CN109391038B - Deployment method of intelligent substation interval measurement and control function - Google Patents

Deployment method of intelligent substation interval measurement and control function Download PDF

Info

Publication number
CN109391038B
CN109391038B CN201811585916.2A CN201811585916A CN109391038B CN 109391038 B CN109391038 B CN 109391038B CN 201811585916 A CN201811585916 A CN 201811585916A CN 109391038 B CN109391038 B CN 109391038B
Authority
CN
China
Prior art keywords
state
deployment
interval
measurement
turning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811585916.2A
Other languages
Chinese (zh)
Other versions
CN109391038A (en
Inventor
赵硕
朱成超
宋王
田君茹
王洪玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Integrated Electronic Systems Lab Co Ltd
Original Assignee
Integrated Electronic Systems Lab Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Integrated Electronic Systems Lab Co Ltd filed Critical Integrated Electronic Systems Lab Co Ltd
Priority to CN201811585916.2A priority Critical patent/CN109391038B/en
Publication of CN109391038A publication Critical patent/CN109391038A/en
Application granted granted Critical
Publication of CN109391038B publication Critical patent/CN109391038B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/16Electric power substations

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Selective Calling Equipment (AREA)
  • Stored Programmes (AREA)

Abstract

The invention discloses a deployment method of an intelligent substation interval measurement and control function, which increases manual deployment on the basis of automatic deployment. In order to realize manual deployment, state setting is added at each interval, the interval state is modified manually through an interface, each device receives the manual deployment state, sends the manual deployment state to the main control device through the station control layer, is monitored and adjusted by the main control device, and is issued to each device for execution, so that the manual deployment is realized, and meanwhile, the reliability of the manual deployment is ensured through the main control device. And during automatic deployment, the master control monitors the state of each interval and determines a deployment strategy, and manual control on the automatic deployment is realized through interval state setting and interval state monitoring. Both deployment modes are finally determined by the master control, and the cooperation of manual deployment and automatic deployment is realized. And the measurement and control programs of the running and hot standby are started simultaneously, and only the measurement and control program in the running state realizes the measurement and control function at intervals, so that the uniqueness of the measurement and control function is ensured, and meanwhile, the seamless switching of the measurement and control function is realized.

Description

Deployment method of intelligent substation interval measurement and control function
Technical Field
The invention belongs to the technical field of a secondary equipment cluster measurement and control device of an electric power system, and particularly relates to a deployment method of an interval measurement and control function of an intelligent substation.
Background
In an intelligent substation, the clustering of measurement and control devices is a development trend of the current measurement and control devices, and how to deploy the measurement and control functions of the clustered measurement and control devices becomes a main subject of current research. The current measurement and control device deployment mainly considers the centralized deployment of a plurality of interval measurement and control functions and the automatic deployment of the measurement and control devices when the measurement and control devices are abnormal, the manual online deployment and the control capability of the measurement and control devices on the automatic deployment are lacked, and the current research mainly aims at the main measurement and control and does not research how to realize the automatic deployment of a plurality of sets of measurement and control devices. In addition, the measurement and control function does not consider the migration time during deployment, so that the rapidity is poor, and the measurement and control function at intervals is influenced.
The document [ research and application of an intelligent substation cluster measurement and control system ] proposes that a virtual measurement and control device is migrated to another cluster measurement and control device when a fault occurs, and provides a related technology of network communication, but how to implement deployment and how to migrate is not provided with a certain mode, and the document does not relate to manual management. Documents (intelligent substation cluster measurement and control device and system with the same) adopt automatic and manual management modes, and realize management through a master task manager and a slave task manager. However, the manual deployment adopts a mode of manually starting the backup measurement and control device, which belongs to an off-line deployment mode, and manual control is difficult during automatic deployment, so that the controllability of automatic deployment is poor, real-time management of automatic deployment is lacked, and meanwhile, the document does not mention how to improve the migration speed.
Disclosure of Invention
In order to solve the technical problem, the invention provides a manual and automatic online collaborative deployment method for an intelligent substation interval measurement and control function. According to the method, manual deployment is added on the basis of automatic deployment, state setting is added for different intervals, and manual online deployment and real-time control of automatic deployment are achieved. The automatic deployment and the manual deployment are centralized in the main control device for processing, and the cooperativity of the manual deployment and the automatic deployment is ensured. The method can be applied to measurement and control of multiple clusters, the application range of the method is expanded, and the deployment among multiple devices is realized.
Technical terms involved in the present invention include:
spacing: a part with an electrical connection relation in the transformer substation comprises a designated loop and related equipment.
The device comprises the following steps: an electronic instrument with a processor having all or part of the following functions: (1) collecting and processing data; (2) receiving or transmitting data; (3) receiving or sending a control instruction; (4) and executing the control instruction.
Measurement and control device: a device having all or part of the following functions: (1) collecting and processing analog quantity or state quantity data; (2) sending the collected and processed data; (3) receiving and executing a control instruction; (4) and carrying out logic judgment on the data and outputting a result.
The main control device: and the measurement and control device is responsible for completing the function of deployment control decision. Each measurement and control device has the function, but only one measurement and control device operates the function at the same time to become a master control device. Under the condition that the master control device is absent, each measurement and control device can automatically compete to determine which measurement and control device is the master control device by comparing the priority parameter with the address parameter.
And (3) management program: the measurement and control device is provided with a functional module which is deployed in the container to operate, so that the deployment of interval parameters and measurement and control programs in the container and the start-stop control of the measurement and control programs are realized.
Measurement and control program: the measurement and control device is provided with a functional module which is deployed in the container to operate, so that the measurement and control function at intervals is realized.
A container: the hardware resources are divided in a virtualization mode to obtain a plurality of mutually isolated resource spaces, each space is a container, the operating environment and the program module can be independently deployed, and starting and stopping can be achieved through independent control.
GOOSE: related model objects and services of generic substation event data values in the data set and the mapping between these model objects and services to ISO/IEC8802-3 frames are exchanged quickly and reliably based on a publish/subscribe mechanism.
Deploying a message: and the message with the interval state configuration is generated after being manually set or decided by the master control device.
Heartbeat messages: the message containing the status information of each interval is sent in a broadcasting mode, and is received and processed by the main control device.
The technical scheme adopted by the invention is as follows:
a deployment method of an interval measurement and control function of an intelligent substation is carried out in cooperation of manual deployment and automatic deployment and comprises the following steps:
step 1, deploying a plurality of intervals of measurement and control function parameter information and measurement and control programs in a root directory of a device, setting state information of each interval, and deploying a management program in a container;
step 2, power-on initialization is carried out, management programs of all devices realize initial deployment of interval parameters and measurement and control programs in a container based on state files, and corresponding measurement and control programs are started;
step 3, judging whether a main control device exists, if so, turning to the step 5, and if not, turning to the next step;
step 4, determining a main control device for monitoring each interval state by comparing the priority and the IP address of the device;
step 5, the master control device obtains the message and determines whether the message is a deployment message or a heartbeat message through message analysis; if the message is deployed, turning to the step 8, and if the message is a heartbeat message, turning to the next step;
step 6, judging whether the abnormality exists, if not, turning to the step 5, and if so, turning to the next step;
and 7, automatically deploying according to the interval state change. The master control device monitors the state of each device, determines a migration strategy, and issues an execution instruction by the master control device, and the management program of each device redeployes the measurement and control function of the interval according to the obtained state; the specific steps for automatic deployment are:
step 7.1, the master control device receives the heartbeat message;
7.2, judging whether an abnormal state exists, if so, turning to the next step, and if not, turning to the step 7.1;
7.3, judging whether the migration condition is met, if so, turning to the next step, and if not, turning to the step 7.1;
7.4, analyzing and determining a deployment strategy;
7.5, the main control device issues a migration command;
7.6, reading and storing the task table by the target device;
7.7, executing migration;
and 7.8, after the migration is finished, issuing a heartbeat message according to the new state, and turning to the step 7.1.
And 8, carrying out manual deployment. Manually issuing a deployment result through an operation and maintenance interface, receiving and sending each device to a main control device, monitoring the issuing result by the main control device, automatically modifying an unreasonable state, and then issuing the result to each device through a station control layer network for execution;
and 9, all devices send heartbeat messages in the current state.
Preferably, the specific steps of performing manual deployment in step 8 are:
step 8.1, judging whether the manual work issues the state information through the operation and maintenance interface, if so, turning to the next step, and if not, turning to the step 8.1;
8.2, each device receives the state information issued by the operation and maintenance interface and sends the state information to the master control device;
step 8.3, the master control device receives the state information;
step 8.4, judging whether a deployment conflict exists, if so, adjusting a deployment mode, turning to the next step, and if not, turning to the next step;
8.5, the main control device issues a migration command;
step 8.6, the target device reads and stores the task table;
step 8.7, executing migration;
and 8.8, after the migration is finished, issuing a heartbeat message according to the new state, and turning to the step 8.1.
Preferably, the specific step of determining the master control device monitoring the status of each interval in step 4 is:
step 4.1, when the non-master control device can not obtain the deployment message sent by the master control device within the set time, the non-master control device requests the management authority in a broadcasting mode through the station control layer network;
step 4.2, judging whether request messages of other nodes are received or not, if so, turning to the next step, if not, judging that no other node requests in preset time, determining that the node obtains the management authority, and turning to step 4.4;
4.3, comparing the priority and the IP address of the device, wherein the priority is high and the IP value is small, so as to obtain the management authority;
and 4.4, entering a management process, receiving and processing the heartbeat message, executing state monitoring, executing a scheduling strategy, and turning to the step 4.1.
Preferably, the specific method for setting the status information of each interval in step 1 is: for each interval increment state setting, respectively: and in the states of running, hot standby, cold standby and non-running, a strategy of simultaneously starting the running state interval measurement and control program and the hot standby state interval measurement and control program is adopted.
Preferably, in the uplink data, the measurement and control program for the "running" and "hot standby" state intervals uploads the data information and the current state of the intervals to the monitoring background through IEC61850-MMS service, and the monitoring background obtains running state interval data according to the interval states; in the downlink data, the measurement and control program judges whether to issue the GOOSE based on the current state of the interval, if the interval is in the running state, the GOOSE is issued, otherwise, the GOOSE issuing is terminated.
Preferably, each container deploys information of one interval, and stores the event file generated by the interval in the container, each container can operate independently, and the containers are not affected by each other.
Preferably, the events generated by the operation state interval and the modified parameter file are updated to other devices in real time through the station control layer network.
Preferably, the state monitoring of each device and each interval is realized by operation and maintenance software instead of traditional liquid crystal, which is integrated in the background and supports independent deployment.
The invention has the beneficial effects that:
1) the manual deployment is added on the basis of the automatic deployment, so that the measurement and control functions of each interval when the device is abnormal are ensured, the manual online deployment and the real-time control on the automatic deployment are realized, and the flexibility and the reliability of the automatic deployment are improved.
2) The main control device is used as a control center for manual and automatic deployment, so that the reliability of manual deployment is improved, and the cooperation of automatic deployment and manual deployment is realized.
3) The measurement and control program in the hot standby state is started, so that the migration speed is improved, and seamless switching of the measurement and control functions is realized.
4) Different states can be set on the devices at the same interval, and the master control device monitors the states of the intervals, so that the application range of the deployment mode is expanded, and the deployment among the devices is realized.
Drawings
Fig. 1 is a main flow chart of an interval measurement and control function deployment method;
FIG. 2 is a schematic diagram of the migration of the interval measurement and control function;
FIG. 3 is a diagram of a monitoring system for logical measurement and control of "run" and "hot standby" intervals;
FIG. 4 is a flow chart of determining a master device;
FIG. 5 is a flow chart of automated deployment;
FIG. 6 is a flow chart of manual deployment.
Detailed Description
The invention is further described with reference to the following figures and examples.
As shown in fig. 1, it is a main flow chart of an interval measurement and control function deployment method. A deployment method of an interval measurement and control function of an intelligent substation is carried out in cooperation of manual deployment and automatic deployment and comprises the following steps:
step 1, deploying measurement and control function parameter information and measurement and control programs of a plurality of intervals in a root directory of a device, and setting state information of each interval; the hypervisor is deployed in a container.
In order to realize the cooperative execution of manual deployment, automatic deployment among multiple devices, manual deployment and automatic deployment, state settings are added for each interval, which are respectively as follows: running, hot standby, cold standby and non-running state.
Each cluster measurement and control device can be deployed with a plurality of intervals, and measurement and control functions of the plurality of intervals are realized. When the measurement and control functions of an interval are deployed from one measurement and control device to another measurement and control device, the measurement and control functions are called "migration", and as shown in fig. 2, the migration schematic diagram of the measurement and control functions of an interval is shown. Manual deployment and automatic deployment are two ways to implement migration.
And 2, electrifying and initializing. And the management program of each device is set based on the state parameter file, so that the initial deployment of the interval parameters and the measurement and control program in the container is realized, and the corresponding measurement and control program is started.
When the device is initially powered on, the device management program reads the state parameters of each interval, deploys the measurement and control programs of the intervals of the 'running' state and the 'hot standby' state and respective parameter files in a container, and starts the corresponding measurement and control programs to realize initial deployment of interval information. Each container is deployed with information of one interval, and item files generated by the interval are stored in the container, each container can be operated independently, the containers are not influenced mutually, and the independence of logic measurement and control is guaranteed. The running state of the corresponding parameter file and the program can be checked by entering different containers of the device. Meanwhile, in order to ensure that the parameters of the 'operation' state interval are consistent with the parameters of other devices, items generated by the 'operation' state interval and the modified parameter file are updated to other devices in real time through the station control layer network.
In order to realize seamless switching of the measurement and control functions, an interval measurement and control program of 'operation' and 'hot standby' is started simultaneously. In the operation process, in order to ensure that the measurement and control function of the interval is realized only by the measurement and control program of the 'operation' state interval, in the uplink data, the measurement and control program of the 'operation' and 'hot standby' state interval sends the data information and the current state of the interval to the monitoring background through the IEC61850-MMS service, and the monitoring background obtains the 'operation' state interval data according to the interval state. In the downlink data, the measurement and control program judges whether to issue the GOOSE based on the current state of the interval, if the interval is in the 'running' state, the GOOSE is issued, otherwise, the GOOSE issuing is terminated. By starting the measurement and control programs of the 'running' and 'hot standby' state intervals simultaneously and ensuring that the measurement and control programs of only the 'running' state intervals realize the measurement and control functions of the intervals, the uniqueness of the measurement and control functions of the intervals is ensured, the migration speed is improved, and the seamless switching of the measurement and control functions is realized. Fig. 3 is a diagram of a monitoring system for logic measurement and control of "running" and "hot standby" state intervals.
And 3, judging whether the main control device exists, if so, turning to the step 5, and if not, turning to the next step.
In the device operation process, in order to realize automatic deployment of multiple devices and cooperation of the multiple devices and manual deployment, a main control device needs to be determined, a heartbeat message and a manual deployment message are obtained by the main control device, and a final deployment scheme of the manual deployment and the automatic deployment is analyzed and determined. In automatic deployment, the master control device obtains the state of each interval through a station control layer network, and analyzes and determines a measurement and control function redeployment strategy; in manual deployment, the master control device monitors the manual deployment result, adjusts the manual deployment according to the needs, and issues the final deployment result.
And 4, determining the master control device for monitoring the state of each interval by comparing the priority parameter and the IP address of the device.
In the operation process, if the master control device does not exist, the device broadcasts the request management authority, after receiving the message of requesting management by other devices, the priority and the IP address of the device are compared, the device with the high priority and the small IP address is used as the master control device, and if the message of requesting management by other devices is not received, the device is used as the master control device after a period of time, so that the uniqueness of the master control device is ensured. When the main control device operates abnormally, other devices determine the main control device according to the same mode, and perform state monitoring of each interval and issue a deployment command. In all cluster measurement and control, there is one and only one master control device. Fig. 4 shows a flowchart for determining the master control device, which specifically includes the following steps:
step 4.1, when the non-master control device can not obtain the deployment message sent by the master control device within the set time, the non-master control device requests the management authority in a broadcasting mode through the station control layer network;
step 4.2, judging whether request messages of other nodes are received or not, if so, turning to the next step, if not, judging that no other node requests in preset time, determining that the node obtains the management authority, and turning to step 4.4;
step 4.3, comparing the priority of the device with the IP address, wherein the priority is high and the IP value is small, so as to obtain the management authority;
and 4.4, entering a management process, receiving and processing the heartbeat message, executing state monitoring, executing a scheduling strategy, and turning to the step 4.1.
Step 5, the master control device obtains the message, and determines whether the message is a deployment message or a heartbeat message through message analysis; if the message is deployed, the step 8 is carried out, and if the message is a heartbeat message, the next step is carried out.
The master control device obtains the messages sent by each device through the station control layer network, analyzes and processes the obtained messages and determines the types of the messages.
And 6, judging whether the abnormality exists, if not, turning to the step 5, and if so, turning to the next step.
And 7, automatically deploying according to the interval state change.
The automatic deployment is that the main control device monitors the state of each device, determines the migration strategy and sends an execution instruction by the main control device. And the management program of each device redeployes the measurement and control function of the interval according to the obtained state.
When automatic deployment is performed, the management program of the main control device monitors the running state of each interval, such as CPU load, memory usage and the like, and forms a deployment condition. In order to cooperate with manual deployment and realize the constraint of manual deployment on automatic deployment, the master control device simultaneously monitors the states of the interval settings. In the operation process, when the cluster measurement and control device is found to be overloaded, abnormal in state and the like, namely the deployment state of each interval is determined again through analysis and processing according to the current state distribution of each interval, and the deployment result is sent to each device in a broadcast mode through a station control layer network. And the management program of each device redeploys interval parameters according to the acquired deployment message, starts and stops the corresponding measurement and control program or GOOSE to issue, realizes redeployment of interval measurement and control functions, and stores the current state into a specific parameter file. Meanwhile, the management program of each device monitors the execution state of the device and ensures the correct execution of the issued command. The flow chart of automatic deployment is shown in fig. 5, and specifically includes the following steps:
step 7.1, the master control device receives the heartbeat message;
7.2, judging whether an abnormal state exists, if so, turning to the next step, and if not, turning to the step 7.1;
7.3, judging whether the migration condition is met, if so, turning to the next step, and if not, turning to the step 7.1;
7.4, analyzing and determining a deployment strategy;
7.5, the main control device issues a migration command;
7.6, reading and storing the task table by the target device;
7.7, executing migration;
and 7.8, after the migration is finished, issuing a heartbeat message according to the new state, and turning to the step 7.1.
Considering the operation of the measurement and control program of the 'hot standby', the state conversion of the 'cold standby' and the 'operation' or the 'hot standby' is different from the conversion of the 'hot standby' and the 'operation'.
(1) And (3) switching between the running state and the hot standby state, modifying the state of the interval by a management program of the device, and issuing by a monitoring program start-stop GOOSE.
(2) The conversion between the cold standby state and the running state or the hot standby state is realized by deploying interval parameters and a measurement and control program by a management program and starting and stopping the corresponding measurement and control program.
And 8, carrying out manual deployment.
And manual online deployment is realized by setting the state on the operation and maintenance interface. In order to realize the cooperativity of manual deployment and automatic deployment and improve the reliability of the manual deployment, the main control device is used as a final decision center of the manual deployment.
In the operation process, the manual deployment modifies the state of each interval through the operation and maintenance interface, when each device receives the deployment state sent by the operation and maintenance interface, the state result is not immediately executed, but is sent to the main control device, the state result is analyzed by the main control device and then sent to each device, each device management program realizes the deployment of interval parameters and the starting and stopping of the measurement and control program or the GOOSE release according to the obtained interval state, and the parameter deployment result is stored in a parameter file. If the result obtained by the main control device does not meet the actual requirement, the main control device can automatically adjust the deployment mode according to the setting result and the current state of other devices so as to meet the actual requirement and realize reasonable utilization of resources. If the two sets of devices are set to be in the running state for the same interval if manual deployment is carried out, and if the issued result is not monitored, the running states of the two sets of devices at the same interval exist in the station at the moment, and the data uploading and the command issuing can be disordered, so that the reliability of the manual deployment can be improved by concentrating the manual deployment into the main control device, and meanwhile, the cooperativity of the manual deployment and the automatic deployment is ensured. A flowchart of manual deployment is shown in fig. 6, and specifically includes the following steps:
step 8.1, judging whether the manual work issues the state information through the operation and maintenance interface, if so, turning to the next step, and if not, turning to the step 8.1;
8.2, each device receives the state information issued by the operation and maintenance interface and sends the state information to the master control device;
step 8.3, the master control device receives the state information;
step 8.4, judging whether a deployment conflict exists, if so, adjusting a deployment mode, turning to the next step, and if not, turning to the next step;
8.5, the main control device issues a migration command;
step 8.6, the target device reads and stores the task table;
step 8.7, executing migration;
and 8.8, after the migration is finished, issuing a heartbeat message according to the new state, and turning to the step 8.1.
The main control device realizes the adjustment of manual deployment by considering the priority of the device and the reasonable configuration of resources, but the main control device is manually set as the main control device.
(1) In the two running states, the main control device preferentially considers manual deployment, and automatically sets the logic measurement and control of the original running state to be a hot standby state. Therefore, only one logic measurement and control function for realizing the interval exists.
(2) In a plurality of sets of measurement and control devices, for the same interval, the 'running' state is not set manually, but the 'hot standby' setting exists. At this time, the main control device automatically switches the hot standby state of the corresponding interval of the corresponding device into the running state so as to ensure that at least one running state exists in the interval.
(3) If all the intervals of the two sets of measurement and control devices are set to be in the 'running' state, the uniqueness of the 'running' state in the same interval and the reasonable distribution of resources are considered, and a plurality of 'running' states are evenly distributed in the two sets of devices at intervals, so that the burden of a single device is reduced, and the reasonable utilization of resources is realized.
(4) If in a plurality of sets of measurement and control devices, the hot standby state is not set manually for the same interval, but the cold standby state is set. The main control device automatically adjusts the cold standby state into the hot standby state so as to ensure the rapidity of the next automatic deployment.
Considering the operation of the 'hot standby' measurement and control program, for manual deployment, the processing modes of the management program and the measurement and control program during switching of different states are as follows:
(1) and (3) switching between the running state and the hot standby state, modifying the state of the interval by a management program of the device, and issuing by a monitoring program start-stop GOOSE.
(2) And the conversion between the states of cold standby or stop and running or hot standby is realized, the interval parameters and the measurement and control program are deployed by the management program, and the corresponding measurement and control program is started and stopped.
Because the 'running' state realizes the measurement and control function at intervals, manual online deployment is realized by modifying the device where the 'running' state is located manually, meanwhile, the logical measurement and control program of the 'hot standby' state starts the corresponding measurement and control program, the management program of the main control device can give priority to the logical measurement and control device of the 'hot standby' state during migration, and meanwhile, the state information of the cluster device is analyzed to determine the deployment strategy. Thus, the migration direction of the automated deployment is influenced manually by modifying the device in which the "hot standby" state resides. To limit the scope of the devices for automatic deployment or automatic deployment migration, the interval not participating in automatic deployment may be set to a "deactivated" state. At this time, the logic measurement and control in the 'off' state is not considered in the automatic deployment. Therefore, manual deployment and manual real-time control over automatic deployment thereof are simultaneously realized through state setting.
And 9, all devices send heartbeat messages in the current state.
In the embodiment, the state monitoring of each device and each interval is realized by operation and maintenance software instead of traditional liquid crystal, which is integrated in the background and supports independent deployment. For manual deployment and automatic deployment, the operation and maintenance software can refresh the state of each interval in real time, and the current state of each interval can be checked manually through the operation and maintenance software. Meanwhile, the states of all devices corresponding to intervals can be modified through the operation and maintenance interface, and manual online deployment is achieved.
In order to verify the feasibility and the rationality of the method, the measurement and control functions of a certain 110kV transformer substation are deployed. The substation requires 12 bays to be deployed in a cluster. And 3 sets of cluster measurement and control devices are configured in the station, and each set of device is provided with 12 measurement and control parameters at intervals, which correspond to 12 intervals of a 110kV circuit, each side of a main transformer, a 110kV bus, an inner bridge and the like. In the initial state setting, the 12-interval state of the apparatus 1 is set to "on", all the states of the apparatus 2 are set to "hot standby", and the apparatus 3 is set to "cold standby", taking into account the specific weight of the number of arrangement intervals.
The state of the interval is modified by the operation and maintenance software, and the second time and the third time in the table 1 are manually set in the first state. The setting results in table 1 show that, when the "running" state of the logical measurement and control of the device 1 is manually set as the "hot standby" state, and the "hot standby" state is not modified to the "running" state, two "hot standby" states exist for the same interval, and the "running" state does not exist. Because of the loss of the spaced running state, the master control device preferentially considers the manual deployment, and changes the hot standby state of the device 2 into the running state, thereby not only ensuring the uniqueness of the running state, but also ensuring the priority of the manual configuration. Meanwhile, when the 'hot standby' state does not exist in the manual setting, the manual setting is preferentially considered, and the 'cold standby' state of the device 3 is modified into the 'hot standby' state.
In table 2, after the second manual deployment is completed and the device 2 is abnormal, the device 3 is selected as the migration target device instead of migrating to the device 1. Therefore, when the device in the "hot standby" state is manually modified, the migration direction of the automatic deployment will also change. And for the same interval, except for the logic measurement and control in the 'running' state, the rest are 'inactive', and at the moment, the logic measurement and control in the 'running' state is abnormal, and the migration cannot occur.
TABLE 1 Effect of Master control on Manual deployment
Figure GDA0002498185720000071
TABLE 2 impact of manual deployment on automated deployment
Figure GDA0002498185720000081
Tables 1 and 2 show that manual deployment is added in automatic deployment, and the manual online deployment and the manual deployment are controlled by setting corresponding states for different intervals and adding a main control device to monitor the manual deployment, so that the purpose of manual and automatic collaborative deployment is achieved.
Although the embodiments of the present invention have been described with reference to the accompanying drawings, it is not intended to limit the scope of the present invention, and it should be understood by those skilled in the art that various modifications and variations can be made without inventive efforts by those skilled in the art based on the technical solution of the present invention.

Claims (8)

1. A deployment method of an interval measurement and control function of an intelligent substation is carried out in cooperation of manual deployment and automatic deployment, and is characterized by comprising the following steps:
step 1, deploying a plurality of intervals of measurement and control function parameter information and measurement and control programs in a root directory of a device, setting state information of each interval, and deploying a management program in a container;
step 2, power-on initialization is carried out, management programs of all devices realize initial deployment of interval parameters and measurement and control programs in a container based on state files, and corresponding measurement and control programs are started;
step 3, judging whether a main control device exists, if so, turning to the step 5, and if not, turning to the next step;
step 4, determining a main control device for monitoring each interval state by comparing the priority and the IP address of the device;
step 5, the master control device obtains the message and determines whether the message is a deployment message or a heartbeat message through message analysis; if the message is deployed, turning to the step 8, and if the message is a heartbeat message, turning to the next step;
step 6, judging whether the abnormality exists, if not, turning to the step 5, and if so, turning to the next step;
step 7, automatic deployment is carried out according to the change of the interval state; the master control device monitors the state of each device, determines a migration strategy, and issues an execution instruction by the master control device, and the management program of each device redeployes the measurement and control function of the interval according to the obtained state; the specific steps for automatic deployment are:
step 7.1, the master control device receives the heartbeat message;
7.2, judging whether an abnormal state exists, if so, turning to the next step, and if not, turning to the step 7.1;
7.3, judging whether the migration condition is met, if so, turning to the next step, and if not, turning to the step 7.1;
7.4, analyzing and determining a deployment strategy;
7.5, the main control device issues a migration command;
7.6, reading and storing the task table by the target device;
7.7, executing migration;
7.8, after the migration is finished, issuing a heartbeat message according to a new state, and turning to the step 7.1;
step 8, carrying out manual deployment; manually issuing a deployment result through an operation and maintenance interface, receiving and sending each device to a main control device, monitoring the issuing result by the main control device, automatically modifying an unreasonable state, and then issuing the result to each device through a station control layer network for execution;
and 9, all devices send heartbeat messages in the current state.
2. The method for deploying the interval measurement and control function of the intelligent substation according to claim 1, wherein the specific steps of manually deploying in step 8 are as follows:
step 8.1, judging whether the manual work issues the state information through the operation and maintenance interface, if so, turning to the next step, and if not, turning to the step 8.1;
8.2, each device receives the state information issued by the operation and maintenance interface and sends the state information to the master control device;
step 8.3, the master control device receives the state information;
step 8.4, judging whether a deployment conflict exists, if so, adjusting a deployment mode, turning to the next step, and if not, turning to the next step;
8.5, the main control device issues a migration command;
step 8.6, the target device reads and stores the task table;
step 8.7, executing migration;
and 8.8, after the migration is finished, issuing a heartbeat message according to the new state, and turning to the step 8.1.
3. The method for deploying the interval measurement and control function of the intelligent substation according to claim 2, wherein the specific step of determining the master control device for monitoring the state of each interval in the step 4 is as follows:
step 4.1, when the non-master control device can not obtain the deployment message sent by the master control device within the set time, the non-master control device requests the management authority in a broadcasting mode through the station control layer network;
step 4.2, judging whether request messages of other nodes are received or not, if so, turning to the next step, if not, judging that no other node requests in preset time, determining that the node obtains the management authority, and turning to step 4.4;
4.3, comparing the priority and the IP address of the device, wherein the priority is high and the IP value is small, so as to obtain the management authority;
and 4.4, entering a management process, receiving and processing the heartbeat message, executing state monitoring, executing a scheduling strategy, and turning to the step 4.1.
4. The method for deploying the intelligent substation bay measurement and control function according to any one of claims 1 to 3, wherein the specific method for setting the status information of each bay in the step 1 is as follows: for each interval increment state setting, respectively: and in the states of running, hot standby, cold standby and non-running, a strategy of simultaneously starting the running and hot standby interval measurement and control programs is adopted.
5. The method for deploying the interval measurement and control function of the intelligent substation according to claim 4, wherein in the uplink data, a measurement and control program running at an interval between the hot standby state and the hot standby state uploads data information and the current state of the interval to a monitoring background through IEC61850-MMS service, and the monitoring background obtains running state interval data according to the interval state; in the downlink data, the measurement and control program judges whether to issue the GOOSE based on the current state of the interval, if the interval is in the running state, the GOOSE is issued, otherwise, the GOOSE issuing is terminated.
6. The method for deploying the interval measurement and control function of the intelligent substation according to claim 5, wherein each container deploys information of an interval, and stores item files generated by the interval in the container, each container can operate independently, and the containers are not affected by each other.
7. The method for deploying the interval measurement and control function of the intelligent substation according to claim 6, wherein the items generated at the operation state interval and the modified parameter files are updated to other devices in real time through a station control layer network.
8. The method for deploying the intelligent substation interval measurement and control function according to claim 7, wherein the state monitoring of each device and each interval is realized by operation and maintenance software instead of traditional liquid crystal, and the method is integrated in the background and supports independent deployment.
CN201811585916.2A 2018-12-24 2018-12-24 Deployment method of intelligent substation interval measurement and control function Active CN109391038B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811585916.2A CN109391038B (en) 2018-12-24 2018-12-24 Deployment method of intelligent substation interval measurement and control function

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811585916.2A CN109391038B (en) 2018-12-24 2018-12-24 Deployment method of intelligent substation interval measurement and control function

Publications (2)

Publication Number Publication Date
CN109391038A CN109391038A (en) 2019-02-26
CN109391038B true CN109391038B (en) 2020-10-09

Family

ID=65430626

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811585916.2A Active CN109391038B (en) 2018-12-24 2018-12-24 Deployment method of intelligent substation interval measurement and control function

Country Status (1)

Country Link
CN (1) CN109391038B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110350661B (en) * 2019-07-12 2020-09-25 南京国电南自电网自动化有限公司 Virtual measurement and control unit and entity measurement and control seamless switching method
CN112532446B (en) * 2020-11-26 2023-10-17 许继集团有限公司 Dynamic migration method of cluster measurement and control device
CN113541310A (en) * 2021-06-25 2021-10-22 许继电气股份有限公司 Measurement and control system and control method based on GOOSE message state
CN113556248B (en) * 2021-07-16 2023-05-12 广东电网有限责任公司 Cluster measurement and control dynamic deployment method, device, equipment and storage medium

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104578409A (en) * 2014-12-16 2015-04-29 国家电网公司 Cluster measurement and control device for intelligent transformer substation and system with cluster measurement and control device
CN105262210A (en) * 2015-09-21 2016-01-20 中国南方电网有限责任公司 System and method for analysis and early warning of substation network security

Also Published As

Publication number Publication date
CN109391038A (en) 2019-02-26

Similar Documents

Publication Publication Date Title
CN109391038B (en) Deployment method of intelligent substation interval measurement and control function
US11307943B2 (en) Disaster recovery deployment method, apparatus, and system
US20170048123A1 (en) System for controlling switch devices, and device and method for controlling system configuration
US7716373B2 (en) Method, apparatus, and computer product for updating software
CN105743995A (en) Transplantable high-available container cluster deploying and managing system and method
CN106843170B (en) Method for scheduling task based on token
CN106293934B (en) A kind of cluster system management optimization method and platform
CN110933137B (en) Data synchronization method, system, equipment and readable storage medium
CN111290834A (en) Method, device and equipment for realizing high availability of service based on cloud management platform
CN102810908B (en) Communication base station and electric power connection monitoring method and communication base station and electric power system
CN105553741A (en) Automatic deployment method for application system based on cloud computing
US20050216910A1 (en) Increasing fault-tolerance and minimizing network bandwidth requirements in software installation modules
CN111799805B (en) 5G technology-based virtual power plant regulation and control method and device
CN111147565B (en) Cluster node control method, device and equipment and readable storage medium
CN114070739B (en) Cluster deployment method, device, equipment and computer readable storage medium
CN112437129B (en) Cluster management method and cluster management device
CN110086726A (en) A method of automatically switching Kubernetes host node
CN103905337A (en) Network resource processing device, method and system
CN113835834A (en) K8S container cluster-based computing node capacity expansion method and system
WO2022267646A1 (en) Pod deployment method and apparatus
CN114338670B (en) Edge cloud platform and network-connected traffic three-level cloud control platform with same
CN114721827A (en) Data processing method and device
CN112653571B (en) Mixed scheduling method based on virtual machine and container
CN113342466A (en) Kubernetes cloud native container-based variable starting resource limitation method and system
Jang et al. Enhancing Node Fault Tolerance through High-Availability Clusters in Kubernetes

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant