CN109365537A - The method of adjustment of tandem mill memorial archway and its pedestal - Google Patents
The method of adjustment of tandem mill memorial archway and its pedestal Download PDFInfo
- Publication number
- CN109365537A CN109365537A CN201811304150.6A CN201811304150A CN109365537A CN 109365537 A CN109365537 A CN 109365537A CN 201811304150 A CN201811304150 A CN 201811304150A CN 109365537 A CN109365537 A CN 109365537A
- Authority
- CN
- China
- Prior art keywords
- isometry block
- rolling mill
- carries out
- mill base
- adjustment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B21—MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21B—ROLLING OF METAL
- B21B31/00—Rolling stand structures; Mounting, adjusting, or interchanging rolls, roll mountings, or stand frames
- B21B31/02—Rolling stand frames or housings; Roll mountings ; Roll chocks
Abstract
The present invention relates to the installing area of multi-set of rolling mill, the method for adjustment of specifically a kind of tandem mill memorial archway and its pedestal;It is characterized in that: including step 1, the preparation of isometry block;Step 2, the erection of isometry block;Step 3 carries out rolling mill base longitudinal center centering with isometry block;Step 4 carries out rolling mill base entrance, the outlet horizontal centering of pedestal with isometry block;Step 5 carries out the adjacent horizontal centering of rolling mill base with isometry block;Step 6 carries out adjacent milling train with isometry block and exports pedestal depth of parallelism centering;Step 7 carries out mutually neck mill stand frame depth of parallelism adjustment with isometry block.This method of adjustment carries out subsidiary compared with traditional tandem mill memorial archway and pedestal method of adjustment, using isometry block, accurately datum clamp face can be made effectively to extend, the installation progress of equipment is also accelerated while improving detection accuracy.
Description
Technical field
The present invention relates to the installing area of multi-set of rolling mill, the adjustment side of specifically a kind of tandem mill memorial archway and its pedestal
Method.
Background technique
During tandem mill rolling mill base and memorial archway adjust, rolling mill base upper surface and be all non-fully smooth high-precision
Machined surface is spent, rolling-mill housing installation site is usually polished surface, and other positions are non-processing face and to form certain cushion cap convex
It rises, directly affects leveling ruler erection.It is usual to improve rolling mill base Adjustment precision during adjacent rolling mill base depth of parallelism centering
Using rolling mill base side as detection reference, the spacing in two parallel vertical faces how is detected, detection faces is needed to be extended, passed
The construction technology means of system cannot be effectively resolved.
Summary of the invention
It is an object of the invention to overcome the shortcomings of existing traditional construction means, milling train bottom can effectively be solved by providing one kind
The non-processing influence in face of the detection of rolling mill base levelness of seat and adjacent milling train export the debugging of pedestal parallelism detection problem
Method.
In order to achieve the above object, the present invention is implemented as follows:
A kind of method of adjustment of tandem mill memorial archway and its pedestal, including
Step 1, the preparation of isometry block:
Step 1.1 is quenched bloom, its hardness values is made to reach HRC58-HRC62;
Step 1.2 carries out fine grinding operation to step 1.1 gained bloom, makes its flatness tolerance no more than 0.005mm, any two
The parallelism tolerance of parallel surface is not more than 0.01mm;
Step 2, the erection of isometry block:
Step 2.1, the polished surface position for being directly placed at rolling mill base upper surface for setting up the isometry block that leveling ruler uses;
Step 2.2, the isometry block for cooperating inside micrometer to use, need to use hold out against screw rod isometry block held out against at milling train bottom
Seat side;Wherein, it holds out against screw rod to be made using 16mm screw rod, both ends are locked with double nut;
Step 3 carries out rolling mill base longitudinal center centering with isometry block:
Step 3.1 has set up isometry block in rolling mill base side;
Step 3.2 places inside micrometer bracket, selects inside micrometer to measure isometry block to milling train center according to measurement distance
The distance of line is adjusted rolling mill base by design drawing size;
Step 4 carries out rolling mill base entrance, the outlet horizontal centering of pedestal with isometry block:
Step 4.1 places isometry block in inlet of rolling mill, outlet rolling mill base diagonal positions, and leveling ruler is placed on isometry block,
Frame level is placed in the middle part of leveling ruler carries out entrance, outlet rolling mill base adjustment;
Step 5 carries out the adjacent horizontal centering of rolling mill base with isometry block:
Step 5.1 sets up leveling ruler between adjacent rolling mill base, places isometry block in leveling ruler bottom, frame is placed in the middle part of leveling ruler
Level meter carries out the adjustment of adjacent rack rolling mill base;
Step 6 carries out adjacent milling train with isometry block and exports pedestal depth of parallelism centering:
Step 6.1, in the outlet of adjacent milling train, base side sets up isometry block, uses distance tune between inside micrometer measurement isometry block
Whole adjacent rack exports wing base;
Step 7 carries out mutually neck mill stand frame depth of parallelism adjustment with isometry block:
Step 7.1 sets up isometry block in adjacent rack window inner side;Isometry block is fixed in milling train window using screw rod is held out against
Side measures the adjacent rack memorial archway depth of parallelism using inside micrometer.
This method of adjustment carries out auxiliary survey using isometry block compared with traditional tandem mill memorial archway and pedestal method of adjustment
Amount, accurately can be such that datum clamp face effectively extends, the installation progress of equipment is also accelerated while improving detection accuracy.
Detailed description of the invention
Fig. 1 is that isometry block holds out against screw rod fabrication and installation schematic diagram.
Fig. 2 is isometry block for rolling mill base adjustment schematic diagram.
Fig. 3 is that isometry block is used for rolling mill base diagonal line Level-adjusting schematic diagram.
Fig. 4 is that isometry block is used for adjacent rolling mill base Level-adjusting schematic diagram.
Fig. 5 is isometry block for adjacent rack outlet pedestal depth of parallelism adjustment schematic diagram.
Fig. 6 is isometry block for adjacent rack window depth of parallelism adjustment schematic diagram.
In figure:
1 rolling mill base, 2 isometry blocks, 3 hold out against screw rod, 4 milling train center lines, 5 inside micrometers, 6 inside micrometer supports
Seat, 7 leveling rulers, 8 frame levels, 9 dial gauges, 10 mill housings.
Specific embodiment
The present invention is further illustrated below by way of specific embodiment.
The embodiment that the invention will now be described in detail with reference to the accompanying drawings.
A method of tandem mill memorial archway is carried out using isometry block and pedestal adjusts, including
Step 1,2 type selecting of isometry block:
Isometry block 2 is selected to use for setting up leveling ruler and inside micrometer is cooperated to use.Two kinds of specification isometry blocks 2 respectively choose processing
10-20 block adjusts needs convenient for multi-frame memorial archway pedestal simultaneously.The outer diameter that isometry block 2 is 0.01mm using preceding service precision grade
Each part thickness of miking monolithic isometry block 2 and muti-piece are superimposed thickness.Width is selected for setting up the isometry block 2 that leveling ruler uses
20mm × thickness 10mm × long 150mm, the isometry block 2 for cooperating inside micrometer to carry out depth of parallelism adjustment select wide 40mm × thickness
10mm × long 150mm.
Step 2, the erection of isometry block 2:
It is directly placed at rolling mill base upper surface polished surface position for setting up the isometry block 2 that leveling ruler uses, in cooperating
The isometry block 2 that diameter micrometer uses, need to use hold out against screw rod 3 isometry block 2 held out against in rolling mill base side.Holding out against screw rod 3 makes
It is made with 16mm screw rod, both ends are locked with double nut, are held out against as shown in Figure 1 in rolling mill base side.
Step 3, isometry block 2 are used for rolling mill base longitudinal center centering:
Isometry block 2 is set up in rolling mill base side, first placement inside micrometer bracket 6, internal diameter is selected according to measurement distance
Micrometer 5 measures distance such as Fig. 2 that isometry block 2 arrives milling train center line 4, is adjusted rolling mill base by design drawing size.
Step 4, isometry block 2 is for rolling mill base entrance, the outlet horizontal centering of pedestal:
Enter in milling train, export 1 diagonal positions of rolling mill base and place isometry block 2, leveling ruler 7 is placed on isometry block 2, in leveling ruler
It places frame level 8 and carries out entrance, the outlet adjustment of rolling mill base 1 in 7 middle parts.
Step 5, isometry block are used for the horizontal centering of adjacent rolling mill base:
Adjacent: setting up leveling ruler 7 between rolling mill base 1 as shown in figure 3, placing isometry block 2 in leveling ruler bottom, put in the middle part of leveling ruler 7
It sets frame level 8 and carries out the adjustment of adjacent rack rolling mill base 1.
Step 6, isometry block 2 export pedestal depth of parallelism centering for adjacent milling train:
In the outlet of adjacent milling train, base side sets up isometry block 2 as shown in figure 4, measuring 2 spacing of isometry block using inside micrometer 5
Wing base is exported from adjustment adjacent rack.
Step 7, isometry block 2 is for mutually neck mill stand frame depth of parallelism adjustment:
Screw rod 3 is held out against in erection 2 use of isometry block of adjacent rack window inner side, and isometry block 2 is fixed on milling train window inner side as schemed
Shown in 5, the adjacent rack memorial archway depth of parallelism is measured using inside micrometer 5.
Claims (1)
1. the method for adjustment of a kind of tandem mill memorial archway and its pedestal, it is characterized in that: including
Step 1, the preparation of isometry block:
Step 1.1 is quenched bloom, its hardness values is made to reach HRC58-HRC62;
Step 1.2 carries out fine grinding operation to step 1.1 gained bloom, makes its flatness tolerance no more than 0.005mm, any two
The parallelism tolerance of parallel surface is not more than 0.01mm;
Step 2, the erection of isometry block:
Step 2.1, the polished surface position for being directly placed at rolling mill base upper surface for setting up the isometry block that leveling ruler uses;
Step 2.2, the isometry block for cooperating inside micrometer to use, need to use hold out against screw rod isometry block held out against at milling train bottom
Seat side;Wherein, it holds out against screw rod to be made using 16mm screw rod, both ends are locked with double nut;
Step 3 carries out rolling mill base longitudinal center centering with isometry block:
Step 3.1 has set up isometry block in rolling mill base side;
Step 3.2 places inside micrometer bracket, selects inside micrometer to measure isometry block to milling train center according to measurement distance
The distance of line is adjusted rolling mill base by design drawing size;
Step 4 carries out rolling mill base entrance, the outlet horizontal centering of pedestal with isometry block:
Step 4.1 places isometry block in inlet of rolling mill, outlet rolling mill base diagonal positions, and leveling ruler is placed on isometry block,
Frame level is placed in the middle part of leveling ruler carries out entrance, outlet rolling mill base adjustment;
Step 5 carries out the adjacent horizontal centering of rolling mill base with isometry block:
Step 5.1 sets up leveling ruler between adjacent rolling mill base, places isometry block in leveling ruler bottom, frame is placed in the middle part of leveling ruler
Level meter carries out the adjustment of adjacent rack rolling mill base;
Step 6 carries out adjacent milling train with isometry block and exports pedestal depth of parallelism centering:
Step 6.1, in the outlet of adjacent milling train, base side sets up isometry block, uses distance tune between inside micrometer measurement isometry block
Whole adjacent rack exports wing base;
Step 7 carries out mutually neck mill stand frame depth of parallelism adjustment with isometry block:
Step 7.1 sets up isometry block in adjacent rack window inner side;Isometry block is fixed in milling train window using screw rod is held out against
Side measures the adjacent rack memorial archway depth of parallelism using inside micrometer.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811304150.6A CN109365537B (en) | 2018-11-03 | 2018-11-03 | Continuous mill housing and adjusting method of base thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811304150.6A CN109365537B (en) | 2018-11-03 | 2018-11-03 | Continuous mill housing and adjusting method of base thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109365537A true CN109365537A (en) | 2019-02-22 |
CN109365537B CN109365537B (en) | 2020-05-26 |
Family
ID=65397135
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811304150.6A Active CN109365537B (en) | 2018-11-03 | 2018-11-03 | Continuous mill housing and adjusting method of base thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109365537B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110743918A (en) * | 2019-09-20 | 2020-02-04 | 中国二十冶集团有限公司 | Method for installing main transmission device of continuous rolling mill in place |
CN112658035A (en) * | 2020-11-30 | 2021-04-16 | 中国十九冶集团有限公司 | Positioning and aligning method for rolling mill base plate and frame |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101456039A (en) * | 2007-12-12 | 2009-06-17 | 中国二十冶建设有限公司 | Rolling-mill base installation measurement method |
CN101458057A (en) * | 2007-12-12 | 2009-06-17 | 中国二十冶建设有限公司 | Housing window squareness and parallelism measurement method |
CN101664760A (en) * | 2008-09-05 | 2010-03-10 | 中国二十冶建设有限公司 | Method for adjusting housings outside single stand reversible rolling mill |
CN102240680A (en) * | 2011-05-06 | 2011-11-16 | 天津二十冶建设有限公司 | Method for adjusting verticality of rolling mill |
CN104858238A (en) * | 2015-05-26 | 2015-08-26 | 中冶陕压重工设备有限公司 | Roll changing mechanism for working roll of rolling mill |
CN105798067A (en) * | 2016-04-28 | 2016-07-27 | 中冶天工集团有限公司 | Accurate installation measuring method for rolling mill bases |
CN105880298A (en) * | 2015-01-26 | 2016-08-24 | 鞍钢股份有限公司 | Centering calibration method for rolling center line |
CN107234138A (en) * | 2017-06-30 | 2017-10-10 | 攀钢集团工程技术有限公司 | Mill housing aligning method |
-
2018
- 2018-11-03 CN CN201811304150.6A patent/CN109365537B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101456039A (en) * | 2007-12-12 | 2009-06-17 | 中国二十冶建设有限公司 | Rolling-mill base installation measurement method |
CN101458057A (en) * | 2007-12-12 | 2009-06-17 | 中国二十冶建设有限公司 | Housing window squareness and parallelism measurement method |
CN101664760A (en) * | 2008-09-05 | 2010-03-10 | 中国二十冶建设有限公司 | Method for adjusting housings outside single stand reversible rolling mill |
CN102240680A (en) * | 2011-05-06 | 2011-11-16 | 天津二十冶建设有限公司 | Method for adjusting verticality of rolling mill |
CN105880298A (en) * | 2015-01-26 | 2016-08-24 | 鞍钢股份有限公司 | Centering calibration method for rolling center line |
CN104858238A (en) * | 2015-05-26 | 2015-08-26 | 中冶陕压重工设备有限公司 | Roll changing mechanism for working roll of rolling mill |
CN105798067A (en) * | 2016-04-28 | 2016-07-27 | 中冶天工集团有限公司 | Accurate installation measuring method for rolling mill bases |
CN107234138A (en) * | 2017-06-30 | 2017-10-10 | 攀钢集团工程技术有限公司 | Mill housing aligning method |
Non-Patent Citations (2)
Title |
---|
李春至: "铝板带箔冷轧引进设备的安装实践(2)", 《轻合金加工技术》 * |
秦付良: "《实用机电工程安装技术手册》", 30 September 2006, 北京:中国电力出版社 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110743918A (en) * | 2019-09-20 | 2020-02-04 | 中国二十冶集团有限公司 | Method for installing main transmission device of continuous rolling mill in place |
CN110743918B (en) * | 2019-09-20 | 2021-05-14 | 中国二十冶集团有限公司 | Method for installing main transmission device of continuous rolling mill in place |
CN112658035A (en) * | 2020-11-30 | 2021-04-16 | 中国十九冶集团有限公司 | Positioning and aligning method for rolling mill base plate and frame |
Also Published As
Publication number | Publication date |
---|---|
CN109365537B (en) | 2020-05-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101318280B (en) | Overlength bed way precision finishing process | |
CN101664760B (en) | Method for adjusting housings outside of single stand reversible rolling mill | |
CN101456039A (en) | Rolling-mill base installation measurement method | |
CN203908746U (en) | Bridge flexibility tester | |
CN109365537A (en) | The method of adjustment of tandem mill memorial archway and its pedestal | |
CN107234138A (en) | Mill housing aligning method | |
CN106091992A (en) | Plane milling and boring machine bed ways parallelism detecting device and detection method | |
CN101398118A (en) | Installing and centering method for power reels | |
CN106181571A (en) | Large-sized numerical control gear hobbing machine knife frame registration detects device and detection and method of adjustment | |
CN102416496B (en) | Method for eliminating bending deformation of rolling mill-type heavy part | |
CN206876098U (en) | A kind of detection means of bend glass | |
CN106424161B (en) | A kind of method and dedicated unit of determining rolling centerline | |
CN102535275B (en) | Calibrating device for standard frame of rail plate | |
CN103398704B (en) | Method for measuring foundation frame at continuous-casting sector-shaped section | |
CN107626752B (en) | A kind of bearing calibration of roll pass station | |
CN102350523B (en) | Method for eliminating twist deformation of rolling mill heavy parts | |
CN206308568U (en) | A kind of measurement apparatus of auxiliary track panel coarse adjustment | |
CN110548844B (en) | Square billet continuous casting sector section assembling method | |
CN110230749B (en) | Method for installing and adjusting rail seat of high-precision roll grinder | |
CN203274662U (en) | Flatness measuring device for producing machine tools | |
CN102179661B (en) | Method for machining frame of cold continuous rolling mill | |
CN103411575B (en) | Hydraulic dynamometer main shaft and the detection method processing and coordinating tapering of rotor | |
CN104440387A (en) | Tool for machining and correcting 180-degree-distributed double-key groove in large motor shaft stretching end | |
CN205537436U (en) | Utensil is examined in external diameter measurement of axle, dish, wheel type part | |
CN104308110B (en) | Alignment table centering contact mechanism precision micromatic setting and method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |