CN109494647A CN201811541789.6A CN201811541789A CN109494647A CN 109494647 A CN109494647 A CN 109494647A CN 201811541789 A CN201811541789 A CN 201811541789A CN 109494647 A CN109494647 A CN 109494647A
Authority
CN
China
Prior art keywords
angle steel
bridge bracket
column
arm
trailing arm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811541789.6A
Other languages
Chinese (zh)
Other versions
CN109494647B (en
Inventor
成宇飞
赵培勇
钱叶飞
相里海浪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHAANXI CHEMICAL CONSTRUCTION CO Ltd
Original Assignee
SHAANXI CHEMICAL CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHAANXI CHEMICAL CONSTRUCTION CO Ltd filed Critical SHAANXI CHEMICAL CONSTRUCTION CO Ltd
Priority to CN201811541789.6A priority Critical patent/CN109494647B/en
Publication of CN109494647A publication Critical patent/CN109494647A/en
Application granted granted Critical
Publication of CN109494647B publication Critical patent/CN109494647B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G3/00Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
    • H02G3/02Details
    • H02G3/04Protective tubing or conduits, e.g. cable ladders or cable troughs
    • H02G3/0456Ladders or other supports
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K31/00Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups
    • B23K31/02Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups relating to soldering or welding

Abstract

The present invention relates to a kind of installation mold and its production/application methods, more particularly to a kind of cable bridge bracket Rapid installing mould and its production/application method, the column constituted including two vertical angle steel, the crossbeam that several cross level angle steel are constituted, is characterized in that the opening direction of described two vertical angle steel is identical;The present invention provides a kind of cable bridge bracket Rapid installing moulds, skew after trailing arm welding caused by which solve the easy physical strength overdraw because for people, and cotton rope for a long time be straightened after be easy to appear loosenings, collapse the problems such as, and reduce manpower use, improve installation effectiveness;It is its scientific structure, reasonable and practical, improve bridge bracket arm installation quality and construction speed, also ensure the aesthetics of bridge bracket arm, it is effectively guaranteed that electric bridge construction smoothly completes, and good application effect is achieved, it is worth promoting and applying in the construction of project electric substation interlayer cable bridge bracket.

Description

A kind of cable bridge bracket Rapid installing mould and its production/application method
Technical field
The present invention relates to a kind of installation mold and its production/application methods, and in particular to a kind of cable bridge bracket is quick Installation mold and its production/application method.
Background technique
At present during cable testing bridge rack construction, bridge upright and trailing arm use site channel steel are made, and trailing arm In installation process, needing to help trailing arm by manpower, another people welds trailing arm, and require manpower more in this way, inefficiency, and hold It easily causes in trailing arm installation process and deforms, distorts, influence the construction quality and aesthetic measure of bridge bracket arm, increase construction period, The problems such as increasing cost, the factors such as electric substation's cable interlayer bridge bracket arm project amount is big improve bridge bracket arm for save the cost Installation effectiveness, quality and aesthetic measure, be badly in need of a kind of easy to operate simple tool.
In the installation of previous cable interlayer bridge bracket arm, need first to install first and last root on same column column Then cable bridge bracket is tensed with cotton rope, a people or two people hold cable bridge bracket, and another people carries out electric welding fixation, Skew after trailing arm welding caused by such method is generally easy because of the physical strength overdraw for people, and cotton rope is easy after being straightened for a long time It is integral inclined in turn result in trailing arm welding for the problems such as now loosening, collapsing.
Summary of the invention
The purpose of the present invention is to provide a kind of cable bridge bracket Rapid installing mould and its production/application methods.Its Solve it is crooked after trailing arm welding caused by being easy because of the physical strength overdraw for being people, and cotton rope be easy to appear after long-term be straightened loosening, The problems such as collapsing, and manpower use is reduced, improve installation effectiveness.
The technical solution of the invention is as follows:
A kind of cable bridge bracket Rapid installing mould, including the column that two vertical angle steel are constituted, the cross of several cross level angle steel compositions Beam is characterized in that the opening direction of described two vertical angle steel is identical, the opening direction phase of several cross level angle steel structures Together, and with the opening direction of described two vertical angle steel on the contrary, and mutual angle in 90 °;
The horizontal space of several cross level angle steel is the spacing at two layers of cable testing bridge bottom;
Spacing is more than or equal to trailing arm length outside the two sides of described two vertical angle steel;
Described two one of vertical angle steel of vertical angle steel are connect by steel pipe with castor, another vertical angle steel is equipped with for fixing The angle steel block of cable bridge bracket.
Above-mentioned castor is equipped with lifting device.
Above-mentioned lifting device is screw lifting device, and rotation screw thread is provided on lead screw, and the lead screw is equipped with for solid The nut set is positioned, nut is connect by spiral screw thread with threads of lead screw.
Above-mentioned angle steel block is at least two groups four.
It is welded to connect between above-mentioned vertical angle steel and cross level angle steel.
A kind of cable bridge bracket Rapid installing mould production method, is characterized in that, comprising:
1) rapidoprint is got out, required rapidoprint is as follows:
The angle steel of 50*5 or 40*4, the steel pipe of DN32 or DN40, castor or jenny scaffold Moving caster;
2) bridge bracket arm mold main frame is processed using angle steel, using construction site waste-material-preparing;Ensure that angle steel leans against At 90 degree of right angles when tool back plane welds;
3) steel pipe of DN32 or DN40 is connect in angle steel inside groove, 10~20cm of weld length, firm welding, then looks for a castor Or Moveable scaffold truckle, lifting device or self-control lifting device are carried on castor or Moveable scaffold truckle, to adjust Whole bridge bracket arm mold rise and fall, then enter castor grafting in steel pipe, and pipe diameter is slightly larger than castor upper leading screw outer diameter;
4) angle steel of 4 pieces of 10cm, and every two pieces one group are welded in unwelded steel pipe side on angle iron frame, and angle steel face is straight each other Angle, upper and lower two groups point-blank, and Mold Making is completed.
A kind of cable bridge bracket Rapid installing mould application method, is characterized in that, comprising:
A) use condition, hardened ground is completed in electric substation, and column welding is completed, and electric substation's bridge bracket arm installation number is big, Need to measure some bridge bracket arm installed height marks in same column column with level before use, general measure bridge bracket arm it is most one Layer absolute altitude, then marks the elevation line of this layer of bridge bracket arm with cotton rope on column;
B) after having marked, column is touched with bridge bracket arm Rapid installing mould, according to the elevation line of mark, uses lifting device tune Reshaping die height, absolute altitude is consistent after installing trailing arm, then locks mold with F spanner or other locking devices;
