CN109390833A CN201811138416.4A CN201811138416A CN109390833A CN 109390833 A CN109390833 A CN 109390833A CN 201811138416 A CN201811138416 A CN 201811138416A CN 109390833 A CN109390833 A CN 109390833A
Authority
CN
China
Prior art keywords
conductor silk
cable
joining technology
stock
technology method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811138416.4A
Other languages
Chinese (zh)
Other versions
CN109390833B (en
Inventor
付俊彪
李海亮
郝红国
张健
吕保
黄正全
泮志亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Huaye Group Co Ltd
Original Assignee
China Huaye Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Huaye Group Co Ltd filed Critical China Huaye Group Co Ltd
Priority to CN201811138416.4A priority Critical patent/CN109390833B/en
Publication of CN109390833A publication Critical patent/CN109390833A/en
Application granted granted Critical
Publication of CN109390833B publication Critical patent/CN109390833B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01RELECTRICALLY-CONDUCTIVE CONNECTIONS; STRUCTURAL ASSOCIATIONS OF A PLURALITY OF MUTUALLY-INSULATED ELECTRICAL CONNECTING ELEMENTS; COUPLING DEVICES; CURRENT COLLECTORS
    • H01R43/00Apparatus or processes specially adapted for manufacturing, assembling, maintaining, or repairing of line connectors or current collectors or for joining electric conductors
    • H01R43/033Apparatus or processes specially adapted for manufacturing, assembling, maintaining, or repairing of line connectors or current collectors or for joining electric conductors for wrapping or unwrapping wire connections

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Cable Accessories (AREA)

Abstract

The invention discloses a kind of drag cable Joining Technology methods, are mainly divided to 3 steps to the connection of single-phase core: first is that the conductor silk that two broken ends of cable will be connected as same phase core is respectively classified into multiply;Second is that by the share split conductor silk of two broken end phase cores of previous step respectively from intermediate position doubling, with the hook-type that is formed after doubling, mutual hook connects correspondingly;Third is that the fold-back section behind each stock conductor silk fold point of previous step is successively staggeredly passed through from the gap between the reservation paragraph adjacent strands before fold point, recycle successively to intert repeatedly and be mutually woven together, until fold-back segment length all weaves completion;After the completion of braiding, insulation processing is carried out to the individual event core junction.Using the method, the excessively electric sectional area of conductor silk, but also tension stress when guarantor's energy barrier cable dragging not only can guarantee, it is ensured that power supply safety is reliable.The process is simple and easy to operate, and improvement cost is very cheap, has promotional value.

Description

A kind of drag cable Joining Technology method
Technical field
The invention belongs to electrical technology fields, more particularly to a kind of drag cable Joining Technology method.
Background technique
It is since electric LHD has advantages, the domestic and international mine main force ore removal equipment multiselect type such as energy-saving and environmental protection, efficient Electric LHD.By taking certain mountain mine ore removal lectotype selection is the EST-3.5 type electric LHD of voltage class 1000v as an example, due to For the electric LHD without cable-remover, working environment at coal mines is severe, and the appearance drag cable after operation through perseverance is scratched, broken.It should Equipment uses 1000V voltage, and voltage class is higher, and impaired cable can not be reused without dealing carefully with, and returns operation Personnel bring very big security risk.If renew every time, because drag cable is expensive, production cost is considerably increased, Mine overall efficiency is affected.
For the drag cable connection processing broken, existing electrician's wiring technique is all unable to reach the safety of long period Requirement, cable junctions are difficult to be subjected to constantly pulling stress back and forth, are often dragged uncoupling point again quickly, or cause contact Place's conductor cross sectional area is small, is not able to satisfy the requirement for carrying the electric power, becomes the risk point or cable for be easy to causeing safety accident Contact global sections are more much larger than the section of former cable itself, influence cable dragging, also unsightly.
Summary of the invention
In order to solve the above-mentioned technical problem, by various trials, a kind of drag cable Joining Technology side is creatively found Method will first need the cable connected broken end damaged portion to remove, then be attached, connect if cable broken end is had damage Process is: the outer layer insulation skin (5) of (1) two broken end (2) of cable is peeled off one section, preferably external insulation skin (5) Peel each phase core (3) that at least 40cm length exposes the corresponding length in cable off;Cable (1) outer layer insulation skin (5) is shelled again The interior insulation skin (6) for each phase core (3) exposed after falling peels one section off, and interior insulation skin (6) preferably peels at least 20cm length off Expose the conductor silk (4) of the corresponding length in phase core (3);Then each phase core (3) is attached respectively, single phase core (3) connection the following steps are included:
Step 1: the conductor silk (4) that (1) two broken end (2) of cable will be connected as same phase core (3) is divided respectively At multiply, it can be 3 strands or 3 strands or more, each stock conductor silk (4) of a broken end (2) is calculated as A1, A2 ... respectively An, separately Each stock conductor silk (4) of one broken end (2) is calculated as B1, B2 ... respectively Bn, n are the number of share of stock that is divided into;It is led in order to prevent with stock Body silk (4) is broken up, and respectively can will be snarled on conductor silk (4) head with root with adhesive plaster with stock conductor silk (4);
Step 2: by the share split conductor silk (4) of two broken end (2) phase cores (3) of previous step respectively from middle part Position doubling, with the hook-type that is formed after doubling, mutual hook connects correspondingly, it may be assumed that the break of A1 and the break hook of B1 connect, the folding of A2 Point connects with the break hook of B2, and so on to the break of An and the break hook company of Bn;
Step 3: by the fold-back section (9) after each stock conductor silk (4) fold point (10) of previous step successively staggeredly from doubling It passes through in the gap between reservation paragraph (11) adjacent strands before point (10), is mutually woven together, such as: by the fold-back section (9) of A1 It is passed through from the gap of A1, A2 strands of reservation paragraphs (11) conductor silk (4), the fold-back section (9) of A2 is from A2, A3 strands of reservation paragraph (11) It is passed through in the gap of conductor silk (4), and so on, that is to say, that the fold-back section (9) of An is from An, A1 strands reservation paragraph (11) conductor It is passed through in the gap of silk (4), passes through the gap of two conductor silks (4) every time, recycled successively intert until fold-back section repeatedly (9) length all weaves completion;Using same method to B1, B2 ..., Bn bursts of conductor silks (4) are woven, and after the completion of braiding, are removed It prevents that same stock conductor silk (4) from breaing up in the adhesive plaster that conductor silk (4) head and root snarl, which is connected Place carries out insulation processing;Insulation processing can be the insulating tape winding with relevant voltage, in order to guarantee insulation effect, preferably twine Around no less than 3 layers;
After each phase core (3) connection, each phase core (3) can all be wound with black tape integral.In order to increase The abrasionproof performance of the forceful electric power cable connecting portion increases scuff-resistant coating (8) outside insulation processing, and scuff-resistant coating (8) can be wound around black Adhesive tape is preferably entwined around no less than 3 layers.In addition, as needed, in order to increase waterproof performance, increasing waterproof outside insulation processing Layer (7), waterproof layer (7), which can be, is first wound in waterproof layer (7), waterproof with adhesive waterproof tape before the winding of scuff-resistant coating (8) black tape It is more secure that adhesive tape winding is no less than 3 layers of waterproof effect.In use, preferably every once to be checked using 8 hours, it sees It sees the abrasion condition of cable, and carries out the reparation of scuff-resistant coating (8) as needed, to better ensure that the service life of junction.
It is preferred that each stock that the conductor silk (4) of same phase core (3) is divided into step 1 keeps thickness equal It is even, to guarantee that it is relatively uniform that each stock bears ability.
It is preferred that the conductor silk (4) of same phase core (3) is respectively classified into 5-12 strands in step 1, Bu Huiyin Cause per share too small and sub-thread to bear power too much for share split number too small, can guarantee bonding strength needs, and weave too complicated;Again not It can make very little the too thick bad braiding of sub-thread because of share split number, and influence braiding intensity.
It is preferred that the conductor silk (4) of same phase core (3) is respectively classified into even number stock in step 1, if same Conductor silk (4) radical in phase core (3) is odd number, can will wherein 1 conductor silk (4) from step 2 conductor silk doubling position Amputation, so that braiding process is more convenient.
It is preferred that stock conductor silk (4) fold point (10) is located at same section in step 2, so that each stock conductor silk (4) pulling force undertaken when using is relatively uniform, and sub-thread will not be caused to be broken and influence conductor energization section because of pulling force unevenness Product, or even accident occurs.
Using such drag cable Joining Technology method, the conductor silk (4) of phase core (3) is not divided into multiply and carries out intersection volume It knits, on the basis of guaranteeing the electric sectional area excessively of conductor silk (4), has also ensured tension stress when cable (1) pulls;By right Connecting portion carries out waterproof, insulation, Wear-resistant Treatment, it is ensured that power supply safety is reliable, ensures operator's safety, cuts at cable connection Face even thickness facilitates equipment drag cable without bulge, and and beautiful.The process is tried out and has been ground in certain mine Study carefully, it is determined that the feasibility of the process ensure that electric LHD operator's safe construction, reduce construction cost. The process is simple and easy to operate, and improvement cost is very cheap, has promotional value.
Detailed description of the invention
Fig. 1 is that multiply conductor silk doubling hook connects schematic diagram in single-phase core;
Fig. 2 is that cable is broken schematic diagram;
Fig. 3 is cable cross-section schematic diagram, and schematic diagram selection is the cable containing three phase cores;
Fig. 4 is that cable broken end peels the schematic diagram after SI semi-insulation skin off, and schematic diagram selection is containing three phase cores Cable;
Fig. 5 is that schematic cross-section is managed in the phase core junction of cable;
In figure: 1- cable, 2- broken end, 3- phase core, 4- conductor silk, 5- outer layer insulation skin, 6- interior insulation skin, 7- waterproof Layer, 8- scuff-resistant coating, the fold-back section of 9- conductor silk (4), the fold point of 10- conductor silk (4), the reservation paragraph of 11- conductor silk (4).
Specific embodiment
The drag cable Joining Technology method is described in detail below in conjunction with some embodiment, which only should One of embodiment of process is not unique embodiment, so the implementation embodiment should not be understood as to this Invent the restriction of claimed practical range.
The embodiment Joining Technology method is: first the outer layer insulation skin (52) of (1) two broken end (2) of cable being peeled off One section of 40cm length exposes each phase core (3) of the about 40cm length in cable (1);Again by each of the 40cm length of exposing The interior insulation skin (6) of phase core (3) peels one section of about 20cm length off, and the conductor silk (4) of phase line in-core exposes 20cm length One section;Then each phase core (3) is attached respectively, the connection of single phase core (3) the following steps are included:
One, the conductor silk (4) that two broken ends (2) will be connected as the 20cm length of same phase core (3) divides respectively At uniform 6 strands, each stock conductor silk (4) of a broken end (2) is calculated as A1, A2 ... respectively A6, another broken end (2) it is each Stock conductor silk (4) B6 that is calculated as B1, B2 respectively ...;It is broken up in order to prevent with stock conductor silk (4), adhesive plaster will be used respectively with stock conductor silk Conductor silk (4) head is snarled with root;
Two, by the share split conductor silk (4) of two broken end (2) phase cores (3) of previous step respectively from exposed portion Centre about 10cm position doubling, with the hook-type that is formed after doubling, mutual hook connects correspondingly, it may be assumed that the break of A1 and the break of B1 Hook connects, and the break of A2 and the break hook of B2 connect, and so on, the break of A6 and the break hook of B6 connect;The step keeps each stock to lead Body silk fold point (10) cross section place is identical;
Three, the fold-back section (9) after each stock conductor silk (4) fold point (10) of previous step is successively interlocked before fold point Reservation paragraph (11) adjacent strands between gap in pass through, be mutually woven together, such as: by the fold-back section (9) of A1 from A1, A2 strands Reservation paragraph (passed through in the gap of 11 conductor silks (4), the fold-back section (9) of A2 from A2, A3 strands of reservation paragraph (11 conductor silks (4) It is passed through in gap, and so on, that is to say, that the fold-back section (9) of A6 is from A6, A1 strands of the reservation paragraph (gap of 11 conductor silks (4) In pass through, every time pass through two conductor silks (4) gap, recycle repeatedly successively intert until fold-back section (9) length is all compiled It casts off into;Using same method to B1, B2 ..., B6 bursts of conductor silks (4) are woven, and after the completion of braiding, dismounting prevents same stock conductor Silk (4) is broken up in the adhesive plaster that conductor silk (4) head and root snarl, and winds 3 layers of insulation to single phase core (3) junction Adhesive tape carries out insulation processing;
After each phase core (3) connection, in order to increase waterproof performance, 3 layers first are wound into waterproof layer with adhesive waterproof tape (7), then black tape is used to wind 3 layers as scuff-resistant coating (8), enhances the abrasionproof performance of the cable connecting portion.In addition it was using Electrician personnel are arranged in journey, it is every once to be checked using 8 hours, look at the abrasion condition of cable, and prevented as needed The reparation of layer (8) is ground, to better ensure that the service life of junction.

Claims (12)

1. a kind of drag cable Joining Technology method peels the outer layer insulation skin (5) of (1) two broken end (2) of cable off one section; The interior insulation skin (6) for each phase core (3) exposed after cable (1) outer layer insulation skin (5) is peeled off again peels one section off;Then to each Phase core (3) is attached respectively, it is characterised in that: the connection of single phase core (3) the following steps are included:
Step 1: the conductor silk (4) that (1) two broken end (2) of cable will be connected as same phase core (3) is respectively classified into more Stock, each stock conductor silk (4) of a broken end (2) is calculated as A1, A2 ... respectively An, each stock conductor silk (4) point of another broken end (2) Be not calculated as B1, B2 ... Bn, n is the number of share of stock that is divided into;
Step 2: by the share split conductor silk (4) of two broken end (2) phase cores (3) of previous step respectively from intermediate position pair Folding, with the hook-type that is formed after doubling, mutual hook connects correspondingly;
Step 3: by the fold-back section (9) after each stock conductor silk (4) fold point (10) of previous step successively staggeredly from fold point (10) mode passed through in the gap between reservation paragraph (11) adjacent strands before mutually weaves, and circulation is successively interted until fold-back section (9) length all weaves completion;Using same method to B1, B2 ..., Bn bursts of conductor silks (4) are woven, after the completion of braiding, to this Single-phase core (3) junction carries out insulation processing.
2. drag cable Joining Technology method according to claim 1, it is characterised in that: described disconnected by (1) two, cable The length that the outer layer insulation skin (5) of head end (2) peels one section off is no less than 40cm.
3. drag cable Joining Technology method according to claim 1, it is characterised in that: described that cable (1) outer layer is exhausted The length that the interior insulation skin (6) for each phase core (3) that edge skin (5) exposes after peeling off peels one section off is no less than 20cm.
4. drag cable Joining Technology method according to claim 1, it is characterised in that: same phase in the step 1 The conductor silk (4) of core (3) is respectively classified into 3 strands or 3 strands or more.
5. drag cable Joining Technology method according to claim 1, it is characterised in that: will be led with stock in the step 1 Body silk (4) is respectively snarled on conductor silk head with root with adhesive plaster.
6. drag cable Joining Technology method according to claim 1, it is characterised in that: same phase in the step 1 Each stock that the conductor silk (4) of core (3) is divided into keeps even thickness.
7. drag cable Joining Technology method according to claim 1, it is characterised in that: same phase in the step 1 The conductor silk (4) of core (3) is respectively classified into 5-12 strands.
8. drag cable Joining Technology method according to claim 1, it is characterised in that: same phase in the step 1 The conductor silk (4) of core (3) is respectively classified into even number stock.
9. drag cable Joining Technology method according to claim 1, it is characterised in that: stock conductor silk in the step 2 (4) fold point (10) are located at same section.
10. drag cable Joining Technology method according to claim 1, it is characterised in that: the step 3 insulation processing It is wound around the insulating tape of no less than 3 layers relevant voltage.
11. drag cable Joining Technology method described in one of -10 according to claim 1, it is characterised in that: connect in the cable Increase waterproof layer (7) outside the place's of connecing insulation processing.
12. drag cable Joining Technology method described in one of -10 according to claim 1, it is characterised in that: connect in the cable Increase scuff-resistant coating (8) outside the place's of connecing insulation processing.
CN201811138416.4A 2018-09-27 2018-09-27 Towing cable connection process method Active CN109390833B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811138416.4A CN109390833B (en) 2018-09-27 2018-09-27 Towing cable connection process method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811138416.4A CN109390833B (en) 2018-09-27 2018-09-27 Towing cable connection process method

Publications (2)

Publication Number Publication Date
CN109390833A true CN109390833A (en) 2019-02-26
CN109390833B CN109390833B (en) 2020-07-10

Family

ID=65418271

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811138416.4A Active CN109390833B (en) 2018-09-27 2018-09-27 Towing cable connection process method

Country Status (1)

Country Link
CN (1) CN109390833B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113257535A (en) * 2021-03-25 2021-08-13 深圳市科达嘉电子有限公司 Braided wire inductance coil and braided wire large current inductance

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS628106U (en) * 1985-06-29 1987-01-19
CN1734874A (en) * 2005-07-19 2006-02-15 上海上缆辐照技术开发有限公司 Equal diameter connector of power cable
CN101115668A (en) * 2005-02-08 2008-01-30 株式会社岛精机制作所 Method of piercing spun yarn and knitting including piercing of yarn
CN203150716U (en) * 2013-04-07 2013-08-21 福安市冠华电机有限公司 Copper wire joint for motor
CN203377579U (en) * 2013-06-28 2014-01-01 3M中国有限公司 Cable joint protecting structure
CN104505690A (en) * 2014-12-24 2015-04-08 贵州开磷(集团)有限责任公司 Rubber-sheathed drag cable butt joint process
CN106229785A (en) * 2016-07-27 2016-12-14 苏州水木清华设计营造有限公司 Electrical wire connection method
CN106469899A (en) * 2015-08-19 2017-03-01 浙江正泰电缆有限公司 A kind of gum cover cable water-blocking joint structure and preparation method thereof
CN108233142A (en) * 2017-12-08 2018-06-29 中国北方发动机研究所(天津) A kind of automobile-used thermocouple temperature sensor and cable bridging method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS628106U (en) * 1985-06-29 1987-01-19
CN101115668A (en) * 2005-02-08 2008-01-30 株式会社岛精机制作所 Method of piercing spun yarn and knitting including piercing of yarn
CN1734874A (en) * 2005-07-19 2006-02-15 上海上缆辐照技术开发有限公司 Equal diameter connector of power cable
CN203150716U (en) * 2013-04-07 2013-08-21 福安市冠华电机有限公司 Copper wire joint for motor
CN203377579U (en) * 2013-06-28 2014-01-01 3M中国有限公司 Cable joint protecting structure
CN104505690A (en) * 2014-12-24 2015-04-08 贵州开磷(集团)有限责任公司 Rubber-sheathed drag cable butt joint process
CN106469899A (en) * 2015-08-19 2017-03-01 浙江正泰电缆有限公司 A kind of gum cover cable water-blocking joint structure and preparation method thereof
CN106229785A (en) * 2016-07-27 2016-12-14 苏州水木清华设计营造有限公司 Electrical wire connection method
CN108233142A (en) * 2017-12-08 2018-06-29 中国北方发动机研究所(天津) A kind of automobile-used thermocouple temperature sensor and cable bridging method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113257535A (en) * 2021-03-25 2021-08-13 深圳市科达嘉电子有限公司 Braided wire inductance coil and braided wire large current inductance

Also Published As

Publication number Publication date
CN109390833B (en) 2020-07-10

Similar Documents

Publication Publication Date Title
CN109830342A (en) Bank electricity optoelectronic composite cable
CN109390833A (en) A kind of drag cable Joining Technology method
CN211045062U (en) High-shielding-efficiency cable
CN209118800U (en) A kind of movable rubber jacketed flexible cable
CN106537207A (en) Cable connections
CN105825935B (en) Pressure-resistant network cable
CN219676933U (en) Double-core coaxial cable
CN105958349B (en) A kind of disconnecting link hard combined shielding cover
CN209895824U (en) High-voltage cable
CN210296007U (en) Electric wire
CN203826038U (en) Outdoor cable
CN207868772U (en) A kind of breaking line preventive of overhead distribution endangers mechanism
CN207718032U (en) A kind of insulating splice closure for line feeder fiber composite overhead ground wire
CN206697861U (en) The quick insulation recovery device of 10kV suspended insulated guide wires
CN207925176U (en) A kind of cable for new-energy automobile with splicing button
CN216564271U (en) Induced electricity eliminator for high-voltage cable
CN208400595U (en) A kind of waterproof cable being easy to fixed support
CN105976917B (en) Durable type cable
CN209657890U (en) High-rise building safe clean type mineral-insulated fireproof shield type frequency-conversion power cable
CN110379545A (en) A kind of two cores and the above separated type shell-less cotton covered wire
CN216719537U (en) Anti-cutting low-voltage cable
CN107069591A (en) The quick insulation recovery device of 10kV suspended insulated guide wires and its application method
CN209029134U (en) A kind of reinforced mobile flexible cable
CN210015715U (en) Composite cable
CN219418532U (en) Connecting cable convenient to peel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant