CN109510148A CN201810936195.9A CN201810936195A CN109510148A CN 109510148 A CN109510148 A CN 109510148A CN 201810936195 A CN201810936195 A CN 201810936195A CN 109510148 A CN109510148 A CN 109510148A
Authority
CN
China
Prior art keywords
fixture block
handle
beryllium copper
power transmission
transmission line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810936195.9A
Other languages
Chinese (zh)
Inventor
吴秀松
黄兰英
朱筱玮
吴建伟
惠文博
吴旭静
金文杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinhua Bada Group Co Ltd Science And Technology Information Branch
Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
Jinhua Bada Group Co Ltd Science And Technology Information Branch
Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinhua Bada Group Co Ltd Science And Technology Information Branch, Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical Jinhua Bada Group Co Ltd Science And Technology Information Branch
Priority to CN201810936195.9A priority Critical patent/CN109510148A/en
Publication of CN109510148A publication Critical patent/CN109510148A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G7/00Overhead installations of electric lines or cables
    • H02G7/16Devices for removing snow or ice from lines or cables

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The invention discloses a kind of power transmission line DC de-icing devices of Fast Installation, it is desirable to provide provide it is a kind of it is highly-safe, pull intensity it is low, it is time-consuming less, a kind of power transmission line DC de-icing device for Fast Installation that work efficiency is high.Including spliced cables, described spliced cables one end is provided with cable hitching frame, the cable hitching frame includes upper fixture block and lower fixture block, the upper and lower fixture block front end is provided with clamping face, upper and lower installation clip slot is provided on clamping face, upper and lower beryllium copper sleeve with overhead line diameter matches is installed on installation clip slot above and below, the beryllium copper channel of integrally connected is provided with below the lower beryllium copper sleeve Depression Centers, internal screw thread is provided in the beryllium copper channel, the beryllium copper channel penetrates lower fixture block until its surface flushes;The folder gill is provided among the upper and lower fixture block, the frame gill is connected by a hinge;The upper lower fixture block rear end is provided with the handle of through-hole.The present invention is suitble to electric power maintenance personnel operation.

Description

A kind of power transmission line DC de-icing device of Fast Installation
Technical field
The present invention relates to a kind of power cable splicing fittings more particularly to a kind of power transmission line DC ice melting of Fast Installation to fill It sets.
Background technique
Current ice-melt operation be mostly by the way of direct current be shorted ice-melt, need staff will be shorted cable sling into The installation of row high-altitude requires more careful, workload to the wiring in high-altitude because having the requirement of ice-melt high current and conduction time Greatly, need to fill, tear open the connection of Stranded cable connector and high-tension line.In order to reduce power off time, new regulatory requirements subtract as far as possible Few ice-melt time (ice-melt operates overall time control within 4 hours), and use the retractable of current technology short-circuiting cable It is more time-consuming with fixation, staff is easy to happen fatigue, and in addition working environment general summer coolness is wet and slippery, working time length and peace Full property is also inversely proportional.Winter, largely a large amount of ice-melt operations caused by existing high-voltage line icing phenomenon will seriously affect work at present Industry safety.Therefore, the exploitation of the design and novel ice-melt fitting that carry out novel ice-melt scheme has important practical value, can be with A large amount of manpower, material resources and financial resources spent by the progress line ice-melting operation for solving to be widely present are reduced, are improved in harsh weather Under operational security, operation quality and efficiency solve the relative complex high-altitude application of original dependence and limited operation means Insoluble de-icing technology problem.It carries out turning spiral shell in the case where needing to raise high in device on traditional short-circuit device Silk or nut, generally require two people and operate, even if people's operation is also to need to expend the biggish mind and physical strength, This has just met the reason of " working time is longer, and safety is poorer " of above-mentioned background description, considers toward other situations, electric power dimension Nurse people not just dismantles or installs one, in multiple installations, disassembly, will be finished strength quickly and carry out rotation, From this point on for very unfavorable on teams and groups' working efficiency and labor intensity.It is considered based on the above actual conditions, had been badly in need of one kind both Energy Fast Installation can save the mounting device of physical strength again.
Summary of the invention
Poor, installing and dismounting large labor intensity that present invention mainly solves safeties, time-consuming problem more, working efficiency is slow, Provide it is a kind of it is highly-safe, pull intensity it is low, it is time-consuming less, a kind of power transmission line DC ice melting for Fast Installation that work efficiency is high Device
The technical solution adopted by the present invention to solve the technical problems is: a kind of power transmission line DC de-icing device of Fast Installation, Including spliced cables, the spliced cables are connect by wire connection device with cable hitching frame, and the cable hitching frame includes Upper fixture block and lower fixture block, the upper and lower fixture block front end are provided with clamping face, and upper and lower installation clip slot is provided on clamping face, Upper and lower beryllium copper sleeve with overhead line diameter matches is installed on upper and lower installation clip slot, is set below the lower beryllium copper sleeve Depression Centers Be equipped with the beryllium copper channel of integrally connected, be provided with internal screw thread in the beryllium copper channel, the beryllium copper channel penetrate lower fixture block until Its surface flushes;The folder gill is provided among the upper and lower fixture block, the frame gill is connected by a hinge;The upper lower fixture block rear end It is provided with the handle of through-hole.This programme takes full advantage of lever principle by the way that upper lower fixture block is extended handle at the folder gill It is sufficiently opened face is clamped at two, the cable connect required for being conveniently inserted in, beryllium copper channel is set at lower fixture block and facilitates outside Auxiliary equipment access, reaches modular requirement.
Scheme as a preference of the above scheme, the upper installation clip slot two sides are provided with convex rubber seal strip, described Lower installation clip slot two sides are provided with spill rubber seal strip, and the convex rubber seal strip and spill rubber seal strip are clamped, the rubber Strip of paper used for sealing uses silicone sealing strip.This programme plays buffer function by the way that rubber seal strip is arranged in installation clip slot two sides, avoids fitting Face is clamped up and down, hard collision occurs, influence fitting service life, buffering is haved the function that by using silicone sealing strip, simultaneously Meet the requirement of cold resistance.
Scheme as a preference of the above scheme, the lower fixture block lower section are provided with wire connection device, the conducting wire Beryllium copper cross connecting piece is provided in attachment device, beryllium copper cross connecting piece side is provided with protrusion wire connection device table The interconnecting piece in face is provided with external screw thread on the interconnecting piece, and excess-three side is respectively arranged with the electricity for being embedded in wire connection device Cable interface is provided with internal screw thread in the cable interface, and is furnished with interface plug, and the wire connection device is by interconnecting piece under Beryllium copper channel connection on fixture block, the wire connection device shell use plastic cement engineering electrical material;In the spliced cables It is provided with clamping joint, external screw thread is provided on the clamping joint, the clamping joint and cable interface are connected through a screw thread.This programme By the way that the wire connection device there are three cable interface is arranged, in attaching armour clamp device suitable for different connection orientations, increase Strong operability, how when not in use standby interface plug closed interface, prevents dirty entrance from influencing using effect, takes the side of injection molding Formula, so that accessory module.
Scheme as a preference of the above scheme, the handle are provided with return spring at the folder gill.This programme is logical It crosses and is provided with return spring at the folder gill in handle, not grudging two panels to clamp face is usually closed state, first makes it using preceding It opens then with regard to Natural closure on cable.
Scheme as a preference of the above scheme, the handle are divided into upper fixture block handle and lower fixture block handle, it is described on Fixture block handle is connected through through-hole by screw bolt and nut with lower fixture block handle, and the through-hole includes through-hole one and through-hole two, institute It states upper end in through-hole one and is arranged to hexagon ring, lower end is the circular hole that diameter becomes smaller.This programme on upper fixture block handle by being arranged Through-hole with hexagon ring, which facilitates, sinks to the head of bolt.
Scheme as a preference of the above scheme, the nut are divided into nut one and nut two, and the nut one is arranged Between upper lower fixture block handle, using band locking nut.Up knob is firmly locked locking nut by this programme by the way that band is arranged It is fixed, guarantee not deviating for position.
Scheme as a preference of the above scheme, the upper fixture block handle and lower fixture block handle end are provided with connection Hole is provided with assist handle on the connecting hole.This programme increases the convenience of user in operation by setting assist handle Degree.
Scheme as a preference of the above scheme, the assist handle use the electrical verification stick of thread contact head.This programme Set assist handle to the electrical verification stick of threaded contact head, in order to allow user's secondary determination when pressing from both sides fixture Whether phase line has electricity.
Scheme as a preference of the above scheme, the spliced cables use lightweight soft copper cable.This programme is using light Matter soft copper cable increases operability when cable connection.
Scheme as a preference of the above scheme, the upper lower fixture block are all made of LP3I improvement duralumin, hard alumin ium alloy.This programme Duralumin, hard alumin ium alloy is improved using LP3I in order to enhance electric conductivity, intensity, etch resistant properties, heating conduction.
The invention has the advantages that
(1) fixture is arranged to lever form and has return spring, holder is facilitated to hang over fixture on cable.
(2) one convenience of through-hole with hexagonal through-hole is provided on fixture handle, bolt head is sunk to, and does not need user Both ends are fixed.
(3) extend assist handle in the side of upper fixture handle convenient for users to hold-doun nut, so that both hands operation Working level is deepened, and assist handle guarantees to power on safety once again using the electrical verification stick that can be threaded connection with.
(4) wire connection device and cable hitching frame are separated, reaches modularization, so that the more convenient maintenance of maintenance personnel.
Detailed description of the invention
Fig. 1 is side overall structure diagram of the invention;
Fig. 2 is schematic top plan view of the invention;
Fig. 3 is wire connection device cross-sectional view of the invention;
In figure, 1, spliced cables, 2, cable hitching frame, 3, upper fixture block, 4, lower fixture block, 5, upper installation clip slot, 6, lower installation clip slot, 7, upper beryllium copper sleeve, 8, lower beryllium copper sleeve, 9, upper fixture block handle, 10, lower fixture block handle, 11, assist handle, 12, nut, 121, nut One, 122, nut two, 13, return spring, 14, through-hole, 141, through-hole one, 142 through-holes two, 15, the folder gill, 16, conducting wire connection dress It sets, 17, beryllium copper cross connecting piece, 18, beryllium copper channel, 19, interconnecting piece, 20, interface plug, 21, cable interface, 22, bolt, 23, Handle, 24, clamping joint, 25, rubber seal strip, 26, connecting hole.
Specific embodiment
Below with reference to the embodiments and with reference to the accompanying drawing further description of the technical solution of the present invention.
Embodiment: as shown in Figure 1, the cable hitching frame 2 includes upper fixture block 3 and lower fixture block 4, the upper and lower fixture block 3,4 Front end is provided with clamping face, and upper and lower installation clip slot 5,6 is provided on clamping face, be equipped on installation clip slot 5,6 above and below with The upper and lower beryllium copper sleeve 7,8 of overhead line diameter matches;The folder gill 15 is provided among the upper and lower fixture block 3,4, the frame gill 15 is logical Cross hinge connection;The upper and lower fixture block 3,4 rear ends are provided with upper and lower fixture block handle 9,10, the upper and lower fixture block handle 9,10 Return spring 13 is provided at the folder gill 15, the upper fixture block handle 9 can pass through bolt 22 and nut 12 and lower fixture block hand Handle 10 connects, and the upper fixture block handle 9 extends assist handle 11.The spliced cables 1 are provided with clamping joint 24 and pass through screw thread Any one connect with three cable interfaces 21 on wire connection device 16, and the wire connection device 16 is arranged in lower fixture block 4 lower end and the electrical connection of lower beryllium copper sleeve 8.
As shown in Fig. 2, being provided with the through-hole 1 that top is arranged to hexagonal through-hole on upper fixture block handle 9.
Specific embodiment described herein is only an example for the spirit of the invention.The neck of technology belonging to the present invention The technical staff in domain can make various modifications or additions to the described embodiments or replace by a similar method In generation, however, it does not deviate from the spirit of the invention or beyond the scope of the appended claims.
Although the terms such as the clamping face of being used more herein, the folder gill, torsionspring, are not precluded and use other terms A possibility that.The use of these items is only for be more convenient to describe and explain essence of the invention;It is construed as appointing The additional limitation of what one kind is disagreed with spirit of that invention.

Claims (10)

1. a kind of power transmission line DC de-icing device of Fast Installation, including spliced cables (1), the spliced cables (1) are by leading Wire-connecting device (16) is connect with cable hitching frame (2), it is characterized in that: the cable hitching frame (2) include upper fixture block (3) and under Fixture block (4), the upper fixture block (3), lower fixture block (4) front end are provided with clamping face, be provided on clamping face upper installation clip slot (5), Lower installation clip slot (6) is equipped with the upper beryllium copper sleeve with overhead line diameter matches on upper installation clip slot (5), lower installation clip slot (6) (7), lower beryllium copper sleeve (8), lower beryllium copper sleeve (8) the Depression Centers lower section is provided with the beryllium copper channel (18) of integrally connected, described Internal screw thread is provided in beryllium copper channel (18), the beryllium copper channel (18) penetrates lower fixture block (4) until its surface flushes;It is described It is provided with the folder gill (15) among upper and lower fixture block (3,4), the frame gill (15) is connected by a hinge;The upper and lower fixture block (3,4) Rear end is provided with the handle (23) with through-hole (14).
2. the power transmission line DC de-icing device of a kind of Fast Installation according to claim 1, it is characterized in that: the upper installation It is provided with the rubber seal strip (25) of convex on the clamping face of clip slot (5), is provided on the clamping face of lower installation clip slot (6) recessed The rubber seal strip (25) of shape, two rubber seal strips (25) of different shapes are mutually clamped, and the rubber seal strip (25) is close using silica gel Strip of paper used for sealing.
3. the power transmission line DC de-icing device of a kind of Fast Installation according to claim 1, it is characterized in that: the lower fixture block (4) lower section is provided with wire connection device (16), is provided with beryllium copper cross connecting piece (17) in the wire connection device (16), Beryllium copper cross connecting piece (17) side is provided with the interconnecting piece (19) on protrusion wire connection device surface, the interconnecting piece (19) external screw thread is provided on, excess-three side is respectively arranged with the cable interface (21) for being embedded in wire connection device (16), institute It states and is provided with internal screw thread in cable interface (21), and be furnished with interface plug (20), the wire connection device (16) passes through interconnecting piece (19) it is connect with the beryllium copper channel (18) in lower fixture block, wire connection device (16) shell uses plastic cement engineering electrical material Material;It is provided with clamping joint (24) on the spliced cables (1), is provided with external screw thread, the clamping joint on the clamping joint (24) (24) it is connected through a screw thread with cable interface (21).
4. the power transmission line DC de-icing device of a kind of Fast Installation according to claim 1, it is characterized in that: the handle (23) return spring (13) are provided at the folder gill (15).
5. the power transmission line DC de-icing device of a kind of Fast Installation according to claim 1, it is characterized in that: the handle (23) it is divided into upper fixture block handle (9) and lower fixture block handle (10), the upper fixture block handle (9) and lower fixture block handle (10) are through logical Hole (14) is connected by bolt (22) and nut (12), and the through-hole (14) includes through-hole one (141) and through-hole two (142), institute It states the interior upper end of through-hole one (141) and is arranged to hexagon ring, lower end is the circular hole that diameter becomes smaller.
6. the power transmission line DC de-icing device of a kind of Fast Installation according to claim 1 or 5, it is characterized in that: the spiral shell Female (12) are divided into nut one (121) and nut two (122), and the nut one (121) is arranged in upper fixture block handle (9), lower fixture block Between handle (10), using band locking nut.
7. the power transmission line DC de-icing device of a kind of Fast Installation according to claim 1 or 5, it is characterized in that: on described Fixture block handle (9) and lower fixture block handle (10) end are provided with connecting hole (26), are provided with nondominant hand on the connecting hole (26) Handle (11).
8. a kind of power transmission line DC de-icing device of Fast Installation described according to claim 1 or 5 or 7, it is characterized in that: described Assist handle (11) uses the electrical verification stick of thread contact head.
9. the power transmission line DC de-icing device of a kind of Fast Installation according to claim 1, it is characterized in that: the overlap joint is electric Cable (1) uses lightweight soft copper cable.
10. the power transmission line DC de-icing device of a kind of Fast Installation according to claim 1, it is characterized in that: the upper folder Block (3), lower fixture block (4) are all made of LP3I improvement duralumin, hard alumin ium alloy.
CN201810936195.9A 2018-08-16 2018-08-16 A kind of power transmission line DC de-icing device of Fast Installation Pending CN109510148A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810936195.9A CN109510148A (en) 2018-08-16 2018-08-16 A kind of power transmission line DC de-icing device of Fast Installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810936195.9A CN109510148A (en) 2018-08-16 2018-08-16 A kind of power transmission line DC de-icing device of Fast Installation

Publications (1)

Publication Number Publication Date
CN109510148A true CN109510148A (en) 2019-03-22

Family

ID=65745650

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810936195.9A Pending CN109510148A (en) 2018-08-16 2018-08-16 A kind of power transmission line DC de-icing device of Fast Installation

Country Status (1)

Country Link
CN (1) CN109510148A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112909596A (en) * 2021-01-28 2021-06-04 国网河南省电力公司信阳供电公司 Clamp-on flexible cable lap joint

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0759239A (en) * 1993-08-11 1995-03-03 Hitachi Cable Ltd Snow dropper for transmission line and shield ring at end of spiral rod
CN202363854U (en) * 2011-12-09 2012-08-01 武汉里得科技有限公司 Ice-melting lap joint line device
CN103490363A (en) * 2013-09-13 2014-01-01 郴州市东塘电气设备有限公司 Rapid Direct-current deicing short circuit device of electric transmission line
CN107437776A (en) * 2017-10-07 2017-12-05 江苏捷通管业科技有限公司 A kind of cross power cross connecting pipe
CN207490118U (en) * 2017-12-06 2018-06-12 贵州电网有限责任公司 A kind of line type ice-melt clamping device
CN208835706U (en) * 2018-08-16 2019-05-07 金华八达集团有限公司科技信息分公司 A kind of power transmission line DC de-icing device of Fast Installation

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0759239A (en) * 1993-08-11 1995-03-03 Hitachi Cable Ltd Snow dropper for transmission line and shield ring at end of spiral rod
CN202363854U (en) * 2011-12-09 2012-08-01 武汉里得科技有限公司 Ice-melting lap joint line device
CN103490363A (en) * 2013-09-13 2014-01-01 郴州市东塘电气设备有限公司 Rapid Direct-current deicing short circuit device of electric transmission line
CN107437776A (en) * 2017-10-07 2017-12-05 江苏捷通管业科技有限公司 A kind of cross power cross connecting pipe
CN207490118U (en) * 2017-12-06 2018-06-12 贵州电网有限责任公司 A kind of line type ice-melt clamping device
CN208835706U (en) * 2018-08-16 2019-05-07 金华八达集团有限公司科技信息分公司 A kind of power transmission line DC de-icing device of Fast Installation

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112909596A (en) * 2021-01-28 2021-06-04 国网河南省电力公司信阳供电公司 Clamp-on flexible cable lap joint
CN112909596B (en) * 2021-01-28 2022-10-18 国网河南省电力公司信阳供电公司 Clamp-on flexible cable lap joint

Similar Documents

Publication Publication Date Title
CN103490363B (en) Rapid Direct-current deicing short circuit device of electric transmission line
CN208835706U (en) A kind of power transmission line DC de-icing device of Fast Installation
CN109510148A (en) A kind of power transmission line DC de-icing device of Fast Installation
CN102545091B (en) Charged disconnecting wire lead clamp device
CN205488591U (en) Penetrating cable clamp
CN112071527A (en) Bolt-fixed composite jumper insulator for uninterrupted operation
CN201233972Y (en) Multifunctional connecting plug
CN103078284A (en) Rapid working clamp of pre-hanging type power distribution line de-icing engaged line
CN110994220A (en) Connecting wire clamp for drainage of subscriber line under 10KV overhead line
CN209249718U (en) A kind of shutter ground line
CN205355272U (en) Thrusting earthing clamp
CN203103518U (en) Hook type rapid connecting connector for emergency power supply vehicle
CN209626663U (en) It is a kind of convenient for fixed low voltage distribution cabinet bus-bar structure
CN208608380U (en) A kind of conductor shunt
CN205194876U (en) Test electricity and touch ring
CN207819057U (en) The harness-integrated of battery and controller is connected for new-energy automobile
CN208522109U (en) A kind of puncture grounding rod
CN209389600U (en) A kind of fitting wire clamp
CN206195175U (en) Wiring mode modified LNG ship fuel switch board
CN203014322U (en) Pre-hanging type power transmission line ice melting connecting line rapid operation clamp
CN205610063U (en) Temporary wiring order gram stick of convenient operation
CN203150719U (en) Conductor grip for ground leads
CN219165057U (en) Insulating shielding device for cross arm of tension rod of distribution network
CN221096026U (en) Linear type composite insulating cross arm of distribution line
CN204835367U (en) High pressure cable cleat install instrument

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190322

RJ01 Rejection of invention patent application after publication