After mold-locked, starts to place trailing arm, be close to trailing arm in angle steel groove, then welded;
C) next column trailing arm welding is being carried out, trailing arm welding most in a row is completed;
D) final step carries out repetition measurement, and through live practical operation, error is in 5mm after repetition measurement.
The beneficial effects of the present invention are:
The present invention provides a kind of cable bridge bracket Rapid installing moulds, and which solve caused by the easy physical strength overdraw because for people The problems such as crooked after trailing arm welding, and cotton rope is easy to appear loosening, collapses after being straightened for a long time, and manpower use is reduced, it mentions High installation effectiveness;It is its scientific structure, reasonable and practical, bridge bracket arm installation quality and construction speed are improved, also ensures bridge The aesthetics of frame torr arm it is effectively guaranteed that electric bridge construction smoothly completes, and achieves good application effect, is worth It is promoted and applied in the construction of project electric substation interlayer cable bridge bracket.
Detailed description of the invention
Fig. 1 is inventive die block schematic illustration.
Fig. 2 is lifting device schematic diagram of the present invention.
Fig. 3 is angle steel block scheme of installation of the present invention.
Fig. 4 is angle steel block installation requirement schematic diagram of the present invention.
Fig. 5 is installation mold structural schematic diagram of the present invention.
Fig. 6 is installation mold use state diagram of the present invention.
Drawing reference numeral explanation:
1- vertical angle steel, 2- cross level angle steel, 4- castor, 5- angle steel block, 6- lifting device, 7- rotate screw thread, 8- nut, 9- column, 10- F spanner or other locking devices.
Specific embodiment
Referring to Fig. 1, a kind of cable bridge bracket Rapid installing mould, including the column that two vertical angle steel 1 are constituted, several cross The crossbeam that angle steel 2 is constituted, it is characterised in that: the opening direction of described two vertical angle steel 1 is on the contrary, several cross level angle steel 2 are opened Mouth direction is identical, and the opening direction angle in 90 ° with one of vertical angle steel 1 in described two vertical angle steel 1;
The horizontal space of several cross level angle steel 2 is the spacing at two layers of cable testing bridge bottom;
The one of vertical angle steel 1 of described two vertical angle steel 1 is connect by steel pipe with castor 4, another vertical angle steel 1 is equipped with and is used for The angle steel block 5 of fixed cable bridge bracket.
Referring to fig. 2, castor 4 is equipped with lifting device 6.Lifting device 6 is screw lifting device, is provided with rotation on lead screw Screw thread 7, the lead screw are equipped with the nut 8 for fixing position, and nut 8 is connect by spiral screw thread 7 with threads of lead screw.
It is at least two groups four referring to Fig. 3 angle steel block 5.It is welded to connect between vertical angle steel 1 and cross level angle steel 2.
A kind of cable bridge bracket Rapid installing mould production method, including,
1) rapidoprint is got out, required rapidoprint is as follows:
The angle steel of 50*5 or 40*4, the steel pipe of DN32 or DN40, castor or jenny scaffold Moving caster
2) bridge bracket arm mold main frame is processed using angle steel, using construction site waste-material-preparing;Ensure that angle steel leans against At 90 degree of right angles when tool back plane welds;
3) steel pipe of DN32 or DN4 is connect in angle steel inside groove, 10~20cm of weld length, firm welding, then looks for a castor Or Moveable scaffold truckle, lifting device or self-control lifting device are carried on castor or Moveable scaffold truckle, to adjust Whole bridge bracket arm mold rise and fall, then enter castor grafting in steel pipe;
4) angle steel of 4 pieces of 10cm, and every two pieces one group are welded in unwelded steel pipe side on angle iron frame, and angle steel face is straight each other Angle, upper and lower two groups point-blank, and vertical interval is equal to vertical interval inside column side to trailing arm, mold between every group of angle steel It completes.
Referring to Fig. 6, a kind of cable bridge bracket Rapid installing mould application method, comprising:
A) use condition, hardened ground is completed in electric substation, and column welding is completed, and column trailing arm is become by common section steel manufacture Electric institute's bridge bracket arm installation number is big, needs to measure some bridge bracket arm installation marks in same column column with level before use Height, one layer of most absolute altitude of general measure bridge bracket arm, then marks the absolute altitude of this layer of bridge bracket arm with cotton rope on column Line, cotton rope need to tense exceptionally straight, then carry out setting-out label with angle square;
B) after having marked, column is touched with bridge bracket arm Rapid installing mould, according to the elevation line of mark, uses lifting device tune Reshaping die height, absolute altitude always, then locks mold with F spanner or other locking devices 10 after installing trailing arm;
After mold-locked, starts to place trailing arm, be close to trailing arm in angle steel groove, then welded;
C) next 9 trailing arm of column welding is being carried out, trailing arm welding most in a row is completed;
D) final step carries out repetition measurement, and through live practical operation, error is in 5mm after repetition measurement.
Embodiment
1, small technological innovation achievement
Cable bridge bracket Rapid installing mould
According to the requirement of cable testing bridge construction speed and site operation needs, cable bridge bracket Rapid installing mould is developed, In project construction, good effect is achieved.
2, economic benefit
In the installation of previous cable interlayer bridge bracket arm, need first to install the cable of first He last root on same column column Then bridge bracket arm is tensed with cotton rope, a people or two people hold cable bridge bracket, and another people carries out electric welding fixation, in this way Method be generally easy because of the physical strength overdraw for being people caused by it is crooked after trailing arm welding, and cotton rope is easy to appear pine after long-term be straightened The problems such as moving, collapsing, it is integral inclined in turn result in trailing arm welding, and these problems are met sword by cable testing bridge Rapid installing mould and Solution, and manpower use is reduced, installation effectiveness is improved, cable testing bridge Rapid installing mould technological innovation tool is by applying table It is its bright scientific structure, reasonable and practical, bridge bracket arm installation quality and construction speed are improved, also ensures the beauty of bridge bracket arm Degree it is effectively guaranteed that electric bridge construction smoothly completes, and achieves good application effect, is worth in project electric substation It is promoted and applied in the construction of interlayer cable bridge bracket.
3, production method
In electrical construction, cable testing bridge construction is one of important link, and most important link is exactly gantry in gantry construction The installation of bracket, if faced, bridge bracket arm amount in electric substation's interlayer is larger, and construction speed requires tight.For improving gantry construction Quality and construction speed, bridge bracket arm mold are exactly an all well and good method, if can the secondary gantry support of construction site production one Arm mold is very convenient and practical.
The production method for now introducing cable bridge bracket Rapid installing mould,
3.1 get out rapidoprint, and required rapidoprint is as follows:
Angle steel (50*5 or 40*4), steel pipe (DN32 or DN40), castor (jenny scaffold Moving caster)
3.2 process bridge bracket arm mold main frame using angle steel, using construction site waste-material-preparing.
Points for attention: at 90 degree of right angles when 1, ensuring the back-to-back plane-welding of angle steel;2, it is unsuitable when angle bar frame welds It is welded on the upside of channel steel trailing arm placing, in case trailing arm causes trailing arm that cannot be attached to completely in angle steel inner side plane when installing.
3.3 steel pipes (DN32 or DN40) are welded in angle steel inside groove, 10~20cm of weld length, firm welding, then look for one Castor (Moveable scaffold truckle) carries lifting device or self-control lifting device on castor, to adjust bridge bracket arm mould Have rise and fall, then enter castor grafting in steel pipe, pipe diameter is slightly larger than castor upper leading screw outer diameter.
3.4 referring to fig. 4 and Fig. 5, and the angle steel block 5 of 4 pieces of 10cm, and every two are welded in unwelded steel pipe side on angle iron frame One group of block, angle steel face right angle each other, upper and lower two groups point-blank vertical interval is equal to column side to holding in the palm between every group of angle steel of Vertical interval inside arm.
4, the application method of bridge bracket arm Rapid installing mould
A) use condition, hardened ground is completed in electric substation, and column welding is completed, and electric substation's bridge bracket arm installation number is big, Need to be measured in same column column with level before use some bridge bracket arm installed height marks (general measure bridge bracket arm it is most one Layer absolute altitude), then mark the elevation line of this layer of bridge bracket arm on column with cotton rope, cotton rope need to tense exceptionally straight, then use angle Ruler carries out setting-out label, as shown in Figure 6.
B) after having marked, column is touched with bridge bracket arm Rapid installing mould, according to the elevation line of mark, is filled using lifting Adjustment mold height is set, absolute altitude always, then locks mold with F spanner (or other locking devices), such as schemes after installing trailing arm 6。
After mold-locked, start to place trailing arm, be close to trailing arm in angle steel groove, then welded (can first spot welding live, It is fully welded after installing).
C) next column trailing arm welding is being carried out, trailing arm welding most in a row is completed.
D) final step carries out repetition measurement, and through live practical operation, error is in 5mm after repetition measurement.Substantially increase gantry support The installation quality of arm, to create good condition with rear axle stand installation.
The use of cable bridge bracket Rapid installing mould improves the construction quality of cable interlayer gantry bracket, also can Ensure the requirement of construction speed, while preferably saving human and material resources, has supplied a kind of method for bridge bracket arm installation, be worth It must learn and promote.

Claims (7)

1. a kind of cable bridge bracket Rapid installing mould, including the column that two vertical angle steel (1) are constituted, several cross level angle steel (2) The crossbeam of composition, it is characterised in that: the opening directions of described two vertical angle steel (1) on the contrary, several cross level angle steel (2) opening Direction is identical, and the opening direction angle in 90 ° with one of vertical angle steel (1) in described two vertical angle steel (1);
The horizontal space of several cross level angle steel (2) is the spacing at two layers of cable testing bridge bottom;
Described two one of vertical angle steel (1) of vertical angle steel (1) are connect by steel pipe with castor (4), on another vertical angle steel (1) Equipped with the angle steel block (5) for fixing cable bridge bracket;
The spacing of the angle steel block (5) is column side to trailing arm side vertical range.
2. cable bridge bracket Rapid installing mould as described in claim 1, it is characterised in that: the castor (4), which is equipped with, to rise Falling unit (6).
3. cable bridge bracket Rapid installing mould as claimed in claim 2, it is characterised in that: the lifting device (6) is silk Thick stick lifting device, rotation screw thread (7) is provided on lead screw, and the lead screw is equipped with the nut (8) for fixing position, nut (8) it is connect by spiral screw thread (7) with threads of lead screw.
4. the cable bridge bracket Rapid installing mould as described in claims 1 to 3 is any, it is characterised in that: the angle steel block (5) At least two groups four.
5. cable bridge bracket Rapid installing mould as claimed in claim 3, it is characterised in that: the vertical angle steel (1) and cross level angle Steel is welded to connect between (2).
6. a kind of cable bridge bracket Rapid installing mould production method, which is characterized in that including,
1) rapidoprint is got out, required rapidoprint is as follows:
The angle steel of 50*5 or 40*4, the steel pipe of DN32 or DN40, castor or jenny scaffold Moving caster
2) bridge bracket arm mold main frame is processed using angle steel, using construction site waste-material-preparing;Ensure that angle steel leans against At 90 degree of right angles when tool back plane welds;
3) steel pipe of DN32 or DN40 is connect in angle steel inside groove, 10~20cm of weld length, firm welding, then looks for a castor Or Moveable scaffold truckle, lifting device or self-control lifting device are carried on castor or Moveable scaffold truckle, to adjust Whole bridge bracket arm mold rise and fall, then enter castor grafting in steel pipe, and pipe diameter is slightly larger than castor upper leading screw outer diameter;
4) angle steel of 4 pieces of 10cm, and every two pieces one group are welded in unwelded steel pipe side on angle iron frame, and angle steel face is straight each other Angle, upper and lower two groups point-blank, and vertical interval is equal to vertical interval inside column side to trailing arm, mold between every group of angle steel It completes.
7. a kind of cable bridge bracket Rapid installing mould application method characterized by comprising
A) use condition, hardened ground is completed in electric substation, and column welding is completed, and column trailing arm is become by common section steel manufacture Electric institute's bridge bracket arm installation number is big, needs to measure some bridge bracket arm installation marks in same column column with level before use Height, one layer of most absolute altitude of general measure bridge bracket arm, then marks the mark of this layer of bridge bracket arm with cotton rope on column (9) High line, cotton rope need to tense exceptionally straight, then carry out setting-out label with angle square;
B) after having marked, column is touched with bridge bracket arm Rapid installing mould, according to the elevation line of mark, uses lifting device tune Reshaping die height, absolute altitude is consistent after installing trailing arm, then locks mold with F spanner or other locking devices (10);
After mold-locked, starts to place trailing arm, be close to trailing arm in angle steel groove, then welded;
C) next column (9) trailing arm welding is being carried out, final in a row trailing arm welding is completed;
D) final step carries out repetition measurement, and through live practical operation, error is in 5mm after repetition measurement.
CN201811541789.6A 2018-12-17 2018-12-17 Quick installation die for cable bridge bracket and manufacturing/using method thereof Active CN109494647B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811541789.6A CN109494647B (en) 2018-12-17 2018-12-17 Quick installation die for cable bridge bracket and manufacturing/using method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811541789.6A CN109494647B (en) 2018-12-17 2018-12-17 Quick installation die for cable bridge bracket and manufacturing/using method thereof

Publications (2)

Publication Number Publication Date
CN109494647A true CN109494647A (en) 2019-03-19
CN109494647B CN109494647B (en) 2024-01-23

Family

ID=65710435

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811541789.6A Active CN109494647B (en) 2018-12-17 2018-12-17 Quick installation die for cable bridge bracket and manufacturing/using method thereof

Country Status (1)

Country Link
CN (1) CN109494647B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113210991A (en) * 2021-05-13 2021-08-06 中国一冶集团有限公司 Device and method for quickly positioning and mounting bridge stand column and supporting arm

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202252366U (en) * 2011-09-30 2012-05-30 中国二十二冶集团有限公司 Multilayer bridge frame support arm installation mold
CN203301061U (en) * 2013-06-13 2013-11-20 国家电网公司 Combined special tool for elevation of supporting erecting bottle of bus
CN203774693U (en) * 2014-04-10 2014-08-13 中国十九冶集团有限公司 Cable bridge supporting arm mounting and positioning device
CN204012418U (en) * 2014-08-25 2014-12-10 中冶建工集团有限公司 A kind of cable testing bridge mounting auxiliary
CN105202265A (en) * 2015-08-28 2015-12-30 中国一冶集团有限公司 Multilayer bridge framework bracket arm mounting locating device and method
KR101678849B1 (en) * 2016-09-07 2016-11-23 (주) 코리아에스이 Cable Bridge and Constructing Method thereof
CN209134013U (en) * 2018-12-17 2019-07-19 陕西化建工程有限责任公司 A kind of cable bridge bracket Rapid installing mould

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202252366U (en) * 2011-09-30 2012-05-30 中国二十二冶集团有限公司 Multilayer bridge frame support arm installation mold
CN203301061U (en) * 2013-06-13 2013-11-20 国家电网公司 Combined special tool for elevation of supporting erecting bottle of bus
CN203774693U (en) * 2014-04-10 2014-08-13 中国十九冶集团有限公司 Cable bridge supporting arm mounting and positioning device
CN204012418U (en) * 2014-08-25 2014-12-10 中冶建工集团有限公司 A kind of cable testing bridge mounting auxiliary
CN105202265A (en) * 2015-08-28 2015-12-30 中国一冶集团有限公司 Multilayer bridge framework bracket arm mounting locating device and method
KR101678849B1 (en) * 2016-09-07 2016-11-23 (주) 코리아에스이 Cable Bridge and Constructing Method thereof
CN209134013U (en) * 2018-12-17 2019-07-19 陕西化建工程有限责任公司 A kind of cable bridge bracket Rapid installing mould

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113210991A (en) * 2021-05-13 2021-08-06 中国一冶集团有限公司 Device and method for quickly positioning and mounting bridge stand column and supporting arm

Also Published As

Publication number Publication date
CN109494647B (en) 2024-01-23

Similar Documents

Publication Publication Date Title
CN103994280B (en) A kind of pipe clamping device fixed for pipeline or like
CN202622238U (en) Locator for welding furniture supporting frame
CN206780705U (en) A kind of splicing bench of silicon single crystal rod
CN205571772U (en) Thin wall barrel anti -deformation device of adjustable diameter
CN204657837U (en) A kind of vertical tube weld jig
CN103410328A (en) Method for constructing large-area concrete surface
CN109494647A (en) A kind of cable bridge bracket Rapid installing mould and its production/application method
CN209134013U (en) A kind of cable bridge bracket Rapid installing mould
CN108915278B (en) Ball node net rack small unit ground welding support splicing jig
CN206716765U (en) A kind of aluminium alloy extrusions KAFO
CN206445347U (en) The outer longitudinal seam welding frame of wind power tower
CN209597917U (en) Pipe straightener structure
CN106271353A (en) A kind of pipe welding clamp being applicable to T-shaped structure
CN206369010U (en) A kind of construction gib frame
CN110154626A (en) Mural painting drafting circular curve setting-out auxiliary tool
CN207325653U (en) A kind of municipal construction steel pipe straightening machine
CN205773161U (en) Pipe bus lifting device
CN205189410U (en) Hang mould template triangle location support frame with adjustable
CN214384043U (en) Scaffold frame of encorbelmenting of building engineering construction usefulness
CN211172608U (en) Keel of cold-bending glass curtain wall
CN210262731U (en) Guardrail main reinforcement positioning jig frame
CN203696288U (en) Test board welding tool for mechanical property testing of deposited metal
CN206452900U (en) A kind of Garden Engineering lodging-prevention support
CN104084725B (en) A kind of device and method for preventing pipeline of nuclear power plant welding deformation
CN215903014U (en) Multistation rack member assembly welding frock

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant