantity acquisition unit is provided in Substation secondary circuit, the electrical quantity acquisition unit is for acquiring power transformation Stand secondary circuit electric data and by communication port transfers to Cloud Server;
In Cloud Server, corresponding Substation secondary circuit topological diagram is established according to actual Substation secondary circuit, together When electrical quantity acquisition unit electric quantity information collected is transmitted in Substation secondary circuit topological diagram, realize electrical quantity with The association of Substation secondary circuit topological diagram;
The electrical quantity of acquisition is judged with the electrical quantity range that should have when Substation secondary circuit normal work, if No longer in range, alarm is carried out in Substation secondary circuit topological diagram and is shown, while warning information is sent to live movement Terminal informs that service personnel carries out in time targetedly maintenance.
6. shorten the method for Substation secondary circuit corrective maintenance time using planar bar code technology as claimed in claim 5, It is characterized in, the electrical quantity acquisition unit information collected includes voltage data and current data, voltage data and electric current number According to there is corresponding sample circuit to obtain respectively, obtains data and be filtered, amplify and A/D conversion process first, treated number According to Cloud Server is being transmitted to, wired mode or wireless mode is can be used when transmitting in data, when obtaining data not in Cloud Server When enough complete, the supplement of data can be carried out, the supplement of data can refer to historical data and be supplemented herein.
7. shortening the system of Substation secondary circuit corrective maintenance time using planar bar code technology, characterized in that include:
Electronic document obtains module, for the corresponding paper drawing of Substation secondary circuit to be converted to the file of PDF format, becomes Secondary circuit corresponding paper drawing in power station includes second loop return wiring figure, and the file of PDF format is carried out classification storage, so that The file of PDF format carries out corresponding with actual Substation secondary circuit;
Two dimensional code conversion module wraps in the two dimensional code for the file of each PDF format to be converted into corresponding two dimensional code All information of file containing the PDF format can be obtained corresponding to Substation secondary circuit by scanning the two dimensional code Electric hookup.
8. a kind of cloud platform for shortening Substation secondary circuit corrective maintenance time using planar bar code technology, characterized in that including Cloud Server, the Cloud Server obtain electronic document, and the electronic document is by the corresponding papery figure of Substation secondary circuit Paper is converted to the file of PDF format, and the corresponding paper drawing of Substation secondary circuit includes second loop return wiring figure, by PDF lattice The file of formula carries out classification storage so that the file of PDF format carried out with actual Substation secondary circuit it is corresponding;
In Cloud Server, including two dimensional code conversion module, for the file of each PDF format to be converted into corresponding two Code is tieed up, includes all information of the file of the PDF format in the two dimensional code;
Mobile terminal device can be obtained electric hookup corresponding to Substation secondary circuit, institute by scanning the two dimensional code It states mobile terminal device also to communicate with Cloud Server, the information issued for receiving Cloud Server.
9. a kind of computer readable storage medium, wherein being stored with a plurality of instruction, characterized in that described instruction is suitable for being set by terminal Standby processor is loaded and executes the method for being shortened Substation secondary circuit corrective maintenance time using planar bar code technology.
10. a kind of terminal device, including processor and computer readable storage medium, processor is for realizing each instruction;It calculates Machine readable storage medium storing program for executing is for storing a plurality of instruction, characterized in that described instruction is suitable for being loaded by processor and being executed utilizing two Tie up the method that code technology shortens Substation secondary circuit corrective maintenance time.
CN201811475891.0A 2018-12-04 2018-12-04 Shorten the method for Substation secondary circuit corrective maintenance time using planar bar code technology Pending CN109523042A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811475891.0A CN109523042A (en) 2018-12-04 2018-12-04 Shorten the method for Substation secondary circuit corrective maintenance time using planar bar code technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811475891.0A CN109523042A (en) 2018-12-04 2018-12-04 Shorten the method for Substation secondary circuit corrective maintenance time using planar bar code technology

Publications (1)

Publication Number Publication Date
CN109523042A true CN109523042A (en) 2019-03-26

Family

ID=65794369

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811475891.0A Pending CN109523042A (en) 2018-12-04 2018-12-04 Shorten the method for Substation secondary circuit corrective maintenance time using planar bar code technology

Country Status (1)

Country Link
CN (1) CN109523042A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110750662A (en) * 2019-10-16 2020-02-04 国网山东省电力公司汶上县供电公司 Transformer substation secondary drawing searching method and system
CN112000831A (en) * 2020-08-13 2020-11-27 贵州电网有限责任公司 Abnormal data identification optimization method based on transformer substation graph transformation
CN112307497A (en) * 2020-10-28 2021-02-02 国网福建省电力有限公司 Terminal strip informatization management method based on two-dimensional code and cloud storage technology
CN113238171A (en) * 2021-05-13 2021-08-10 贵州电网有限责任公司 Remote and rapid positioning and judging method for electric secondary circuit fault

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003235120A (en) * 2002-02-06 2003-08-22 Toshiba Eng Co Ltd Automatic load measuring device
CN106408091A (en) * 2016-08-29 2017-02-15 国家电网公司 Transformer station equipment information management platform
CN206021410U (en) * 2016-08-29 2017-03-15 江苏尚博信息科技有限公司 Concealed code identifier
CN108418304A (en) * 2018-03-09 2018-08-17 国家电网公司 Substation secondary circuit state monitoring method, apparatus and system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003235120A (en) * 2002-02-06 2003-08-22 Toshiba Eng Co Ltd Automatic load measuring device
CN106408091A (en) * 2016-08-29 2017-02-15 国家电网公司 Transformer station equipment information management platform
CN206021410U (en) * 2016-08-29 2017-03-15 江苏尚博信息科技有限公司 Concealed code identifier
CN108418304A (en) * 2018-03-09 2018-08-17 国家电网公司 Substation secondary circuit state monitoring method, apparatus and system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110750662A (en) * 2019-10-16 2020-02-04 国网山东省电力公司汶上县供电公司 Transformer substation secondary drawing searching method and system
CN112000831A (en) * 2020-08-13 2020-11-27 贵州电网有限责任公司 Abnormal data identification optimization method based on transformer substation graph transformation
CN112000831B (en) * 2020-08-13 2024-04-19 贵州电网有限责任公司 Abnormal data identification optimization method based on substation graph transformation
CN112307497A (en) * 2020-10-28 2021-02-02 国网福建省电力有限公司 Terminal strip informatization management method based on two-dimensional code and cloud storage technology
CN113238171A (en) * 2021-05-13 2021-08-10 贵州电网有限责任公司 Remote and rapid positioning and judging method for electric secondary circuit fault

Similar Documents

Publication Publication Date Title
CN109523042A (en) Shorten the method for Substation secondary circuit corrective maintenance time using planar bar code technology
Grimaccia et al. PV plant digital mapping for modules’ defects detection by unmanned aerial vehicles
CN105279937A (en) Internet of Things intelligent gas meter system
CN102811863B (en) Automated Inspection Of A Printed Image
CN107527081A (en) Based on luggage RFID tracing systems, method and service terminal
CN105182275B (en) Outdoor electrical energy meter fault self-verifying method
CN107391520B (en) Intelligent power distribution network planning and design auxiliary decision platform based on big data
CN105303805A (en) Thing internet intelligent water meter system
CN104698426B (en) Outdoor electrical energy meter fault examines terminal automatically
CN104794624A (en) Anti-counterfeiting system and anti-counterfeiting method based on random anti-counterfeiting marks
CN107315774A (en) Battalion's auxiliary tone integration data survey system and census method based on mobile Internet
CN103543378B (en) Platform sheet relation detection method
CN110346093A (en) Oil-immersed sleeve pipe leakage of oil detection system and method based on intelligent patrol detection platform
CN109283439A (en) A kind of discharge condition recognition methods based on three primary colours chrominance information and machine learning
CN105306589A (en) Intelligent water meter system with regular data reporting function
CN108305347A (en) A kind of controller switching equipment inspection operational method
CN103248779A (en) Image information managing method, image information managing apparatus, image information managing system, and evaluation chart
CN116660317B (en) Hot spot detection method, system, processor and storage medium of photovoltaic array
CN108269202A (en) Power equipment data information management system
CN116883717A (en) Platen checking method and device, computer readable storage medium and computer equipment
CN106248215A (en) A kind of real-time calculating system of power transformer critical component running temperature
CN104568492A (en) On-line detection device for printing machine breakdown and detection method
CN208460077U (en) Overvoltage inspection device based on Internet of Things
CN207968546U (en) A kind of highway green channel collecting vehicle information Transmission system
CN107273882A (en) A kind of non-intrusion type power screen cabinet identity description and intelligent identification Method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190326