A kind of friction pile suitable for side slope model test-anchor cable attachment device Download PDFInfo
- Publication number
- CN109440840A CN109440840A CN201811526615.2A CN201811526615A CN109440840A CN 109440840 A CN109440840 A CN 109440840A CN 201811526615 A CN201811526615 A CN 201811526615A CN 109440840 A CN109440840 A CN 109440840A
- Authority
- CN
- China
- Prior art keywords
- fastener
- anchor cable
- friction pile
- side slope
- model test
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D33/00—Testing foundations or foundation structures
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The invention discloses a kind of friction pile suitable for side slope model test-anchor cable attachment devices, the anchor cable of friction pile is passed through to connect friction pile and one end, comprising: the first fastener that is connected on friction pile, the second fastener for being connected to anchor cable one end, the third fastener connecting with the second fastener nest;First fastener is fixedly connected on friction pile by several first fasteners, and the anchor cable one end for being connected with the second fastener passes through friction pile;The outside of third fastener is connect with first fastener nested encryptions, inside with the second fastener nest;By adjusting the depth of third fastener insertion first fastener, to apply different prestressing force to anchor cable.The connection depth of anchor cable and friction pile is adjusted in the present invention, and accurately adjusts the prestressing force size on anchor cable, greatly enhances connection effect, improve the prestressed validity of application, the test period is shortened, test difficulty is reduced, improves the precision of model test.
Description
Technical field
The present invention relates to geological disaster modeling techniques field more particularly to a kind of resisting suitable for side slope model test
Sliding pile-anchor cable attachment device.
Background technique
Since landslide class geological disaster takes place frequently, and its range being related to is wide, brings to SURVEYING OF LANDSLIDE work very big
Inconvenience, therefore, side slope model test are applied to more and more in slope analysis field.Using side slope model test apparatus
When simulating entity side slope, it is also desirable to simulate entity ruggedized construction present in side slope.Currently, pre-stress anti-slide pile (is commonly called as
Anchorage pile) the characteristics of rock mass self-strength and bearing capacity can make full use of due to its own, more and more it is used as reinforcing
One of measure of side slope.
When simulating pre-stress anti-slide pile in side slope model test, due to the limitation of technological means, usually all use
The mode of antiskid pile material and anchorage cable materials directly is fixedly connected with to simulate the connection status of friction pile and anchor cable, to be formed anti-
Sliding pile-anchor cable system reaches the effect of reinforcing side slope, but this method can not determine and have lost pre- answer due to various reasons
True prestress value after power, to need further Adjustment Tests device;Also as using antiskid piling is directly fixedly connected with
The mode of material and anchorage cable materials, leads to not dynamically adjust the prestressing force size for applying anchor cable, will cause model test in this way
Result be not inconsistent with truth, influence the precision of test result;It is also unable to satisfy the purpose that the diversity of test is inquired into simultaneously.
In order to change this test situation, need to make the friction pile and anchor cable that effectively can accurately adjust prestressing force size
Attachment device, with the requirement of prestressing force sizes different in adaptive model, this necessarily extends the test period, and it is difficult to increase test
Degree, improves testing expenses.
Summary of the invention
In view of this, the embodiment provides a kind of friction pile suitable for side slope model test-anchor cable connections
The features such as device has structure simple, and strong using duration, prestress application works well, and simplified model is tested, can be accurate
Apply the prestressing force of specific value to anchor cable, operating procedure is easy.
To achieve the above object, present invention employs a kind of technical solutions: a kind of antiskid suitable for side slope model test
Stake-anchor cable attachment device passes through the anchor cable of the friction pile to connect friction pile and one end, comprising: be connected to the antiskid
First fastener in stake, is connect the second fastener for being connected to described anchor cable one end with second fastener nest
Third fastener;
The first fastener is fixedly connected on friction pile by several first fasteners, is connected with described second
Anchor cable one end of fastener passes through friction pile;
Outside and first fastener nested encryptions, the inside and second fastener nest of the third fastener connect
It connects;
It is different pre- to apply to the anchor cable by adjusting the depth of third fastener insertion first fastener
Stress.
Further, first fastener, the second fastener are screw.
Further, the third fastener is two-way bolt, outside and first fastener nested encryptions, interior
Side is connect with second fastener nest.
Further, the first fastener be equipped with first through hole, the third fastener by first through hole with
First fastener nested encryptions.
Further, the friction pile is equipped with the first hole, so that the anchor cable is connected with one end of the second fastener
It passes through, after second fastener passes through the first hole, and is connect in the first through hole with third fastener nest.
Further, the first fastener is additionally provided with several the second through-holes, for several the first fasteners pair
It should pass through.
Further, several second holes, the position of second hole and the second through-hole are additionally provided on the friction pile
Set it is corresponding, for pass through second through-hole the first fastener pass through.
Further, the first fastener for sequentially passing through second through-hole and the second hole, passes through second fastener
It is fixed.
Further, the first fastener and second fastener are nut.
Further, it is provided with scale on the outside of the third fastener, the anchor cable is applied by scale reflection
Prestressing force size.
The technical solution that the embodiment of the present invention provides has the benefit that (1) can be imitated according to different reinforcings
Fruit dynamically adjusts the prestressing force size being applied on anchor cable, can more preferable simulation friction pile and anchor cable true connection status, more
Actual conditions are accurately restored, the analysis result of model test is enriched;(2) the connection depth between adjustable attachment device
Accurately adjust the prestressing force size being applied on anchor cable;(3) it can satisfy the slope reinforcement requirement in the case of different tests, make to fill
The availability set is stronger;(4) structure is simple, and manufacturing cost is lower, and sustainable usability is stronger, is improved with more economical means
The lasting usability of attachment device;(5) it can be widely used in side slope model test, remarkable in economical benefits has a extensive future.
Detailed description of the invention
Fig. 1 is friction pile of the invention-anchor cable attachment device overall structure figure;
Fig. 2 is friction pile of the invention-anchor cable attachment device left view;
Fig. 3 is friction pile of the invention-anchor cable attachment device sectional view;
Fig. 4 is friction pile of the invention-anchor cable attachment device partial enlarged view.
In figure: 1- third fastener, the first fastener of 2-, 3- first fastener, 4- friction pile, 5- anchor cable, 6- anchor pole,
7- first through hole, the second fastener of 8-, the second through-hole of 9-, the first hole of 10-, the second hole of 11-, 12- second fastener.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, below in conjunction with attached drawing to embodiment party of the present invention
Formula is further described.
As shown in Figs 1-4, the embodiment provides a kind of friction pile suitable for side slope model test-anchor cables to connect
Connection device (hereinafter referred to as " attachment device "), to connect friction pile 4 and anchor cable 5, wherein one end of the anchor cable 5 passes through anti-
Sliding pile 4, the attachment device include: the first fastener 3 being connected on the friction pile 4, are connected to described 5 one end of anchor cable
The second fastener 8, the third fastener 1 that is connect with second fastener 8.For example, the friction pile 4 is highly dense using column
Polyethylene is spent, the anchor cable 5 uses steel strand wires.The other end of the anchor cable 5 is connected with anchor pole 6, to the anchor cable 5 is fixed
To basement rock.
The first fastener 3 is fixedly connected on friction pile 4 by several first fasteners 2, and described first is tight
It is fixedly mounted with and sets 3 equipped with 7 (not shown) of first through hole, the third fastener 1 passes through first through hole 7 and first fastener
3 nested encryptions.The first fastener 3 is additionally provided with several 9 (not shown)s of the second through-hole, for first fastening
Part 2 passes through.The friction pile 4 is equipped with the first hole 10, so that one end that the anchor cable 5 is connected with the second fastener 8 passes through,
It is described after second fastener 8 passes through the first hole 10, and with 1 nested encryptions of third fastener in the first through hole 7
Second fastener 8 is connected to the inside of third fastener 1.Several second holes 11 are additionally provided on the friction pile 4 (in figure not
Show), so that first fastener 2 passes through.Second hole 11 is corresponding with the position of the second through-hole 9, sequentially passes through
First fastener 2 of second through-hole 9 and the second hole 11, can be fixed by second fastener 12.
It is provided with scale (with reference to Fig. 4) on the outside of the third fastener 1, can be reflected by scale to the anchor cable
The 5 prestressing force sizes applied.The degree of first fastener 3 institute in other words can be screwed out by establishing the third fastener 1
The relationship that third fastener 1 is embedded in depth (namely corresponding scale value) and prestressing force size of first fastener 3 is stated, is based on
The third fastener 1 screws out the scale value of first fastener 3, knows the prestressing force size applied to the anchor cable 5.Pass through
The scale value that the third fastener 1 screws out first fastener 3 is adjusted, to apply different prestressing force to the anchor cable 5.
Preferably, first fastener 2, the second fastener 8 are screw, and the third fastener 1 is two-way bolt,
Its outside and 3 nested encryptions of first fastener, inside and 8 nested encryptions of the second fastener.Preferably, described
One clamp device 3 and second fastener 12 are nut.
As shown in Fig. 2, four the first fasteners 2 are located at the first fastening dress by taking four the first fasteners 2 as an example
It sets on 3 four angles, the quantity of second hole 11 and the second through-hole 9 is four.
The working principle of attachment device of the present invention is as follows: firstly, being fastened using several first fasteners 2 by first
Device 3 is fixed on friction pile 4;The second fastener 8 being fixedly connected with the anchor cable 5 is passed through to first in friction pile 4 again
Hole 10 rotates nested encryptions with the inside of the third fastener 1, while the outside of the third fastener 1 and first is tightly
It is fixedly mounted with and sets 3 rotation nested encryptions, and guarantee that the fixation of anchor pole 6 is intact;After being fixed to the attachment device, described in holding
Third fastener 1 and the connection building-in depth of the second fastener 8 are constant, and the third fastener 1 is slowly screwed out the first fastening
Device 3 (for example, counterclockwise), that is, reduce connection building-in depth between the two, reach and apply prestressed mesh to the anchor cable 5
's.For example, can be obtained by test corresponding described when the third fastener 1 produces fixed 3 one lattice of first fastener
The scale of prestressing force size is arranged, thus in mould in the prestressing force size that anchor cable 5 applies on the outside of the third fastener 1
The prestressed specific value applied to the anchor cable 5 is accurately obtained in type test.
The technical solution that the embodiment of the present invention provides has the benefit that (1) can be imitated according to different reinforcings
Fruit dynamically adjusts the prestressing force size being applied on anchor cable, can more preferable simulation friction pile and anchor cable true connection status, more
Actual conditions are accurately restored, the analysis result of model test is enriched;(2) the connection depth between adjustable attachment device
Accurately adjust the prestressing force size being applied on anchor cable;(3) it can satisfy the slope reinforcement requirement in the case of different tests, make to fill
The availability set is stronger;(4) structure is simple, and manufacturing cost is lower, and sustainable usability is stronger, is improved with more economical means
The lasting usability of attachment device;(5) it can be widely used in side slope model test, remarkable in economical benefits has a extensive future.
It is worth noting that: in the description of the present invention, " several " are meant that one or more, unless otherwise
Clear specific restriction.In the present invention unless specifically defined or limited otherwise, term " installation ", " connected ", " connection ",
Terms such as " fixations " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected,
It can be mechanical connection, for the ordinary skill in the art, can understand above-mentioned term at this as the case may be
Concrete meaning in invention.
Herein, the nouns of locality such as related front, rear, top, and bottom are to be located in figure with components in attached drawing and zero
Part mutual position defines, only for the purpose of expressing the technical solution clearly and conveniently.It should be appreciated that the noun of locality
Use should not limit the claimed range of the application.
In the absence of conflict, the feature in embodiment and embodiment herein-above set forth can be combined with each other.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, it is all in spirit of the invention and
Within principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.
Claims (10)
1. a kind of friction pile suitable for side slope model test-anchor cable attachment device passes through institute to connect friction pile and one end
State the anchor cable of friction pile, it is characterised in that: include: the first fastener being connected on the friction pile, be connected to the anchor
The second fastener of Suo Yiduan, the third fastener being connect with second fastener nest;
The first fastener is fixedly connected on friction pile by several first fasteners, is connected with second fastening
Anchor cable one end of part passes through friction pile;
The outside of the third fastener is connect with first fastener nested encryptions, inside with second fastener nest;
By adjusting the depth of third fastener insertion first fastener, to apply different pre- answer to the anchor cable
Power.
2. the friction pile suitable for side slope model test-anchor cable attachment device according to claim 1, it is characterised in that:
First fastener, the second fastener are screw.
3. the friction pile suitable for side slope model test-anchor cable attachment device according to claim 1, it is characterised in that:
The third fastener is two-way bolt, outside and the first fastener nested encryptions, inside and second fastening
Part nested encryptions.
4. the friction pile suitable for side slope model test-anchor cable attachment device according to claim 1, it is characterised in that:
The first fastener is equipped with first through hole, and the third fastener connects by the way that first through hole is nested with first fastener
It connects.
5. the friction pile suitable for side slope model test-anchor cable attachment device according to claim 4, it is characterised in that:
The friction pile is equipped with the first hole, so that one end that the anchor cable is connected with the second fastener passes through, second fastening
After part passes through the first hole, and it is connect in the first through hole with third fastener nest.
6. the friction pile suitable for side slope model test-anchor cable attachment device according to claim 1, it is characterised in that:
The first fastener is additionally provided with several the second through-holes, for several first fasteners it is corresponding across.
7. the friction pile suitable for side slope model test-anchor cable attachment device according to claim 6, it is characterised in that:
Several the second holes are additionally provided on the friction pile, second hole is corresponding with the position of the second through-hole, for passing through
First fastener of second through-hole passes through.
8. the friction pile suitable for side slope model test-anchor cable attachment device according to claim 7, it is characterised in that:
The first fastener for sequentially passing through second through-hole and the second hole, is fixed by second fastener.
9. the friction pile suitable for side slope model test-anchor cable attachment device according to claim 8, it is characterised in that:
The first fastener and second fastener are nut.
10. the friction pile suitable for side slope model test-anchor cable attachment device according to claim 1, it is characterised in that:
It is provided with scale on the outside of the third fastener, the prestressing force size applied to the anchor cable is reflected by scale.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811526615.2A CN109440840A (en) | 2018-12-13 | 2018-12-13 | A kind of friction pile suitable for side slope model test-anchor cable attachment device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811526615.2A CN109440840A (en) | 2018-12-13 | 2018-12-13 | A kind of friction pile suitable for side slope model test-anchor cable attachment device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109440840A true CN109440840A (en) | 2019-03-08 |
Family
ID=65558096
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811526615.2A Pending CN109440840A (en) | 2018-12-13 | 2018-12-13 | A kind of friction pile suitable for side slope model test-anchor cable attachment device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109440840A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112461466A (en) * | 2020-10-27 | 2021-03-09 | 同济大学 | Dynamic simulation test system for pile-anchor supporting side slope under earthquake action |
CN112761171A (en) * | 2021-01-05 | 2021-05-07 | 安徽理工大学 | Anti-slide pile inserter |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2773222Y (en) * | 2005-03-28 | 2006-04-19 | 李炳奇 | Structural member for fixing heads of anchor or cable |
CN2830644Y (en) * | 2004-06-03 | 2006-10-25 | 中国科学院武汉岩土力学研究所 | Controllable prestressed super-strength anchor arm |
CN101343882A (en) * | 2008-08-18 | 2009-01-14 | 山东大学 | Miniature pre-stress anchor wire used for model experiment and its burying and loading method |
CN102108703A (en) * | 2010-12-20 | 2011-06-29 | 中铁隧道集团有限公司 | Adjustable prestressed anchoring device |
KR20130028489A (en) * | 2011-09-09 | 2013-03-19 | 주식회사고려이엔시 | Tension control bracket |
KR20160039841A (en) * | 2014-10-02 | 2016-04-12 | 엘케이테크 주식회사 | A Rebar anchoring device for hooped reinforcement |
CN107447756A (en) * | 2017-09-25 | 2017-12-08 | 西南石油大学 | A kind of constructing device for compensating prestressd anchor cable loss and compensation construction method |
KR101852082B1 (en) * | 2017-11-02 | 2018-04-27 | (주) 피티솔루션 | Re-tensioning anchorage device |
CN108532615A (en) * | 2018-04-23 | 2018-09-14 | 武汉工程大学 | Cable adjustable power anchor draws friction pile and its construction method |
CN208183771U (en) * | 2018-05-08 | 2018-12-04 | 四川大学 | A kind of side slope shaking table model stream line prestress application device |
CN209412882U (en) * | 2018-12-13 | 2019-09-20 | 中国地质大学(武汉) | A kind of friction pile suitable for side slope model test-anchor cable attachment device |
-
2018
- 2018-12-13 CN CN201811526615.2A patent/CN109440840A/en active Pending
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2830644Y (en) * | 2004-06-03 | 2006-10-25 | 中国科学院武汉岩土力学研究所 | Controllable prestressed super-strength anchor arm |
CN2773222Y (en) * | 2005-03-28 | 2006-04-19 | 李炳奇 | Structural member for fixing heads of anchor or cable |
CN101343882A (en) * | 2008-08-18 | 2009-01-14 | 山东大学 | Miniature pre-stress anchor wire used for model experiment and its burying and loading method |
CN102108703A (en) * | 2010-12-20 | 2011-06-29 | 中铁隧道集团有限公司 | Adjustable prestressed anchoring device |
KR20130028489A (en) * | 2011-09-09 | 2013-03-19 | 주식회사고려이엔시 | Tension control bracket |
KR20160039841A (en) * | 2014-10-02 | 2016-04-12 | 엘케이테크 주식회사 | A Rebar anchoring device for hooped reinforcement |
CN107447756A (en) * | 2017-09-25 | 2017-12-08 | 西南石油大学 | A kind of constructing device for compensating prestressd anchor cable loss and compensation construction method |
KR101852082B1 (en) * | 2017-11-02 | 2018-04-27 | (주) 피티솔루션 | Re-tensioning anchorage device |
CN108532615A (en) * | 2018-04-23 | 2018-09-14 | 武汉工程大学 | Cable adjustable power anchor draws friction pile and its construction method |
CN208183771U (en) * | 2018-05-08 | 2018-12-04 | 四川大学 | A kind of side slope shaking table model stream line prestress application device |
CN209412882U (en) * | 2018-12-13 | 2019-09-20 | 中国地质大学(武汉) | A kind of friction pile suitable for side slope model test-anchor cable attachment device |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112461466A (en) * | 2020-10-27 | 2021-03-09 | 同济大学 | Dynamic simulation test system for pile-anchor supporting side slope under earthquake action |
CN112461466B (en) * | 2020-10-27 | 2021-11-16 | 同济大学 | Dynamic simulation test system for pile-anchor supporting side slope under earthquake action |
CN112761171A (en) * | 2021-01-05 | 2021-05-07 | 安徽理工大学 | Anti-slide pile inserter |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Cubrinovski et al. | Modelling of sand behaviour based on state concept | |
Lin et al. | Experimental structural behavior of wall-diaphragm connections for older masonry buildings | |
Costa et al. | Free rocking response of a regular stone masonry wall with equivalent block approach: experimental and analytical evaluation | |
Rijal et al. | Experimental and analytical study on dynamic performance of timber-concrete composite beams | |
CN109440840A (en) | A kind of friction pile suitable for side slope model test-anchor cable attachment device | |
Tsinidis et al. | Experimental and numerical investigation of the seismic behavior of rectangular tunnels in soft soils | |
Gams et al. | Full-scale shaking table test of a reinforced concrete precast building with horizontal concrete cladding panels and a numerical simulation | |
CN209412882U (en) | A kind of friction pile suitable for side slope model test-anchor cable attachment device | |
Talesnick et al. | Development of a soil boundary friction meter: application to scale model testing | |
Sebastian et al. | Resonant column tests and nonlinear elasticity in simulated rocks | |
Singh et al. | Analysis of the combined load behaviour of rock bolt installed across discontinuity and its modelling using FLAC3D | |
Ellis | Full-scale measurements of the dynamic characteristics of buildings in the UK | |
Kim | Incrementally nonlinear responses of soft Chicago glacial clays | |
DE102006053965A1 (en) | Building damage recognizing method for e.g. dam, involves analyzing monitored stress conditions on changes in time interval, and comparing monitored stress conditions with stored actual condition values | |
Pavic et al. | Experimental assessment of vibration serviceability of existing office floors under human-induced excitation | |
Bayhan | Numerical simulation of shaking table tests on 3D reinforced concrete structures | |
Keightley | Vibration tests of structures | |
Carrillo et al. | Deformation analysis of concrete walls under shaking table excitations | |
Wood | Experiments to study the earthquake response of reinforced concrete frames with setbacks | |
Wang | Research on fundamental frequencies and dynamic characteristics of pre-stressed concrete beams based on experiment and numerical simulation | |
Farrar et al. | Damping in low‐aspect‐ratio, reinforced concrete shear walls | |
Galé-Lamuela et al. | Energy dissipation capacity of RC columns subjected to unidirectional and bidirectional seismic loading | |
KR102093099B1 (en) | Evaluating equipment and method of prestressing force tendon | |
Dolšek et al. | Post-test analyses of the SPEAR test building | |
Carrillo et al. | Stiffness decay and damping ratios of steel fiber reinforced concrete walls |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |