CN109488339A - Yield of deep-buried cavities excavation supporting method in supporting construction and prismatical joint basalt - Google Patents

Yield of deep-buried cavities excavation supporting method in supporting construction and prismatical joint basalt Download PDF

Info

Publication number
CN109488339A
CN109488339A CN201811549975.4A CN201811549975A CN109488339A CN 109488339 A CN109488339 A CN 109488339A CN 201811549975 A CN201811549975 A CN 201811549975A CN 109488339 A CN109488339 A CN 109488339A
Authority
CN
China
Prior art keywords
excavation
supporting
nanometer
steel
deep
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811549975.4A
Other languages
Chinese (zh)
Inventor
陈益民
倪绍虎
杨飞
郑海圣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN201811549975.4A priority Critical patent/CN109488339A/en
Publication of CN109488339A publication Critical patent/CN109488339A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention relates to yield of deep-buried cavities excavation supporting methods in a kind of supporting construction and prismatical joint basalt.The object of the present invention is to provide yield of deep-buried cavities excavation supporting methods in a kind of simple and easy supporting construction and prismatical joint basalt to reduce project cost to shorten the construction period.The technical scheme is that a kind of supporting construction, it sprays it is characterized by: having in the nanometer steel fiber concrete layer in excavation face, nanometer steel fiber concrete layer surface covers steel mesh, and steel mesh is fixed on excavation face through prestressed anchor, and reinforcing bar net surface has sprayed plain concrete layer.The present invention be suitable for building, water power, mining, can store up, the industries such as scientific research the prismatical joint cavern basalt Nei great abutment wall excavation supporting design.

Description

Yield of deep-buried cavities excavation supporting method in supporting construction and prismatical joint basalt
Technical field
The present invention relates to yield of deep-buried cavities excavation supporting methods in a kind of supporting construction and prismatical joint basalt.It is applicable in In building, water power, mining, can store up, the industries such as scientific research are designed in the excavation supporting of the prismatical joint cavern basalt Nei great abutment wall.
Background technique
With China's basis instrument construction Persisting exploitation, large quantities of huge, underground engineerings are emerged, such as huge water power Engineering, deep tunnel traffic engineering etc..Excavation size, design buried depth, the hole group's scale of underground chamber are increasing, cavern's preservation Geological conditions also becomes increasingly complex.
The development of Southwestern China portion area high mountain gorge, complex geologic conditions multiplicity, especially in the basalt of prismatical joint Excavate large underground hole, generally face high-ground stress, self are poor, prismatical joint is loose, discontinuities array collapsing The problems such as.Under this condition, using conventional excavation supporting construction technology, underground chamber abutment wall relaxation depth is often deep, has Be more than 6 meters, also be even up to 9 meters, have exceeded conventional suspension roof support length, it is forced to implement anchor cable, this Not only the duration is extended, but also increases project cost.
Summary of the invention
The technical problem to be solved by the present invention is in view of the above problems, providing a kind of simple and easy supporting knot Yield of deep-buried cavities excavation supporting method in structure and prismatical joint basalt reduces project cost to shorten the construction period.
The technical scheme adopted by the invention is that: a kind of supporting construction, it is characterised in that: have and spray in excavation face Nanometer steel fiber concrete layer, nanometer steel fiber concrete layer surface cover steel mesh, and steel mesh is fixed on through prestressed anchor Excavation face, reinforcing bar net surface have sprayed plain concrete layer.
Nano particle and volume content of steel fibers are more than or equal to 45kg/m in the nanometer steel fiber concrete layer3
The thickness of the nanometer steel fiber concrete layer is more than or equal to 10cm.
One end of the prestressed anchor is fixed in country rock, described in the other end of the prestressed anchor is compressed through anchor plate Steel mesh.
Yield of deep-buried cavities excavation supporting method in a kind of prismatical joint basalt, which is characterized in that steps are as follows:
Using stage excavation, same layer subregion, successively middle part pumping slot mode is excavated, and every layer of excavation height controls within 5m, Underground chamber designs and reserves protective layer at sideline, 2~3m of protective layer thickness, and underground chamber designs sideline and uses photoface exploision;
After the completion of excavation, closed immediately using spray nanometer steel fiber reinforced concrete in excavation face, spray concrete thickness is greater than etc. It is more than or equal to 45kg/m in 10cm, nano particle and steel fibre quality3
Steel mesh is hung on nanometer steel fiber reinforced concrete surface, steel mesh is fixed on country rock, steel mesh through prestressed anchor Plain concrete is sprayed again in surface.
In work progress, keep carrying out explosion, displacement, stress, strain, crack folding, underground water etc. to country rock and supporting Data are monitored, and are timely feedbacked;
Collected monitoring data are assessed and analyzed, verified and correct existing design scheme, can be directed to when necessary It monitors mutation point and carries out strengthening supporting, it is ensured that adjoining rock stability.
Supporting construction should be completed in 3 days after the completion of excavation, and lag face < 30m.
The beneficial effects of the present invention are: the present invention is in the case where prismatical joint basalt is developed, huge underground cavity is using thin Layer excavation, photoface exploision substantially reduce the relaxation of country rock caused by explosion, by sealing to the timely stir cement and soft soil in deep ground of excavation face It closes and applies prestressed anchor and control further pine of the cavern prismatical joint basalt rock mass when excavation unloads loose lotus It relaxes, finally hangs integrality and globality that the spray plain concrete of steel mesh+again ensures support system.The present invention substantially reduces side The relaxation degree of wall, it is ensured that abutment wall adjoining rock stability saves construction investment, accelerates construction speed.
Detailed description of the invention
Fig. 1 is excavation construction schematic diagram in embodiment.
Fig. 2 is the A-A cross-sectional view of Fig. 1.
Fig. 3 is support construction schematic diagram in embodiment.
Fig. 4 is the structural schematic diagram of supporting construction in embodiment.
Fig. 5 is the connection schematic diagram of steel mesh and prestressed anchor in embodiment.
Specific embodiment
The present embodiment is yield of deep-buried cavities excavation supporting method in a kind of prismatical joint basalt, the specific steps are as follows:
1, blasting technology:
As shown in Figure 1 and Figure 2, it is influenced to reduce explosion to high side wall, in such a way that stage excavation, same layer subregion excavate It excavates, underground chamber abutment wall (design sideline) reserved protective layer 1,1 2~3m of thickness of protective layer, every layer of excavation height control is in 5m Within.To control Forming Quality, abutment wall (design sideline) uses photoface exploision, strict control blasting scale, explosive quantity in a sound, explosion Parameter can be determined by engineer testing.Successively middle part pumping slot excavates in the present embodiment, first abutment wall outside (namely in same layer Portion) excavate to fall to form free face, then when explosion can light it is quick-fried, abutment wall excavation effect is more preferable.The present embodiment reasonably divides Layer subregion is both conducive to limit explosion, is also conducive to work continuously, shorten the construction period.
2, zero propagation preliminary bracing:
Prismatical joint hole section self-stable ability is poor, and usually shorter from the steady time, the more timely supporting stronger, the better.It excavates and completes Afterwards, it is closed immediately using spray nanometer steel fiber reinforced concrete, spray concrete thickness is not less than 10cm, nano particle and steel fibre quality Recommend to be not less than 45kg/m3(being determined in combination with scene wall rock condition and engineer testing).Pneumatically placed concrete can be implemented rapidly, and closing is enclosed Rock ensures supporting timeliness;Shotcrete strength can be improved in reasonable mixing of steel fiber, increases supporting intensity.
3, in due course preliminary bracing:
For the relationship for balancing rapid construction and adjoining rock stability, after preferential completion zero propagation preliminary bracing, Ying Zeji is complete as early as possible At remaining preliminary bracing, it is included in a nanometer steel fiber reinforced concrete surface and hangs steel mesh, steel mesh is fixed on through prestressed anchor Country rock, reinforcing bar net surface spray plain concrete again (see Fig. 3).Remaining preliminary bracing should be completed in 3 days after the completion of excavation, and supporting is stagnant Face length answers < 30m afterwards.
After preliminary bracing structure is fully completed, has and spray in the nanometer steel fiber concrete layer 2 in excavation face, nanometer steel 2 surface of fiber concrete layer covers steel mesh 3, and steel mesh 3 is fixed on excavation face through prestressed anchor 4, and 3 surface of steel mesh sprays There is plain concrete layer 5 (see Fig. 4), form complete initial stage flexible support system, can effectively limit prismatical joint basalt pine Relax deformation.One end of prestressed anchor 4 is fixed in country rock in this example, and the other end of the prestressed anchor is pressed through anchor plate 401 Tight steel mesh (see Fig. 5).
The present embodiment in the construction process, keeps opening country rock and supporting progress explosion, displacement, stress, strain, crack The data such as conjunction, underground water are monitored, and are timely feedbacked, and are specifically included: periodical visual inspection observation;The suitable typical monitoring of selection is disconnected Corresponding monitoring instrument, including blasting vibration detector, Convergence monitoring, bolt stress meters, Multiple contact deformeter are simultaneously arranged etc. in face.To adopting The monitoring data collected are assessed and are analyzed, and are verified and are corrected existing design scheme, can be clicked through when necessary for monitoring mutation Row strengthening supporting, it is ensured that adjoining rock stability.

Claims (7)

1. a kind of supporting construction, it is characterised in that: have and spray in the nanometer steel fiber concrete layer (2) in excavation face, nanometer Steel fiber concrete layer (2) surface covers steel mesh (3), and steel mesh (3) is fixed on excavation face, reinforcing bar through prestressed anchor (4) Net (3) surface has sprayed plain concrete layer (5).
2. supporting construction according to claim 1, it is characterised in that: nanometer in the nanometer steel fiber concrete layer (2) Particle and volume content of steel fibers are more than or equal to 45kg/m3
3. supporting construction according to claim 1 or 2, it is characterised in that: the thickness of the nanometer steel fiber concrete layer (2) Degree is more than or equal to 10cm.
4. supporting construction according to claim 1, it is characterised in that: one end of the prestressed anchor (4), which is fixed on, encloses In rock, the other end of the prestressed anchor (4) compresses the steel mesh (3) through anchor plate (401).
5. yield of deep-buried cavities excavation supporting method in a kind of prismatical joint basalt, which is characterized in that steps are as follows:
Using stage excavation, same layer subregion, successively middle part pumping slot mode is excavated, and every layer of excavation height control is within 5m, underground Cavern designs and reserves protective layer (1) at sideline, and protective layer (1) 2~3m of thickness, underground chamber designs sideline and uses photoface exploision;
After the completion of excavation, closed immediately using spray nanometer steel fiber reinforced concrete in excavation face, spray concrete thickness is more than or equal to 10cm, nano particle and steel fibre quality are more than or equal to 45kg/m3
It is hung steel mesh (3) on nanometer steel fiber reinforced concrete surface, steel mesh (3) is fixed on country rock, steel through prestressed anchor (4) Plain concrete is sprayed again in muscle net (3) surface.
6. yield of deep-buried cavities excavation supporting method in prismatical joint basalt according to claim 5, it is characterised in that:
In work progress, keep carrying out the data such as explosion, displacement, stress, strain, crack folding, underground water to country rock and supporting It is monitored, and timely feedbacks;
Collected monitoring data are assessed and analyzed, verified and correct existing design scheme, it when necessary can be for monitoring Mutation point carries out strengthening supporting, it is ensured that adjoining rock stability.
7. yield of deep-buried cavities excavation supporting method in prismatical joint basalt according to claim 5, it is characterised in that: Supporting construction should be completed in 3 days after the completion of excavation, and lag face < 30m.
CN201811549975.4A 2018-12-18 2018-12-18 Yield of deep-buried cavities excavation supporting method in supporting construction and prismatical joint basalt Pending CN109488339A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811549975.4A CN109488339A (en) 2018-12-18 2018-12-18 Yield of deep-buried cavities excavation supporting method in supporting construction and prismatical joint basalt

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811549975.4A CN109488339A (en) 2018-12-18 2018-12-18 Yield of deep-buried cavities excavation supporting method in supporting construction and prismatical joint basalt

Publications (1)

Publication Number Publication Date
CN109488339A true CN109488339A (en) 2019-03-19

Family

ID=65710643

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811549975.4A Pending CN109488339A (en) 2018-12-18 2018-12-18 Yield of deep-buried cavities excavation supporting method in supporting construction and prismatical joint basalt

Country Status (1)

Country Link
CN (1) CN109488339A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112483121A (en) * 2020-11-11 2021-03-12 中国电建集团华东勘测设计研究院有限公司 Anti-loosening support method for columnar joint surrounding rock of underground cavern
CN114087020A (en) * 2021-10-09 2022-02-25 中国电建集团华东勘测设计研究院有限公司 Underground cavern stability evaluation method based on dual safety of rock mass and supporting structure

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101440708A (en) * 2008-12-19 2009-05-27 中建国际建设有限公司 PBA shallow buried underground excavating close range large section three-hole separated island type structure construction method
CN108518232A (en) * 2018-04-11 2018-09-11 中铁十七局集团有限公司 The anti-rock burst method for protecting support of single-track railway tunnel of corresponding different rock burst intensity grades
CN209483378U (en) * 2018-12-18 2019-10-11 中国电建集团华东勘测设计研究院有限公司 Supporting construction

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101440708A (en) * 2008-12-19 2009-05-27 中建国际建设有限公司 PBA shallow buried underground excavating close range large section three-hole separated island type structure construction method
CN108518232A (en) * 2018-04-11 2018-09-11 中铁十七局集团有限公司 The anti-rock burst method for protecting support of single-track railway tunnel of corresponding different rock burst intensity grades
CN209483378U (en) * 2018-12-18 2019-10-11 中国电建集团华东勘测设计研究院有限公司 Supporting construction

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
倪绍虎等: "柱状节理玄武岩的破坏模式、破坏机制及工程对策", 岩石力学与工程学报, vol. 35, pages 3064 - 3075 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112483121A (en) * 2020-11-11 2021-03-12 中国电建集团华东勘测设计研究院有限公司 Anti-loosening support method for columnar joint surrounding rock of underground cavern
CN112483121B (en) * 2020-11-11 2023-06-06 中国电建集团华东勘测设计研究院有限公司 Anti-loosening supporting method for columnar joint surrounding rock of underground cavern
CN114087020A (en) * 2021-10-09 2022-02-25 中国电建集团华东勘测设计研究院有限公司 Underground cavern stability evaluation method based on dual safety of rock mass and supporting structure
CN114087020B (en) * 2021-10-09 2024-04-02 中国电建集团华东勘测设计研究院有限公司 Underground cavern stability evaluation method based on rock mass and supporting structure dual safety

Similar Documents

Publication Publication Date Title
CN111594229B (en) Construction method for multi-arch tunnel entrance under shallow-buried water-rich geological condition
Meng et al. Support technology for mine roadways in extreme weakly cemented strata and its application
Hao et al. Analysis of mining roadway with large deformation of broken soft coal and research on supporting technology: A case study in Xin’an coal mine, China
CN109854252B (en) Underground engineering staged complete control method
CN102839680B (en) The high slope earthwork and support engineering construction method
CN104790978A (en) Small-clear-distance grade separation tunnel annular guide pit construction method
CN109083655A (en) A kind of high-ground stress environment stratiform surrounding rock tunnel orientation support reinforcement method
Yong et al. Rock mass response ahead of an advancing face in faulted shale
CN107478803B (en) Construction adaptability grading method for tunnel cantilever heading machine
CN109488339A (en) Yield of deep-buried cavities excavation supporting method in supporting construction and prismatical joint basalt
CN109779653B (en) Construction method for crossing of soft rock large-section tunnel
CN110593924A (en) Support method based on full life cycle of mining roadway
CN112502720A (en) Method for breaking zone by passing open TBM through fault
CN110206547A (en) The method for being adapted to deep formation and high stress areas shaft sinking and supporting
CN112483121A (en) Anti-loosening support method for columnar joint surrounding rock of underground cavern
Yao et al. Key technique study of stability control of surrounding rock in deep chamber with large cross-section: A case study of the Zhangji Coal Mine in China
CN209483378U (en) Supporting construction
CN110513124A (en) A kind of inserted slip casting pipe network supporting construction of high stress stratiform relief joint rock laneway
CN107514266A (en) Shield export & import bolt anchorage soil body construction method
CN105952459B (en) A kind of tunnel pin-connected panel preliminary bracing method
HOEK et al. Design of large powerhouse caverns in weak rock
CN113653506B (en) Control method for high-stress soft rock tunnel bottom plate
CN109882206B (en) Multi-support cooperative method for controlling coal mine broken surrounding rock
Wang et al. Analytical method for mechanical behaviors of pipe roof reinforcement
Trisugiwo et al. Joint analysis to evaluate geological over-break in excavation of surge chamber cavern

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190319