CN109390981A - The sending end power grid Unit Combination progress control method of new energy participation electric quantity balancing - Google Patents

The sending end power grid Unit Combination progress control method of new energy participation electric quantity balancing Download PDF

Info

Publication number
CN109390981A
CN109390981A CN201811459376.3A CN201811459376A CN109390981A CN 109390981 A CN109390981 A CN 109390981A CN 201811459376 A CN201811459376 A CN 201811459376A CN 109390981 A CN109390981 A CN 109390981A
Authority
CN
China
Prior art keywords
unit
new energy
steps
thening follow
load
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811459376.3A
Other languages
Chinese (zh)
Other versions
CN109390981B (en
Inventor
周全
路亮
魏明奎
江栗
蔡绍荣
柳璐
陈佩华
程浩忠
袁杨
张程铭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Jiaotong University
State Grid Corp of China SGCC
Southwest Branch of State Grid Corp
Original Assignee
Shanghai Jiaotong University
State Grid Corp of China SGCC
Southwest Branch of State Grid Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jiaotong University, State Grid Corp of China SGCC, Southwest Branch of State Grid Corp filed Critical Shanghai Jiaotong University
Priority to CN201811459376.3A priority Critical patent/CN109390981B/en
Publication of CN109390981A publication Critical patent/CN109390981A/en
Application granted granted Critical
Publication of CN109390981B publication Critical patent/CN109390981B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/46Controlling of the sharing of output between the generators, converters, or transformers

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Control Of Eletrric Generators (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention relates to the sending end power grid Unit Combination progress control methods that a kind of new energy participates in electric quantity balancing, comprising the following steps: 1) obtains the booting prioritised list of prediction the power output confidence interval and conventional electric power generation unit of new energy;2) it introduces spare unit pond and abandons motor group pond, while considering that new energy participates in balance, spinning reserve constraint and minimum start-off time constraints, control set state;3) set state obtained using step 2) is adjusted particle position based on the power-balance for considering unit climbing rate, obtains the optimal output of particle swarm algorithm as the input of particle swarm algorithm, controls Unit Combination operating status according to the optimal output.Compared with prior art, the present invention has many advantages, such as to improve the economy of system operation.

Description

The sending end power grid Unit Combination progress control method of new energy participation electric quantity balancing
Technical field
The present invention relates to electric system automation fields, and the sending end of electric quantity balancing is participated in more particularly, to a kind of new energy Power grid Unit Combination progress control method.
Background technique
Optimization of Unit Commitment By Improved (UC problem) generally refers to meeting system load demand, spare capacity and minimum start-stop time Etc. determine that the start and stop of each unit of day part in research cycle and power output arrange under constraint conditions, keep total power generation expense minimum, number Learning model is substantially higher-dimension, discrete, non-convex mixed-integer nonlinear programming model, is not easy to obtain theoretic optimal solution.With The expansion of system scale, the optimality of the increase of model solution spatial complex degree, model solution time and solution decline therewith, have Therefore a little methods can not even acquire feasible solution.Reasonably optimizing Unit Combination can bring distinct economic to electric system, right Bulk power grid economy reliability is promoted to be of great significance.
Domestic scholars have carried out extensive research to UC problem, propose many method for solving: priority method, Dynamic Programming Method, Lagrangian Relaxation, intelligent optimization algorithm, mixed integer programming approach etc..Li Jinghua, Lan Fei " protecting electrical power system with Control " " the extension priority method for being suitable for Optimization of Unit Commitment By Improved " that delivers on (2010,38 (02): 1-7) define unit Utilization coefficient UUR (Unit Utilization Ratio) optimization unit priority, and introduce state modulator unit group It closes the scale of neighborhood and taking strategy to be adjusted Unit Combination makes it meet all constraints.Zhai Junyi, Ren Jianwen, Lee are whole etc. " a kind of dimensionality reduction solution unit delivered on " North China Electric Power University's journal (natural science edition) " (2016,43 (01): 32-38) The dual particle swarm optimization algorithm of combinatorial problem " by the optimization of entire dispatching cycle be converted into each scheduling instance successively, It is separately optimized, i.e., will be converted into the optimization to row vector to the optimization of matrix, reduce and solve dimension.In conjunction with discrete and continuous particle Group's (particle swarm optimization, PSO) algorithm, respectively obtains current scheduling moment optimal Unit Combination shape State and corresponding optimum load dispatch.Deng Jun, Wei Hua, Li Jinghua etc. " Proceedings of the CSEE " (2015,35 (11): " a kind of Unit Combination mixed integer linear programming model containing four class 0-1 variables " delivered on 2770-2778) is auxiliary by introducing Help variable indicate cold start, propose a kind of linear expression of starting expense, at the same enhance MILP model terseness and Compactedness;It is limited using Ramp Rate and minimum runing time, proposes new unit output constraint expression, greatly have compressed machine The feasible zone of group power output, further enhances compactedness, improves model solution efficiency.Zhang Shu, Hu Zechun, Song Yonghua etc. exist " the security constraint based on network loss factor iteration delivered on " Proceedings of the CSEE " (2012,32 (07): 76-82+194) Unit Combination algorithm " the SCUC problem for fixing the network loss factor is first solved in each iteration, the operating status of unit is acquired, is then carried out AC power flow calculates, and the network loss factor is updated, into next iteration.For the network loss factor oscillation problem being likely to occur, propose The method that SCUC and economic load dispatching combine selects the corresponding lesser Unit Commitment state of cost of electricity-generating, it is excellent to carry out economic load dispatching Change and the network loss factor iterates to calculate, until algorithmic statement.In document above, priority method solves extensive UC problem precision not Height, intelligent algorithm is computationally intensive, solving speed is slow, easily limits into locally optimal solution, and mixed integer programming class Method Modeling is complicated, counts Calculation amount is big, convergence is slow, it is also possible to cause solver that can not acquire feasible solution.In patent, Zhang Jingrui, Lin Shuan, the hair such as Qiu Weixia The patent of invention " the Unit Commitment optimization method for considering ramping rate constraints " of bright people's application is in discrete particle cluster frame Difference acceleration technique is introduced in frame to improve solving speed, infeasible individual is repaired to improve feasibility, and using with The equivalent λ iterative method of machine carries out sharing of load and handles ramping rate constraints.The inventors such as Cai Qiuna, Liu Sijie, Yang Yun application Patent of invention " a method of Unit Combination is arranged based on power plant sequence coefficient " using sequence coefficient, and consider that electric power is flat Weighing apparatus, security constraint arrange Unit Combination by day, and Unit Combination can be arranged for power dispatching station, carries out monthly electricity regulation. A kind of patent of invention " energy coordination optimization Unit Combination method " of the inventors such as Liu Fang, Pan Yi, Zhou Jingyang application considers wind-powered electricity generation Power output confidence interval, the operating parameter and operation characteristic of the operating parameter of fired power generating unit and consumption coal characteristic and pump-storage generator Mixed integer non-linear programming problems model is established to be solved.Li Lili, fourth is proper, the inventors such as Geng Jian application patent of invention " in Long-term Unit Combination optimization method " it examines and is established according to the electric network model of actual electric network with unit generation amount and Expected energy deviation most The small medium-term and long-term security constraint Unit Combination model for target;Unit is calculated within dispatching cycle using mixed integer programming approach Then start and stop state, rate of load condensate and the active power output of peak load period in each day pass through the iteration of optimisation technique and Security Checking, It is final to obtain the medium-term and long-term Unit Combination scheme for meeting power grid security.The above patent all only with single priority method or Person's intelligent algorithm, or call directly mature Mathematical Planning solver and solve UC problem, thus above-mentioned class cannot be solved very well Type method is applied to existing computational efficiency low inherent shortcoming when extensive UC problem.Therefore the Unit Combination of large scale system The efficient solution of problem is worth further investigation.
Summary of the invention
It is an object of the present invention to overcome the above-mentioned drawbacks of the prior art and provide a kind of new energy to participate in electricity Measure the sending end power grid Unit Combination progress control method of balance.
The purpose of the present invention can be achieved through the following technical solutions:
A kind of new energy participates in the sending end power grid Unit Combination progress control method of electric quantity balancing, comprising the following steps:
1) the booting prioritised list of prediction the power output confidence interval and conventional electric power generation unit of new energy is obtained;
2) it introduces spare unit pond and abandons motor group pond, while considering that new energy participates in balance, spinning reserve constraint and most Small start-off time constraints control set state;
3) set state obtained using step 2) is flat based on the power for considering unit climbing rate as the input of particle swarm algorithm Weighing apparatus adjustment particle position, obtains the optimal output of particle swarm algorithm, controls Unit Combination operating status according to the optimal output.
Further, the conventional electric power generation unit includes fired power generating unit and Hydropower Unit, is obtained based on sequence reference factor The booting prioritised list of fired power generating unit, the sequence reference factor include adjustable generating set coal consumption index factor, starting Cost reference factor and the power output upper limit reference factor obtain different fire according to the difference of the parameter selection of sequence reference factor Motor group booting prioritised list;
The Hydropower Unit obtains corresponding booting prioritised list according to regulation performance.
Further, generating set booting priority is determined after respectively sequence reference factor is combined by following formula:
F=index1, i+index2, i+index3, i
In formula, index1, i、index2, i、index3, iRespectively press adjustable generating set coal consumption index factor, start-up cost The ranking of unit i after reference factor and the power output upper limit reference factor sort from small to large, f value is smaller, and corresponding unit more preferentially opens It is dynamic.
Further, the motor group pond of abandoning includes abandoning the Hydropower Unit of water and just in abandonment, the new energy of abandoning light Unit;
Spare unit pond includes the fired power generating unit for being currently at hot stand-by duty.
Further, the step 2) specifically includes the following steps:
A1) according to load prediction curve, judge whether subsequent period load prediction increment is positive, if so, thening follow the steps A2), if it is not, thening follow the steps a3);
A2) be based on the booting prioritised list, successively control abandon motor group pond, new energy unit, spare unit pond, Corresponding unit starting in fired power generating unit executes step a4 until meeting the growth of load and spinning reserve constraint);
A3 it) is based on the booting prioritised list, fired power generating unit is successively controlled, many years regulation Hydropower Unit, adjusts in year Hydropower Unit, season adjust Hydropower Unit, new energy unit, the corresponding unit adjusted in Hydropower Unit day and shut down, until meeting rotation Turn Reserve Constraint and load is reduced, execute step a4);
A4) judge whether that the set state of all periods controls to finish, if so, thening follow the steps 3), if it is not, then returning Step a1).
Further, the step a2) it specifically includes:
201) under channel constraints, unit starting is selected from abandoning in motor group pond;
202) judge whether meet the growth of load and spinning reserve constraint after abandoning the corresponding unit starting in motor group pond, if so, Then follow the steps a4), if it is not, thening follow the steps 203);
203) under channel constraints, new energy unit is started according to prediction power output confidence interval;
204) it whether is able to satisfy the growth of load and spinning reserve constraint after judging new energy unit starting, if so, executing Step a4), if it is not, thening follow the steps 205);
205) fired power generating unit starting is selected from spare unit pond;
206) it whether is able to satisfy the growth of load and spinning reserve constraint after judging fired power generating unit starting, if so, executing step Rapid a4), if it is not, thening follow the steps 207);
207) limited load control is carried out, and starts fired power generating unit, increases the unit quantity in spare unit pond, executes step a4)。
Further, the step a3) it specifically includes:
301) after insignificant support fired power generating unit is shut down in judgement, spinning reserve constraint whether is met in 24 hours and load subtracts It is few, if so, step 302) is executed after shutting down qualified unit, if it is not, thening follow the steps 302);
302) after many years regulation Hydropower Unit is shut down in judgement, spinning reserve constraint whether is met in 3 hours and load is reduced, If so, step 303) is executed after shutting down qualified unit, if it is not, thening follow the steps 303);
303) after year adjusting Hydropower Unit is shut down in judgement, spinning reserve constraint whether is met in 3 hours and load is reduced, if It is execution step 304) after then shutting down qualified unit, if it is not, thening follow the steps 304);
304) after season adjusting Hydropower Unit is shut down in judgement, spinning reserve constraint whether is met in 3 hours and load is reduced, if It is execution step 305) after then shutting down qualified unit, if it is not, thening follow the steps 305);
305) after new energy unit is shut down in judgement, if meet load and reduce, if so, after shutting down qualified unit Step 306) is executed, if it is not, thening follow the steps 306);
306) after day adjusting Hydropower Unit is shut down in judgement, if meet load and reduce, if so, shutting down qualified machine Step a4 is executed after group), if it is not, thening follow the steps a4).
Further, the objective function that the particle swarm algorithm uses are as follows:
Wherein, number of segment when T is total, Nh、Ns、NxIt is thermoelectricity, water power, new energy unit number, PH respectivelyI, tIt is fired power generating unit i In the power output of period t, PSI, tIt is power output of the Hydropower Unit i in period t, PXI, tIt is power output of the new energy unit i in period t, uI, t It is start and stop state of the unit i in period t, is indicated with 0 or 1, FHI, t(PHI, t) it is operating cost of the fired power generating unit i in period t, STiIt is the start-up and shut-down costs of fired power generating unit i, FSI, t(PSI, t) it is operating cost of the Hydropower Unit i in period t, FXI, t(PXI, t) be Operating cost of the new energy unit i in period t;
The constraint condition of use includes system power Constraints of Equilibrium, the constraint of unit output bound, spinning reserve constraint, machine Group Climing constant and startup and shutdown of units time-constrain.
It is further, described based on the power-balance adjustment particle position for considering unit climbing rate specifically:
221) initialization period t=1;
222) all unit output summation SUM of calculation interval ttAnd the power output range PH (i) and PL (i) of each unit i, PH (i) is highest power output, and PL (i) is minimum output;
223) a booting list is established, which, which is stored with, is in the unit of open state in period t;
224) SUM is judged whether there ist< DtAnd count > 0, if so, thening follow the steps 225), if it is not, thening follow the steps 226), wherein DtIndicate that the workload demand of period t, count indicate unit number in booting list;
225) unit i is chosen from the booting list, enables PI, t=PH (i), recalculates SUMt, judge whether there is SUMt< Dt, if so, thening follow the steps 226), if it is not, then deleting unit i from booting list, update count, return step 224);
226) booting list is re-established, count is updated;
227) SUM is judged whether there ist> DtAnd count > 0, if so, thening follow the steps 228), if it is not, thening follow the steps 229);
228) unit i is chosen from the booting list, enables PI, t=PL (i), recalculates SUMt, judge whether there is SUMt< Dt, if so, executing step 229), if it is not, then deleting unit i from booting list, update count;
If 229) SUM at this timet≠DtAnd count > 0, then enable PI, t=min { PI, t-(SUMt-Dt), PH (i) }, otherwise, PI, t=max { PI, t, PL (i) };
230) step 222) -229 is repeated), until t=T.
Further, the power output range PH (i) and PL (i) are obtained in the following manner:
To each unit i in each period t, if uit=1, ui(t-1)=0, then PH (i)=min { PI, max, RUi, PL (i) =max { PI, min, RDi};
If uit=1, ui(t-1)=1, then PH (i)=min { PI, m α x, PI, t-1+RUi, PL (i)=max { PI, min, PI, t-1- RDi};
If t=1, PH (i)=PI, max, PL (i)=PI, min
If uit=1, ui(t+1)=0, then PH (i)=PL (i)=PI, min
If uit=1, ui(t+1)=1, then PH (i)=min { PH (i), PI, t+1-RDi, PL (i)=max { PL (i), PI, t+1- RUi};
Wherein, RDi、RUiIndicate the upper and lower creep speed of unit.
Compared with prior art, the present invention have with following the utility model has the advantages that
1, the present invention considers that the new energy such as wind-powered electricity generation, solar energy participate in systematic electricity electric quantity balancing, control as normal power supplies Precision is higher.
2, abandoning motor group pond and spare unit pond, optimization system balance of electric power and ener process, on the one hand, so that the mistake are utilized Journey more meets reality, on the other hand, improves the economy of system operation.
3, according to Hydropower Unit regulation performance, fired power generating unit energy consumption index, priority row is carried out to conventional electric power generation unit Sequence.
4, single for tradition PL method sequence index, it is unable to the deficiency of thoroughly evaluating unit operating cost, present invention introduces Adjustable generating set coal consumption, unit maximum output, three indexs of unit starting cost, the economy for reflecting generating set comprehensively, The economy of Unit Commitment plan can be improved in improved Unit Economic type sequence index, saves coal-fired cost.
5, the present invention carries out prioritizing to conventional electric power generation unit, system economical operation type can be improved, energy conservation subtracts Row.
6, it first arranges Unit Commitment to meet spinning reserve different from traditional PL method, then adjusts set state and meet minimum start and stop Time, the present invention consider the two constraints simultaneously, the preferential unlatching lesser unit of operating cost is better achieved.
7, for the more difficult deficiency for meeting this equality constraint of power-balance constraint of original PSO, a kind of consideration unit is proposed The power-balance adjustable strategies of climbing rate guarantee the multifarious of particle while avoiding rapidly converging to locally optimal solution, improve The quality of last solution.
8, the two-phase optimization method that the present invention uses improves large scale system Unit Combination computational efficiency and calculates essence Degree.
Detailed description of the invention
Fig. 1 is flow diagram of the invention;
Fig. 2 is that power-balance constraint of the invention adjusts process schematic.
Specific embodiment
The present invention is described in detail with specific embodiment below in conjunction with the accompanying drawings.The present embodiment is with technical solution of the present invention Premised on implemented, the detailed implementation method and specific operation process are given, but protection scope of the present invention is not limited to Following embodiments.
The present invention provides the sending end power grid Unit Combination progress control method that a kind of new energy participates in electric quantity balancing, including with Lower step:
1) annual load curve, annual wind-powered electricity generation, photovoltaic power output probabilistic forecasting confidecne curve, fired power generating unit coal consumption system are obtained Number, minimum open, the basic datas such as downtime, upper and lower climbing rate, and then obtains the prediction power output confidence interval and biography of new energy It is flat to participate in systematic electricity electricity with new energy power output prediction confidence intervals lower limit for the booting prioritised list of system generating set Weighing apparatus;
2) it introduces spare unit pond and abandons motor group pond, while considering that new energy participates in balance, spinning reserve constraint and most Small start-off time constraints control set state, optimization system balance of electric power and ener process;
3) set state obtained using step 2) is flat based on the power for considering unit climbing rate as the input of particle swarm algorithm Weighing apparatus adjustment particle position, obtains the optimal output of particle swarm algorithm, controls Unit Combination operating status according to the optimal output.
New energy includes wind-powered electricity generation, solar energy etc., and the 10%-20% of new energy installed capacity is generally taken to contribute as new energy Confidence capacity can take at night 0 for photovoltaic power generation to take 10% daytime.
Conventional electric power generation unit includes fired power generating unit and Hydropower Unit.It, can be according to fired power generating unit energy consumption for fired power generating unit Index obtains booting prioritised list.When considering thermoelectricity booting tab sequential, the important support node fire of power grid security is ensured The fired power generating unit priority of motor group highest priority, energy consumption bottom is high.
The specific power coal consumption of thermoelectricity generating set in different power output ranges is not identical, thus may cause unit Priority changes with the change of power output range.Therefore, the present invention is reflection unit coal consumption situation under different power outputs, It is as follows to introduce adjustable generating set coal consumption index.
[0,1] α ∈ in formula, referred to as power output Dynamic gene, according to the f under different α values1, i, available generating set The coal consumption for power generation ordering scenario under different power outputs.The adjustment of generating set state is carried out accordingly, can be obtained closer to optimal solution Unit Commitment plan.The value of α is adjusted, available different unit priority repeats the above steps, to obtain one group Different initial solutions.
In addition, the maximum unit of start-up cost that should give priority in arranging for is switched in long duration and runs, is frequently opened, shut down with reduction Increase total system start-up cost, therefore introduces second sequence reference factor, start-up cost reference factor:
Finally, the power output upper limit highest and multiple electricity of economy preferably unit should allow, make with load variations and the machine of start and stop Group quantity is reduced, and is further reduced start-up cost, therefore introduces third sequence reference factor, the upper limit reference factor of contributing:
Three sequence reference factors of unit are smaller, more preferential starting.Notice f2, i> 1, f3, i> 1, f1, i< 1, directly Three is added to be ranked up and may cause total sequence index by f2, i、f3, iIt is leading, it is improved using following sequence index:
F=index1, i+index2, i+index3, i
In formula, index1, i、index2, i、index3, iRespectively press adjustable generating set coal consumption index factor, start-up cost The ranking of unit i after reference factor and the power output upper limit reference factor sort from small to large, f value is smaller, and corresponding unit more preferentially opens It is dynamic.
Water power power up sequences table is formed according to the regulation performance of water power for Hydropower Unit.According to Optimized Operation, save The principle of the energy before the water power of general without regulation comes most, is adjusted followed by day, season is adjusted, year is adjusted, many years tune Section.For the power station with reservoir with regulating power, generating capacity is removed to be restricted by Hydropower Unit technical factor itself Except, also by the artificial restraint of water management department, therefore, when considering that power output and climbing rate constrain, it should by this Some factors are taken into account, and smaller section is taken.
As shown in Figure 1, above-mentioned Unit Combination progress control method can specifically describe are as follows:
Step S101: the new energy such as wind-powered electricity generation and solar energy prediction power output confidence interval curves are obtained.
Step S102: according to the regulation performance of water power, water power power up sequences table is formed.
Step S103: according to fired power generating unit energy consumption index, fired power generating unit booting list is formed.
Step S104: do you according to load prediction curve, judge that subsequent period load increment is positive? if so, turning next Step, if not, going to step S112.
Step S105: under channel constraints, unit starting is selected from motor group pond is abandoned.It is logical for what is currently taken Road, the abandoning motor group portion below channel participate in this starting operation.
Abandon motor group pond: record is currently at the unit id for abandoning electricity condition, and abandoning motor group mainly includes abandoning the water of water Motor group and just abandonment, abandon light new energy unit.
Step S106: after abandoning motor group pond unit starting, if meet load growth and revolve standby capacity requirement? if it is not, turning In next step, if so, going to step S118.
Step S107: under channel constraints, start clean energy resource unit.
Step S108: after judging clean energy resource unit starting, if meet load growth and revolve standby capacity requirement? if it is not, Turn in next step, if so, going to step S118.
Step S109: from spare unit pond, selecting fired power generating unit starting, is wanted with meeting load growth and revolving standby capacity It asks.
Spare unit pond: record is currently at the fired power generating unit id of hot stand-by duty, the second level as spinning reserve unit It is spare, according to spinning reserve capacity demand and load growth situation, the Dynamic Maintenance unit pond, safeguards system safety and stability economy Operation.
Step S110: do you judge to meet load growth demand after the fired power generating unit in spare unit pond all starts? if it is not, Turn in next step, if so, going to step S118.
Step S111: it is current it is all start unit starting after, be unable to satisfy load growth needs, then carry out limited load Control, and start fired power generating unit, increase the unit quantity in spare unit pond.
Step S112: after insignificant support fired power generating unit is shut down in judgement, in 24 hours, if meet system rotation it is standby constrain and Is load reduced? if so, shutting down qualified unit, S113 is gone to step, if it is not, directly executing step S113.
Step S113: after many years regulation Hydropower Unit is shut down in judgement, in 3 hours, if meet the standby constraint of system rotation and bear Is lotus reduced? if so, shutting down qualified unit, S114 is gone to step, if it is not, directly executing step S114.
Step S114: after year adjusting Hydropower Unit is shut down in judgement, in 3 hours, if meet the standby constraint of system rotation and load Reduce? if so, shutting down qualified unit, S115 is gone to step, if it is not, directly executing step S115.
Step S115: after season adjusting Hydropower Unit is shut down in judgement, in 3 hours, if meet the standby constraint of system rotation and load Reduce? if so, shutting down qualified unit, S116 is gone to step, if it is not, directly executing step S116.
Step S116: after new energy unit is shut down in judgement, if meet the standby constraint of system rotation and load is reduced? if so, closing Stop qualified unit, go to step S117, if it is not, directly executing step S117.
Step S117: after day adjusting Hydropower Unit is shut down in judgement, if meet the standby constraint of system rotation and load is reduced? if It is to shut down qualified unit, goes to step S118, if it is not, directly executes step S118.
Step S118: do you judge that all periods arrange to finish? if so, turning in next step, if it is not, going to step 2.
Step S119: it is input that Unit Commitment, which is arranged as Optimized Operation particle swarm algorithm,.
Step S120: initialization the number of iterations iter=1 creates initial population, and adjust particle position, it is made to meet function Rate Constraints of Equilibrium.
Step S121: particle rapidity and position are updated.
Does step S122:iter=iter+1 judge iter < itermax? if so, turning to terminate, if it is not, turning previous step.
In above-mentioned steps S109, when selecting fired power generating unit starting from spare unit pond, according to minimum startup-shutdown time tune Whole initial Unit Commitment plan.State according to three classes constraint adjustment generating set: the original state constraint of generating set, power generation The power constraint and unit minimum of machine open/downtime limitation.
It is as follows that generating set state adjusts process:
1. the value of α is arranged, prioritised list is formed.
2. load increases in period t, determine that needing successively to open how many units is just able to satisfy according to priority list Workload demand adds spinning reserve.
3. calculating since period t, " the necessary available machine time " of unit i, M_ON is usediIt indicates.M_ONiThat is load is from period t It is reduced to afterwards and does not need unit i boot system and be still able to satisfy spinning reserve to constrain passed through when number of segment.If M_ONi< TOi, then Continue that unit i booting is kept to meet minimum available machine time constraint until it, conversely, then entering in next step.
4. load reduces in period t, judgement is shut down on preferred list after unit i, and it is standby whether system is able to satisfy rotation With constraint.If it is not, unit i booting is kept, conversely, into 5. judging whether to shut down unit i.
5. calculating since period t, " necessity shuts down the time " of unit i uses M_OFFiIt indicates.M_OFFiI.e. load from when Increase to after section t to needing unit i boot system to be just able to satisfy the passed through when number of segment of spinning reserve constraint.If M_OFFi< TSi, then still need to that unit i is kept to open, because as load increases, if being not turned on unit i spinning reserve will be unable to meet.If M_ OFFi≥TSi, and unit i has reached the minimum available machine time, then shuts down unit i, into subsequent period.
6. detection unit first initially shuts down whether the time is less than its minimum in unit original state constraint adjustment member Shut down the time, if so, and the unit need to be switched on (2. calculating through step), then keep the unit to shut down, detection is preferential suitable Next unit on sequence table.If this unit be initially powered up the time less than its minimum available machine time or its initially shut down the time and be greater than Its minimum downtime, then open the unit.This step is repeated to all units until the whole detection of its original state finishes.
7. adjusting the value of α, available different unit priority repeats the above steps, to obtain one group of difference Initial solution.
The objective function that the particle swarm algorithm uses are as follows:
Wherein, number of segment when T is total, Nh、Ns、NxIt is thermoelectricity, water power, new energy unit number, P respectivelyHi, tIt is fired power generating unit i In the power output of period t, PSI, tIt is power output of the Hydropower Unit i in period t, PXI, tIt is power output of the new energy unit i in period t, uI, t It is start and stop state of the unit i in period t, is indicated with 0 or 1, FHI, t(PHI, t) it is operating cost of the fired power generating unit i in period t, STiIt is the start-up and shut-down costs of fired power generating unit i, FSI, t(PSI, t) it is operating cost of the Hydropower Unit i in period t, FXI, t(PXI, t) be Operating cost of the new energy unit i in period t.
A in formulai、bi、ciFor the coal consumption coefficient of unit i.SHi、SCiIt is thermal starting, the cold start-up expense of unit i respectively.TSi The minimum downtime of unit i, TI, offIt is the time of unit i persistently shut down, TCiIt is the cold start-up time of unit i.
The constraint condition of use includes system power Constraints of Equilibrium, the constraint of unit output bound, spinning reserve constraint, machine Group Climing constant and startup and shutdown of units time-constrain.
System power Constraints of Equilibrium:
In formula, PHI, tIt is power output of the fired power generating unit i in period t, PSI, tIt is power output of the Hydropower Unit i in period t, PXI, tIt is Power output of the new energy unit i in period t, uI, tIt is start and stop state of the unit i in period t, is indicated with 0 or 1, DtIt is the negative of period t Lotus demand.
The constraint of unit output bound:
PHI, min≤PHI, t≤PHI, max
PSI, min≤PSI, t≤PSI, max
PXI, min≤PXI, t≤PXI, max
PH in formulaI, max、PHI, minIt is fired power generating unit i minimax technology power output, PSI, max、PSI, minIt is Hydropower Unit technology Power output bound, PXI, max、PXI, minIt is new energy unit output bound.
Spinning reserve constraint
In formula, uI, tIt is start and stop state of the unit i in period t, is indicated with 0 or 1, is power output of the fired power generating unit i in period t, PSI, tIt is power output of the Hydropower Unit i in period t, PXT, minIt is new energy in period t prediction power output lower limit of confidence interval, generally may be used Take 90% confidence interval, Nh、NsIt is thermoelectricity, water power group number, P respectivelytIt is total load of the system in the t period, RtSystem when Spinning reserve needed for section t.
Unit ramp loss
-PHI, down≤PHI, t-PHI, t-1≤PHI, up
-PSI, down≤PSI, t-PSI, t-1≤PSI, up
-PXI, down≤PXI, t-PXI, t-1≤PXI, up
In formula, PHI, down、PHI, upIt is the upper and lower climbing rate of fired power generating unit, PSI, down、PSI, upIt is the upper and lower climbing of Hydropower Unit Rate, PXI, down、PXI, upIt is the upper and lower climbing rate of new energy unit, PHI, t、PSI, t、PXI, tIt is respectively i-th thermoelectricity, water power, new Power output of the energy unit in the t period.
Startup and shutdown of units time-constrain
TI, on≥TOi
TI, off≥TSi
T in formulaI, onIt is open state duration, the TO of unit iiIt is the minimum available machine time of unit i.TSiUnit i's Minimum downtime, TI, offIt is the time of unit i persistently shut down.
The power-balance constraint of system is an equality constraint, and using the more difficult satisfaction of original PSO, the present invention proposes consideration machine The power-balance adjustable strategies of group climbing rate, guarantee the multifarious of particle while avoiding rapidly converging to locally optimal solution.For This, the present invention introduces the array of two constraint unit output ranges: PH (i) and PL (i), PH (i) are for highest power output, PL (i) Minimum output.
PH (i) and PL (i) are obtained in the following manner:
To each unit i in each period t, if uit=1, ui(t-1)=0, then PH (i)=min { PI, max, RUi, PL (i) =max { PI, min, RDi};
If uit=1, ui(t-1)=1, then PH (i)=min { PI, m α x, PI, t-1+RUi, PL (i)=max { PI, min, PI, t-1- RDi};
If t=1, PH (i)=PI, max, PL (i)=PI, min
If uit=1, ui(t+1)=0, then PH (i)=PL (i)=PI, min
If uit=1, ui(t+1)=1, then PH (i)=min { PH (i), PI, t+1-RDi, PL (i)=max { PL (i), PI, t+1- RUi}。
It is specific as shown in Figure 2 based on the power-balance adjustment particle position for considering unit climbing rate, comprising:
Step S201, initialization period t=1;
All unit output summation SUM of step S202, calculation interval ttAnd the power output range PH (i) of each unit i and PL (i),;
Step S203 establishes a booting list, which, which is stored with, is in the unit of open state in period t;
Step S204, judges whether there is SUMt< DtAnd count > 0, if so, S205 is thened follow the steps, if it is not, then holding Row step S206, wherein DtIndicate that the workload demand of period t, count indicate unit number in booting list;
Step S205 chooses unit i from the booting list, enables PI, t=PH (i), recalculates SUMt, judge whether There are SUMt< Dt, if so, thening follow the steps S206, if it is not, then deleting unit i from booting list, count is updated, is returned Step S204;
Step S206 re-establishes booting list, updates count;
Step S207, judges whether there is SUMt> DtAnd count > 0, if so, S208 is thened follow the steps, if it is not, then holding Row step S209;
Step S208 chooses unit i from the booting list, enables PI, t=PL (i), recalculates SUMt, judge whether There are SUMt< Dt, if so, executing step S209, if it is not, then deleting unit i from booting list, update count;
Step S209, if SUM at this timet≠DtAnd count > 0, then enable PI, t=min { PI, t-(SUMt-Dt), PH (i) }, it is no Then, PI, t=max { PI, t, PL (i) };
Step S210 judges whether there is t < T, if so, t=t+1, return step S202, if it is not, then terminating.
In particle swarm algorithm, particle position and speed update calculation formula are as follows:
W is inertia weight parameter in formula, for the ability of searching optimum of control algolithm, c1And c2It is accelerated factor.
The preferred embodiment of the present invention has been described in detail above.It should be appreciated that those skilled in the art without It needs creative work according to the present invention can conceive and makes many modifications and variations.Therefore, all technologies in the art Personnel are available by logical analysis, reasoning, or a limited experiment on the basis of existing technology under this invention's idea Technical solution, all should be within the scope of protection determined by the claims.

Claims (10)

1. the sending end power grid Unit Combination progress control method that a kind of new energy participates in electric quantity balancing, which is characterized in that including with Lower step:
1) the booting prioritised list of prediction the power output confidence interval and conventional electric power generation unit of new energy is obtained;
2) it introduces spare unit pond and abandons motor group pond, while considering that new energy participates in balance, spinning reserve constraint and minimum and opens Stop time-constrain, controls set state;
3) set state obtained using step 2) is the input of particle swarm algorithm, based on the power-balance tune for considering unit climbing rate Whole particle position obtains the optimal output of particle swarm algorithm, controls Unit Combination operating status according to the optimal output.
2. new energy according to claim 1 participates in the sending end power grid Unit Combination progress control method of electric quantity balancing, It is characterized in that, the conventional electric power generation unit includes fired power generating unit and Hydropower Unit, obtains fired power generating unit based on sequence reference factor Booting prioritised list, the sequence reference factor include adjustable generating set coal consumption index factor, start-up cost reference The factor and the power output upper limit reference factor obtain different fired power generating units and open according to the difference of the parameter selection of sequence reference factor Machine prioritised list;
The Hydropower Unit obtains corresponding booting prioritised list according to regulation performance.
3. new energy according to claim 2 participates in the sending end power grid Unit Combination progress control method of electric quantity balancing, It is characterized in that, each reference factor that sorts determines generating set booting priority after combining by following formula:
F=index1, i+index2, i+index3, i
In formula, index1, i、index2, i、index3, iRespectively referred to by adjustable generating set coal consumption index factor, start-up cost The ranking of unit i after the factor and the power output upper limit reference factor sort from small to large, f value is smaller, the corresponding more preferential starting of unit.
4. new energy according to claim 1 participates in the sending end power grid Unit Combination progress control method of electric quantity balancing, It is characterized in that, the motor group pond of abandoning includes abandoning the Hydropower Unit of water and just in abandonment, the new energy unit of abandoning light;
Spare unit pond includes the fired power generating unit for being currently at hot stand-by duty.
5. new energy according to claim 1 participates in the sending end power grid Unit Combination progress control method of electric quantity balancing, Be characterized in that, the step 2) specifically includes the following steps:
A1) according to load prediction curve, judge whether subsequent period load prediction increment is positive, if so, thening follow the steps a2), If it is not, thening follow the steps a3);
A2 it) is based on the booting prioritised list, successively motor group pond, new energy unit, spare unit pond, thermoelectricity are abandoned in control Corresponding unit starting in unit executes step a4 until meeting the growth of load and spinning reserve constraint);
A3 it) is based on the booting prioritised list, fired power generating unit is successively controlled, many years regulation Hydropower Unit, adjusts water power in year Unit, season adjust Hydropower Unit, new energy unit, the corresponding unit adjusted in Hydropower Unit day and shut down, until it is standby to meet rotation It is reduced with constraint and load, executes step a4);
A4) judge whether that the set state of all periods controls to finish, if so, thening follow the steps 3), if it is not, then return step a1)。
6. new energy according to claim 5 participates in the sending end power grid Unit Combination progress control method of electric quantity balancing, It is characterized in that, the step a2) it specifically includes:
201) under channel constraints, unit starting is selected from abandoning in motor group pond;
202) judge whether meet the growth of load and spinning reserve constraint after abandoning the corresponding unit starting in motor group pond, if so, holding Row step a4), if it is not, thening follow the steps 203);
203) under channel constraints, new energy unit is started according to prediction power output confidence interval;
204) it whether is able to satisfy the growth of load and spinning reserve constraint after judging new energy unit starting, if so, thening follow the steps A4), if it is not, thening follow the steps 205);
205) fired power generating unit starting is selected from spare unit pond;
206) it whether is able to satisfy the growth of load and spinning reserve constraint after judging fired power generating unit starting, if so, thening follow the steps A4), if it is not, thening follow the steps 207);
207) limited load control is carried out, and starts fired power generating unit, increases the unit quantity in spare unit pond, executes step a4).
7. new energy according to claim 5 participates in the sending end power grid Unit Combination progress control method of electric quantity balancing, It is characterized in that, the step a3) it specifically includes:
301) after insignificant support fired power generating unit is shut down in judgement, spinning reserve constraint whether is met in 24 hours and load is reduced, If so, step 302) is executed after shutting down qualified unit, if it is not, thening follow the steps 302);
302) after many years regulation Hydropower Unit is shut down in judgement, spinning reserve constraint whether is met in 3 hours and load is reduced, if It is execution step 303) after then shutting down qualified unit, if it is not, thening follow the steps 303);
303) after year adjusting Hydropower Unit is shut down in judgement, spinning reserve constraint whether is met in 3 hours and load is reduced, if so, Step 304) is executed after then shutting down qualified unit, if it is not, thening follow the steps 304);
304) after season adjusting Hydropower Unit is shut down in judgement, spinning reserve constraint whether is met in 3 hours and load is reduced, if so, Step 305) is executed after then shutting down qualified unit, if it is not, thening follow the steps 305);
305) after new energy unit is shut down in judgement, if meet load and reduce, if so, being executed after shutting down qualified unit Step 306), if it is not, thening follow the steps 306);
306) after day adjusting Hydropower Unit is shut down in judgement, if meet load and reduce, if so, after shutting down qualified unit Execute step a4), if it is not, thening follow the steps a4).
8. new energy according to claim 1 participates in the sending end power grid Unit Combination progress control method of electric quantity balancing, It is characterized in that, the objective function that the particle swarm algorithm uses are as follows:
Wherein, number of segment when T is total, Nh、Ns、NxIt is thermoelectricity, water power, new energy unit number, PH respectivelyI, tFired power generating unit i when The power output of section t, PSI, tIt is power output of the Hydropower Unit i in period t, PXI, tIt is power output of the new energy unit i in period t, uI, tIt is machine I is in the start and stop state of period t for group, is indicated with 0 or 1, FHI, t(PHI, t) it is operating cost of the fired power generating unit i in period t, STiIt is The start-up and shut-down costs of fired power generating unit i, FSI, t(PSI, t) it is operating cost of the Hydropower Unit i in period t, FXI, t(PXI, t) it is new energy Operating cost of the unit i in period t;
The constraint condition of use includes system power Constraints of Equilibrium, the constraint of unit output bound, spinning reserve constrains, unit is climbed Slope constraint and startup and shutdown of units time-constrain.
9. new energy according to claim 1 participates in the sending end power grid Unit Combination progress control method of electric quantity balancing, It is characterized in that, it is described based on the power-balance adjustment particle position for considering unit climbing rate specifically:
221) initialization period t=1;
222) all unit output summation SUM of calculation interval ttAnd the power output range PH (i) and PL (i) of each unit i, PH (i) For highest power output, PL (i) is minimum output;
223) a booting list is established, which, which is stored with, is in the unit of open state in period t;
224) SUM is judged whether there ist< DtAnd count > 0, if so, thening follow the steps 225), if it is not, thening follow the steps 226), wherein DtIndicate that the workload demand of period t, count indicate unit number in booting list;
225) unit i is chosen from the booting list, enables PI, t=PH (i), recalculates SUMt, judge whether there is SUMt< Dt, if so, thening follow the steps 226), if it is not, then deleting unit i from booting list, update count, return step 224);
226) booting list is re-established, count is updated;
227) SUM is judged whether there ist> DtAnd count > 0, if so, thening follow the steps 228), if it is not, thening follow the steps 229);
228) unit i is chosen from the booting list, enables PI, t=PL (i), recalculates SUMt, judge whether there is SUMt< Dt, if so, executing step 229), if it is not, then deleting unit i from booting list, update count;
If 229) SUM at this timet≠DtAnd count > 0, then enable PI, t=min { PI, t-(SUMt-Dt), PH (i) }, otherwise, PI, t= max{PI, t, PL (i) };
230) step 222) -229 is repeated), until t=T.
10. new energy according to claim 9 participates in the sending end power grid Unit Combination progress control method of electric quantity balancing, It is characterized in that, the power output range PH (i) and PL (i) are obtained in the following manner:
To each unit i in each period t, if uit=1, ui(t-1)=0, then PH (i)=min { PI, max, RUi, PL (i)=max {PI, min, RDi};
If uit=1, ui(t-1)=1, then PH (i)=min { PI, max, PI, t-1+RUi, PL (i)=max { PI, min, PI, t-1-RDi};
If t=1, PH (i)=PI, max, PL (i)=PI, min
If uit=1, ui(t+1)=0, then PH (i)=PL (i)=PI, min
If uit=1, ui(t+1)=1, then PH (i)=min { PH (i), PI, t+1-RDi, PL (i)=max { PL (i), PI, t+1-RUi};
Wherein, RDi、RUiIndicate the upper and lower creep speed of unit.
CN201811459376.3A 2018-11-30 2018-11-30 Combined operation control method for new energy participating in electric quantity balance of sending-end power grid unit Active CN109390981B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811459376.3A CN109390981B (en) 2018-11-30 2018-11-30 Combined operation control method for new energy participating in electric quantity balance of sending-end power grid unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811459376.3A CN109390981B (en) 2018-11-30 2018-11-30 Combined operation control method for new energy participating in electric quantity balance of sending-end power grid unit

Publications (2)

Publication Number Publication Date
CN109390981A true CN109390981A (en) 2019-02-26
CN109390981B CN109390981B (en) 2022-05-27

Family

ID=65430236

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811459376.3A Active CN109390981B (en) 2018-11-30 2018-11-30 Combined operation control method for new energy participating in electric quantity balance of sending-end power grid unit

Country Status (1)

Country Link
CN (1) CN109390981B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110266058A (en) * 2019-05-31 2019-09-20 国网山东省电力公司济南供电公司 A kind of modeling of the Unit Combination model based on range optimization and method for solving
CN110826773A (en) * 2019-10-17 2020-02-21 内蒙古电力(集团)有限责任公司电力调度控制分公司 Thermal power generating unit monthly power generation plan optimization method considering new energy access
CN112186734A (en) * 2020-08-20 2021-01-05 西安交通大学 Medium-and-long-term operation simulation method for power system, storage medium and computing equipment
CN114336777A (en) * 2021-11-29 2022-04-12 中国华能集团清洁能源技术研究院有限公司 Thermal power generating unit starting sequence determination method and system considering energy utilization sequence
CN115307274A (en) * 2022-10-12 2022-11-08 蘑菇物联技术(深圳)有限公司 Method, apparatus and storage medium for controlling host of air conditioning system
CN116488212A (en) * 2023-06-19 2023-07-25 长沙电机厂集团长瑞有限公司 Method and system for virtually controlling multiple motor groups to perform power energy storage configuration
CN116760111A (en) * 2023-08-23 2023-09-15 太原理工大学 Distributed energy access and electric energy storage control method, device, equipment and medium

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120310608A1 (en) * 2011-06-03 2012-12-06 Nikovski Daniel N Method for Scheduling Power Generators Based on Optimal Configurations and Approximate Dynamic Programming
CN103345663A (en) * 2013-07-18 2013-10-09 厦门大学 Combinatorial optimization method of electric power system set considering creep speed constraints
CN104978629A (en) * 2015-06-18 2015-10-14 广西电网有限责任公司 Optimal multi-type power supply complementary peak-adjusting mode and model thereof
CN104993524A (en) * 2015-07-17 2015-10-21 三峡大学 Wind power-containing electric system dynamic dispatching method based on improved discrete particle swarm optimization
CN105760959A (en) * 2016-02-24 2016-07-13 武汉大学 Unit commitment (UC) optimization method based on two-phase firefly encoding
CN108075494A (en) * 2016-11-10 2018-05-25 中国电力科学研究院 A kind of Unit Combination method a few days ago taken into account new energy consumption and performed with transaction

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120310608A1 (en) * 2011-06-03 2012-12-06 Nikovski Daniel N Method for Scheduling Power Generators Based on Optimal Configurations and Approximate Dynamic Programming
CN103345663A (en) * 2013-07-18 2013-10-09 厦门大学 Combinatorial optimization method of electric power system set considering creep speed constraints
CN104978629A (en) * 2015-06-18 2015-10-14 广西电网有限责任公司 Optimal multi-type power supply complementary peak-adjusting mode and model thereof
CN104993524A (en) * 2015-07-17 2015-10-21 三峡大学 Wind power-containing electric system dynamic dispatching method based on improved discrete particle swarm optimization
CN105760959A (en) * 2016-02-24 2016-07-13 武汉大学 Unit commitment (UC) optimization method based on two-phase firefly encoding
CN108075494A (en) * 2016-11-10 2018-05-25 中国电力科学研究院 A kind of Unit Combination method a few days ago taken into account new energy consumption and performed with transaction

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
ABDULLAH M. ELSAYED等: "A new priority list unit commitment method for large-scale power systems", 《2017 NINETEENTH INTERNATIONAL MIDDLE EAST POWER SYSTEMS CONFERENCE (MEPCON)》 *
MD. SAJID ALAM等: "Priority list and particle swarm optimization based unit commitment of thermal units including renewable uncertainties", 《2016 IEEE INTERNATIONAL CONFERENCE ON POWER SYSTEM TECHNOLOGY (POWERCON)》 *
李整: "基于粒子群优化算法的机组组合问题的研究", 《中国优秀博硕士学位论文全文数据库(博士)基础科学辑》 *
黎静华等: "适合于机组组合问题的扩展优先顺序法", 《电力系统保护与控制》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110266058A (en) * 2019-05-31 2019-09-20 国网山东省电力公司济南供电公司 A kind of modeling of the Unit Combination model based on range optimization and method for solving
CN110266058B (en) * 2019-05-31 2023-07-14 国网山东省电力公司济南供电公司 Modeling and solving method of unit combination model based on interval optimization
CN110826773A (en) * 2019-10-17 2020-02-21 内蒙古电力(集团)有限责任公司电力调度控制分公司 Thermal power generating unit monthly power generation plan optimization method considering new energy access
CN110826773B (en) * 2019-10-17 2023-04-07 内蒙古电力(集团)有限责任公司电力调度控制分公司 Thermal power generating unit monthly power generation plan optimization method considering new energy access
CN112186734A (en) * 2020-08-20 2021-01-05 西安交通大学 Medium-and-long-term operation simulation method for power system, storage medium and computing equipment
CN114336777A (en) * 2021-11-29 2022-04-12 中国华能集团清洁能源技术研究院有限公司 Thermal power generating unit starting sequence determination method and system considering energy utilization sequence
CN114336777B (en) * 2021-11-29 2023-08-25 中国华能集团清洁能源技术研究院有限公司 Thermal power generating unit startup sequence determination method and system considering energy utilization sequence
CN115307274A (en) * 2022-10-12 2022-11-08 蘑菇物联技术(深圳)有限公司 Method, apparatus and storage medium for controlling host of air conditioning system
CN116488212A (en) * 2023-06-19 2023-07-25 长沙电机厂集团长瑞有限公司 Method and system for virtually controlling multiple motor groups to perform power energy storage configuration
CN116488212B (en) * 2023-06-19 2023-08-22 长沙电机厂集团长瑞有限公司 Method and system for virtually controlling multiple motor groups to perform power energy storage configuration
CN116760111A (en) * 2023-08-23 2023-09-15 太原理工大学 Distributed energy access and electric energy storage control method, device, equipment and medium
CN116760111B (en) * 2023-08-23 2023-11-10 太原理工大学 Distributed energy access and electric energy storage control method, device, equipment and medium

Also Published As

Publication number Publication date
CN109390981B (en) 2022-05-27

Similar Documents

Publication Publication Date Title
CN109390981A (en) The sending end power grid Unit Combination progress control method of new energy participation electric quantity balancing
AU2020100983A4 (en) Multi-energy complementary system two-stage optimization scheduling method and system considering source-storage-load cooperation
Merdanoğlu et al. Finding optimal schedules in a home energy management system
Anvari-Moghaddam et al. A multi-agent based energy management solution for integrated buildings and microgrid system
CN109687532B (en) Combined heat and power scheduling method for improving wind power consumption based on cooperative game
CN111555281B (en) Method and device for simulating flexible resource allocation of power system
CN111340274A (en) Virtual power plant participation-based comprehensive energy system optimization method and system
US20140094980A1 (en) Electric/thermal energy storage schedule optimizing device, optimizing method and optimizing program
US20140058571A1 (en) Multi-objective energy management methods for micro-grids
CN111008739B (en) Optimal regulation and control and income distribution method and system for cogeneration virtual power plant
Fux et al. Economic and environmental aspects of the component sizing for a stand-alone building energy system: A case study
CN109038686A (en) A kind of rolling optimal dispatching method based on wind power output prediction error
Wakui et al. Predictive management for energy supply networks using photovoltaics, heat pumps, and battery by two-stage stochastic programming and rule-based control
CN110991773A (en) Two-stage source load-storage optimization scheduling method for wind power consumption
CN109546689A (en) A kind of two stages Unit Combination progress control method suitable for large scale system
CN112215433B (en) Virtual power plant day-ahead optimal scheduling method based on uncertainty of market electricity price
CN114301081B (en) Micro-grid optimization method considering storage battery energy storage life loss and demand response
CN111817296B (en) Electric energy scheduling method and system for micro-grid
CN111293682A (en) Multi-microgrid energy management method based on cooperative model predictive control
Tomar et al. An integrated flexibility optimizer for economic gains of local energy communities—A case study for a University campus
CN110165715A (en) A method of by electric car energy storage type charging station access of virtual power plant
CN116384039A (en) Intelligent power grid energy optimization efficient management method based on model prediction
CN114462696A (en) Comprehensive energy system source-load cooperative operation optimization method based on TD3
CN109976155A (en) Participate in the virtual plant internal random optimal control method and system in pneumoelectric market
CN117791643A (en) Intelligent frequency modulation method and system for wind, light, water and fire storage cooperative game power grid

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant