CN109460881A CN201711470958.7A CN201711470958A CN109460881A CN 109460881 A CN109460881 A CN 109460881A CN 201711470958 A CN201711470958 A CN 201711470958A CN 109460881 A CN109460881 A CN 109460881A
Authority
CN
China
Prior art keywords
equipment
guarantor
electric
power supply
stand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711470958.7A
Other languages
Chinese (zh)
Inventor
王文华
唐锦江
朱伟
陈国恩
沈超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Zhejiang Electric Power Co Ltd
Jiaxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Zhejiang Huayun Information Technology Co Ltd
Original Assignee
State Grid Zhejiang Electric Power Co Ltd
Jiaxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Zhejiang Huayun Information Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Zhejiang Electric Power Co Ltd, Jiaxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd, Zhejiang Huayun Information Technology Co Ltd filed Critical State Grid Zhejiang Electric Power Co Ltd
Priority to CN201711470958.7A priority Critical patent/CN109460881A/en
Publication of CN109460881A publication Critical patent/CN109460881A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/20Administration of product repair or maintenance
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Educational Administration (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

A kind of guarantor's power supply trouble excludes and stand-by equipment planing method: according to protecting electric user, protecting electric task, protect electricity and make an inspection tour and weather monitoring situation, by the progress priority division of each guarantors electric line;Every guarantor's electric equipment in same guarantor's electric line corresponds to different equipment preferred numbers;After receiving equipment alarm information, the repairing order of faulty equipment is first determined, then carry out repairing resource allocation layout;First device is set by important guarantor's electric equipment, each first device is equipped with stand-by equipment, when first device breaks down, first switches to stand-by equipment power supply, then determine repairing order, switches back into former first device after the completion of repairing again.The present invention protects power supply trouble around reply in time and excludes this target, emergency electric supply unit is set for important guarantor's electric equipment first, when an error occurs, first switch to emergency electric supply unit power supply, the comprehensive importance for protecting electric line and the same importance for protecting distinct device in electric line again, are ranked up the priority of troubleshooting.

Description

A kind of guarantor's power supply trouble excludes and stand-by equipment planing method
Technical field
The present invention relates to power industry safety management technology field, in particular to a kind of guarantor's power supply trouble is excluded and spare is set Standby planing method.
Background technique
With the rapid development of economic life various aspects, face more and more some momentous conferences, high standard activity and Heavyweight receives task, and protecting power supply capacity to power supply companies at different levels also proposed more higher requirements.Electric system guarantees to supply Electricity demanding, processing burst accident, ensure electric power netting safe running platform, the key problem to be solved be emergency event occur after, Comprehensive response how is made within the shortest time, guarantees the reliable, fast of power supply task, to reduce accident to greatest extent Caused by lose, promoted electric service level and power supply supportability.
China Patent Publication No. CN10252170B, grant date on 2 18th, 2015, the entitled power train of innovation and creation System early warning command system, this application discloses a kind of electric system early warning command system and its methods, including early warning commander's clothes Be engaged in platform, Communications service equipment and subscriber terminal equipment, the early warning commander service platform by graphical user interface, using center Module and bottom data interface are constituted, and processing result information are sent to graphical user interface or bottom data interface, this is The reliability and operational efficiency of electric system early warning system can be improved in system and its method, is used for power system power supply management.Its It is disadvantageous in that the description laid particular emphasis on to early warning command process, what it is to the description of power system power supply management method is not to have very much Body.
Summary of the invention
It is an object of the invention to make comprehensive response to power supply trouble within the shortest time, according to the weight for protecting electric task Degree is wanted, faulty equipment priority is ranked up, so that processing equipment failure in time, guarantees that the failure of important equipment is preferentially arranged It removes, provides a kind of guarantor's power supply trouble and exclude and stand-by equipment planing method.
The technical solution adopted by the present invention to solve the technical problems is: a kind of guarantor's power supply trouble excludes and stand-by equipment rule The method of drawing: according to protecting electricity user, the electric task of guarantor, protecting electricity tour and weather monitoring situation, by each guarantor's electric line progress priority It divides;Every guarantor's electric equipment in same guarantor's electric line corresponds to different equipment preferred numbers;After receiving equipment alarm information, It first determines the repairing order of faulty equipment, then carries out repairing resource allocation layout;Level-one is set by important guarantor's electric equipment to set Standby, each first device is equipped with stand-by equipment, when first device breaks down, first switches to stand-by equipment power supply, then determine Order is repaired, switches back into former first device after the completion of repairing again.
In the present invention, power supply trouble monitoring is protected around reply in time and excludes this target, after receiving warning message, is determined Electric priority is protected, it is preferential to exclude the higher guarantor's electric equipment failure of priority level, it makes a distinction between the important and the lesser one, it is ensured that the validity of electric task is protected, For important guarantor's electric equipment, stand-by equipment is equipped with to it in advance and is powered.
Preferably, the method for the determining repairing order is: guarantor is divided into several periods, each period root in the electric period One minor sort is carried out to faulty equipment according to electric preferred number is protected, so that it is determined that repairing order.
Preferably, the electric preferred number=guarantor's electricity weight * equipment preferred number of the guarantor;Electric weight=user of the guarantor etc. Grade * task grade * makes an inspection tour specific gravity * meteorology stability;The size of electric weight is protected by guarantor's electricity user, the Bao electricity Ren in guarantor's electric line Situation and meteorologic factor decision are maked an inspection tour in business;If every guarantor's electric line connection Ganlei protects electric user, every class protects electric user and corresponds to phase The user gradation answered;Each period undertakes the significance level of the electric task of guarantor according to electric line is protected, and corresponding task grade is arranged; It makes an inspection tour situation to measure to make an inspection tour specific gravity, meteorologic factor is measured with meteorological stability.
Preferably, the priority that electric equipment is respectively protected in same guarantor's electric line is determined by equipment preferred number, it is described to set Standby preferred number=∑ failure rate/(load number * utilization rate * specific gravity factor), equipment preferred number is by the company, guarantor's electric equipment institute Loadtype, load number, load utilization rate and the load faulty rate connect determines;Each period sets for each loadtype Set corresponding specific gravity factor.
Preferably, setting preferred number threshold value, the slave power distribution cabinet that equipment preferred number is greater than preferred number threshold value is set For first device, equipment preferred number is less than the slave power distribution cabinet of preferred number threshold value alternately stand-by equipment;Stand-by equipment institute Category task grade is lower than the corresponding affiliated task grade of first device.
Preferably, selection is set with the affiliated task rank difference of first device away from maximum power supply in alternative stand-by equipment Standby middle percent ten five power supply unit of the surplus at least more than first device electricity consumption of powering is as stand-by equipment.
Preferably, the electricity consumption=∑ unit time electricity consumption * electricity consumption duration * load number * utilization rate.
Preferably, the power supply surplus=equipment maximum power supply volume-electricity consumption.
Substantial effect of the invention: power supply trouble is protected around timely reply and excludes this target, is first important guarantor Emergency electric supply unit is arranged in electric equipment, when an error occurs, first switches to emergency electric supply unit power supply, then synthesis protects electric line Importance and the same importance for protecting distinct device in electric line, according to electric preferred number is protected, to the preferential grading of troubleshooting Row sequence, to guarantee the quality and efficiency of electric task.
Specific embodiment
Below by specific embodiment, technical scheme of the present invention will be further explained in detail.
A kind of guarantor's power supply trouble excludes and stand-by equipment planing method, according to protect electric user, protect electric task, protect electricity make an inspection tour with And weather monitoring situation, each guarantor's electric line is subjected to priority division;Every guarantor's electric equipment in same guarantor's electric line is corresponding not Same equipment preferred number;After receiving equipment alarm information, the repairing order of faulty equipment is first determined, then carry out repairing resource Allotment layout;First device is set by important guarantor's electric equipment, each first device is equipped with stand-by equipment, when first device is sent out When raw failure, stand-by equipment power supply is first switched to, then determines repairing order, switches back into former first device again after the completion of repairing, with Guarantee the continuity of short time power supply.
The method for determining repairing order is: guarantor being divided into several periods the electric period, each period, electricity is preferential to be according to protecting Several pairs of faulty equipments carry out a minor sort, so that it is determined that repairing order.Protect electric preferred number by guarantor's electricity weight of guarantor's electric line and The equipment preferred number of connected power supply unit determines, protects electric preferred number=guarantor's electricity weight * equipment preferred number.Protect electricity power It is reused in the importance of overall merit every guarantor's electric line, electric weight=user gradation * task grade * is protected and makes an inspection tour specific gravity * meteorology Stability.The importance of electric line is protected by the electric task of guarantor's electricity user, guarantor, tour situation and the meteorologic factor in guarantor's electric line It determines.It protects electric user and is divided into different grades, such as general meeting, momentous conference, high-level meeting etc., user gradation is the guarantor The equivalent coefficient of electric user, user gradation is higher, and coefficient is smaller;According to the electricity consumption scene of different periods, electric task will be protected and be divided into Meeting has dinner, lies fallow, going to bed, receiving ... several junior's tasks that wait, different periods, the importance of each junior's task Be not quite similar, such as night will preferentially guarantee electricity consumption of going to bed, mealtime preferentially guarantee to have dinner electricity consumption ... need according to when Between section the importance of these junior's tasks is divided, the significance level of junior's task, important journey are represented with task grade Degree is higher, and task equivalent coefficient is smaller;Tour resource provisioned in the electric region of each guarantor is not quite similar, and tour resource is equipped with high Regional processing efficiency is relatively high, and tour specific gravity factor is smaller, and it is more sufficient to represent tour resource;Meteorologic factor is to the electric task of guarantor There is a very big influence, when thunderstorm weather, the task of rush repair can also be aggravated, and time and frequency all can be impacted, meteorological steady Determine coefficient is smaller, represents meteorological more stable.
Equipment preferred number=∑ failure rate/(load number * utilization rate * specific gravity factor);The electricity consumption of every guarantor's electric equipment Situation is related with loadtype, load number, utilization rate, failure rate, and specific gravity system is arranged for each loadtype in each period Number, every kind of loadtype have quantity and frequency of use, the difference of failure rate.Such as a lighting apparatus, loadtype may wrap Include: ceiling lamp, desk lamp, socket etc., when daytime is bright and clear, ceiling lamp, the specific gravity factor of desk lamp are relatively low, it is corresponding this when The utilization rate and failure rate of section are also just lower;To night, ceiling lamp, desk lamp specific gravity factor will become larger, utilization rate and therefore Barrier rate also just improves.The electricity consumption situation of every equipment of overall merit helps accurately to estimate overall electricity consumption, so which judge A little equipment can be used as and the stand-by equipment of equipment guarantees overall power supply cloth under the premise of meeting power itself demand Office.To sum up, protecting electric priority is to carry out dynamic update according to different periods, in order to according to specific service condition, When an error occurs, the higher power demand protected electric task or protect electricity object of preferential guarantee priority, motor-driven carries out guarantor's electricity The allotment of goods and materials.
According to actual guarantor's electricity demanding, preferred number threshold value is set, equipment preferred number is greater than preferred number threshold value First device is set as from power distribution cabinet, and equipment preferred number is less than the slave power distribution cabinet of preferred number threshold value alternately stand-by equipment. The setting of preferred number threshold value need to consider power supply unit quantity, and emphasis is needed to protect the quantity of the object of electricity.Stand-by equipment with it is corresponding First device belong to different task grades, the affiliated task grade of stand-by equipment is lower than the corresponding affiliated task dispatching of first device Grade.In alternative stand-by equipment, selection with the affiliated task rank difference of first device away from maximum power supply unit power surplus extremely Less greater than 1 15 power supply unit of first device electricity consumption as stand-by equipment.Power supply unit belongs to first device The equipment of different task grades, different task grade carries out intersection stand-by power supply, can expand whole power supply capacity, guarantees The rational flow of overall power.Task rank difference is away from bigger, and a possibility that illustrating two equipment while powering is smaller, as level-one The stand-by equipment of equipment is powered, on the stand-by equipment itself power task influence just it is smaller.The power supply surplus of stand-by equipment At least more than the 1 15 of first device electricity consumption, it is selected to the electrical demand of stand-by equipment, it is therefore intended that guarantee standby With equipment will not overload operation, guarantee power supply stability and safety.When electricity consumption=∑ unit time electricity consumption * electricity consumption Long * load number * utilization rate connects several different power load on every power supply unit, and the electricity consumption of power supply unit is The summation of all load electricity consumptions, the electricity consumption of load is by load number, electricity consumption duration, unit time electricity consumption and utilization rate It determines, surplus=equipment maximum power supply volume-electricity consumption of powering, power supply surplus is for measuring the power supply unit as stand-by equipment Power supply capacity.
Embodiment described above is a kind of preferable scheme of the invention, not makees limit in any form to the present invention System, there are also other variants and remodeling on the premise of not exceeding the technical scheme recorded in the claims.

Claims (8)

1. a kind of guarantor's power supply trouble excludes and stand-by equipment planing method, which is characterized in that according to protect electric user, protect electric task, Electricity tour and weather monitoring situation are protected, each guarantor's electric line is subjected to priority division;Every guarantor electricity in same guarantor's electric line Equipment corresponds to corresponding equipment preferred number;After receiving equipment alarm information, first determine faulty equipment repairing order, then into It robs and repairs resource allocation layout;Electric equipment is protected into part and is set as first device, each first device is equipped with stand-by equipment, when one When grade device fails, stand-by equipment power supply is first switched to, then determines repairing order, switches back into former level-one after the completion of repairing again Equipment.
2. a kind of guarantor's power supply trouble according to claim 1 excludes and stand-by equipment planing method, which is characterized in that described The method for determining repairing order is: guarantor being divided into several periods the electric period, each period is according to the electric preferred number of guarantor to failure Equipment carries out a minor sort, so that it is determined that repairing order.
3. a kind of guarantor's power supply trouble according to claim 2 excludes and stand-by equipment planing method, which is characterized in that described It protects electric preferred number to be determined by the electric weight of guarantor of guarantor's electric line with the equipment preferred number for protecting the connected power supply unit of electric line, protect Electric preferred number=guarantor's electricity weight * equipment preferred number;
Electric weight=user gradation * task grade the * of the guarantor makes an inspection tour specific gravity * meteorology stability;The size of electric weight is protected by the guarantor The electric task of guarantor's electricity user, guarantor, tour situation and meteorologic factor in electric line determine;If every guarantor's electric line connection Ganlei protects Electric user, every class protect electric user and correspond to corresponding user gradation;Each period undertakes the weight of the electric task of guarantor according to electric line is protected Degree is wanted, corresponding task grade is set;It makes an inspection tour situation to measure to make an inspection tour specific gravity, meteorologic factor is weighed with meteorological stability Amount.
4. a kind of guarantor's power supply trouble according to claim 3 excludes and stand-by equipment planing method, which is characterized in that same The priority that electric equipment is respectively protected in guarantor's electric line is determining by equipment preferred number, and the equipment preferred number=∑ failure rate/ (load number * utilization rate * specific gravity factor), loadtype that equipment preferred number is connected by guarantor's electric equipment, load number, It loads utilization rate and load faulty rate determines;Corresponding specific gravity factor is arranged for each loadtype in each period.
5. a kind of guarantor's power supply trouble according to claim 1 excludes and stand-by equipment planing method, which is characterized in that setting The slave power distribution cabinet that equipment preferred number is greater than preferred number threshold value is set as first device by preferred number threshold value, and equipment is preferentially Number is less than the slave power distribution cabinets alternately stand-by equipment of preferred number threshold value;The affiliated task grade of stand-by equipment is lower than corresponding level-one The affiliated task grade of equipment.
6. guarantor's power supply trouble according to claim 5 excludes and stand-by equipment planing method, which is characterized in that alternative standby With in equipment, selection is set away from surplus of powering in maximum power supply unit at least more than level-one with the affiliated task rank difference of first device 1 15 power supply unit of spare electricity is as stand-by equipment.
7. a kind of guarantor's power supply trouble according to claim 6 excludes and stand-by equipment planing method, which is characterized in that described Electricity consumption=∑ unit time electricity consumption * electricity consumption duration * load number * utilization rate.
8. a kind of guarantor's power supply trouble according to claim 6 excludes and stand-by equipment planing method, which is characterized in that described Power supply surplus=equipment maximum power supply volume-electricity consumption.
CN201711470958.7A 2017-12-28 2017-12-28 A kind of guarantor's power supply trouble excludes and stand-by equipment planing method Pending CN109460881A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711470958.7A CN109460881A (en) 2017-12-28 2017-12-28 A kind of guarantor's power supply trouble excludes and stand-by equipment planing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711470958.7A CN109460881A (en) 2017-12-28 2017-12-28 A kind of guarantor's power supply trouble excludes and stand-by equipment planing method

Publications (1)

Publication Number Publication Date
CN109460881A true CN109460881A (en) 2019-03-12

Family

ID=65606215

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711470958.7A Pending CN109460881A (en) 2017-12-28 2017-12-28 A kind of guarantor's power supply trouble excludes and stand-by equipment planing method

Country Status (1)

Country Link
CN (1) CN109460881A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112488336A (en) * 2020-12-09 2021-03-12 深圳供电局有限公司 Power grid fault processing method and system used in extreme weather

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102623910A (en) * 2012-04-27 2012-08-01 重庆大学 Reliability-based maintenance decision method for switch equipment
CN103679547A (en) * 2013-11-29 2014-03-26 国家电网公司 Optimization method for missed steps of relay protection
CN104573989A (en) * 2015-01-28 2015-04-29 国家电网公司 Transmission line fault probability assessment method based on historical fault information
CN108806014A (en) * 2018-04-24 2018-11-13 佛山市中凯机电工程有限公司 A kind of remote computer machine room intelligent cruising inspection system based on cloud computer

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102623910A (en) * 2012-04-27 2012-08-01 重庆大学 Reliability-based maintenance decision method for switch equipment
CN103679547A (en) * 2013-11-29 2014-03-26 国家电网公司 Optimization method for missed steps of relay protection
CN104573989A (en) * 2015-01-28 2015-04-29 国家电网公司 Transmission line fault probability assessment method based on historical fault information
CN108806014A (en) * 2018-04-24 2018-11-13 佛山市中凯机电工程有限公司 A kind of remote computer machine room intelligent cruising inspection system based on cloud computer

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
无: "重要用户保电方案", 《百度》 *
汤继生等: "基于GIS的电网抢修车辆综合调度技术研究", 《电力信息与通信技术》 *
编纂委员会编: "《汶川特大地震抗震救灾志 卷5 抢险救灾志》", 31 August 2015, 北京:方志出版社 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112488336A (en) * 2020-12-09 2021-03-12 深圳供电局有限公司 Power grid fault processing method and system used in extreme weather

Similar Documents

Publication Publication Date Title
JP2011205871A (en) Electric power supply system
CN111369021A (en) Automatic maintenance method of power transmission and transformation equipment
CN207542843U (en) Intelligent remote charge and discharge monitoring equipment
CN103490492B (en) High voltage direct current electric power system
CN109472383A (en) An a kind of method for optimizing scheduling protecting electric-examination and repairing
CN103887862B (en) A kind of flexible management of charging and discharging rectification module, management tree device and system
CN103151790A (en) Intelligent power supply system of peak moving and valley filling
CN109460881A (en) A kind of guarantor's power supply trouble excludes and stand-by equipment planing method
CN102801204B (en) A kind of 240VDC high voltage direct current electric power system and method
CN104951884A (en) Visual display method of accident emergency repair and inversion based on distribution network
Malla et al. Coordinated priority-aware charging of distributed batteries in oversubscribed data centers
CN106789278B (en) The power failure restorative procedure of power failure repair system and the application system
CN105389667B (en) Support that the distribution system framework of integration is robbed in allotment
CN110212526B (en) Power supply system and micro-module data center
CN109472382A (en) An a kind of method for optimizing scheduling protecting electric-examination and repairing
CN109472368A (en) A kind of method for optimizing scheduling for protecting electric equipment troubleshooting and vehicle
CN202043327U (en) Marker lamp with guiding light stream
CN107465258A (en) A kind of electric power system and method for IDC computer rooms
CN109472427A (en) A kind of guarantor's power supply trouble excludes and stand-by equipment planing method
CN109474000B (en) Intelligent analysis system and method for distributed photovoltaic power supply of distribution transformer area
CN207677504U (en) Communication base station moves energy source dispatch system
CN109784775A (en) A kind of micro-grid system dispatching method and device
CN109472381A (en) A kind of guarantor's electric equipment upkeep operation optimization method
CN112698714B (en) Intelligent management method and system for virtual resources when UPS is started
CN204465136U (en) A kind of communication power supply of Rail Transit System

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190312