CN109424179A - The fulcrum bearing of metal roofing board construction - Google Patents

The fulcrum bearing of metal roofing board construction Download PDF

Info

Publication number
CN109424179A
CN109424179A CN201710744410.0A CN201710744410A CN109424179A CN 109424179 A CN109424179 A CN 109424179A CN 201710744410 A CN201710744410 A CN 201710744410A CN 109424179 A CN109424179 A CN 109424179A
Authority
CN
China
Prior art keywords
mounting blocks
screw rod
locking nut
positioning screw
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201710744410.0A
Other languages
Chinese (zh)
Inventor
曾成富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710744410.0A priority Critical patent/CN109424179A/en
Publication of CN109424179A publication Critical patent/CN109424179A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/20Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • E04G5/046Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on walls

Abstract

The invention discloses the fulcrum bearings of metal roofing board construction, including bearing plate, mounting blocks and fixed mechanism, wherein mounting blocks are longitudinally vertically arranged and wall right side is close in its left side, and bearing plate is transversely and horizontally set and its left end is connected to mounting blocks right side.Fixed mechanism includes positioning screw rod, internal locking nut and outer locking nut, the head of positioning screw rod and internal locking nut are set in wall, the other end of the opposite connection head end of the screw rod of positioning screw rod sequentially passes through internal locking nut and mounting blocks and is set to outside wall, outer locking nut is set on the screw rod that positioning screw rod is located at outside wall, and its left end and mounting blocks right end face contact.Overall structure of the present invention is simply secured, is easy to implement, and it is convenient that when installation operates, time saving and energy saving, convenient for setting up the halfpace that construction is trampled for construction personnel.

Description

The fulcrum bearing of metal roofing board construction
Technical field
The present invention relates to technical field of building construction, the specifically fulcrum bearing of metal roofing board construction.
Background technique
In the work progress of metal roofing board, construction location, work progress are reached convenient for construction personnel when in order to construct In all need mating halfpace, now in metal roofing board work progress, in order to guarantee the structural strength of halfpace, it is numerous that halfpace sets up process It is trivial and time-consuming and laborious.
Summary of the invention
It is an object of the invention to overcome the deficiencies of the prior art and provide the fulcrum bearing of metal roofing board construction, knots Structure is firm, and operate during installation it is convenient, it is time saving and energy saving, convenient for setting up construction halfpace.
The present invention, which solves the above problems, to be achieved through the following technical solutions: the fulcrum bearing of metal roofing board construction, packet Bearing plate, mounting blocks and fixed mechanism are included, the mounting blocks are longitudinally vertically arranged and wall right side is close in its left side, described Bearing plate is transversely and horizontally set and its left end is connected to mounting blocks right side;The fixed mechanism includes positioning screw rod, internal locking Nut and outer locking nut, the head of the positioning screw rod and internal locking nut are set in wall, the screw rod phase of positioning screw rod Internal locking nut and mounting blocks are sequentially passed through to the other end of connection head end and are set to outside wall, the outer locking nut is arranged It is located on the screw rod outside wall in positioning screw rod, and its left end and mounting blocks right end face contact.The present invention is in application, in cast-in-place wall Positioning screw rod and internal locking nut are preset in wall when wall.
Further, the internal locking nut right end is concordant with wall right side.
Firm position when in order to apply the present invention, further, the mounting blocks are rectangular slab, the quantity of fixed mechanism Be four groups, the positioning screw rods of four groups of fixed mechanisms pass through the positions of mounting blocks respectively close to four right angle corners of mounting blocks at.
In conclusion being easy to implement, cost the invention has the following advantages: overall structure of the present invention is simply secured Low, in application, the head of positioning screw rod and internal locking nut are set in wall, the screw rod of positioning screw rod is opposite to be connected the present invention The other end of head end sequentially passes through internal locking nut and mounting blocks and is set to outside wall, effect of the present invention in outer locking nut Under so that mounting blocks is tightly attached to wall, and then bearing plate is fixed, it is easy to install and disassemble, it is time saving and energy saving;When the present invention applies Required quantity of the invention be it is multiple, formed on wall it is ladder-like set up, and then formed halfpace, so that construction personnel tramples Specific construction location.
Detailed description of the invention
Attached drawing described herein is used to provide to further understand the embodiment of the present invention, constitutes one of the application Point, do not constitute the restriction to the embodiment of the present invention.In the accompanying drawings:
Fig. 1 is schematic structural view of the invention.
Label and corresponding parts title in attached drawing: 1, wall, 2, bearing plate, 3, mounting blocks, 4, positioning screw rod, 5, interior Locking nut, 6, outer locking nut.
Specific embodiment
To make the objectives, technical solutions, and advantages of the present invention clearer, below with reference to embodiment and attached drawing, to this Invention is described in further detail, and exemplary embodiment of the invention and its explanation for explaining only the invention, are not made For limitation of the invention.
Embodiment 1:
As shown in Figure 1, the fulcrum bearing of metal roofing board construction, including bearing plate 2, mounting blocks 3 and fixed mechanism, wherein 3 longitudinal direction of mounting blocks is vertically arranged and 1 right side of wall is close in its left side, and bearing plate 2 is transversely and horizontally set and its left end connects In 3 right side of mounting blocks.The embodiment of the present invention fixed mechanism includes positioning screw rod 4, internal locking nut 5 and outer locking nut 6, The head of positioning screw rod 4 and internal locking nut 5 are set in wall 1, and the screw rod of positioning screw rod 4 is opposite to connect the another of head end End sequentially passes through internal locking nut 5 and mounting blocks 3 and is set to outside wall 1.Outer locking nut 6 is set in positioning screw rod 4 and is located at wall On screw rod outside wall 1, and its left end and 3 right end face contact of mounting blocks.
Embodiment 2:
The present embodiment is made that restriction further below on the basis of embodiment 1: internal locking nut 5 is right in the present embodiment It holds concordant with 1 right side of wall.
Embodiment 3:
The present embodiment is made that restriction further below: the installation of the present embodiment on the basis of embodiment 1 or embodiment 2 Block 3 is rectangular slab, and the quantity of fixed mechanism is four groups, and the position that the positioning screw rod 4 of four groups of fixed mechanisms passes through mounting blocks 3 is distinguished At four right angle corners of mounting blocks 3.
Above-described specific embodiment has carried out further the purpose of the present invention, technical scheme and beneficial effects It is described in detail, it should be understood that being not intended to limit the present invention the foregoing is merely a specific embodiment of the invention Protection scope, all within the spirits and principles of the present invention, any modification, equivalent substitution, improvement and etc. done should all include Within protection scope of the present invention.

Claims (3)

1. the fulcrum bearing of metal roofing board construction, which is characterized in that including bearing plate (2), mounting blocks (3) and fixed mechanism, institute State that mounting blocks (3) are longitudinally vertically arranged and wall (1) right side is close in its left side, the bearing plate (2) is transversely and horizontally set And its left end is connected to mounting blocks (3) right side;The fixed mechanism includes positioning screw rod (4), internal locking nut (5) and external lock Tight nut (6), the head of the positioning screw rod (4) and internal locking nut (5) are set in wall (1), the spiral shell of positioning screw rod (4) The other end of the opposite connection head end of bar sequentially passes through internal locking nut (5) and mounting blocks (3) and is set to wall (1) outside, described Outer locking nut (6) is set in positioning screw rod (4) and is located on the screw rod of wall (1) outside, and its left end and mounting blocks (3) right side Contact.
2. the fulcrum bearing of metal roofing board construction according to claim 1, which is characterized in that the internal locking nut (5) Right end is concordant with wall (1) right side.
3. the fulcrum bearing of metal roofing board according to claim 1 or 2 construction, which is characterized in that the mounting blocks (3) are Rectangular slab, the quantity of fixed mechanism are four groups, and the position that the positioning screw rod (4) of four groups of fixed mechanisms passes through mounting blocks (3) is distinguished At four right angle corners of mounting blocks (3).
CN201710744410.0A 2017-08-25 2017-08-25 The fulcrum bearing of metal roofing board construction Withdrawn CN109424179A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710744410.0A CN109424179A (en) 2017-08-25 2017-08-25 The fulcrum bearing of metal roofing board construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710744410.0A CN109424179A (en) 2017-08-25 2017-08-25 The fulcrum bearing of metal roofing board construction

Publications (1)

Publication Number Publication Date
CN109424179A true CN109424179A (en) 2019-03-05

Family

ID=65500668

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710744410.0A Withdrawn CN109424179A (en) 2017-08-25 2017-08-25 The fulcrum bearing of metal roofing board construction

Country Status (1)

Country Link
CN (1) CN109424179A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117108006B (en) * 2023-10-18 2024-01-12 哈尔滨龙庆钢构彩板有限公司 Bearing plate structure in metal roof boarding construction engineering

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117108006B (en) * 2023-10-18 2024-01-12 哈尔滨龙庆钢构彩板有限公司 Bearing plate structure in metal roof boarding construction engineering

Similar Documents

Publication Publication Date Title
CN109424179A (en) The fulcrum bearing of metal roofing board construction
CN204152202U (en) Column template clamp frame
CN207616526U (en) A kind of platform and fixture of multipurpose building material
CN206956989U (en) A kind of building curtain wall of installation easy to disassemble
CN204326533U (en) A kind of formwork reinforcement fixture
CN204456836U (en) Collapsible formwork structure
CN207974424U (en) A kind of mounting device of strip panel
CN103590498A (en) Thin-wall steel structure house corner connecting structure and connection method
CN203334678U (en) Outer wall formwork strengthening system for concrete pouring
CN208473297U (en) A kind of cast-in-place concrete square cross section column type mould sizing bracing means
CN109424209A (en) Load-bearing plate structure in metal roofing board construction work
CN202627275U (en) Keel structure for dry-hanging stone curtain walls
CN203640275U (en) Limiting mold clamp for building beam column pouring construction
CN204738531U (en) Turnover formula finished product is assembled steel and is hung mould
CN201202278Y (en) Building shuttering fastening means
CN202990404U (en) Tubular fast fixture
CN204059970U (en) Cement for walls stay and walling equipment
CN204126260U (en) Masonry structure external corner part joint pin support mould tool
CN205051270U (en) Cable support with adjustable it is rotatory
CN210597675U (en) Heat preservation rock wool board convenient to wall body installation
CN211548796U (en) Stagnant water bolt assembly
CN203808494U (en) Cross bridging connecting piece for construction
CN209704373U (en) A kind of U-shaped glass fixing device for plug-in window
CN210857741U (en) Novel building structure reinforcing device
CN207348482U (en) The torsion structure of supporting rod

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20190305

WW01 Invention patent application withdrawn after publication