CN109339451A - The floor heating construction method of factory's energy pressure-bearing weight - Google Patents
The floor heating construction method of factory's energy pressure-bearing weight Download PDFInfo
- Publication number
- CN109339451A CN109339451A CN201811477522.5A CN201811477522A CN109339451A CN 109339451 A CN109339451 A CN 109339451A CN 201811477522 A CN201811477522 A CN 201811477522A CN 109339451 A CN109339451 A CN 109339451A
- Authority
- CN
- China
- Prior art keywords
- floor heating
- concrete
- heating pipe
- laid
- factory
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Abstract
The invention discloses a kind of factory floor heating construction methods of energy pressure-bearing weight, comprising the following steps: is laid with a layer concrete in the factory for needing to be laid with floor heating, then draws a line at a certain distance on the concrete laid;It is punched on each line, the quantity in hole is several, and is uniformly placed equidistant with;The stopper in above-mentioned hole internal plug, the size of stopper are identical as the diameter in the hole;Foam strip is tied up on floor heating pipe for use with adhesive tape;The effective plastic clamp with nail of the floor heating bound is fixed on the stopper;It installs and is poured concrete in the gap location of floor heating pipe after floor heating pipe, concrete height and the floor heating pipe of casting are flush;It is being laid with one layer of wire netting above after pouring concrete between floor heating pipe and floor heating pipe, is then being poured a layer concrete, it is levelling finally to carry out surface.The method of the present invention is simple, and load bearing effect is good, the weight of 10 tons of pressure-bearing of energy, and heat dissipation effect is preferable, and extends the service life of floor heating.
Description
Technical field
The present invention relates to floor heating technical field of construction, more particularly, to a kind of factory floor heating construction party of energy pressure-bearing weight
Method.
Background technique
In existing floor heating structure, in-site installation laying is usually used, but was installed since scene carries out floor heating
Each structure sheaf and pipeline are laid with respectively in journey, and thickness is big;It is fixed also to need to carry out pipeline scene, procedure complexity, so that
The laying duration of floor heating is longer under normal circumstances;In addition, existing floor heating structure pipeline is needed in process of deployment by whole foam
It is laid on and pours on the concrete being poured in, then floor heating pipe is installed on foam, install after floor heating pipe in the coagulation for being laid with 10cm thickness
Soil, such structure and paving mode are easy to appear the phenomenon that being not fixed firmly, destructible interlayer structure;And use whole foam
It being easily deformed, load-bearing is poor, and heat dissipation effect is bad, service life is reduced, for factory, this common laying
Mode is simultaneously not suitable for, because needing to place very heavy equipment and fork truck in factory, fork truck is easy to damage by pressure on ground and floor heating pipe, from
And influence to use, and for factory, it is impossible to floor heating is frequently replaced, brings many inconvenience to enterprise.In view of the above original
Cause, design a kind of factory with can the floor heating construction method of pressure-bearing weight be necessary.
Summary of the invention
The object of the present invention is to provide a kind of factory floor heating construction methods of energy pressure-bearing weight, and method is simple, load-bearing effect
Fruit is good, the weight of 10 tons of pressure-bearing of energy, and heat dissipation effect is preferable, and extends the service life of floor heating.
To achieve the above object, the present invention provides a kind of factory floor heating construction methods of energy pressure-bearing weight, including with
Lower step:
A, it draws lines: a layer concrete is laid in the factory for needing to be laid with floor heating, then on the concrete laid
A line is drawn at a certain distance;
B, it punches: being punched on each line, the quantity in hole is several, and is uniformly placed equidistant with;
C, fill in stopper: the stopper in above-mentioned hole internal plug, the size of stopper are identical as the diameter in the hole;
D, foam strip is bound on floor heating pipe: being tied up foam strip on floor heating pipe for use with adhesive tape;
E, floor heating pipe is installed: the effective plastic clamp with nail of the floor heating bound is fixed on the stopper;
F, it is poured concrete: installing and be poured concrete in the gap location of floor heating pipe after floor heating pipe, the concrete of casting is high
Degree is flush with floor heating pipe;
G, it is surface-treated: being laid with one layer of wire netting above after pouring concrete between floor heating pipe and floor heating pipe, then
It is being poured a layer concrete, it is levelling finally to carry out surface.
Preferably, the concrete thickness being laid in the step A is 18-20cm.
Preferably, the spacing of the step B mesoporous is 40cm, and the diameter in hole is 5cm.
Preferably, the foam strip in the step D is set as rectangular parallelepiped structure, and the width of the foam strip is 2cm.
Preferably, the plastic clamp in the step E is made of fixed part and clamping portion, and the clamping portion is set as semicircle
It shape structure and is integrally formed with the fixed part, is provided with fixation hole on the fixed part.
Preferably, in the step F concrete with a thickness of 4cm.
Preferably, the wire netting in the step G is set as square structure, and the width of the wire netting is 1cm, institute
State concrete with a thickness of 4cm.
Therefore, the factory of the present invention using the above structure floor heating construction method of energy pressure-bearing weight, method is simple, load-bearing
Effect is good, the weight of 10 tons of pressure-bearing of energy, and heat dissipation effect is preferable, and extends the service life of floor heating.
Below by drawings and examples, technical scheme of the present invention will be described in further detail.
Detailed description of the invention
Fig. 1 is a kind of process flow chart of the floor heating construction method embodiment of factory's energy pressure-bearing weight of the present invention;
Fig. 2 is a kind of plastic clamp structural representation of the floor heating construction method embodiment of factory's energy pressure-bearing weight of the present invention
Figure.
Specific embodiment
Embodiment
Fig. 1 is a kind of process flow chart of the floor heating construction method embodiment of factory's energy pressure-bearing weight of the present invention, is such as schemed
Shown, the present invention provides a kind of factory floor heating construction methods of energy pressure-bearing weight, comprising the following steps:
A, it draws lines: being laid with a layer concrete in the factory for needing to be laid with floor heating, concrete thickness 18-20cm, then
Draw a line at a certain distance on the concrete laid;
B, it punches: being punched on each line, the quantity in hole is several, and is uniformly placed equidistant with, the spacing in hole
For 40cm, the diameter in hole is 5cm;
C, fill in stopper: the stopper in above-mentioned hole internal plug, the size of stopper are identical as the diameter in the hole;
D, foam strip is bound on floor heating pipe: being tied up foam strip on floor heating pipe for use with adhesive tape, foam strip is set as rectangular
Body structure, and the width of the foam strip is 2cm;
E, floor heating pipe is installed: the effective plastic clamp with nail of the floor heating bound is fixed on the stopper;
F, be poured concrete: installing and be poured concrete in the gap location of floor heating pipe after floor heating pipe, concrete with a thickness of
4cm, concrete height and the floor heating pipe of casting are flush;
G, it is surface-treated: being laid with one layer of wire netting, iron wire above after pouring concrete between floor heating pipe and floor heating pipe
Net is set as square structure, and the width of the wire netting is 1cm, is then being poured a layer concrete, the thickness of concrete
For 4cm, it is levelling finally to carry out surface.
The present invention punches on the line of the concrete laid first, then in hole internal plug stopper, will have foam strip
The effective plastic clamp of floor heating is fixed on stopper, and concrete is poured at the gap of floor heating pipe and floor heating pipe, is then laid with iron wire
Net re-lays concrete on wire netting, and such weight is pressed in above, and the concrete and floor heating pipe at floor heating pipe gap are mutually neat
Flat, the two undertakes weight together in this way, to increase pressure-bearing effect, extends the service life of floor heating pipe.
Fig. 2 is a kind of plastic clamp structural representation of the floor heating construction method embodiment of factory's energy pressure-bearing weight of the present invention
Figure, as shown, plastic clamp is made of fixed part 1 and clamping portion 2, clamping portion 2 be set as semicircular structure and with fixed part 1
It is integrally formed, is provided with fixation hole 3 on fixed part 1.
Therefore, the factory of the present invention using the above structure floor heating construction method of energy pressure-bearing weight, method is simple, load-bearing
Effect is good, the weight of 10 tons of pressure-bearing of energy, and heat dissipation effect is preferable, and extends the service life of floor heating.
Finally, it should be noted that the above embodiments are merely illustrative of the technical solutions of the present invention rather than is limited,
Although the present invention is described in detail with reference to preferred embodiments, those skilled in the art should understand that: its according to
So can be with modification or equivalent replacement of the technical solution of the present invention are made, and these modifications or equivalent replacement cannot also make to repair
Technical solution after changing is detached from the spirit and scope of technical solution of the present invention.
Claims (7)
1. a kind of factory floor heating construction method of energy pressure-bearing weight, which comprises the following steps:
A, draw lines: a layer concrete is laid in the factory for needing to be laid with floor heating, then on the concrete laid every
Certain distance draws a line;
B, it punches: being punched on each line, the quantity in hole is several, and is uniformly placed equidistant with;
C, fill in stopper: the stopper in above-mentioned hole internal plug, the size of stopper are identical as the diameter in the hole;
D, foam strip is bound on floor heating pipe: being tied up foam strip on floor heating pipe for use with adhesive tape;
E, floor heating pipe is installed: the effective plastic clamp with nail of the floor heating bound is fixed on the stopper;
F, be poured concrete: installing and be poured concrete in the gap location of floor heating pipe after floor heating pipe, the concrete height of casting with
Floor heating pipe is flush;
G, it is surface-treated: being laid with one layer of wire netting above after pouring concrete between floor heating pipe and floor heating pipe, then pouring
It is levelling finally to carry out surface for one layer concrete of note.
2. the factory according to claim 1 floor heating construction method of energy pressure-bearing weight, it is characterised in that: the step A
The concrete thickness of middle laying is 18-20cm.
3. the factory according to claim 1 floor heating construction method of energy pressure-bearing weight, it is characterised in that: the step B
The spacing of mesoporous is 40cm, and the diameter in hole is 5cm.
4. the factory according to claim 1 floor heating construction method of energy pressure-bearing weight, it is characterised in that: the step D
In foam strip be set as rectangular parallelepiped structure, and the width of the foam strip is 2cm.
5. the factory according to claim 1 floor heating construction method of energy pressure-bearing weight, it is characterised in that: the step E
In plastic clamp be made of fixed part and clamping portion, the clamping portion be set as semicircular structure and with fixed part one
It forms, is provided with fixation hole on the fixed part.
6. the factory according to claim 1 floor heating construction method of energy pressure-bearing weight, it is characterised in that: the step F
Middle concrete with a thickness of 4cm.
7. the factory according to claim 1 floor heating construction method of energy pressure-bearing weight, it is characterised in that: the step G
In wire netting be set as square structure, and the width of the wire netting is 1cm, the concrete with a thickness of 4cm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811477522.5A CN109339451A (en) | 2018-12-05 | 2018-12-05 | The floor heating construction method of factory's energy pressure-bearing weight |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811477522.5A CN109339451A (en) | 2018-12-05 | 2018-12-05 | The floor heating construction method of factory's energy pressure-bearing weight |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109339451A true CN109339451A (en) | 2019-02-15 |
Family
ID=65320297
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811477522.5A Pending CN109339451A (en) | 2018-12-05 | 2018-12-05 | The floor heating construction method of factory's energy pressure-bearing weight |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109339451A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113125077A (en) * | 2021-04-13 | 2021-07-16 | 湖州建院环境艺术工程有限公司 | Water floor heating construction method |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3554067B2 (en) * | 1995-04-04 | 2004-08-11 | 東京瓦斯株式会社 | Interior body |
CN101825308A (en) * | 2010-05-07 | 2010-09-08 | 奉政一 | Geothermal paved heating device |
CN101914987A (en) * | 2010-09-13 | 2010-12-15 | 天津天一建设集团有限公司 | Ground construction method of ground heating fiber steel reinforcing concrete |
CN201883549U (en) * | 2010-12-13 | 2011-06-29 | 上海朗诗建筑科技有限公司 | Concrete structure capable of improving energy accumulation and heat insulation of building ground surface |
CN102777013A (en) * | 2012-07-17 | 2012-11-14 | 黄茂景 | Water floor heating construction method |
JP2014129975A (en) * | 2012-12-28 | 2014-07-10 | Sumisho Metalex Corp | Construction method on site of hot water mat for floor heating |
CN204693559U (en) * | 2015-05-22 | 2015-10-07 | 广州豪特电器设备有限公司 | Pressure-bearing type floor heating structure |
CN205908946U (en) * | 2016-05-04 | 2017-01-25 | 王丰景 | Warm up laying device with heat preservation fixed band |
CN206016166U (en) * | 2016-08-31 | 2017-03-15 | 青岛中建联合建设工程有限公司 | A kind of anticracking floor heating earth construction |
CN206989295U (en) * | 2017-07-21 | 2018-02-09 | 常州市武进建筑设计院有限公司 | Ground radiation heating floor panel structure |
-
2018
- 2018-12-05 CN CN201811477522.5A patent/CN109339451A/en active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3554067B2 (en) * | 1995-04-04 | 2004-08-11 | 東京瓦斯株式会社 | Interior body |
CN101825308A (en) * | 2010-05-07 | 2010-09-08 | 奉政一 | Geothermal paved heating device |
CN101914987A (en) * | 2010-09-13 | 2010-12-15 | 天津天一建设集团有限公司 | Ground construction method of ground heating fiber steel reinforcing concrete |
CN201883549U (en) * | 2010-12-13 | 2011-06-29 | 上海朗诗建筑科技有限公司 | Concrete structure capable of improving energy accumulation and heat insulation of building ground surface |
CN102777013A (en) * | 2012-07-17 | 2012-11-14 | 黄茂景 | Water floor heating construction method |
JP2014129975A (en) * | 2012-12-28 | 2014-07-10 | Sumisho Metalex Corp | Construction method on site of hot water mat for floor heating |
CN204693559U (en) * | 2015-05-22 | 2015-10-07 | 广州豪特电器设备有限公司 | Pressure-bearing type floor heating structure |
CN205908946U (en) * | 2016-05-04 | 2017-01-25 | 王丰景 | Warm up laying device with heat preservation fixed band |
CN206016166U (en) * | 2016-08-31 | 2017-03-15 | 青岛中建联合建设工程有限公司 | A kind of anticracking floor heating earth construction |
CN206989295U (en) * | 2017-07-21 | 2018-02-09 | 常州市武进建筑设计院有限公司 | Ground radiation heating floor panel structure |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113125077A (en) * | 2021-04-13 | 2021-07-16 | 湖州建院环境艺术工程有限公司 | Water floor heating construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203924112U (en) | Prefabricated pipe gallery | |
CN103591628A (en) | Floor radiant heating construction method | |
KR102106058B1 (en) | System for prevention of pavement freezing | |
CN109339451A (en) | The floor heating construction method of factory's energy pressure-bearing weight | |
KR20110041937A (en) | Power supply device for electric vehicle protected by concrete structure | |
CN206759013U (en) | Framework assembly type cable slot unit and cable duct | |
US8806811B1 (en) | Thermally non-conductive lifting insert for insulated concrete sandwich panels | |
CN205541639U (en) | Electron sign marker peg | |
CN207453225U (en) | A kind of superstructure unit and assembly concrete integrated floor | |
JP4111616B2 (en) | Concrete slab | |
KR102141577B1 (en) | Method and structure for constructing ventilation duct | |
CN207685852U (en) | The multi-faceted guyed foundation of anticorrosion shaft tower | |
CN201153205Y (en) | High-voltage cable S shaped laying-out construction | |
CN109537635B (en) | Waterproof node for deformation joint of top plate of underground garage and construction method | |
KR101967402B1 (en) | Foundation structure and construction method thereof | |
CN202495309U (en) | Directly-inserting type simple insulator | |
CN201713933U (en) | Trench cover plate | |
CN204311606U (en) | A kind of footing reinforced body of wall | |
CN215253712U (en) | Anchor plate and partition wall connecting device for building reconstruction | |
JP6514947B2 (en) | Construction method of waterproof structure and board connector used therefor | |
CN205738733U (en) | A kind of coil of strip preventer | |
CN213390689U (en) | New and old wall overlap joint prevents processing apparatus that ftractures | |
CN203866857U (en) | Universal base for mounting MINI equipment cabinet | |
CN208267116U (en) | Built-in fitting for the installation of electromechanical pipeline bracket | |
KR20190028167A (en) | Apparatus for load distribution of underground structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190215 |