Prior art keywords
tunnel
air
valve
pollutant concentration
opened
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811241210.4A
Other languages
Chinese (zh)
Inventor
王丽慧
张继华
胡田伟
张雨蒙
郑懿
宋洁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
University of Shanghai for Science and Technology
Original Assignee
University of Shanghai for Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by University of Shanghai for Science and Technology filed Critical University of Shanghai for Science and Technology
Priority to CN201811241210.4A priority Critical patent/CN109375501A/en
Publication of CN109375501A publication Critical patent/CN109375501A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B11/00Automatic controllers
    • G05B11/01Automatic controllers electric
    • G05B11/36Automatic controllers electric with provision for obtaining particular characteristics, e.g. proportional, integral, differential
    • G05B11/42Automatic controllers electric with provision for obtaining particular characteristics, e.g. proportional, integral, differential for obtaining a characteristic which is both proportional and time-dependent, e.g. P. I., P. I. D.
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F1/00Ventilation of mines or tunnels; Distribution of ventilating currents
    • E21F1/003Ventilation of traffic tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F1/00Ventilation of mines or tunnels; Distribution of ventilating currents
    • E21F1/14Air partitions; Air locks
    • E21F1/145Air locks

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Automation & Control Theory (AREA)
  • Ventilation (AREA)

Abstract

The present invention proposes a kind of method being opened and closed according to tunnel inner air and outer air quality control piston air-valve, comprising the following steps: step S1: determining the response condition of regulation;Step S2: the PM value in monitoring tunnel and outside tunnel judges whether to meet response condition;It is such as unsatisfactory for response condition, piston air-valve is open state, repeats step S2;Such as meet response condition, enters step S3;Step S3: the regulation duration is calculated;Step S4: closure piston air-valve, when closing a length of regulation duration;Step S5: the regulation duration terminates, return step S2.In this application, (1) completely cuts off the air environment inside and outside tunnel by closure piston air-valve, when especially winter haze is serious, haze outside tunnel can be prevented to enter in tunnel and platform, air environment in tunnel is influenced, be unfavorable for human health.(2) it is suitable for the subway system of various structures and form, can voluntarily adds correction factor according to the actual situation.

Description

A method of it is opened and closed according to tunnel inner air and outer air quality control piston air-valve
Technical field
The present invention relates to air environment control technique fields more particularly to a kind of living according to tunnel inner air and outer air quality control Fill in the method for air-valve opening and closing.
Background technique
When studying air quality in subway tunnel, the characteristics of relatively closing due to subway tunnel structure, pollutants in air It is easily accumulated in running tunnel under Piston Action Wind valve action, this some of the contaminants includes PM10, PM2.5, formaldehyde, benzene homologues, virtue Fragrant hydrocarbon etc..In many scholars research, it is found that the pollutant in section is platform air pollutants main source, it is always dirty to account for platform Contaminate the 30% of object source.Running tunnel gas pollutant source is according to research shows that be mainly derived from two parts, a part of source In tunnel external environment, major pollutants type is PM2.5, benzene homologues, aromatic hydrocarbon etc., is fluctuated with tunnel external environment quality;It is another Part is mainly derived from train operation, mainly includes some metal particulates.Wherein, train travelling process generates pollutant with logical Cross the measures such as electrostatic precipitation, anion fine-purification, the aspiration of negative pressure solution.It is generally acknowledged that air quality is better than running tunnel outside tunnel Interior air quality, but as haze sky in recent years occurs again and again, air quality might not be better than running tunnel air outside tunnel High pollution air outside tunnel can be introduced in running tunnel if piston air-valve still uses as usual at this time, pollute subway by quality Tunnel internal air environment.
Summary of the invention
The purpose of the invention is to provide a kind of method being opened and closed according to tunnel inner air and outer air quality control piston air-valve, Structure is simple, effectively completely cuts off pollutant outside tunnel and enters in tunnel.
To achieve the goals above, the present invention propose it is a kind of according to tunnel inner air and outer air quality control piston air-valve opening and closing Method, comprising the following steps:
Step S1: the response condition of regulation is determined;
Step S2: the PM value in monitoring tunnel and outside tunnel judges whether to meet the response condition;
It is such as unsatisfactory for the response condition, piston air-valve is open state, repeats step S2;
Such as meet the response condition, enters step S3;
Step S3: the regulation duration is calculated;
Step S4: closing the piston air-valve, when closing a length of regulation duration;
Step S5: the regulation duration terminates, return step S2.
Further, in the method according to the opening and closing of tunnel inner air and outer air quality control piston air-valve, step S1 In, the response condition is the pollutant in pollutant concentration-tunnel outside tunnel when continuing to monitor time > setting monitoring time Concentration > sets pollutant concentration, the mathematic(al) representation of the response condition are as follows: e (t)=PMo (t)-PMn (t) > setting pollution Object concentration, and △ t > 3 (k+1) min;
E (t) is the pollutant concentration difference outside tunnel and in tunnel;PMo (t) is pollutant concentration outside tunnel, PMn (t) For pollutant concentration in tunnel;T is to continue to monitor the time, and k is pollutant disturbance fluctuation duration.
Further, described to set in the method according to the opening and closing of tunnel inner air and outer air quality control piston air-valve Determining PM monitor value is PM2.5, and the pollutant concentration that sets is 40 μ g/m3
Further, in the method according to the opening and closing of tunnel inner air and outer air quality control piston air-valve, k 5.
Further, in the method according to the opening and closing of tunnel inner air and outer air quality control piston air-valve, step S2 In, the regulation duration is obtained by the differential control item, integration control item and first order read group total of PID control function , the mathematic(al) representation of the differential control item isThe mathematic(al) representation of the integration control item is
Ett is with pollutant concentration difference in tunnel outside tunnel in cycle time TdInterior prediction variable quantity, TdFor differential control Item calculating cycle time processed, de (t) are variable quantity of the e (t) in dt transformation period, and de (t) and dt ratio is to the micro- of e (t) Divide derivation;
△ et is with static difference of the pollutant concentration difference in cycle time T in tunnel outside tunnel, and T is integration control item meter Cycle time is calculated, dt is time variation amount.
Further, in the method according to the opening and closing of tunnel inner air and outer air quality control piston air-valve, the tune Control the duration mathematic(al) representation be
U (t) is the knots modification also needed outside regulation tunnel with pollutant concentration difference PM value in tunnel, and Kp is proportionality coefficient.
Further, in the method according to the opening and closing of tunnel inner air and outer air quality control piston air-valve, TdIt is 5, T For 5, Kp 1.1.
Further, in the method according to the opening and closing of tunnel inner air and outer air quality control piston air-valve, in tunnel When for peak state, the calculating of e (t) need to be modified, the correction formula of e (t) when peak are as follows:The peak e (t) is substituted into the calculation formula of the regulation duration, Gcar is amendment system Number.
Compared with prior art, the beneficial effects are mainly reflected as follows: (1) by closure piston air-valve completely cut off tunnel Inside and outside air environment when especially winter haze is serious, can prevent haze outside tunnel from entering in tunnel and platform, influence tunnel Air environment in road, is unfavorable for human health.(2) it is suitable for the subway system of various structures and form, it can be according to the actual situation Voluntarily add correction factor, such as driving method, the habit by bus of different regions people, the equipment of different trains of different trains Equal correction factors.
Detailed description of the invention
Fig. 1 is in the present invention according to the flow diagram of the method for tunnel inner air and outer air quality control piston air-valve opening and closing;
Fig. 2 is the tables of data of the PM2.5 monitor value after stroke valve of the present invention is closed in tunnel and outside tunnel;
Fig. 3 is the tables of data of Shanghai World Park winter PM2.5 in 2018 monitor value.
Specific embodiment
Below in conjunction with schematic diagram to the method for the invention being opened and closed according to tunnel inner air and outer air quality control piston air-valve It is described in more detail, which show the preferred embodiment of the present invention, it should be appreciated that those skilled in the art can modify Invention described herein, and still realize advantageous effects of the invention.Therefore, following description should be understood as ability Field technique personnel's is widely known, and is not intended as limitation of the present invention.
In the description of the present invention, it should be noted that " transverse direction ", " vertical if any term " center " for the noun of locality To ", " length ", " width ", " thickness ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", The indicating positions such as "bottom", "inner", "outside", " clockwise ", " counterclockwise " and positional relationship are orientation based on the figure or position Relationship is set, the narration present invention is merely for convenience of and simplifies description, rather than the device or element of indication or suggestion meaning are necessary It constructs and operates with specific orientation, with particular orientation, should not be understood as limiting specific protection scope of the invention.
In the present invention, except as otherwise clear stipulaties and restriction, should make if any term " assembling ", " connected ", " connection " term Broad sense goes to understand, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It is also possible to mechanical connect It connects;It can be directly connected, be also possible to be connected by intermediary, can be and be connected inside two elements.For ability For the those of ordinary skill of domain, the concrete meaning of above-mentioned term in the present invention can be understood as the case may be.
The present invention is more specifically described by way of example referring to attached drawing in the following passage.According to following explanation, the present invention The advantages of and feature will become apparent from.It should be noted that attached drawing is all made of very simplified form and uses non-accurate ratio, Only for the purpose of facilitating and clarifying the purpose of the embodiments of the invention.
As shown in Figure 1, the present invention proposes a kind of method being opened and closed according to tunnel inner air and outer air quality control piston air-valve, packet Include following steps:
Step S1: the response condition of regulation is determined;
Response condition is to pollute in pollutant concentration-tunnel outside tunnel when continuing to monitor time > setting monitoring time Object concentration > sets pollutant concentration, the mathematic(al) representation of response condition are as follows: e (t)=PMo (t)-PMn (t) > sets pollutant Concentration, and △ t > 3 (k+1) min;
E (t) is the pollutant concentration difference outside tunnel and in tunnel;PMo (t) is pollutant concentration outside tunnel, PMn (t) For pollutant concentration in tunnel;T is to continue to monitor the time, and k is pollutant disturbance fluctuation duration.
Step S2: the PM value in monitoring tunnel and outside tunnel judges whether to meet response condition;
It is such as unsatisfactory for response condition, piston air-valve is open state, repeats step S2;
Such as meet response condition, enters step S3.
Step S3: the regulation duration is calculated;
The regulation duration is obtained by the differential control item, integration control item and first order read group total of PID control function , i.e., when outside monitoring time inner tunnel with PM2.5 difference e (t) in tunnel, prediction variable quantity ett (differential control item) and static difference △ et's (integration control item) and be 0 when, can calculate and continue to monitor time t.
The mathematic(al) representation of differential control item isThe mathematic(al) representation of integration control item isRegulation the duration mathematic(al) representation be
Ett is with pollutant concentration difference in tunnel outside tunnel in cycle time TdInterior prediction variable quantity is outside tunnel With the product of the change rate of pollutant concentration difference and time in tunnel;TdFor the differential control item calculating cycle time;De (t) is Variable quantity of the e (t) in dt transformation period, de (t) and dt ratio are the differential derivation to e (t).
△ et is that tunnel is outer with static difference of the pollutant concentration difference in cycle time T in tunnel, be with tunnel outside and tunnel The variable quantity e (t) of pollutant concentration difference is the integral of function in road;T is the integration control item calculating cycle time;Dt is the time Variable quantity.
U (t) is the knots modification also needed outside regulation tunnel with pollutant concentration difference PM value in tunnel, and Kp is proportionality coefficient.
When e (t) change rate is 0, differential control item ett is 0, but pollutant concentration difference PM value in outside tunnel and tunnel There are still static difference, which is eliminated by integration control item.And when u (t) is 0, then it does not need, Piston Action Wind can be opened Valve.
Step S4: closure piston air-valve, when closing a length of regulation duration.
Step S5: the regulation duration terminates, return step S2.
Further, in the present embodiment, PM monitor value is set as PM2.5, sets pollutant concentration as 40 μ g/m3.Tunnel PM2.5 level of pollution is divided into good (35-75 μ g/m outside road3), slight pollution (75-115 μ g/m3), intermediate pollution (115-150 μ g/ m3), serious pollution (150-250 μ g/m3).Subway sectional tunnel PM2.5 level of pollution is generally good, preferably more than intermediate pollution To set pollutant concentration.Meanwhile according to different situations on the spot, other detectable air pollutants also can be used as prison Measured value, such as formaldehyde, benzene homologues, aromatic hydrocarbon, and pollutant concentration can also choose suitable level of pollution according to different demands.
Meanwhile because the interval time of prison chronometric data acquisition is 1 minute, the disturbance fluctuation duration of common contaminant is less than 5 minutes, the engineering experience formula of basic demand sample size was n >=3 (k+1), when k is 5, n >=18, that is, set monitoring time as 18min or more.In the present embodiment, taking n is 18, i.e. △ t > 18min.
To sum up, the PM value in tunnel and outside tunnel is monitored, when PM2.5 pollutes in PM2.5 pollutant concentration-tunnel outside tunnel 40 μ g/m of object concentration >3, then exclusion accidentally response time is set, sets monitoring time as 18min.Data monitoring equipment takes per minute One group of data of record, that is, obtain 18 groups of data in 18 minutes, and specific tables of data is as shown in Figure 2.
Tables of data according to Fig.2, carries out the calculating of PID control function, is held with obtaining the regulation of closure piston air-valve The continuous time.
In the calculating of PID control function, the differential control item of PID control function illustrates the calculating week in a PID In phase, from moment t to moment t+TdControl parameter tunnel outside with tunnel in pollutant concentration difference PM2.5 variable quantity, directly To control parameter variable be 0 when, differential control terminate.Differential control item calculating cycle time TdIt is the frequency acquisition according to data Setting, due to that can take 5 groups of above data in each cycle, and the smaller calculated result of value is more accurate, i.e. TdTake 5.Even if differential Control item has been 0, but there are still static differences for target value and monitor value, to eliminate this part static difference, is suitble to that integration control item is added. I.e. when integration control item is also 0, then regulating and controlling the duration terminates.
Regulating and controlling duration u (t) is t moment, and the amount to be regulated and controled of remaining difference e (t) is substituted into and obtained according to monitoring data The regulation duration for needing closure piston air-valve, Proportional coefficient K p response regulatory week can be calculated in pollutant concentration difference e (t) In time phase, the variation speed of pollutant concentration difference inside and outside tunnel is related to pollutant generation speed in tunnel, is approximately equal to The increment of pollutant concentration in unit period inner tunnel.Monitoring data according to Fig.2, when air-valve is closed, each train Process of passing through tunnel, pollutant concentration variable quantity is 0.5 μ g/m in tunnel3, i.e. de (t)=- 0.5, and e (t) ≈ -0.5 × t+ 45.7 TdTake 5min, T that 5min, Kp is taken to take 1.1, each cycle time all can according to outside the period inner tunnel with pollutant in tunnel A regulation duration for needing closure piston air-valve is calculated in concentration difference variation function e (t), can be in terms of each cycle update A new duration is calculated, the regulation duration is modified, the example at this, which simplifies, only does period first time calculating knot Fruit.And in different application place, Kp value can also be reset according to the actual situation, generally according to PID design principle Kp value 1.1。
That is the μ of u (t)=0 g/m3When, i.e. e (t), e (t) differential control item (derivation is with negative sign) and e (t) integration control And be 0, can calculate and continue to monitor time t, the μ of u (t)=0 g/m3Indicate that pollutant concentration is identical inside and outside tunnel, it should terminate Piston air-valve is opened in regulation.The regulation duration calculation formula of monitoring data and PID control function according to Fig.2, is asked Solution obtains the closing duration △ t ≈ 4h of Piston Action Wind valve.That is the piston air-valve at this time monitoring station, which closes duration, should be 4h, by Pollutant concentration difference after 4h inside and outside tunnel is smaller, and the meaning of polluted gas is not isolated.For newly-built station and equipment Newer subway line, because pollutant occurrence quantity is lower in its tunnel, the shut-in time of piston air-valve opposite can extend.
Further, in the present embodiment, the actual conditions in tunnel are divided into peak state and non-peak state, work as tunnel It is interior be non-peak state when, pollutant concentration difference e (t) and regulation duration u (t) calculating according to calculation formula above It calculates;When in tunnel being peak state, the calculating of pollutant concentration difference e (t) need to be modified, the amendment of e (t) when peak Formula are as follows:The peak e (t) is substituted into the calculation formula of regulation duration, correction factor Gcar is configured according to different operating conditions.
According to actual monitoring data it is found that subway sectional tunnel PM2.5 value is generally 70 hereinafter, belong to good level.Such as Shown in Fig. 3, from December, 17 to 2 months 18 years, there are 25 days air environment PM values to belong to moderate or more and pollute.And it still opens at this time Piston air-valve can then make pollution air outside tunnel enter tunnel pollution tunnel air environment, or even pollution air enters platform harm Passenger's health.
In addition, the acquisition data means obtained in tunnel with PM value outside tunnel are not limited by equipment monitoring, can also pass through Other methods obtain PM value dynamic data, such as on the net or history data collection library, can reduce the investment of monitoring device, reduction at This.
To sum up, in the present embodiment, the method for proposition being opened and closed according to tunnel inner air and outer air quality control piston air-valve, (1) air environment inside and outside tunnel is completely cut off by closure piston air-valve, when especially winter haze is serious, mist outside tunnel can be prevented Haze enters in tunnel and platform, influences air environment in tunnel, is unfavorable for human health.(2) it is suitable for various structures and shape The subway system of formula can voluntarily add correction factor, such as driving method, people from different regions of different trains according to the actual situation Habit by bus, the correction factors such as the equipment of different train.
The above is only a preferred embodiment of the present invention, does not play the role of any restrictions to the present invention.Belonging to any Those skilled in the art, in the range of not departing from technical solution of the present invention, to the invention discloses technical solution and Technology contents make the variation such as any type of equivalent replacement or modification, belong to the content without departing from technical solution of the present invention, still Within belonging to the scope of protection of the present invention.

Claims (8)

1. a kind of method being opened and closed according to tunnel inner air and outer air quality control piston air-valve, which comprises the following steps:
Step S1: the response condition of regulation is determined;
Step S2: the PM value in monitoring tunnel and outside tunnel judges whether to meet the response condition;
It is such as unsatisfactory for the response condition, piston air-valve is open state, repeats step S2;
Such as meet the response condition, enters step S3;
Step S3: the regulation duration is calculated;
Step S4: closing the piston air-valve, when closing a length of regulation duration;
Step S5: the regulation duration terminates, return step S2.
2. the method according to claim 1 being opened and closed according to tunnel inner air and outer air quality control piston air-valve, feature exist In in step S1, the response condition is pollutant concentration-tunnel outside tunnel when continuing to monitor time > setting monitoring time Pollutant concentration > sets pollutant concentration, the mathematic(al) representation of the response condition are as follows: e (t)=PMo (t)-PMn (t) in road > sets pollutant concentration, and △ t > 3 (k+1) min;
E (t) is the pollutant concentration difference outside tunnel and in tunnel;PMo (t) is pollutant concentration outside tunnel, and PMn (t) is tunnel Pollutant concentration in road;△ t is to continue to monitor the time, and k is pollutant disturbance fluctuation duration.
3. the method according to claim 2 being opened and closed according to tunnel inner air and outer air quality control piston air-valve, feature exist In the PM monitor value that sets is PM2.5, and the pollutant concentration that sets is 40 μ g/m3
4. the method according to claim 3 being opened and closed according to tunnel inner air and outer air quality control piston air-valve, feature exist In k 5.
5. the method according to claim 1 being opened and closed according to tunnel inner air and outer air quality control piston air-valve, feature exist In in step S2, the regulation duration is asked by the differential control item, integration control item and first order of PID control function It is obtained with calculating, the mathematic(al) representation of the differential control item isThe mathematical expression of the integration control item Formula is
Ett is with prediction variable quantity of the pollutant concentration difference in cycle time Td in tunnel outside tunnel, and Td is differential control Item calculating cycle time, de (t) are variable quantity of the e (t) in dt transformation period, and de (t) and dt ratio are the differential to e (t) Derivation;
△ et is with static difference of the pollutant concentration difference in cycle time T in tunnel outside tunnel, and T is that integration control item calculates week Time phase, dt are time variation amount.
6. the method according to claim 5 being opened and closed according to tunnel inner air and outer air quality control piston air-valve, feature exist In the mathematic(al) representation of the regulation duration is
U (t) is the knots modification also needed outside regulation tunnel with pollutant concentration difference PM value in tunnel, and Kp is proportionality coefficient.
7. the method according to claim 6 being opened and closed according to tunnel inner air and outer air quality control piston air-valve, feature exist In TdFor 5, T 5, Kp 1.1.
8. the method according to claim 6 being opened and closed according to tunnel inner air and outer air quality control piston air-valve, feature exist In when being peak state in tunnel, the calculating of e (t) need to be modified, the correction formula of e (t) when peak are as follows:The peak e (t) is substituted into the calculation formula of the regulation duration, Gcar is amendment system Number.
CN201811241210.4A 2018-10-24 2018-10-24 A method of it is opened and closed according to tunnel inner air and outer air quality control piston air-valve Pending CN109375501A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811241210.4A CN109375501A (en) 2018-10-24 2018-10-24 A method of it is opened and closed according to tunnel inner air and outer air quality control piston air-valve

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811241210.4A CN109375501A (en) 2018-10-24 2018-10-24 A method of it is opened and closed according to tunnel inner air and outer air quality control piston air-valve

Publications (1)

Publication Number Publication Date
CN109375501A true CN109375501A (en) 2019-02-22

Family

ID=65401040

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811241210.4A Pending CN109375501A (en) 2018-10-24 2018-10-24 A method of it is opened and closed according to tunnel inner air and outer air quality control piston air-valve

Country Status (1)

Country Link
CN (1) CN109375501A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63116022A (en) * 1986-10-31 1988-05-20 Daido Steel Co Ltd Burner combustion control method for industrial furnace
CN102507129A (en) * 2011-10-27 2012-06-20 上海理工大学 Experimental device for simulating isothermal coupling process of two airflows under underground railway environment by use of liquid
CN104006509A (en) * 2014-06-09 2014-08-27 博玺投资有限公司 Fresh air purifying machine having PM2.5 monitoring and adjusting function and control method
CN104776558A (en) * 2015-03-25 2015-07-15 珠海格力电器股份有限公司 Fresh air system and air valve opening control method thereof
CN105091224A (en) * 2015-08-06 2015-11-25 广州朗威电子科技有限公司 Indoor air quality adjusting method and system of large public building
CN106051958A (en) * 2016-07-12 2016-10-26 广东申菱环境系统股份有限公司 Evaporative condensation direct-expansion evaporative air conditioning system for metro station
CN107304758A (en) * 2016-04-25 2017-10-31 上海汽车集团股份有限公司 Hydraulic oil output device and its control method
CN207342896U (en) * 2017-12-18 2018-05-11 北京市市政工程设计研究总院有限公司 Urban transportation tunnel electronic type PM2.5 air cleaning units
TWI626627B (en) * 2017-08-31 2018-06-11 研能科技股份有限公司 Actuating sensor module

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63116022A (en) * 1986-10-31 1988-05-20 Daido Steel Co Ltd Burner combustion control method for industrial furnace
CN102507129A (en) * 2011-10-27 2012-06-20 上海理工大学 Experimental device for simulating isothermal coupling process of two airflows under underground railway environment by use of liquid
CN104006509A (en) * 2014-06-09 2014-08-27 博玺投资有限公司 Fresh air purifying machine having PM2.5 monitoring and adjusting function and control method
CN104776558A (en) * 2015-03-25 2015-07-15 珠海格力电器股份有限公司 Fresh air system and air valve opening control method thereof
CN105091224A (en) * 2015-08-06 2015-11-25 广州朗威电子科技有限公司 Indoor air quality adjusting method and system of large public building
CN107304758A (en) * 2016-04-25 2017-10-31 上海汽车集团股份有限公司 Hydraulic oil output device and its control method
CN106051958A (en) * 2016-07-12 2016-10-26 广东申菱环境系统股份有限公司 Evaporative condensation direct-expansion evaporative air conditioning system for metro station
TWI626627B (en) * 2017-08-31 2018-06-11 研能科技股份有限公司 Actuating sensor module
CN207342896U (en) * 2017-12-18 2018-05-11 北京市市政工程设计研究总院有限公司 Urban transportation tunnel electronic type PM2.5 air cleaning units

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吴妍: "地铁隧道活塞风井通风性能的数值模拟研究", 《建筑科学》 *

Similar Documents

Publication Publication Date Title
Pope 3rd et al. Synoptic weather modeling and estimates of the exposure-response relationship between daily mortality and particulate air pollution.
Gold et al. Particulate and ozone pollutant effects on the respiratory function of children in southwest Mexico City
WO2006120537A3 (en) A method and a system for enhanced flow line control
CN206057283U (en) A kind of many dot matrix type flue gas on-line continuous monitoring devices
DE102009016509A1 (en) Method for adjusting mass flow in exhaust gas recirculation process in diesel engine in passenger car, involves utilizing model-assisted predictive automatic controller for regulating virtually determined nitrogen oxide value
EP1928675B1 (en) Method and device for detecting leaks in an air spring arrangement in a motor vehicle
EP2975486B2 (en) Method for filling a container with a fill product by means of a proportional valve
CN104535714B (en) By controlling the growth conditions assessment plant device to gray haze Air purification
CN109375501A (en) A method of it is opened and closed according to tunnel inner air and outer air quality control piston air-valve
CN105928164A (en) Positive-pressure control system applicable to area air purifying
Christensen et al. RbSr ages and Nd isotopic compositions of melt inclusions from the Bishop Tuff and the generation of silicic magma
CN110466306A (en) For detecting automobile sensor component, vehicle and its application of air quality
Tariq et al. Energy-efficient time-delay compensated ventilation control system for sustainable subway air quality management under various outdoor conditions
Anderson et al. Derailment probability analysis and modeling of mainline freight trains
CASARETT The vital sacs: Alveolar clearance mechanisms in inhalation toxicology
DE102008003237A1 (en) Device and method for controlling the sedation depth of a mechanically ventilated patient
DE112020000430T5 (en) SYSTEM AND METHOD FOR MONITORING THE LEVEL OF A VAPORIZER RESERVOIR IN AN ANESTHETIC VAPORIZER SYSTEM
DE202010000391U1 (en) Device for setting predetermined dilution rates for measuring odors by means of dynamic olfactometry
DE670571C (en) Method and device for the continuous determination of the weight of propane bottles
DE4400385A1 (en) Continuous gas content measurement in liq.
Du Total indoor environmental pollutant control of intelligent building based on dynamic CGE
Bates Detection of chronic respiratory bronchiolitis in oxidant-exposed populations: analogy to tobacco smoke exposure.
DE10239996A1 (en) Methods for leak testing vehicles
CN117053323B (en) Air purification system based on indoor air proportion self-balancing
Sillman et al. Nitrogen oxides, regional transport, and ozone air quality: results of a regional-scale model for the midwestern United States

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190222