CN109457966A - A kind of mold method of foundation beam - Google Patents

A kind of mold method of foundation beam Download PDF

Info

Publication number
CN109457966A
CN109457966A CN201811416591.5A CN201811416591A CN109457966A CN 109457966 A CN109457966 A CN 109457966A CN 201811416591 A CN201811416591 A CN 201811416591A CN 109457966 A CN109457966 A CN 109457966A
Authority
CN
China
Prior art keywords
grc plate
grc
foundation beam
foundation
locating piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811416591.5A
Other languages
Chinese (zh)
Inventor
崔佳龙
朱江枫
倪锋
熊波
费少波
张家浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai No 7 Construction Co Ltd
Original Assignee
Shanghai No 7 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai No 7 Construction Co Ltd filed Critical Shanghai No 7 Construction Co Ltd
Priority to CN201811416591.5A priority Critical patent/CN109457966A/en
Publication of CN109457966A publication Critical patent/CN109457966A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Abstract

The present invention relates to a kind of mold methods of foundation beam, comprising: measurement GRC plate installation site line;Locating piece is installed on the inside of the GRC plate installation site line;The GRC plate, the fixed locating piece are installed on the outside of the locating piece;Backfilling of earthwork on the outside of the GRC plate;Reinforce the GRC plate.The present invention installs the effectively application instead of brick fetal membrane in foundation beam construction by using GRC plate, compared with traditional brick mold, improve effect, shorten the duration, save the cost, GRC speed of application are 5-8 times of brick loose tool speed of application, substantially reduce the duration, the frequency of use for reducing vertical transportation machinery achieves good economic benefit and social benefit.Further, the present invention keeps the installation of GRC Board position more accurate, first installs locating piece before the installation of GRC plate by first measuring GRC plate installation site line, it can effectively prevent GRC board bottom portion from will not move inward under the side pressure effect of backfill, the installation of GRC Board position is more accurate.

Description

A kind of mold method of foundation beam
Technical field
The present invention relates to Architectural Equipment field more particularly to a kind of mold methods of foundation beam.
Background technique
Currently, purchasing house becomes most Man's Demands with the development and the improvement of people's living standards of society, but due to Building is less to often result in the situation that supply falls short of demand.Therefore, real estate developer increasingly pursues the commercial house and builds up speed, thus Cause the duration of commercial house engineering to greatly shorten, for unit in charge of construction construction requirement (including efficiency and quality) increasingly It is high.Currently, many realtors are for quick sales, it is especially short for engineering building construction period.In foundation beam work progress In, due to poured concrete rear pattern plate can not remove or remove it is difficult, in order to save engineering cost, generally use brick Loose tool construction method.
Brick mold have always many engineerings with, be all used in foundation beam mostly, when the side form of foundation beam remove it is inconvenient When brick mold, loose tool inner wall be require painting, so be not present spillage the problem of.Concrete rear pattern plate of having constructed can not be torn open Difficult structure position place is removed or removed, also has using brick and replaces general template.For there are under more basis The engineering of beam is returned, the foundation construction duration is longer, so that the construction period of Party A be not achieved.
Using when the template of part, having the disadvantage that (1) brick fetal membrane building construction period is long based on brick fetal membrane, Quality requirement is high, and difficulty of construction is big, and artificial input amount is big;(2) it after brick mold construction, needs to do waterproof layer, process is tedious, Construction time is long, and construction period is short contradicts;Such as: plastering mortar reaches after some strength that (especially winter wants seeking time It is longer), it can just do the subsequent operations such as waterproof layer;(3) brick mold Construction on Environment requires very high, such as: it is influenced, is rained by weather It can not construct.
Summary of the invention
The present invention in order to generated when solving template of the brick fetal membrane as basic beam long construction period, quality requirement is high, applies The problem that work difficulty is big, artificial input amount is big proposes a kind of brick fetal membrane alternative solution, and used technical solution is: a kind of The mold method of foundation beam, comprising:
Measure GRC plate installation site line;
Locating piece is installed on the inside of the GRC plate installation site line;
The GRC plate, the fixed locating piece are installed on the outside of the locating piece;
Backfilling of earthwork on the outside of the GRC plate;
Reinforce the GRC plate.
Preferably, the mold method of above-mentioned foundation beam, the method for the measurement GRC plate installation site line specifically:
The GRC plate is formulated according to engineering drawing;
Live foundation trench is excavated, is modified;The construction of foundation beam concrete cushion is carried out on the foundation trench top, base plate of foundation pit is whole It is flat;
The GRC plate installation site line is measured according to construction requirement.
Preferably, the mold method of above-mentioned foundation beam, the scene foundation trench excavating sideline are taken the hand digging earthwork, are dug The earthwork is excavated by expecting that tool transports the foundation pit, excavation of earthwork acts in accordance with the foundation trench and excavates sideline vertical excavation.
Preferably, the mold method of above-mentioned foundation beam, and can upper people after the foundation beam concrete cushion construction When construction, the GRC plate installation site line is measured on the foundation beam concrete cushion, guarantees that foundation trench size is correct.
Preferably, the mold method of above-mentioned foundation beam installs the side of locating piece on the inside of the GRC plate installation site line Method specifically:
Timber wedge is installed on the inside of the GRC plate installation site line.
Preferably, the mold method of above-mentioned foundation beam, installs the GRC plate on the outside of the locating piece, it is fixed described in The method of locating piece specifically:
Cutting stock is carried out to the GRC plate, and carries out number label;
The GRC plate of well cutting is placed in concentrate in the foundation pit and is stacked;
The GRC plate of well cutting is marked according to the number and is successively installed on the foundation pit along the locating piece It is interior;
The locating piece is seated in foundation beam substratum, and is fully inserted into the foundation beam concrete cushion It is interior.
The straight angle or external corner are fixed on the outside of foundation beam using flitch nail, and upper, middle and lower are each together on the outside of foundation beam, Inner corner trim is fixed with wire nail, and the top of GRC is installed on fixing piece by connector, and the fixing piece is installed on the back fill course In the native soil layer in outside.
Preferably, the mold method of above-mentioned foundation beam, the connector are iron wire, and the fixing piece is timber wedge.
Preferably, the mold method of above-mentioned foundation beam, the installation of GRC plate and it is fixed after the completion of, check axis and described The sectional dimension of foundation beam is coped with the GRC plate and is adjusted, it is ensured that axis, foundation beam size are correct when there is deviation.
The beneficial effects of the present invention are:
1. the present invention installs the effectively application instead of brick fetal membrane in foundation beam construction by using GRC plate, with Traditional brick mold is compared, and effect is improved, and shortens duration, save the cost, and GRC speed of application is brick loose tool speed of application 5-8 times, substantially reduce the duration, reduce the frequency of use of vertical transportation machinery, achieve good economic benefit and society It can benefit.Further, the present invention keeps the installation of GRC Board position more accurate, in GRC by first measuring GRC plate installation site line Locating piece is first installed before plate installation, can effectively prevent GRC board bottom portion will not inside sidesway under the side pressure effect of backfill Dynamic, the installation of GRC Board position is more accurate.
2. being customized since GRC plate of the invention is required according to foundation beam size by factory, intensity with higher, rigidity Greatly, conveniently, surface is smooth for cleavable, in-site installation, handles without plastering, can be directly as waterproof matrix, not climate of constructing It influences, it is easy for installation greatly to shorten the duration, it can satisfy the short requirement of present construction period.Further, GRC plate is upper Portion is installed on fixing piece by connector, and GRC plate lower part is fixed by locating piece position, and GRC plate is made to be not easy to tilt, and installation is more Add it is firm, construct it is safer.
Detailed description of the invention
Present invention will be further explained below with reference to the attached drawings and examples.
Fig. 1 is the structural schematic diagram that GRC plate of the invention is installed in foundation pit;
Fig. 2 is the mounting structure schematic diagram on the outside of GRC plate external corner and foundation beam of the invention;
Fig. 3 is the mounting structure schematic diagram on the outside of GRC plate inner corner trim and foundation beam of the invention;
Fig. 4 is the flow chart of the mold method of foundation beam of the invention;
Description of symbols:
GRC plate 1, foundation trench 2, foundation beam concrete cushion 3, foundation pit 4, locating piece 5, flitch 6, connector 7, on fixing piece 8, Back fill course 9, native soil layer 10, wire nail 11.
Specific embodiment
In conjunction with the accompanying drawings, the present invention is further explained in detail.These attached drawings are simplified schematic diagram, only with Illustration illustrates basic structure of the invention, therefore it only shows the composition relevant to the invention.
Embodiment 1:
As shown in Fig. 1,4, the mold method of foundation beam of the invention, comprising:
S01: measurement 1 installation site line of GRC plate;
S02: locating piece 5 is installed on the inside of 1 installation site line of GRC plate;
S03: GRC plate 1, fixed positioning piece 5 are installed on the outside of locating piece 5;
1 outside backfilling of earthwork of S04:GRC plate;
S05: GRC plate 1 is reinforced.
The present invention installs the effectively application instead of brick fetal membrane in foundation beam construction by using GRC plate 1, with biography The brick mold of system is compared, and effect is improved, and shortens duration, save the cost, and GRC speed of application is brick loose tool speed of application 5-8 times, the duration is substantially reduced, reduces the frequency of use of vertical transportation machinery, achieves good economic benefit and society Benefit.Further, the present invention keeps the installation of 1 position of GRC plate more accurate, in GRC by first measuring 1 installation site line of GRC plate Plate 1 first installs locating piece 5 before installing, and can effectively prevent 1 bottom of GRC plate will not be inwardly under the side pressure effect of backfill Mobile, the installation of 1 position of GRC plate is more accurate.
Embodiment 2:
As shown in Figure 1, the mold method of foundation beam of the invention, comprising:
S01: measurement GRC plate installation site line, method particularly includes:
GRC plate 1 is formulated according to engineering drawing;
Live foundation trench 2 is excavated, is modified;It carries out foundation beam concrete cushion 3 on 2 top of foundation trench to construct, 4 bottom plate of foundation pit is whole It is flat;
1 installation site line of GRC plate is measured according to construction requirement;
S02: installing locating piece 5 on the inside of 1 installation site line of GRC plate, method particularly includes:
Timber wedge is installed on the inside of 1 installation site line of GRC plate;
S03: the installation GRC plate 1 on the outside of locating piece 5, fixed positioning piece 5, method particularly includes:
Cutting stock is carried out to GRC plate 1, and carries out number label;
The GRC plate 1 of well cutting is placed in concentrate in foundation pit 4 and is stacked;
The GRC plate 1 of well cutting is successively installed in foundation pit 4 according to number label along locating piece 5;
Locating piece 5 is seated in foundation beam substratum, and is fully inserted into foundation beam concrete cushion 3.
As shown in Fig. 2, the straight angle or external corner are fixed on the outside of foundation beam with nail using flitch 6, upper on the outside of foundation beam, In, it is lower it is each together;As shown in figure 3, inner corner trim is fixed with wire nail 11, the top of GRC plate 1 is installed on fixing piece 8 by connector 7 On, fixing piece 8 is installed in the native soil layer 10 in 9 outside of back fill course;
1 outside backfilling of earthwork of S04:GRC plate;
S05: GRC plate 1 is reinforced.
It since GRC plate 1 of the invention is required according to foundation beam size, is customized by factory, intensity with higher, rigidity Greatly, conveniently, surface is smooth for cleavable, in-site installation, handles without plastering, can be directly as waterproof matrix, not climate of constructing It influences, it is easy for installation greatly to shorten the duration, it can satisfy the short requirement of present construction period.Further, GRC plate 1 Top is installed on fixing piece 8 by connector 7, and GRC plate lower part is fixed by locating piece position, and GRC plate is made to be not easy to tilt, and is pacified Dress is more firm, constructs safer.
Further, live 2 excavating sideline of foundation trench takes the hand digging earthwork, excavates the earthwork by expecting that tool transports foundation pit 4, excavation of earthwork acts in accordance with foundation trench 2 and excavates sideline vertical excavation.
Further, after foundation beam concrete cushion 3 is constructed and when can go up people's construction, in foundation beam concrete cushion 1 installation site line of GRC plate is measured on 3, guarantees that 2 size of foundation trench is correct.
Further, connector 7 is iron wire, and fixing piece 8 is timber wedge.
Further, the installation of GRC plate 1 checks the sectional dimension of axis and foundation beam, is there is deviation with after the completion of fixation When, reply GRC plate 1 is adjusted, it is ensured that axis, foundation beam size are correct.The installation accuracy of GRC plate is improved by review, Improve engineering construction safety.
Taking the above-mentioned ideal embodiment according to the present invention as inspiration, through the above description, relevant staff is complete Various changes and amendments can be carried out without departing from the scope of the technological thought of the present invention' entirely.The technology of this invention Property range is not limited to the contents of the specification, it is necessary to which the technical scope thereof is determined according to the scope of the claim.

Claims (8)

1. a kind of mold method of foundation beam characterized by comprising
Measure GRC plate installation site line;
Locating piece is installed on the inside of the GRC plate installation site line;
The GRC plate, the fixed locating piece are installed on the outside of the locating piece;
Backfilling of earthwork on the outside of the GRC plate;
Reinforce the GRC plate.
2. the mold method of foundation beam according to claim 1, which is characterized in that the measurement GRC plate installation site line Method specifically:
The GRC plate is formulated according to engineering drawing;
Live foundation trench is excavated, is modified;The construction of foundation beam concrete cushion, base plate of foundation pit leveling are carried out on the foundation trench top;
The GRC plate installation site line is measured according to construction requirement.
3. the mold method of foundation beam according to claim 2, which is characterized in that the scene foundation trench excavating sideline is taken The hand digging earthwork excavates the earthwork by expecting that tool transports the foundation pit, and it is vertical that excavation of earthwork acts in accordance with foundation trench excavation sideline It excavates.
4. the mold method of foundation beam according to claim 2, which is characterized in that the foundation beam concrete cushion construction After and can upper people's construction when, the GRC plate installation site line is measured on the foundation beam concrete cushion, guarantees foundation trench Size is correct.
5. the mold method of foundation beam according to claim 1, which is characterized in that in the GRC plate installation site line The method of side installation locating piece specifically:
Timber wedge is installed on the inside of the GRC plate installation site line.
6. the mold method of foundation beam according to claim 3, which is characterized in that described in being installed on the outside of the locating piece GRC plate, the method for the fixed locating piece specifically:
Cutting stock is carried out to the GRC plate, and carries out number label;
The GRC plate of well cutting is placed in the foundation pit and concentrates stacking;
The GRC plate of well cutting is marked according to the number, is successively installed in the foundation pit along the locating piece;
The locating piece is seated in foundation beam substratum, and is fully inserted into the foundation beam concrete cushion.
The straight angle or external corner are fixed on the outside of foundation beam using flitch nail, and upper, middle and lower are each together on the outside of foundation beam, inner corner trim It is fixed with wire nail, the top of GRC is installed on fixing piece by connector, and the fixing piece is installed on the outside of the back fill course Native soil layer in.
7. the mold method of foundation beam according to claim 6, which is characterized in that the connector is iron wire, described solid Determining part is timber wedge.
8. the mold method of foundation beam according to claim 1, which is characterized in that after the completion of the installation and fixation of GRC plate, The sectional dimension of review axis and the foundation beam is coped with the GRC plate and is adjusted, it is ensured that axis, basis when there is deviation Beam size is correct.
CN201811416591.5A 2018-11-26 2018-11-26 A kind of mold method of foundation beam Pending CN109457966A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811416591.5A CN109457966A (en) 2018-11-26 2018-11-26 A kind of mold method of foundation beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811416591.5A CN109457966A (en) 2018-11-26 2018-11-26 A kind of mold method of foundation beam

Publications (1)

Publication Number Publication Date
CN109457966A true CN109457966A (en) 2019-03-12

Family

ID=65611611

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811416591.5A Pending CN109457966A (en) 2018-11-26 2018-11-26 A kind of mold method of foundation beam

Country Status (1)

Country Link
CN (1) CN109457966A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114687371A (en) * 2022-03-31 2022-07-01 成都建工第二建筑工程有限公司 Assembled prefabricated brick forming die inclined construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003193482A (en) * 2001-12-26 2003-07-09 Jgc Corp Building foundation constructing method
CN203546726U (en) * 2013-09-17 2014-04-16 中联世纪建设集团有限公司 Blank form made of glass fiber reinforced cement boards
CN104196049A (en) * 2014-09-19 2014-12-10 三箭建设工程集团有限公司 Construction method for brick forms of foundation platforms and grade beams
CN104746873A (en) * 2015-02-17 2015-07-01 中交一航局第四工程有限公司 Novel GRC cement board molding bed construction method
CN108035354A (en) * 2017-11-30 2018-05-15 中国冶集团有限公司 A kind of construction method of GRC cement plates brick mold

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003193482A (en) * 2001-12-26 2003-07-09 Jgc Corp Building foundation constructing method
CN203546726U (en) * 2013-09-17 2014-04-16 中联世纪建设集团有限公司 Blank form made of glass fiber reinforced cement boards
CN104196049A (en) * 2014-09-19 2014-12-10 三箭建设工程集团有限公司 Construction method for brick forms of foundation platforms and grade beams
CN104746873A (en) * 2015-02-17 2015-07-01 中交一航局第四工程有限公司 Novel GRC cement board molding bed construction method
CN108035354A (en) * 2017-11-30 2018-05-15 中国冶集团有限公司 A kind of construction method of GRC cement plates brick mold

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114687371A (en) * 2022-03-31 2022-07-01 成都建工第二建筑工程有限公司 Assembled prefabricated brick forming die inclined construction method

Similar Documents

Publication Publication Date Title
CN102011397B (en) Construction process of concrete form water-stopping occlusion pile
CN101672041B (en) Top-down construction method of large underground structure outer wall
CN107869249B (en) Arcuate structure high-formwork construction method
CN106894422B (en) Complex environment deep foundation pit supporting construction method
CN102430277B (en) Coarse grid sunk well for physically processing waste water and construction method thereof
CN102444143B (en) Construction method for cancelling operation channel for facades of basement
CN106682364A (en) Method and system for determining the depth of each pile driven into rock layer
CN107130611A (en) A kind of design and construction method of the recyclable circular section Row Piles Supporting Structure of flexible compound antiseepage assembled
CN106837341A (en) A kind of construction method of Metro construction shaft wall
CN103643971A (en) Method for rapid construction of tunnel inverted arch forming end mould
CN112411739A (en) Building method for municipal building
CN109457966A (en) A kind of mold method of foundation beam
CN108265969A (en) Plastic building template for ground beam and bearing platform engineering and mounting method thereof
CN110144936A (en) One kind adjoining the unilateral formwork of support pile outer wall of basement and construction method
CN204080841U (en) The fixed structure of basis GRC fetal membrane
CN104314069B (en) Side wall reserved steel bar positioning construction method in reverse construction
CN212405086U (en) Disposal and detection structure for karst cave under rock-socketed pile base
CN108253193A (en) Wall pipe built-in construction method
CN205399397U (en) A vertical support structure of variable cross section wall formula for reverse construction method
CN105064351A (en) Pile planting method
CN108625384A (en) A kind of construction method of deep strong permeable layer base pit dewatering structure
CN104695479B (en) A kind of construction method connecting China Democratic National Construction Association's basement and subway tunnel
CN211598516U (en) Novel anti-slide pile pore-forming device
CN109629590A (en) The construction method of Rock Region building pile foundation cushion cap
KR20220043498A (en) Pre-filing construction apparatus and construction method of offshore jacket foundation structure

Legal Events