CN109424083A - A kind of wall element and its wall for supporting monitoring and warning function - Google Patents

A kind of wall element and its wall for supporting monitoring and warning function Download PDF

Info

Publication number
CN109424083A
CN109424083A CN201710721014.6A CN201710721014A CN109424083A CN 109424083 A CN109424083 A CN 109424083A CN 201710721014 A CN201710721014 A CN 201710721014A CN 109424083 A CN109424083 A CN 109424083A
Authority
CN
China
Prior art keywords
piezallochromy
subregion
wall
plasterboard
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710721014.6A
Other languages
Chinese (zh)
Inventor
何亮
王鹏起
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing New Building Material Group Co Ltd
Original Assignee
Beijing New Building Material Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing New Building Material Group Co Ltd filed Critical Beijing New Building Material Group Co Ltd
Priority to CN201710721014.6A priority Critical patent/CN109424083A/en
Publication of CN109424083A publication Critical patent/CN109424083A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01LMEASURING FORCE, STRESS, TORQUE, WORK, MECHANICAL POWER, MECHANICAL EFFICIENCY, OR FLUID PRESSURE
    • G01L1/00Measuring force or stress, in general
    • G01L1/24Measuring force or stress, in general by measuring variations of optical properties of material when it is stressed, e.g. by photoelastic stress analysis using infrared, visible light, ultraviolet
    • G01V1/01

Abstract

A kind of wall element and its wall for supporting monitoring and warning function is disclosed herein, wall element includes the plasterboard set on wall two sides, the keel unit inside wall and for connecting plasterboard, it further include piezallochromy unit, the front of the plasterboard is arranged in the piezallochromy unit;Wall includes multiple wall elements for supporting monitoring and warning function;Piezallochromy unit is provided on plasterboard between the wall element;Present invention can apply to wall technology fields, defect existing in the prior art can be effectively overcome using the application, it can timely reflect the structural stability of wall, while also can be realized the warning function before earthquake by the piezallochromy unit being arranged on wall.

Description

A kind of wall element and its wall for supporting monitoring and warning function
Technical field
This application involves but be not limited to wall technology field, especially a kind of wall element for supporting monitoring and warning function and Its wall.
Background technique
In the prior art, interior wall production usually carries out site operation using light metal keel and plasterboard, wall body structure The research at home such as shearing force, antidetonation situation is less, generally in terms of seismic behavior, the structure stress for calculating building Comprehensively consider.However, in the construction process, all not accounting for this problem very much.
When gravity occurs for earthquake generation or wall or adjacent wall element misplaces, wall body structure will necessarily go out The effects of existing pressure or frictional force.Such as, when earthquake occurs, avoiding the measure of casualties is by earthquake pre-warning or the Nature Variation, in addition seismic centre farther out or the building of the repercussions zone of action can experience apparent shaking, especially have compared with The building of height.By geological process, perhaps the intracorporal keel of wall have occurred that deformation or wall element dislocation, then Wall or building life certainly will be will affect, or even hidden some dangers for safely to inhabitation or working environment.
Therefore, how a kind of wall element of changeable colour is provided, knows that the structure of wall is played when earthquake occurs in time Warning function helps people to escape in advance;Meanwhile the knot after also fully understanding wall body structure by gravity, shearing force the effects of Structure stability is current problem to be solved.
Summary of the invention
The technical issues of the application solves is to provide a kind of wall element and its wall for supporting monitoring and warning function, can Effectively overcome defect existing in the prior art, can timely be reflected by the piezallochromy unit being arranged on wall The structural stability of wall, while also can be realized the warning function before earthquake.
In order to solve the above technical problems, this application provides a kind of wall elements for supporting monitoring and warning function, including set Plasterboard in wall two sides, the keel unit inside wall and for connecting plasterboard,
It further include piezallochromy unit, the front of the plasterboard is arranged in the piezallochromy unit.
The wall element of above-mentioned support monitoring and warning function, can also have following features,
The back side of the plasterboard include with keel unit not in contact with the first rear surface regions, contacted with keel unit Two rear surface regions.
The wall element of above-mentioned support monitoring and warning function, can also have following features,
The piezallochromy unit includes the first piezallochromy component, and the first piezallochromy component is arranged in the stone Cream plate corresponds in the first front surface region of the first rear surface regions;
The first piezallochromy component includes the piezoluminescence off-color material being uniformly arranged in the first front surface region.
The wall element of above-mentioned support monitoring and warning function, can also have following features,
The piezallochromy unit includes the second piezallochromy component, and the second piezallochromy component is arranged in the stone Cream plate corresponds in the second front surface region of the second rear surface regions;
The second piezallochromy component includes the piezoluminescence off-color material being uniformly arranged in the second front surface region.
The wall element of above-mentioned support monitoring and warning function, can also have following features,
The keel unit include positioned at top day keel, positioned at bottom ground joist and for connect day keel and The centre keel of ground joist.
The wall element of above-mentioned support monitoring and warning function, can also have following features,
Second rear surface regions include the first subregion of the back side contacted with day keel, the back side contacted with ground joist Two subregions and the back side third subregion contacted with centre keel;
Second front surface region includes corresponding to first subregion of front of the first subregion of the back side, corresponding to the back side the The second subregion of front of two subregions and positive third subregion corresponding to back side third subregion.
The wall element of above-mentioned support monitoring and warning function, can also have following features,
The second piezallochromy component include the piezoluminescence off-color material being uniformly arranged in positive first subregion, It the piezoluminescence off-color material that is uniformly arranged in positive second subregion and is uniformly arranged in positive third subregion Piezoluminescence off-color material.
The wall element of above-mentioned support monitoring and warning function, can also have following features,
One or more first groove bodies, the piezoluminescence discoloration material are offered in first front surface region of the plasterboard Material is uniformly filled in the first groove body.
The wall element of above-mentioned support monitoring and warning function, can also have following features,
One or more is offered in positive first subregion, positive second subregion and positive third subregion A second groove body, the piezoluminescence off-color material are uniformly filled in the second groove body.
The wall element of above-mentioned support monitoring and warning function, can also have following features,
The piezoluminescence off-color material is fixed on gypsum by bonded adhesives.
In order to solve the above technical problems, this application provides a kind of wall, including support monitoring and warning function above-mentioned Wall element;Piezallochromy unit is provided on plasterboard between the wall element.
The application above-mentioned technical proposal has the following beneficial effects:
Compared with the prior art, the application can be realized real-time monitoring stone by the setting of above-mentioned piezallochromy unit The stress condition of cream plate, and then whether the structure for being able to reflect out keel unit deforms;When larger change occurs for keel unit When shape, plasterboard connected to it will also be distorted deformation, and above-mentioned piezallochromy unit is produced because of above-mentioned plasterboard torsional deformation Under raw external force, corresponding color change is generated;Wall micro-strain especially before earthquake, can drive piezallochromy Corresponding color change is presented under the external force of deformation of wall in unit, to remind people to escape immediately.
Further, the application can also can be realized plasterboard ontology by the setting of above-mentioned first piezallochromy component Monitoring, when plasterboard ontology, which is distorted, to be deformed, the first piezallochromy component being arranged on plasterboard ontology can be produced Raw corresponding color change;Meanwhile people can also be by the surface of the first piezallochromy component of pressing, so that the first piezallochromy Component generates corresponding discoloration, to enrich real life.
Further, the application can also can be realized plasterboard and dragon by the setting of above-mentioned second piezallochromy component The monitoring of osteon connecting portion can realize the monitoring of keel unit;When keel unit, which is distorted, to be deformed, Huo Zhefa When raw dislocation, the plasterboard being arranged on keel unit also can accordingly deform, and the second piezallochromy component then can be by stone The deformation of cream plate is embodied by the variation of color, enables one to understand constantly the structure of the keel unit inside wall Stability.
Further, the application can also pass through the above-mentioned piezoluminescence discoloration material being uniformly arranged in positive first subregion Material can be realized the real-time monitoring of the structural stability of the day keel of gypsum back connection;It can be also uniformly arranged on by above-mentioned Piezoluminescence off-color material in positive second subregion can be realized the structural stability of the ground joist of gypsum back connection Real-time monitoring;Also stone can be can be realized by the above-mentioned piezoluminescence off-color material being uniformly arranged in positive third subregion The real-time monitoring of the structural stability of the centre keel of cream back connection;It can be by the way that the first sub-district of front being independently arranged be arranged The piezoluminescence off-color material in domain, positive second subregion and positive third subregion, can be realized relatively independent monitoring Function.
Further, the application can be also capable of providing by the setting of above-mentioned first groove body, the second groove body to piezoluminescence The independent setting cavity of off-color material, space requirement needed for capable of effectively meeting the installation of piezoluminescence off-color material;Can also it lead to The setting of above-mentioned bonded adhesives is crossed, the connective stability of piezoluminescence off-color material can be effectively improved, enable to piezoluminescence Off-color material is firmly fixed on gypsum board surface.
Other features and advantage will illustrate in the following description, also, partly become from specification It obtains it is clear that being understood by implementing the embodiment of the present invention.The purpose of the application and other advantages can be by illustrating Specifically noted structure is achieved and obtained in book, claims and attached drawing.
Detailed description of the invention
Attached drawing is used to provide to further understand technical scheme, and constitutes part of specification, with this The embodiment of application is used to explain the technical solution of the application together, does not constitute the limitation to technical scheme.
Fig. 1 is the gypsum board structure schematic diagram one of the embodiment of the present invention one;
Fig. 2 is the keel cellular construction schematic diagram of the embodiment of the present invention one;
Fig. 3 is the gypsum board structure schematic diagram two of the embodiment of the present invention one;
It illustrates:
1- plasterboard, the first front surface region 11-, the second front surface region 12-, the first groove body of 111-, the second groove body of 121-;
2- keel unit, 21- days keel, 22- ground joist, 23- centre keel.
Specific embodiment
Embodiments herein is described in detail below in conjunction with attached drawing.It should be noted that not conflicting In the case of, the features in the embodiments and the embodiments of the present application can mutual any combination.
Embodiment one:
In conjunction with shown in Fig. 1, Fig. 2 and Fig. 3, the embodiment of the invention provides a kind of wall lists for supporting monitoring and warning function Member, the plasterboard 1 including being set to wall two sides, the keel unit 2 inside wall and for connecting plasterboard 1;Further include The front of plasterboard 1 is arranged in piezallochromy unit, piezallochromy unit.
In concrete operations, the stress of real-time monitoring plasterboard 1 can be can be realized by the setting of above-mentioned piezallochromy unit Situation, and then whether the structure for being able to reflect out keel unit 2 deforms;When moderate finite deformation occurs for keel unit 2, with it The plasterboard 1 of connection will also be distorted deformation, the external force that above-mentioned piezallochromy unit is generated by above-mentioned 1 torsional deformation of plasterboard Under effect, corresponding color change is generated;Wall micro-strain especially before earthquake, can drive piezallochromy unit in wall Under the external force of body deformation, corresponding color change is presented, to remind people to escape immediately.
Preferably, in the present embodiment, the back side of above-mentioned plasterboard 1 can be divided into two regions, i.e., do not connect with keel unit 2 First rear surface regions of touching, and the second rear surface regions contacted with keel unit 2.
Further, above-mentioned piezallochromy unit includes the first piezallochromy component, and the setting of the first piezallochromy component exists Plasterboard 1 corresponds in the first front surface region 11 of the first rear surface regions;First piezallochromy component includes being uniformly arranged on the Piezoluminescence off-color material in one front surface region 11.
In concrete operations, the prison of 1 ontology of plasterboard can be can be realized by the setting of above-mentioned first piezallochromy component It surveys, when 1 ontology of plasterboard, which is distorted, to be deformed, the first piezallochromy component being arranged on 1 ontology of plasterboard can be generated Corresponding color change;Meanwhile people can also be by the surface of the first piezallochromy component of pressing, so that the first piezallochromy group Part generates corresponding discoloration, to enrich real life.
Further, above-mentioned piezallochromy unit includes the second piezallochromy component, and the setting of the second piezallochromy component exists Plasterboard 1 corresponds in the second front surface region 12 of the second rear surface regions;Second piezallochromy component includes being uniformly arranged on the Piezoluminescence off-color material in two front surface regions 12.
In concrete operations, plasterboard 1 and keel unit can be can be realized by the setting of above-mentioned second piezallochromy component The monitoring of 2 connecting portions can realize the monitoring of keel unit 2;When keel unit 2, which is distorted, to be deformed, or occur When dislocation, the plasterboard 1 being arranged on keel unit 2 also can accordingly deform, and the second piezallochromy component then can be by stone The deformation of cream plate 1 is embodied by the variation of color, enables one to understand constantly the knot of the keel unit 2 inside wall Structure stability.
Preferably, in the present embodiment, above-mentioned keel unit 2 includes the day keel 21 positioned at top, the pheretima positioned at bottom Bone 22 and centre keel 23 for connecting day keel 21 and ground joist 22.
In concrete operations, above-mentioned day keel 21 can be used for realizing the structure that is bonded at the top of wall, above-mentioned ground joist 22 It can be used for realizing the structure that is bonded of wall bottom, above-mentioned centre keel 23 can be used for realizing between day keel 21 and ground joist 22 Be bonded, and then can be improved the structural stability of wall entirety.
Preferably, in the present embodiment, above-mentioned second rear surface regions include the first subregion of the back side contacted with day keel 21, The second subregion of the back side contacted with ground joist 22 and the back side third subregion contacted with centre keel 23;Second front surface region 12 include the first subregion of front corresponding to the first subregion of the back side, the second sub-district of front corresponding to the second subregion of the back side Domain and positive third subregion corresponding to back side third subregion.
In concrete operations, the second piezallochromy component includes that the piezoluminescence being uniformly arranged in positive first subregion becomes Color material can be realized plasterboard 1 by the above-mentioned piezoluminescence off-color material being uniformly arranged in positive first subregion The real-time monitoring of the structural stability of the day keel 21 of back side connection;Second piezallochromy component, which may also include, to be uniformly arranged on just Piezoluminescence off-color material in the second subregion of face can cause hair by the above-mentioned pressure being uniformly arranged in positive second subregion Photochromic material can be realized the real-time monitoring of the structural stability of the ground joist 22 of 1 back side of plasterboard connection.
Further, above-mentioned second piezallochromy component may also include the pressure being uniformly arranged in positive third subregion and cause Color-changing materials can be realized stone by the above-mentioned piezoluminescence off-color material being uniformly arranged in positive third subregion The real-time monitoring of the structural stability of the centre keel 23 of 1 back side of cream plate connection;It can be by the way that the front first being independently arranged be arranged The piezoluminescence off-color material of subregion, positive second subregion and positive third subregion, can be realized relatively independent Monitoring function.
As shown in Figure 3, it is preferable that in the present embodiment, offered in the first front surface region 11 of above-mentioned plasterboard 1 one or Multiple first groove bodies 111, piezoluminescence off-color material are uniformly filled in the first groove body 111, and it is to fill out that inclined-plane, which cuts open object line, in Fig. 3 Fill the piezoluminescence off-color material in the first groove body 111.
In concrete operations, it can be capable of providing independent to piezoluminescence off-color material by the setting of above-mentioned first groove body 111 Setting cavity, can effectively meet piezoluminescence off-color material installation needed for space requirement;Above-mentioned piezoluminescence discoloration material Material can be bonded in the first groove body 111, and above-mentioned first groove body 111 is preferably rectangle groove body.
Preferably, in the present embodiment, above-mentioned positive first subregion, positive second subregion and positive third subregion One or more second groove bodies 121 are inside offered, piezoluminescence off-color material is uniformly filled in the second groove body 121, in Fig. 3 It is the piezoluminescence off-color material being filled in the second groove body 121 that inclined-plane, which cuts open object line,.
In concrete operations, can also it be capable of providing only to piezoluminescence off-color material by the setting of above-mentioned second groove body 121 Vertical setting cavity, space requirement needed for also capable of effectively meeting the installation of piezoluminescence off-color material;Above-mentioned piezoluminescence becomes Color material can be bonded in the second groove body 121, and above-mentioned second groove body 121 is preferably strip groove body.
Preferably, in the present embodiment, above-mentioned piezoluminescence off-color material is fixed on gypsum by bonded adhesives.Specific behaviour In work, the connective stability of piezoluminescence off-color material can be effectively improved, is enabled to by the setting of above-mentioned bonded adhesives Piezoluminescence off-color material is firmly fixed on gypsum board surface.
Embodiment two:
Second embodiment of the present invention provides a kind of walls, including the wall element recorded in multiple embodiments one.
In the present embodiment, plasterboard, i.e., one end of plasterboard herein are also equipped between two adjacent wall elements The keel unit of side wall element is connected, the other end connects the keel unit of other side Cavity unit.Preferably, wall element Between plasterboard on be provided with piezallochromy unit.
In concrete operations, it is two neighboring can to can be realized place by the above-mentioned piezallochromy unit between wall element The real-time monitoring of connective stability between wall element, and then can be realized the real-time prison of the structural stability of wall entirety It surveys.
In conjunction with the embodiments one, the record in embodiment two it is found that the application can by the setting of above-mentioned piezallochromy unit, It can be realized the stress condition of real-time monitoring plasterboard, and then whether the structure for being able to reflect out keel unit deforms;When When moderate finite deformation occurs for keel unit, plasterboard connected to it will also be distorted deformation, and above-mentioned piezallochromy unit is because upper Under the external force for stating the generation of plasterboard torsional deformation, corresponding color change is generated;Wall especially before earthquake is small Deformation, can drive piezallochromy unit under the external force of deformation of wall, corresponding color change is presented, to remind people vertical Escape.
Further, the application can also can be realized plasterboard ontology by the setting of above-mentioned first piezallochromy component Monitoring, when plasterboard ontology, which is distorted, to be deformed, the first piezallochromy component being arranged on plasterboard ontology can be produced Raw corresponding color change;Meanwhile people can also be by the surface of the first piezallochromy component of pressing, so that the first piezallochromy Component generates corresponding discoloration, to enrich real life.
Further, the application can also can be realized plasterboard and dragon by the setting of above-mentioned second piezallochromy component The monitoring of osteon connecting portion can realize the monitoring of keel unit;When keel unit, which is distorted, to be deformed, Huo Zhefa When raw dislocation, the plasterboard being arranged on keel unit also can accordingly deform, and the second piezallochromy component then can be by stone The deformation of cream plate is embodied by the variation of color, enables one to understand constantly the structure of the keel unit inside wall Stability.
Further, the application can also pass through the above-mentioned piezoluminescence discoloration material being uniformly arranged in positive first subregion Material can be realized the real-time monitoring of the structural stability of the day keel of gypsum back connection;It can be also uniformly arranged on by above-mentioned Piezoluminescence off-color material in positive second subregion can be realized the structural stability of the ground joist of gypsum back connection Real-time monitoring;Also stone can be can be realized by the above-mentioned piezoluminescence off-color material being uniformly arranged in positive third subregion The real-time monitoring of the structural stability of the centre keel of cream back connection;It can be by the way that the first sub-district of front being independently arranged be arranged The piezoluminescence off-color material in domain, positive second subregion and positive third subregion, can be realized relatively independent monitoring Function.
Further, the application can be also capable of providing by the setting of above-mentioned first groove body, the second groove body to piezoluminescence The independent setting cavity of off-color material, space requirement needed for capable of effectively meeting the installation of piezoluminescence off-color material;Can also it lead to The setting of above-mentioned bonded adhesives is crossed, the connective stability of piezoluminescence off-color material can be effectively improved, enable to piezoluminescence Off-color material is firmly fixed on gypsum board surface.
In the description of the present application, term " installation ", " connected ", " connection ", " fixation " etc. be shall be understood in a broad sense, example Such as, " connection " may be fixed connection or may be dismantle connection, or integral connection;It can be directly connected, it can also be with Indirectly connected through an intermediary.For the ordinary skill in the art, above-mentioned art can be understood as the case may be The concrete meaning of language in this application.
In the description of this specification, the description of term " one embodiment ", " some embodiments ", " specific embodiment " etc. Mean that particular features, structures, materials, or characteristics described in conjunction with this embodiment or example are contained at least one reality of the application It applies in example or example.In the present specification, schematic expression of the above terms are not necessarily referring to identical embodiment or reality Example.Moreover, description particular features, structures, materials, or characteristics can in any one or more of the embodiments or examples with Suitable mode combines.
Although those skilled in the art should be understood that embodiment disclosed by the embodiment of the present invention is as above, described The content only embodiment of the present invention and the embodiment that uses for ease of understanding, be not intended to limit the invention embodiment.It is any Technical staff in fields of the embodiment of the present invention, in the premise for not departing from spirit and scope disclosed by the embodiment of the present invention Under, any modification and variation, but the scope of patent protection of the embodiment of the present invention can be carried out in the form and details of implementation, Still it should be subject to the scope of the claims as defined in the appended claims.

Claims (10)

1. a kind of wall element for supporting monitoring and warning function, including be set to the plasterboard of wall two sides, be set to inside wall and For connecting the keel unit of plasterboard, which is characterized in that
It further include piezallochromy unit, the front of the plasterboard is arranged in the piezallochromy unit.
2. the wall element according to claim 1 for supporting monitoring and warning function, which is characterized in that
The back side of the plasterboard include with keel unit not in contact with the first rear surface regions, contacted with keel unit second back Face region;
The piezallochromy unit includes the first piezallochromy component, and the first piezallochromy component is arranged in the plasterboard Corresponding in the first front surface region of the first rear surface regions;The first piezallochromy component includes being uniformly arranged on the first front Piezoluminescence off-color material in region.
3. the wall element according to claim 2 for supporting monitoring and warning function, which is characterized in that
The piezallochromy unit further includes the second piezallochromy component, and the second piezallochromy component is arranged in the gypsum Plate corresponds in the second front surface region of the second rear surface regions;The second piezallochromy component includes being uniformly arranged on second just Piezoluminescence off-color material in the region of face.
4. the wall element according to claim 3 for supporting monitoring and warning function, which is characterized in that
The keel unit includes positioned at the day keel at top, positioned at the ground joist of bottom and for connecting day keel and pheretima The centre keel of bone.
5. the wall element according to claim 4 for supporting monitoring and warning function, which is characterized in that
Second rear surface regions include the first subregion of the back side contacted with day keel, the second son of the back side contacted with ground joist Region and the back side third subregion contacted with centre keel;
Second front surface region includes corresponding to the first subregion of front of the first subregion of the back side, corresponding to the second son of the back side Second subregion of front in region and positive third subregion corresponding to back side third subregion.
6. the wall element according to claim 5 for supporting monitoring and warning function, which is characterized in that
The second piezallochromy component includes the piezoluminescence off-color material being uniformly arranged in positive first subregion, uniformly The piezoluminescence off-color material being arranged in positive second subregion and the pressure being uniformly arranged in positive third subregion cause Color-changing materials.
7. according to the wall element of support monitoring and warning function described in Claims 2 or 3 or 4 or 5 or 6, which is characterized in that
One or more first groove bodies are offered in first front surface region of the plasterboard, the piezoluminescence off-color material is equal It is even to be filled in the first groove body.
8. the wall element according to claim 6 for supporting monitoring and warning function, which is characterized in that
One or more the are offered in positive first subregion, positive second subregion and positive third subregion Two groove bodies, the piezoluminescence off-color material are uniformly filled in the second groove body.
9. the wall element according to claim 2 for supporting monitoring and warning function, which is characterized in that
The piezoluminescence off-color material is fixed on gypsum by bonded adhesives.
10. a kind of wall, which is characterized in that including the support monitoring and warning function any in multiple claim 1-9 Wall element;
Piezallochromy unit is provided on plasterboard between the wall element.
CN201710721014.6A 2017-08-21 2017-08-21 A kind of wall element and its wall for supporting monitoring and warning function Pending CN109424083A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710721014.6A CN109424083A (en) 2017-08-21 2017-08-21 A kind of wall element and its wall for supporting monitoring and warning function

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710721014.6A CN109424083A (en) 2017-08-21 2017-08-21 A kind of wall element and its wall for supporting monitoring and warning function

Publications (1)

Publication Number Publication Date
CN109424083A true CN109424083A (en) 2019-03-05

Family

ID=65498573

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710721014.6A Pending CN109424083A (en) 2017-08-21 2017-08-21 A kind of wall element and its wall for supporting monitoring and warning function

Country Status (1)

Country Link
CN (1) CN109424083A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111982671A (en) * 2020-06-30 2020-11-24 天地科技股份有限公司 Pressure arch visualization gravel anchoring test device and method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2693850Y (en) * 2003-09-09 2005-04-20 孙建华 Inorganic framing joint-insert type composite wall
CN101041980A (en) * 2007-04-13 2007-09-26 刘辉 Lightweight plaster wall and integral pouring procedure thereof
CN202000514U (en) * 2011-03-18 2011-10-05 上海恒绚实业有限公司 Building wall
JP2013170382A (en) * 2012-02-20 2013-09-02 Railway Technical Research Institute Method and system for selecting vibration countermeasure for soundproof wall in overpass
US20140352422A1 (en) * 2013-05-30 2014-12-04 Björn N. P. Paulsson Sensor pod housing assembly and apparatus
CN205224507U (en) * 2015-12-06 2016-05-11 吴滨 Pressure -sensitive wall paper that discolours
JP2016151544A (en) * 2015-02-19 2016-08-22 特種東海製紙株式会社 Stress light emission sheet
CN106284886A (en) * 2016-08-22 2017-01-04 桐乡嘉力丰实业股份有限公司 A kind of heat-sensitive variable colour wallpaper and preparation technology thereof

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2693850Y (en) * 2003-09-09 2005-04-20 孙建华 Inorganic framing joint-insert type composite wall
CN101041980A (en) * 2007-04-13 2007-09-26 刘辉 Lightweight plaster wall and integral pouring procedure thereof
CN202000514U (en) * 2011-03-18 2011-10-05 上海恒绚实业有限公司 Building wall
JP2013170382A (en) * 2012-02-20 2013-09-02 Railway Technical Research Institute Method and system for selecting vibration countermeasure for soundproof wall in overpass
US20140352422A1 (en) * 2013-05-30 2014-12-04 Björn N. P. Paulsson Sensor pod housing assembly and apparatus
JP2016151544A (en) * 2015-02-19 2016-08-22 特種東海製紙株式会社 Stress light emission sheet
CN205224507U (en) * 2015-12-06 2016-05-11 吴滨 Pressure -sensitive wall paper that discolours
CN106284886A (en) * 2016-08-22 2017-01-04 桐乡嘉力丰实业股份有限公司 A kind of heat-sensitive variable colour wallpaper and preparation technology thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111982671A (en) * 2020-06-30 2020-11-24 天地科技股份有限公司 Pressure arch visualization gravel anchoring test device and method
CN111982671B (en) * 2020-06-30 2023-08-08 天地科技股份有限公司 Pressure arch visualized broken stone anchoring test device and method

Similar Documents

Publication Publication Date Title
TW200738027A (en) Capacitive micromachined ultrasound transducer and methods of making the same
MX2010004257A (en) Wo 2009082605 a1 20090702.
WO2010134302A3 (en) Method for manufacturing a capacitive electromechanical transducer
WO2009072323A1 (en) Display element and its fabrication method
CN109424083A (en) A kind of wall element and its wall for supporting monitoring and warning function
WO2009096725A3 (en) Precast temporary facility structure and a construction method for the same
WO2007005849A3 (en) Using messages to extend crm functionality
CN101127169A (en) Soil mass positive and passive destruction demonstrator
CN201915418U (en) Flexible connecting structure between cushion cap and pile
WO2008149850A1 (en) Process for producing electrochemical display element and electrochemical display element
CN102031789A (en) Flexible connecting structure for bearing platform and pile
Hayashi et al. Pressure of the breaker against a vertical wall
CN203929510U (en) Timber testing equipment
CN205051878U (en) Test fixture and test system
CN205541624U (en) Supplementary teaching device of composite pile basic mode type
CN201614858U (en) Screen window corner protector
CN103774818B (en) The cladding adaptor of fiber ceramic board and fiber ceramic board dried hanging method
CN208023764U (en) A kind of piezoelectricity-magnetostriction materials quality coordination damper
CN205594175U (en) Seismic surveillance appearance
CN204465858U (en) The two unit Piezoelectric anisotropy type full frequency speaker of circle sheet
Farouk et al. Effect of elastic soil structure interaction on modulus of subgrade reaction
CN204076460U (en) A kind of variable cross-section Miniature anti-slide pile grinding tool
CN204212178U (en) The constructing structure of a kind of outer wall of basement one side formwork in small space
CN209843058U (en) Building block model, unconstrained masonry structure and house building teaching model
CN202486448U (en) Navigation eyeglasses

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190305