CN109505561A - Oil field flood suction and oil flow production exploitation repeated on-off valve and its working method - Google Patents

Oil field flood suction and oil flow production exploitation repeated on-off valve and its working method Download PDF

Info

Publication number
CN109505561A
CN109505561A CN201811485743.7A CN201811485743A CN109505561A CN 109505561 A CN109505561 A CN 109505561A CN 201811485743 A CN201811485743 A CN 201811485743A CN 109505561 A CN109505561 A CN 109505561A
Authority
CN
China
Prior art keywords
oil
plug
pipe assembly
top connection
inlet passage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811485743.7A
Other languages
Chinese (zh)
Other versions
CN109505561B (en
Inventor
徐红军
徐丰岭
徐士楷
徐鹏政
杨劲松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YANCHENG SENXIN PETROLEUM MACHINERY CO Ltd
Original Assignee
YANCHENG SENXIN PETROLEUM MACHINERY CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YANCHENG SENXIN PETROLEUM MACHINERY CO Ltd filed Critical YANCHENG SENXIN PETROLEUM MACHINERY CO Ltd
Priority to CN201811485743.7A priority Critical patent/CN109505561B/en
Publication of CN109505561A publication Critical patent/CN109505561A/en
Application granted granted Critical
Publication of CN109505561B publication Critical patent/CN109505561B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B34/00Valve arrangements for boreholes or wells
    • E21B34/06Valve arrangements for boreholes or wells in wells
    • E21B34/14Valve arrangements for boreholes or wells in wells operated by movement of tools, e.g. sleeve valves operated by pistons or wire line tools
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/16Enhanced recovery methods for obtaining hydrocarbons
    • E21B43/20Displacing by water
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P70/00Climate change mitigation technologies in the production process for final industrial or consumer products
    • Y02P70/10Greenhouse gas [GHG] capture, material saving, heat recovery or other energy efficient measures, e.g. motor control, characterised by manufacturing processes, e.g. for rolling metal or metal working

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Multiple-Way Valves (AREA)
  • Nozzles (AREA)

Abstract

The invention discloses a kind of oil field flood suction and oil flow production exploitation repeated on-off valve and its working methods, switch valve includes from the upper top connection pipe up axially concatenated, set pipe assembly and lower contact pipe, one opens plug, for being set between top connection pipe and the asphalt channel for covering pipe assembly when needing flood suction, the first oil circuit unit for being equipped in plug and tubular piston inner cavity being connected with second oil inlet passage is opened;One shut-off plug, for being set between top connection pipe and the asphalt channel for covering pipe assembly when needing to close flood suction, shut-off plug is equipped with the second oil circuit unit that top connection tube cavity and second oil inlet passage are connected to and the third oil circuit unit that tubular piston inner cavity is connected with first oil inlet passage.Oil field flood suction of the present invention and oil flow production exploitation repeated on-off valve exempt to dig a branch well, and can carry out multiple switching, meet flood suction, oil flow production process specifications.

Description

Oil field flood suction and oil flow production exploitation repeated on-off valve and its working method
Technical field
The present invention relates to a kind of oilfield exploitation tools, are used for oil field flood suction and oil flow production more particularly, to one kind The repeated on-off valve of technique.
Background technique
Domestic flood suction digs a branch well by drilling well to realize, under the conditions of non-controlling, simply by stratum from one Bottom drains into another stratum.Controllable flood suction switch valve has not been reported.
External Kuwait Oil Company completes the controllable flood suction of a bite using smart well.In addition it completes and passes through flatly Underground electricity immersible pump realizes two-tube flood suction.Smart well mainly oil recovery interlayer control valve and permanent underground detection system, so as to Control flows to the water of reservoir from water layer.Transmit temperature and pressure digital display, and surface acquisition system record and fact.Underground electricity Immersible pump realizes that two-tube flood suction mainly controls water injection rate using electric immersible pump and whether injects.Cable power supply, electric immersible pump End installation detecting device, detection injection data.This two technologies are electromechanical integration, and electronic product is by well depth and temperature Limitation, to deep-well, ultradeep well high temperature and pressure, electronic product is all inadaptable both at home and abroad at present.
Therefore, it is necessary on the basis of existing, a kind of structurally reasonable, repeatable switch motion, economical adaptation are designed. Meet the repeated on-off valve of flood suction, oil flow production process specifications.
Summary of the invention
Goal of the invention: the purpose of the present invention is to solve the deficiencies in the prior art.It is structurally reasonable to design one kind, exempts to give a mark Zhi Jing does not use the products such as cable, downhole submersible pumps.It is delivered from well head freely falling body and opens plug and shut-off plug, hydraulic way is closed It closes or breakdown.It can carry out multiple switching, flexible to operation reliable, meet flood suction, oil flow production process specifications Repeated on-off valve.
Technical solution: in order to achieve the goal above, the technical solution used in the present invention are as follows:
The present invention relates to a kind of oilfield exploitation tools, are used for oil field flood suction and oil flow production more particularly, to one kind The repeated on-off valve of technology.
A kind of oil field flood suction and oil flow production exploitation repeated on-off valve, comprising: from it is upper up axially concatenate it is upper Junction block, set pipe assembly and lower contact pipe, the inner cavity of described sleeve pipe assembly are slidably and sealingly connected with a tubular piston, the tubulose Annular groove is equipped on the outside of the middle part tube wall of piston, cavity wall is equipped with one section of convex annular in the middle part of the inner cavity of described sleeve pipe assembly It rises, is formed to be located between tubular piston outer wall and set pipe assembly inner wall after the annular groove and annular protrusion cooperation and be opened Close the first annular shoe cream room on valve top and the second annular shoe cream room positioned at switch valve lower part;
First oil inlet passage is arranged in top connection tube wall and covers the tube wall side of pipe assembly, with the first annular storage Oil pocket is connected;
Second oil inlet passage, setting top connection tube wall and the tube wall other side for covering pipe assembly are stored up with second annular Oil pocket is connected;
The tube wall of described sleeve pipe assembly is equipped with water-filling nozzle, is located between two annular shoe cream rooms on the tubular piston Tube wall is equipped with the water injection hole being connected with tubular piston inner cavity,
One opens plug, for being set to when needing flood suction between top connection pipe and the asphalt channel for covering pipe assembly, Open the first oil circuit unit for being equipped in plug and tubular piston inner cavity being connected with second oil inlet passage;
One shut-off plug, for be set to when needing to close flood suction top connection pipe and cover pipe assembly asphalt channel it Between, shut-off plug is equipped with the second oil circuit unit for being connected to top connection tube cavity with second oil inlet passage and by tubulose The third oil circuit unit that piston cavity is connected with first oil inlet passage.
The opening plug includes: the first mandrel, the first gum cover, the first gasket and the first nut, wherein the first mandrel Outside the first gum cover of suit, the first nut are mutually solid by the first gum cover and the first mandrel by connecting with the threads of the first mandrel Fixed, first gasket is arranged between the first nut and the first gum cover.
The shut-off plug includes: the second mandrel, the second gum cover, the second gasket and the second nut, wherein the second mandrel Outside the second gum cover of suit, the second nut are mutually solid by the second gum cover and the second mandrel by connecting with the threads of the second mandrel Fixed, second gasket is arranged between the second nut and the second gum cover.
It is equipped with necking down hole between the top connection pipe and the asphalt channel for covering pipe assembly, the aperture in the necking down hole is greater than the The diameter of one mandrel and the second mandrel, less than the diameter of the first gum cover and the second gum cover.
The both ends installation circlip of the tubular piston is supported on the inner wall of set pipe assembly.
The present invention further discloses one kind to be based on the oil field flood suction and oil flow production exploitation repeated on-off valve Working method,
When needing flood suction, the opening plug is put into switch valve, fork clip is opened and is fixed in top connection pipe and casing Between the asphalt channel of assembly, hydraulic oil enters to be filled in by the opening from top connection pipe and stop, and passes through first oil inlet passage Tubular piston uplink in the inner cavity of set pipe assembly is pushed after into the first annular shoe cream room, so that the water-filling nozzle It is connected with water injection hole, water flooding enters water oil reservoir through water-filling nozzle and water injection hole;
When needing to close flood suction, water filling is closed, continues to improve hydraulic fluid pressure, until oil pressure makes to open plug Deformation, by oil pressure top to lower contact pipe tail portion;
Put into the shut-off plug into switch valve, shut-off plug be fastened in top connection pipe and cover pipe assembly asphalt channel it Between, hydraulic oil enters successively after the second oil circuit unit, the second oil inlet passage enter the second annular shoe cream room from top connection pipe Tubular piston downlink in the inner cavity of set pipe assembly is pushed, so that the water-filling nozzle and water injection hole separation, continue to improve liquid Oil pressure, until oil pressure turns off plug, deformation occurs, by the shut-off plug top to lower contact pipe tail portion.
It is described open plug investment top connection pipe and cover pipe assembly asphalt channel between when, first oil inlet passage be into Pressure passageway, the first oil circuit unit and the second oil inlet passage are pressure release passage.
When between shut-off plug investment top connection pipe and the asphalt channel for covering pipe assembly, the third oil circuit unit and the One oil inlet passage is into pressure passageway;
Second oil inlet passage and the second oil circuit unit are pressure release passage.
The utility model has the advantages that compared to the prior art repeated on-off valve provided by the invention has the advantage that
Repeated on-off valve described in the invention is structurally reasonable, simple to operate, switch motion flexibility and reliability, repeats Repeatedly.Same well is not only able to achieve flood suction, but also is able to achieve flowing well DP technology.It reduces cost of investment, reduce labor Fatigue resistance improves working efficiency, environment is protected to avoid pollution.
Detailed description of the invention:
Fig. 1 is the structural schematic diagram of repeated on-off valve provided by the invention;
Wherein, 1, top connection pipe;2, pipe assembly is covered;3, lower contact pipe;4, tubular piston;5, water-filling nozzle;6, valve is opened;7, Close valve;8, circlip;9, first annular shoe cream room;10, the second annular shoe cream room;11, the first oil inlet passage;12, the second oil inlet Channel;13, necking down hole;
Fig. 2 is the structural schematic diagram provided by the invention for opening plug;
Wherein, 6-1, the first nut;6-2, the first gasket;6-3, the first gum cover;6-4, the first mandrel;6-5, the first oil circuit Unit;
Fig. 3 is the structural schematic diagram of shut-off plug provided by the invention;
Wherein, 7-1, the second nut;7-2, the second gasket;7-3, the second gum cover;7-4, the second mandrel;7-5, the second oil circuit Unit;7-6, third oil circuit unit;
Fig. 4 is that opening provided by the invention plug is seated in repeated on-off valve starting waterflood path schematic diagram;
Fig. 5 is that shut-off plug provided by the invention is seated in repeated on-off valve opening and closing waterflood path schematic diagram.
Specific embodiment
In the following with reference to the drawings and specific embodiments, the present invention is furture elucidated, it should be understood that these embodiments are merely to illustrate It the present invention rather than limits the scope of the invention, after the present invention has been read, those skilled in the art are to of the invention each The modification of kind equivalent form falls within the application range as defined in the appended claims.
A kind of oil field flood suction and oil flow production exploitation repeated on-off valve, comprising: from it is upper up axially concatenate it is upper Junction block 1, set pipe assembly 2 and lower contact pipe 3, the inner cavity of described sleeve pipe assembly 2 are slidably and sealingly connected with a tubular piston 4, institute It states and is equipped with annular groove on the outside of the middle part tube wall of tubular piston 4, cavity wall is equipped with one section in the middle part of the inner cavity of described sleeve pipe assembly It is formed between tubular piston outer wall and set pipe assembly inner wall after annular protrusion, the annular groove and annular protrusion cooperation First annular shoe cream room 9 positioned at switch valve top and the positioned at switch valve lower part second annular shoe cream room 10;
First oil inlet passage 11 is arranged in 1 tube wall of top connection pipe and covers the tube wall side of pipe assembly 2, with first ring Shape shoe cream room 9 is connected;
Second oil inlet passage 12 is arranged in 1 tube wall of top connection pipe and covers the tube wall other side of pipe assembly 2, with described second Annular shoe cream room 10 is connected;
The tube wall of described sleeve pipe assembly 2 is equipped with water-filling nozzle 5, be located on the tubular piston 4 two annular shoe cream rooms it Between tube wall be equipped with the water injection hole 4-1 that is connected with tubular piston inner cavity,
One open plug 6, for be set to when needing flood suction top connection pipe 1 and cover pipe assembly 2 asphalt channel it Between, open the first oil circuit unit 6-5 for being equipped in plug 6 and 4 inner cavity of tubular piston being connected with second oil inlet passage 12;
One shut-off plug 7 leads to for being set to top connection pipe 1 when needing to close flood suction and covering the oil circuit of pipe assembly 2 Between road, shut-off plug 7 be equipped with 1 inner cavity of top connection pipe is connected to second oil inlet passage 12 the second oil circuit unit 7-5, And the third oil circuit unit 7-6 that tubular piston inner cavity is connected with first oil inlet passage 11.
Opening plug 6 includes: the first mandrel 6-4, the first gum cover 6-3, the first gasket 6-2 and the first nut 6-1, In, the first gum cover 6-3, the first nut 6-1 of external suit of the first mandrel 6-4 with the threads of the first mandrel 6-4 by connecting It connects and fixes the first gum cover 6-3 and the first mandrel 6-4 phase, the first gasket 6-2 is arranged in the first nut 6-1 and the first gum cover Between 6-3.
The shut-off plug includes: the second mandrel 7-4, the second gum cover 7-3, the second gasket 7-2 and the second nut 7-1, In, the second gum cover 7-3, the second nut 7-1 of external suit of the second mandrel 7-4 with the threads of the second mandrel 7-4 by connecting It connects and fixes the second gum cover 7-3 and the second mandrel 7-4 phase, the second gasket 7-2 is arranged in the second nut 7-1 and the second gum cover Between 7-3.
Further, necking down hole 13, the necking down are equipped between the top connection pipe 1 and the asphalt channel for covering pipe assembly 2 The aperture in hole 13 is greater than the diameter of the first mandrel and the second mandrel, less than the diameter of the first gum cover and the second gum cover.
Further, the both ends installation circlip of the tubular piston is supported on the inner wall of set pipe assembly.
The present invention further discloses one kind to be based on the oil field flood suction and oil flow production exploitation repeated on-off valve Working method,
When needing flood suction, the opening plug is put into switch valve, fork clip is opened and is fixed in top connection pipe and casing Between the asphalt channel of assembly, hydraulic oil enters to be filled in by the opening from top connection pipe and stop, and passes through first oil inlet passage Tubular piston uplink in the inner cavity of set pipe assembly is pushed after into the first annular shoe cream room, so that the water-filling nozzle It is connected with water injection hole, water flooding enters water oil reservoir through water-filling nozzle and water injection hole;
When needing to close flood suction, water filling is closed, continues to improve hydraulic fluid pressure, until oil pressure makes to open plug Deformation, by oil pressure top to lower contact pipe tail portion;
Put into the shut-off plug into switch valve, shut-off plug be fastened in top connection pipe and cover pipe assembly asphalt channel it Between, hydraulic oil enters successively after the second oil circuit unit, the second oil inlet passage enter the second annular shoe cream room from top connection pipe Tubular piston downlink in the inner cavity of set pipe assembly is pushed, so that the water-filling nozzle and water injection hole separation, continue to improve liquid Oil pressure, until oil pressure turns off plug, deformation occurs, by the shut-off plug top to lower contact pipe tail portion, recverable oil production.
It is described open plug investment top connection pipe and cover pipe assembly asphalt channel between when, first oil inlet passage be into Pressure passageway, the first oil circuit unit and the second oil inlet passage are pressure release passage.
When between shut-off plug investment top connection pipe and the asphalt channel for covering pipe assembly, the third oil circuit unit and the One oil inlet passage is into pressure passageway;
Second oil inlet passage and the second oil circuit unit are pressure release passage.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered It is considered as protection scope of the present invention.

Claims (8)

1. a kind of oil field flood suction and oil flow production exploitation use repeated on-off valve, comprising: from it is upper up axially concatenate on connect Head tube, set pipe assembly and lower contact pipe, it is characterized in that, it is living that the inner cavity of described sleeve pipe assembly is slidably and sealingly connected with a tubulose The middle part tube wall outside of plug, the tubular piston is equipped with annular groove, and cavity wall is equipped in the middle part of the inner cavity of described sleeve pipe assembly After one section of annular protrusion, the annular groove and annular protrusion cooperation between tubular piston outer wall and set pipe assembly inner wall Form the first annular shoe cream room for being located at switch valve top and the second annular shoe cream room positioned at switch valve lower part;
First oil inlet passage is arranged in top connection tube wall and covers the tube wall side of pipe assembly, with the first annular shoe cream room It is connected;
Second oil inlet passage, setting top connection tube wall and the tube wall other side for covering pipe assembly, with the described second annular shoe cream room It is connected;The tube wall of described sleeve pipe assembly is equipped with water-filling nozzle, is located between two annular shoe cream rooms on the tubular piston Tube wall is equipped with the water injection hole being connected with tubular piston inner cavity,
One opens plug, for being set between top connection pipe and the asphalt channel for covering pipe assembly when needing flood suction, opens The first oil circuit unit that tubular piston inner cavity is connected with second oil inlet passage is equipped in plug;
One shut-off plug, for being set to when needing to close flood suction between top connection pipe and the asphalt channel for covering pipe assembly, Shut-off plug is equipped with the second oil circuit unit for being connected to top connection tube cavity with second oil inlet passage and by tubular piston The third oil circuit unit that inner cavity is connected with first oil inlet passage.
2. oil field flood suction according to claim 1 and oil flow production exploitation repeated on-off valve, which is characterized in that institute Stating opening plug includes: the first mandrel, the first gum cover, the first gasket and the first nut, wherein the external suit of the first mandrel the One gum cover, the first nut are mutually fixed the first gum cover and the first mandrel by connecting with the threads of the first mandrel, and described One gasket is arranged between the first nut and the first gum cover.
3. oil field flood suction according to claim 1 and oil flow production exploitation repeated on-off valve, which is characterized in that institute Stating shut-off plug includes: the second mandrel, the second gum cover, the second gasket and the second nut, wherein the external suit of the second mandrel the Two gum covers, the second nut are mutually fixed the second gum cover and the second mandrel by connecting with the threads of the second mandrel, and described Two gaskets are arranged between the second nut and the second gum cover.
4. oil field flood suction according to claim 1 and oil flow production exploitation repeated on-off valve, which is characterized in that institute It states and is equipped with necking down hole between top connection pipe and the asphalt channel for covering pipe assembly, the aperture in the necking down hole is greater than the first mandrel and the The diameter of two mandrels, less than the diameter of the first gum cover and the second gum cover.
5. oil field flood suction according to claim 1 and oil flow production exploitation repeated on-off valve, which is characterized in that institute The both ends installation circlip for stating tubular piston is supported on the inner wall of set pipe assembly.
6. a kind of based on the oil field flood suction any in Claims 1 to 5 and oil flow production exploitation repeated on-off valve Working method, which is characterized in that
When needing flood suction, the opening plug is put into switch valve, is opened fork clip and is fixed in top connection pipe and set pipe assembly Asphalt channel between, hydraulic oil from top connection pipe enter by the opening fill in stop, pass through first oil inlet passage enter Tubular piston uplink in the inner cavity of set pipe assembly is pushed after the first annular shoe cream room, so that the water-filling nozzle and note Water hole conducting, water flooding enter water oil reservoir through water-filling nozzle and water injection hole;
When needing to close flood suction, water filling is closed, continues to improve hydraulic fluid pressure, until oil pressure makes opening plug that shape occur Become, opens plug by oil pressure top to lower contact pipe tail portion;
The shut-off plug is put into switch valve, shut-off plug is fastened between top connection pipe and the asphalt channel for covering pipe assembly, liquid Pressure oil enters from top connection pipe successively pushes institute after the second oil circuit unit, the second oil inlet passage enter the second annular shoe cream room Tubular piston downlink in the inner cavity of set pipe assembly is stated, so that the water-filling nozzle and water injection hole separation, continue to improve hydraulic oil pressure Power, until oil pressure turns off plug, deformation occurs, by the shut-off plug top to lower contact pipe tail portion.
7. oil field flood suction and oil flow production the exploitation working method of repeated on-off valve according to claim 6, special Sign is, described when opening between plug investment top connection pipe and the asphalt channel for covering pipe assembly, first oil inlet passage be into Pressure passageway, the first oil circuit unit and the second oil inlet passage are pressure release passage.
8. oil field flood suction and oil flow production the exploitation working method of repeated on-off valve according to claim 6, special Sign is, when between the shut-off plug investment top connection pipe and the asphalt channel for covering pipe assembly, the third oil circuit unit and the One oil inlet passage is into pressure passageway;
Second oil inlet passage and the second oil circuit unit are pressure release passage.
CN201811485743.7A 2018-12-06 2018-12-06 Multiple-time switch valve for self-flow water injection and self-flow oil extraction exploitation of oil field and working method thereof Active CN109505561B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811485743.7A CN109505561B (en) 2018-12-06 2018-12-06 Multiple-time switch valve for self-flow water injection and self-flow oil extraction exploitation of oil field and working method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811485743.7A CN109505561B (en) 2018-12-06 2018-12-06 Multiple-time switch valve for self-flow water injection and self-flow oil extraction exploitation of oil field and working method thereof

Publications (2)

Publication Number Publication Date
CN109505561A true CN109505561A (en) 2019-03-22
CN109505561B CN109505561B (en) 2023-05-12

Family

ID=65752990

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811485743.7A Active CN109505561B (en) 2018-12-06 2018-12-06 Multiple-time switch valve for self-flow water injection and self-flow oil extraction exploitation of oil field and working method thereof

Country Status (1)

Country Link
CN (1) CN109505561B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110566186A (en) * 2019-09-24 2019-12-13 中国石油集团渤海钻探工程有限公司 Method for measuring open blockage encountering and blocking position in two-stage well cementation operation

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3358771A (en) * 1966-01-19 1967-12-19 Schlumberger Well Surv Corp Multiple-opening bypass valve
EP0026105A2 (en) * 1979-09-25 1981-04-01 Otis Engineering Corporation A valve for use in well testing and a method of utilising said valve
CN101265792A (en) * 2008-05-09 2008-09-17 中国石油天然气集团公司 Hydraulic switch sliding bush
CN102261231A (en) * 2011-02-23 2011-11-30 新疆华油油气工程有限公司 Repeated switch sliding sleeve device
CN202946128U (en) * 2012-12-06 2013-05-22 中国石油集团西部钻探工程有限公司 Mechanical sliding sleeve
CN103835690A (en) * 2014-01-29 2014-06-04 中国石油集团西部钻探工程有限公司 Repeatedly-used sliding sleeve
CN104314520A (en) * 2014-08-25 2015-01-28 西南石油大学 Sliding sleeve type subsurface safety valve
CN104790910A (en) * 2015-05-06 2015-07-22 克拉玛依特隆石油技术有限公司 Oil field hydraulic control multi-switching circulating valve and opening and closing tools
CN204532258U (en) * 2014-12-31 2015-08-05 中国石油化工股份有限公司江汉油田分公司采油工艺研究院 A kind of miniature electric valve controlled for underground hydraulic pressure
CN207686700U (en) * 2017-12-30 2018-08-03 哈尔滨艾拓普科技有限公司 A kind of underground fracture sliding sleeve of electric control hydraulic driving

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3358771A (en) * 1966-01-19 1967-12-19 Schlumberger Well Surv Corp Multiple-opening bypass valve
EP0026105A2 (en) * 1979-09-25 1981-04-01 Otis Engineering Corporation A valve for use in well testing and a method of utilising said valve
CN101265792A (en) * 2008-05-09 2008-09-17 中国石油天然气集团公司 Hydraulic switch sliding bush
CN102261231A (en) * 2011-02-23 2011-11-30 新疆华油油气工程有限公司 Repeated switch sliding sleeve device
CN202946128U (en) * 2012-12-06 2013-05-22 中国石油集团西部钻探工程有限公司 Mechanical sliding sleeve
CN103835690A (en) * 2014-01-29 2014-06-04 中国石油集团西部钻探工程有限公司 Repeatedly-used sliding sleeve
CN104314520A (en) * 2014-08-25 2015-01-28 西南石油大学 Sliding sleeve type subsurface safety valve
CN204532258U (en) * 2014-12-31 2015-08-05 中国石油化工股份有限公司江汉油田分公司采油工艺研究院 A kind of miniature electric valve controlled for underground hydraulic pressure
CN104790910A (en) * 2015-05-06 2015-07-22 克拉玛依特隆石油技术有限公司 Oil field hydraulic control multi-switching circulating valve and opening and closing tools
CN207686700U (en) * 2017-12-30 2018-08-03 哈尔滨艾拓普科技有限公司 A kind of underground fracture sliding sleeve of electric control hydraulic driving

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
于明武;何俊杰;靳强;王德贵;王前敏;朱浩铭;: "钻井多次循环开关阀技术现状及发展建议", 石油矿场机械 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110566186A (en) * 2019-09-24 2019-12-13 中国石油集团渤海钻探工程有限公司 Method for measuring open blockage encountering and blocking position in two-stage well cementation operation

Also Published As

Publication number Publication date
CN109505561B (en) 2023-05-12

Similar Documents

Publication Publication Date Title
CN113494273A (en) Well completion pipe string and production pipe string of electric pump oil production well and construction method of well completion pipe string and production pipe string
CN104213888B (en) A kind of thick oil thermal extraction down-hole steam injection string
CN108443126B (en) Hydraulic piston pump, underground pump unit and underground liquid discharge testing system
CN103573214B (en) A kind of Operating Pressure circulation bottom valve
CN109505561A (en) Oil field flood suction and oil flow production exploitation repeated on-off valve and its working method
CN203716940U (en) Y pipe electric submersible pump production string with hydraulic control sliding sleeve
CN105422049A (en) Continuous circulating sand flushing device and method
CN209818025U (en) Multiple switch valve for oil field artesian water injection and artesian oil extraction
CN201103377Y (en) Gas pressure maintaining device of petroleum casing pipe
CN202417410U (en) Well washing packer
CN203879474U (en) CO2 oil displacement injection well anticorrosion anti-seepage production tubular column
CN204344060U (en) The packer that fluid pressure type can repeatedly set
CN104265188A (en) Intelligent crossover coupling
CN203347704U (en) Well washing and oil draining device for pumping well
CN108825172B (en) Unpowered sleeve gas recovery device
CN208982015U (en) A kind of well-flushing oil drain switch
CN208777971U (en) Fixed tubular column changes a layer pumping means
CN207296981U (en) A kind of note with Underwell anti-injection adopts integrated oil-well pump device
CN206592097U (en) A kind of double hose packer
CN203961859U (en) A kind of down-hole low pressure leakage oil reservoir leak-resistance valve
CN205189827U (en) Continuous cycle sand washing device
CN201095970Y (en) Packer preventing refluence of injected water
CN208057089U (en) A kind of oil field well switch valve
CN203559865U (en) Circulating bottom valve
CN103835688A (en) Double-seal steam-injection and oil-extraction dual-purpose oil pumping device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant