CN109468904A - A kind of pitch composite seal coat construction method for road in airport - Google Patents

A kind of pitch composite seal coat construction method for road in airport Download PDF

Info

Publication number
CN109468904A
CN109468904A CN201910005100.6A CN201910005100A CN109468904A CN 109468904 A CN109468904 A CN 109468904A CN 201910005100 A CN201910005100 A CN 201910005100A CN 109468904 A CN109468904 A CN 109468904A
Authority
CN
China
Prior art keywords
emulsified asphalt
road
spread
construction
paver
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910005100.6A
Other languages
Chinese (zh)
Inventor
王春雷
金敏
彭超
杨宝昌
马波
张志昌
潘志平
马骏
蒋正
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Beijing Engineering Group Co Ltd
Original Assignee
China Railway Beijing Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Beijing Engineering Group Co Ltd filed Critical China Railway Beijing Engineering Group Co Ltd
Priority to CN201910005100.6A priority Critical patent/CN109468904A/en
Publication of CN109468904A publication Critical patent/CN109468904A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C9/00Special pavings; Pavings for special parts of roads or airfields
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/35Toppings or surface dressings; Methods of mixing, impregnating, or spreading them
    • E01C7/353Toppings or surface dressings; Methods of mixing, impregnating, or spreading them with exclusively bituminous binders; Aggregate, fillers or other additives for application on or in the surface of toppings with exclusively bituminous binders, e.g. for roughening or clearing

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)
  • Road Paving Machines (AREA)

Abstract

The invention discloses a kind of pitch composite seal coat construction methods for road in airport, combined type sealing is carried out using the asphaltic base of sub-layer, transition zone and upper epidermis, the airfield runway is by MS-2 type micro-surface area upper epidermis, MS-2 type micro-surface area transition zone and modified emulsifying asphalt synchronous surface dressing;The pitch composite seal coat construction method for being used for road in airport can be avoided plat-bottom escape, while can also improve concrete road surface anti-permeability performance, flushing resistance, improve road face durability.

Description

A kind of pitch composite seal coat construction method for road in airport
Technical field
Present invention relates particularly to a kind of pitch composite seal coat construction methods for road in airport.
Background technique
Since the positions such as civil airport runway, parallel taxiway and fast slideway are subjected to heavy traffic, high-intensitive load for a long time Repeated action, deicing level ground position is for a long time by the corrosion impact of deicing liquid, the phenomenon that Yi Fasheng plat-bottom escape, and is difficult to repair.
Caused by the reason of coming to nothing may be many factors, wherein base soak for a long time, top concreting when slurries Lead to concrete temperature strain failure by shear substructure, the failure bottom substrate immersion of cementation of fissures material and boat with bottom substrate consolidation Negative pressure causes edges of boards base purt mud etc. to be the common cause for causing base's destruction to be come to nothing generally believed in the industry when pocket slips over.
When civil airport cement concrete road surface uses cement stabilized macadam base, the type of interlayer of original adoption is stone It considers sealing to be worth doing, mainly uses geomembrane later, Practical Project effect does not reach expected.Current major design scheme is setting Geotextiles, or even it is not provided with middle layer (non-critical areas);In recent engineering design intend consider setting 1 thickness degree 2cm with Upper particulate formula (sand grains formula) bituminous concrete, or (single layer is same for asphaltic base top dressing layer of the setting thickness in monolayer no more than 1cm Walk crushed stone sealing/slurry seal/micro-surface area).The Practical Project effect of different type middle layer is summarized as follows:
(1) middle layer or setting screening seal coat are not provided between cement treated material and cement sheeting.Both do not have buffer action, Also the flushing resistance that cement treated material can not be improved, is substantially designed to abandon, and civil aviaton is in the non-key area in movement area at present Cement road face is directly cast in the design scheme on cement treated material and should avoided by domain.
(2) geomembrane is set between cement treated material and cement sheeting.Engineering practice shows that geomembrane is arranged imitates in isolation Good effect is played in terms of fruit, but due to geotechnological film surface excessively " smooth ", for cement pavement slab block and cutting optimal Interlayer effect of contraction it is too weak, cause plate temperature day (round the clock) variation under the influence of dilatation amount be more than expected design, Even occur the phenomenon that plate " overall movement " under extreme case, and then induces some more serious engineering diseases.Therefore the people Boat substantially no longer uses this technical solution after the large airport engineering of East China.
(3) geotextiles are set between cement treated material and cement sheeting.All there is large area in setting geotextiles and geomembrane When construction, due to geotextiles and geomembrane can not completely with the construction technology problem of cement treated material surface close " fitting ", and In cement sheeting casting process, since heavy mechanical equipment (mainly concrete truck, material distributing machine etc.) is in geotextiles and geotechnique Film surface when driving, can cause local failure to geotextiles and geomembrane.The good geotextiles of making can be sent out well first It waves " isolation features ", and its surface can form the interface with the larger coefficient of friction resistance with cement concrete, be not in plate The excessive problem of block dilatation amount.For geotextiles are with respect to asphaltic base sealing, project cost is lower, this is also that civil aviaton is current One of the reason of considering setting geotextiles in the design.
But the geotextiles under cement sheeting are set and repeat to make in cement sheeting temperature contraction stress and the long-term of warping stress Under, it is easy to the phenomenon that destroying as plate is mobile occur.
Summary of the invention
The technical problem to be solved in the present invention is to provide one kind can be avoided plat-bottom escape, while can also improve concrete Road face anti-permeability performance, flushing resistance, the pitch composite seal coat construction method for road in airport for improving road face durability.
To solve the above problems, the present invention adopts the following technical scheme:
A kind of pitch composite seal coat construction method for road in airport, using the asphaltic base of sub-layer, transition zone and upper epidermis Carry out combined type sealing, comprising the following steps:
1) sub-layer is constructed
(1) shovel dress building stones: the building stones for being packed into hopper should maintain an equal level with the height of hopper left baffle, prevent because expecting excessively to trickle down;
(2) emulsified asphalt: should check oil pick-up tube and its connector whether good seal, forbid emulsified asphalt to splash;
(3) it demarcates: the temperature of emulsified asphalt being heated and is stablized between 60 DEG C ~ 80 DEG C;It is on valve, is at pipe Road recurrent state, spray bars emulsified asphalt are uniformly mixed with asphalt tank internal emulsification pitch, are demarcated in asphalt binder stability controller Emulsified asphalt spread quantity and travel speed, vehicular velocity setting are 30 ~ 60m/min;
(4) spread paves: setting emulsified asphalt and the spraying altitude and dosage gathered materials open building stones dispenser and asphalt distribution Bar;During spread, left and right spray bars are adjusted at any time, guarantee the integrality of seam;It should be met the following requirements when spread: sealing In work progress, chip sealer wants smooth ride, at the uniform velocity;Construct the first width when, should gather materials on spread device in side plus baffle, prevent Only building stones splash, construct last width when, use same method in the other side, among spread when width, unilateral pitch to be kept to spray Spill width than building stones spray width more than 8 ~ 10cm;
(5) defect repair: when discovery sprinkling emulsified asphalt has blank, it should carry out manually mending in time and spill;When there is emulsified asphalt accumulation When should strike off;When emulsified asphalt sprinkling ribbon occurs with the spreading that gathers materials, atomizer and bin gate should be closed in time, check atomizer Pressure whether meet the requirements, whether bin gate is blocked by big particle diameter stone;Gather materials when floating, road surface should be scanned out, and must not Rubbing oneself adhered in place gather materials;When any material is finished, the valve of all conveying materials should be closed, is usually first closed Building stones switch, it is rear to close emulsified asphalt switch, the pitch oil film of Yao Liuyou 50cm, so as to seam.Then chip sealer is pressed into advance side To sailing out of job step;
(6) joint treatment: transverse joint processing, transverse joint are handled using rendezvous method, in every section of joint part, are layered on iron plate or tarred brown paper are horizontal Before this section is spilt a little and after terminal, length is 1 ~ 1.5m;Longitudinal joint processing, emulsified asphalt spread will guarantee that driving is straight suitable, construct When next width, the spread of sealing side building stones should be aligned with the building stones on the right side of a upper width, guarantee that longitudinal joint docking is good, seam pitch Lap must not exceed l0cm;
(7) be compacted and form: synchronous surface dressing laying finishes, after emulsified asphalt demulsification to be modified, using the tire of 16 ~ 30T Road roller roll for 2 ~ 4 times, when rolling, should follow intermediate, first slow rear fast principle behind first both sides, each wheelmark weight when rolling Folded 30cm, rolling speed control road roller in 30m/min ~ 60m/min, roller compaction process arbitrarily must not brake or turn around;
(8) construction terminates chip sealer to be cleaned: chip sealer being driven into no vehicular traffic, is parked without the specified safety place such as slope;
2) upper epidermis and transition zone construction
(1) travelling route of paver, and field lofting construction lofting: are determined according to the actual conditions of construction area;
(2) it charges: mineral aggregate, emulsified asphalt, filler, water, additive etc. being respectively charged into the corresponding hopper of paver, should ensure that mine The humidity uniformity of material;
(3) it paves and blanks and moulding and conserving: charged paver is opened to construction starting point, be directed at strike angle line, and adjust and pave Case thickness and camber are adjacent to paving box periphery with former road surface, and one piece of malthoid of place mat, works as paver preferably under the paving box of starting point After advance, malthoid is taken away together together with mixture above, by production mix proportion and live mineral aggregate water content situation, sufficiently mixes With mineral aggregate, filler, water, additive and lotion, mixed mixture inflow pave slot and be distributed in the slot that paves it is appropriate when, start booth Paving vehicle at the uniform velocity advances, and openable paver vehicle following sparge pipe when needing, water spray is wet, and spreading speed is to keep mixture laying Subject to amount and amount of agitation are almost the same, general forward speed is 1.5 ~ 3.0km/h, should carry out immediately artificial levelling after paving, and is looked for Flat emphasis is: starting point, terminal, longitudinal seam, blocked up, excessively thin or uneven place, especially gathers materials the longitudinal direction of generation to super large partial size Scratch should be removed and be filled and led up as early as possible, and molding rolls, upper epidermis and transition zone during conserving molding, forbid any vehicle and Pedestrian enters, and transition zone carries out 4~6 using pneumatic-tired rollers and rolls, and upper epidermis paving can be carried out after the completion of transition zone rolls It builds;
(4) scene of transition zone and upper epidermis paves: charged paver being opened to construction starting point, manipulator commands paver vehicle It is directed at Construction control line, paving box is stably placed to the place that starts, leveling personnel adjust paving box thickness and camber;Manipulator's root The experience adjustments material jaw opening that actually paves is combined according to calibration result;Mixture uniformly paves, and paver vehicle speed is controlled in 1.5- 3.0KM/h, strict control paving thickness are laid in seam using sheet iron in transverse joint processing to ensure pavement performance Place, vehicle to be paved paves takes out simultaneously manual sorting seam immediately later;Control surface evenness.
The invention has the benefit that for solve plat-bottom escape, improve concrete road surface anti-permeability performance, flushing resistance, Improve road face durability, using the arrangement and method for construction of asphaltic base composite seal coat, asphaltic base composite seal coat design overall thickness be 17 ~ 22mm divides three layers of implementation, the asphaltic base combined type sealing scheme of sub-layer, transition zone and upper epidermis from the bottom to top.
Detailed description of the invention
Fig. 1 is a kind of structure combination diagram of the asphaltic base combined type sealing for road in airport of the present invention;
Fig. 2 is that a kind of sub-layer of the asphaltic base combined type sealing construction method for road in airport of the present invention is mainly constructed signal Figure;
Fig. 3 is main for the upper epidermis and transition zone of a kind of asphaltic base combined type sealing construction method for road in airport of the present invention Construction schematic diagram.
Specific embodiment
A specific embodiment of the invention is described in further detail below in conjunction with attached drawing, so that technical solution of the present invention is easier to In understanding and grasp.
Refering to fig. 1 shown in -3, a kind of pitch composite seal coat construction method for road in airport, using sub-layer 1, transition The asphaltic base of layer 2 and upper epidermis 3 carries out combined type sealing, and the airfield runway is by Portland Cement Concrete Surface Course 4, MS-2 type micro-surface area Surface layer 5, MS-2 type micro-surface area transition zone 7, modified emulsifying asphalt synchronous surface dressing 8 and cement stabilized macadam base 6 form, packet Include following steps:
1) sub-layer is constructed
(1) shovel dress building stones: the building stones for being packed into hopper should maintain an equal level with the height of hopper left baffle, prevent because expecting excessively to trickle down;
(2) emulsified asphalt: should check oil pick-up tube and its connector whether good seal, forbid emulsified asphalt to splash;
(3) it demarcates: the temperature of emulsified asphalt being heated and is stablized between 60 DEG C ~ 80 DEG C;It is on valve, is at pipe Road recurrent state, spray bars emulsified asphalt are uniformly mixed with asphalt tank internal emulsification pitch, are demarcated in asphalt binder stability controller Emulsified asphalt spread quantity and travel speed, vehicular velocity setting are 30 ~ 60m/min;
(4) spread paves: setting emulsified asphalt and the spraying altitude and dosage gathered materials open building stones dispenser and asphalt distribution Bar;During spread, left and right spray bars are adjusted at any time, guarantee the integrality of seam;It should be met the following requirements when spread: sealing In work progress, chip sealer wants smooth ride, at the uniform velocity;Construct the first width when, should gather materials on spread device in side plus baffle, prevent Only building stones splash, construct last width when, use same method in the other side, among spread when width, unilateral pitch to be kept to spray Spill width than building stones spray width more than 8 ~ 10cm;
(5) defect repair: when discovery sprinkling emulsified asphalt has blank, it should carry out manually mending in time and spill;When there is emulsified asphalt accumulation When should strike off;When emulsified asphalt sprinkling ribbon occurs with the spreading that gathers materials, atomizer and bin gate should be closed in time, check atomizer Pressure whether meet the requirements, whether bin gate is blocked by big particle diameter stone;Gather materials when floating, road surface should be scanned out, and must not Rubbing oneself adhered in place gather materials;When any material is finished, the valve of all conveying materials should be closed, is usually first closed Building stones switch, it is rear to close emulsified asphalt switch, the pitch oil film of Yao Liuyou 50cm, so as to seam.Then chip sealer is pressed into advance side To sailing out of job step;
(6) joint treatment: transverse joint processing, transverse joint are handled using rendezvous method, in every section of joint part, are layered on iron plate or tarred brown paper are horizontal Before this section is spilt a little and after terminal, length is 1 ~ 1.5m;Longitudinal joint processing, emulsified asphalt spread will guarantee that driving is straight suitable, construct When next width, the spread of sealing side building stones should be aligned with the building stones on the right side of a upper width, guarantee that longitudinal joint docking is good, seam pitch Lap must not exceed l0cm;
(7) be compacted and form: synchronous surface dressing laying finishes, after emulsified asphalt demulsification to be modified, using the tire of 16 ~ 30T Road roller roll for 2 ~ 4 times, when rolling, should follow intermediate, first slow rear fast principle behind first both sides, each wheelmark weight when rolling Folded 30cm, rolling speed control road roller in 30m/min ~ 60m/min, roller compaction process arbitrarily must not brake or turn around;
(8) construction terminates chip sealer to be cleaned: chip sealer being driven into no vehicular traffic, is parked without the specified safety place such as slope;
2) upper epidermis and transition zone construction
(1) travelling route of paver, and field lofting construction lofting: are determined according to the actual conditions of construction area;
(2) it charges: mineral aggregate, emulsified asphalt, filler, water, additive etc. being respectively charged into the corresponding hopper of paver, should ensure that mine The humidity uniformity of material;
(3) it paves and blanks and moulding and conserving: charged paver is opened to construction starting point, be directed at strike angle line, and adjust and pave Case thickness and camber are adjacent to paving box periphery with former road surface, and one piece of malthoid of place mat, works as paver preferably under the paving box of starting point After advance, malthoid is taken away together together with mixture above, by production mix proportion and live mineral aggregate water content situation, sufficiently mixes With mineral aggregate, filler, water, additive and lotion, mixed mixture inflow pave slot and be distributed in the slot that paves it is appropriate when, start booth Paving vehicle at the uniform velocity advances, and openable paver vehicle following sparge pipe when needing, water spray is wet, and spreading speed is to keep mixture laying Subject to amount and amount of agitation are almost the same, general forward speed is 1.5 ~ 3.0km/h, should carry out immediately artificial levelling after paving, and is looked for Flat emphasis is: starting point, terminal, longitudinal seam, blocked up, excessively thin or uneven place, especially gathers materials the longitudinal direction of generation to super large partial size Scratch should be removed and be filled and led up as early as possible, and molding rolls, upper epidermis and transition zone during conserving molding, forbid any vehicle and Pedestrian enters, and transition zone carries out 4~6 using pneumatic-tired rollers and rolls, and upper epidermis paving can be carried out after the completion of transition zone rolls It builds;
(4) scene of transition zone and upper epidermis paves: charged paver being opened to construction starting point, manipulator commands paver vehicle It is directed at Construction control line, paving box is stably placed to the place that starts, leveling personnel adjust paving box thickness and camber;Manipulator's root The experience adjustments material jaw opening that actually paves is combined according to calibration result;Mixture uniformly paves, and paver vehicle speed is controlled in 1.5- 3.0KM/h, strict control paving thickness are laid in seam using sheet iron in transverse joint processing to ensure pavement performance Place, vehicle to be paved paves takes out simultaneously manual sorting seam immediately later;Control surface evenness.
The invention has the benefit that for solve plat-bottom escape, improve concrete road surface anti-permeability performance, flushing resistance, Improve road face durability, using the arrangement and method for construction of asphaltic base composite seal coat, asphaltic base composite seal coat design overall thickness be 17 ~ 22mm divides three layers of implementation, the asphaltic base combined type sealing scheme of sub-layer, transition zone and upper epidermis from the bottom to top.
The above description is merely a specific embodiment, but scope of protection of the present invention is not limited thereto, any The change or replacement expected without creative work, should be covered by the protection scope of the present invention.

Claims (1)

1. a kind of pitch composite seal coat construction method for road in airport, it is characterised in that: using sub-layer, transition zone and on The asphaltic base on surface layer carries out combined type sealing, comprising the following steps:
1) sub-layer is constructed
(1) shovel dress building stones: the building stones for being packed into hopper should maintain an equal level with the height of hopper left baffle, prevent because expecting excessively to trickle down;
(2) emulsified asphalt: should check oil pick-up tube and its connector whether good seal, forbid emulsified asphalt to splash;
(3) it demarcates: the temperature of emulsified asphalt being heated and is stablized between 60 DEG C ~ 80 DEG C;It is on valve, is at pipe Road recurrent state, spray bars emulsified asphalt are uniformly mixed with asphalt tank internal emulsification pitch, are demarcated in asphalt binder stability controller Emulsified asphalt spread quantity and travel speed, vehicular velocity setting are 30 ~ 60m/min;
(4) spread paves: setting emulsified asphalt and the spraying altitude and dosage gathered materials open building stones dispenser and asphalt distribution Bar;During spread, left and right spray bars are adjusted at any time, guarantee the integrality of seam;It should be met the following requirements when spread: sealing In work progress, chip sealer wants smooth ride, at the uniform velocity;Construct the first width when, should gather materials on spread device in side plus baffle, prevent Only building stones splash, construct last width when, use same method in the other side, among spread when width, unilateral pitch to be kept to spray Spill width than building stones spray width more than 8 ~ 10cm;
(5) defect repair: when discovery sprinkling emulsified asphalt has blank, it should carry out manually mending in time and spill;When there is emulsified asphalt accumulation When should strike off;When emulsified asphalt sprinkling ribbon occurs with the spreading that gathers materials, atomizer and bin gate should be closed in time, check atomizer Pressure whether meet the requirements, whether bin gate is blocked by big particle diameter stone;Gather materials when floating, road surface should be scanned out, and must not Rubbing oneself adhered in place gather materials;When any material is finished, the valve of all conveying materials should be closed, is usually first closed Building stones switch, it is rear to close emulsified asphalt switch, the pitch oil film of Yao Liuyou 50cm, so as to seam;
Then chip sealer is sailed out of into job step by direction of advance;
(6) joint treatment: transverse joint processing, transverse joint are handled using rendezvous method, in every section of joint part, are layered on iron plate or tarred brown paper are horizontal Before this section is spilt a little and after terminal, length is 1 ~ 1.5m;Longitudinal joint processing, emulsified asphalt spread will guarantee that driving is straight suitable, construct When next width, the spread of sealing side building stones should be aligned with the building stones on the right side of a upper width, guarantee that longitudinal joint docking is good, seam pitch Lap must not exceed l0cm;
(7) be compacted and form: synchronous surface dressing laying finishes, after emulsified asphalt demulsification to be modified, using the tire of 16 ~ 30T Road roller roll for 2 ~ 4 times, when rolling, should follow intermediate, first slow rear fast principle behind first both sides, each wheelmark weight when rolling Folded 30cm, rolling speed control road roller in 30m/min ~ 60m/min, roller compaction process arbitrarily must not brake or turn around;
(8) construction terminates chip sealer to be cleaned: chip sealer being driven into no vehicular traffic, is parked without the specified safety place such as slope;
2) upper epidermis and transition zone construction
(1) travelling route of paver, and field lofting construction lofting: are determined according to the actual conditions of construction area;
(2) it charges: mineral aggregate, emulsified asphalt, filler, water, additive etc. being respectively charged into the corresponding hopper of paver, should ensure that mine The humidity uniformity of material;
(3) it paves and blanks and moulding and conserving: charged paver is opened to construction starting point, be directed at strike angle line, and adjust and pave Case thickness and camber are adjacent to paving box periphery with former road surface, and one piece of malthoid of place mat, works as paver preferably under the paving box of starting point After advance, malthoid is taken away together together with mixture above, by production mix proportion and live mineral aggregate water content situation, sufficiently mixes With mineral aggregate, filler, water, additive and lotion, mixed mixture inflow pave slot and be distributed in the slot that paves it is appropriate when, start booth Paving vehicle at the uniform velocity advances, and openable paver vehicle following sparge pipe when needing, water spray is wet, and spreading speed is to keep mixture laying Subject to amount and amount of agitation are almost the same, general forward speed is 1.5 ~ 3.0km/h, should carry out immediately artificial levelling after paving, and is looked for Flat emphasis is: starting point, terminal, longitudinal seam, blocked up, excessively thin or uneven place, especially gathers materials the longitudinal direction of generation to super large partial size Scratch should be removed and be filled and led up as early as possible, and molding rolls, upper epidermis and transition zone during conserving molding, forbid any vehicle and Pedestrian enters, and transition zone carries out 4~6 using pneumatic-tired rollers and rolls, and upper epidermis paving can be carried out after the completion of transition zone rolls It builds;
(4) scene of transition zone and upper epidermis paves: charged paver being opened to construction starting point, manipulator commands paver vehicle It is directed at Construction control line, paving box is stably placed to the place that starts, leveling personnel adjust paving box thickness and camber;Manipulator's root The experience adjustments material jaw opening that actually paves is combined according to calibration result;Mixture uniformly paves, and paver vehicle speed is controlled in 1.5- 3.0KM/h, strict control paving thickness are laid in seam using sheet iron in transverse joint processing to ensure pavement performance Place, vehicle to be paved paves takes out simultaneously manual sorting seam immediately later;Control surface evenness.
CN201910005100.6A 2019-01-03 2019-01-03 A kind of pitch composite seal coat construction method for road in airport Pending CN109468904A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910005100.6A CN109468904A (en) 2019-01-03 2019-01-03 A kind of pitch composite seal coat construction method for road in airport

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910005100.6A CN109468904A (en) 2019-01-03 2019-01-03 A kind of pitch composite seal coat construction method for road in airport

Publications (1)

Publication Number Publication Date
CN109468904A true CN109468904A (en) 2019-03-15

Family

ID=65677109

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910005100.6A Pending CN109468904A (en) 2019-01-03 2019-01-03 A kind of pitch composite seal coat construction method for road in airport

Country Status (1)

Country Link
CN (1) CN109468904A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110578280A (en) * 2019-08-19 2019-12-17 江苏增光复合材料科技有限公司 Crack-resistant anti-scouring cement pavement composite structure
CN110578281A (en) * 2019-08-19 2019-12-17 江苏增光复合材料科技有限公司 construction method of civil aviation airport field way cement pavement structure layer

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2012041298A1 (en) * 2010-07-02 2012-04-05 Purus Arzberg Gmbh Laying plate for useful surfaces
CN107354834A (en) * 2017-07-26 2017-11-17 北京中航空港建设工程有限公司 The construction technique and reinforced structure complex in Civil Aviation Airport field road
CN209636583U (en) * 2019-01-03 2019-11-15 中铁北京工程局集团有限公司 A kind of pitch composite seal coat for road in airport

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2012041298A1 (en) * 2010-07-02 2012-04-05 Purus Arzberg Gmbh Laying plate for useful surfaces
CN107354834A (en) * 2017-07-26 2017-11-17 北京中航空港建设工程有限公司 The construction technique and reinforced structure complex in Civil Aviation Airport field road
CN209636583U (en) * 2019-01-03 2019-11-15 中铁北京工程局集团有限公司 A kind of pitch composite seal coat for road in airport

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张志凌: "沥青基复合封层技术在民用机场水泥道面中的应用", 山西建筑, vol. 44, no. 20, pages 142 - 143 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110578280A (en) * 2019-08-19 2019-12-17 江苏增光复合材料科技有限公司 Crack-resistant anti-scouring cement pavement composite structure
CN110578281A (en) * 2019-08-19 2019-12-17 江苏增光复合材料科技有限公司 construction method of civil aviation airport field way cement pavement structure layer
CN110578281B (en) * 2019-08-19 2021-07-09 江苏增光新材料科技股份有限公司 Construction method of civil aviation airport field way cement pavement structure layer
CN110578280B (en) * 2019-08-19 2021-08-24 江苏增光新材料科技股份有限公司 Crack-resistant anti-scouring cement pavement composite structure

Similar Documents

Publication Publication Date Title
CN104762858B (en) Asphalt concrete construction method for soft soil matrix pavement
US20140270953A1 (en) Road strengthening and reinforcement during a recycling process
CN110258236A (en) A kind of high-performance steel slag road surface and its construction method
CN103669152A (en) Road surface construction method of ultrathin stone mastic asphalt mixture
CN106894308A (en) A kind of crack resistance construction of cement stable macadam base method
CN102493316A (en) Production method of plant-mixed cold recycling foamed asphalt concrete
CN110453560A (en) A kind of blueness concrete pavement construction technique
CN106120524A (en) A kind of road construction method
CN109468904A (en) A kind of pitch composite seal coat construction method for road in airport
CN111455770A (en) Asphalt pavement splicing structure based on recycled materials and construction method thereof
CN109736161A (en) A kind of composite construction Sub-sealing Course for the road face between the cement road face on airport and semi-rigid type base
CN104612014A (en) Asphalt pavement crack-preventing base fabric construction method
CN111608080A (en) Five-machine linkage bridge deck pavement construction method
CN213625024U (en) Cold regeneration road surface structure of emulsified asphalt
CN102877389B (en) Asphalt pavement paving method
CN107419635A (en) A kind of composite pavement sealing method
CN101481901A (en) Pouring type asphalt concrete construction method for central strip
CN101429746B (en) Road paving method
CN112301826B (en) Emulsified asphalt cold-recycling pavement structure and rapid curing method for pavement
CN114108408A (en) Municipal road engineering pavement construction technology
CN209636583U (en) A kind of pitch composite seal coat for road in airport
CN102635047B (en) Large-span bridge deck composite structure layer construction technology
CN211472012U (en) Signal lamp crossing filling type composite pavement
CN105369706A (en) Cement stabilized tailing gravel road laying technology
CN114016430B (en) Asphalt concrete bridge deck pavement method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination