Prior art keywords
reinforced bar
bar net
longitudinal
grid
rib
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811150363.8A
Other languages
Chinese (zh)
Inventor
杜运兴
谭宇
周芬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan University
Original Assignee
Hunan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan University filed Critical Hunan University
Priority to CN201811150363.8A priority Critical patent/CN109339022A/en
Publication of CN109339022A publication Critical patent/CN109339022A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/005Soil-conditioning by mixing with fibrous materials, filaments, open mesh or the like
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0084Geogrids

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention patent relates to a kind of production method with drain function TGXG, this TGXG is made of grid cross rib, grid longitudinal rib and longitudinal drainage band;Grid cross rib and longitudinal rib are Soil test;Grid cross rib is inserted perpendicularly into hole of the longitudinal drainage with side, and is bonded in intersection melting welding;Grid longitudinal rib is laid on longitudinal drainage band two sides, and welds at square crossing position with grid cross rib;Longitudinal drainage is respectively the fastener and fixings of buckle structure with both ends, for realizing the splicing of muti-piece drainage geogrid longitudinal drainage band.The present invention can not only the operative constraint soil body, reduce the deformation of the soil body, moreover it is possible to reduce soil in pore water pressure, accelerate soil solidifying, enhance soil strength, can be applied to roadbed and barricade engineering.

Description

A kind of production method with drain function TGXG
Technical field
The present invention relates to a kind of Earthworking reinforced bar material and preparation method thereof, belongs to the draining of roadbed and barricade and reinforce and lead Domain.
Technical background
In Reinforced Material with Clay Engineering when using cohesive soil as filler, after surface water or Groundwater infiltration filler, viscosity Water in soil can not be discharged in time, this can reduce the effect of contraction of cohesive soil and reinforcement material, lead to reinforcing body reduced performance, into And reduce the stability of earth structure.Therefore, performance of the cohesive soil as the earth structure of filler is improved, it is necessary to adopt With good draining and reinforcement facility.At present it has been proposed that plastic draining board level to be laid in roadbed to the row for improving roadbed Water effect, but there is following two in such way.First, plastic draining board is easy to be pressed during compacted subgrade It is bad, and then influence its drainage effect;Second, plastic draining board cannot play reinforced action.Therefore, for using cohesive soil to fill Roadbed and barrier wall structure, if can be even more ideal using if a kind of Earthworking reinforced bar material for having both reinforcement and drain function , the bearing capacity and stability of roadbed and barrier wall structure on the one hand can be improved, the draining of cohesive soil on the other hand can be accelerated solid Knot.
Summary of the invention
In view of the above shortcomings of the prior art, technical problem to be solved by the invention is to provide one kind to have draining The TGXG of function not only has the function of excellent reinforcement but also has efficient drainage performance, can be applied to cohesive soil and fill out The roadbed and barricade engineering built.
In order to solve the above-mentioned technical problem, the technical scheme adopted by the invention is that: with drain function TGXG It is made of grid cross rib, grid longitudinal rib and longitudinal drainage band;Grid cross rib is inserted perpendicularly into hole of the longitudinal drainage with side, and It is bonded in intersection melting welding;Grid longitudinal rib and grid cross rib weld at square crossing;
Longitudinal water band is by lower layer's reinforced bar net, drainage belt ribs, suction water cellulose, upper layer reinforced bar net, geotextiles Filter membrane and water suction cotton pad composition;Upper layer reinforced bar net and lower layer's reinforced bar net are bonded in upper surface and the following table of drainage belt ribs respectively Face, and in the support plate fixing groove of the vertical supporting plate insertion upper layer reinforced bar net of lower layer's reinforced bar net, suction water cellulose longitudinal direction cloth It sets between upper layer reinforced bar net and lower layer's reinforced bar net, geotextiles filter membrane is covered on the appearance of upper layer reinforced bar net and lower layer's reinforced bar net Face, water suction cotton pad is placed on longitudinal drainage band both ends, and is in contact with discharging water fiber end.
The grid cross rib and longitudinal rib are Soil test.
The upper layer reinforced bar net and lower layer's reinforced bar net cross section is designed as arc, the aperture of arch section surface, mesh ruler Very little is (3~6) mm × (3~6) mm, wherein has vertical supporting plate on the inside of lower layer's reinforced bar net arch section, height is according to locating for The height of position drainage belt determines, there is support plate fixing groove on the inside of upper layer reinforced bar net arch section, and groove size is according to erecting It is determined to the size of support plate, ginseng is as shown in figure 3 and figure 4.
The drainage belt ribs side hole, end one end are that the fastener other end of buckle structure is then embedding Firmware, it is shown in Figure 2.
A kind of production method with drain function TGXG, follows these steps to carry out: (referring to Fig. 5 institute Show)
Step 1: assembled longitudinal drainage band
A) lower surface of drainage belt ribs is weldingly fixed on to two alar parts of lower layer's reinforced bar net using welding technology;
B) suction water cellulose is longitudinally laid with above lower layer's reinforced bar net;
C) upper layer reinforced bar net is covered above suction water cellulose;The vertical supporting plate of lower layer's reinforced bar net is set to be inserted into upper layer first Then two alar parts of upper layer reinforced bar net are weldingly fixed on drainage belt branch using welding technology by the support plate fixing groove of reinforced bar net The upper surface of stake rib;
D) one layer of geotextiles filter membrane is respectively covered in the outer surface of upper layer reinforced bar net and lower layer's reinforced bar net, and viscous using adhesive Fixation is connect, then one layer of water suction cotton pad is respectively placed at longitudinal drainage band both ends, is in contact with discharging water fiber end, thus makes Obtain longitudinal drainage band.
Step 2: completing the assembly of entire grid
A) position that grid longitudinal rib is marked first on grid cross rib, is then successively inserted perpendicularly into longitudinal row for grid cross rib Hole of the water with side, and melting welding is adhesively fixed in intersection;
B) grid longitudinal rib is laid on the position that grid cross rib marks in advance, the two is viscous using melting welding at crossover location It connects, a kind of TGXG with drain function is finally made.
The present invention has following technological merit:
1. the present invention is made of grid cross rib, grid longitudinal rib and longitudinal drainage band, wherein grid cross rib and longitudinal rib are soil Work band not only has the function of excellent reinforcement, but also has efficient drainage performance.
2. being disposed with suction water cellulose inside longitudinal drainage band, wherein suction water cellulose is made of hydrophilic hygroscopic materials, With a large amount of fine drainage channels, water is sucked out from soil for elder generation, and then the water of suction is discharged along its internal drainage channel The soil body, therefore improve the discharging water efficiency of longitudinal drainage band.
3. longitudinal drainage band is fabricated to flat, its contact area with soil is increased, longitudinal drainage band is conducive to Draining.
4. being evenly arranged with vertical supporting plate inside longitudinal drainage band, it is enough anti-not only to ensure that longitudinal drainage band has Pressure energy power will not be subject to crushing during compacted subgrade, it is thus also avoided that its internal suction water cellulose is crushed, and then influences Its discharging water effect.
5. being provided with buckle structure and water suction cotton pad at longitudinal drainage band both ends, it can easily connect muti-piece and drain geotechnological lattice The longitudinal drainage band of grid, forms unobstructed drainage channel, therefore facilitate site operation, enhances the practical of drainage geogrid Property.
Detailed description of the invention
Attached drawing 1 has the overall structure diagram of drain function TGXG.
The structural schematic diagram of 2 drainage belt ribs of attached drawing.
The structural schematic diagram of 3 lower layer's reinforced bar net of attached drawing.
The structural schematic diagram of 4 upper layer reinforced bar net of attached drawing.
Attached drawing 5 has the assembled procedure chart of drain function TGXG.
The cross-sectional view of 6 longitudinal drainage band of attached drawing.
The part description of main mark in figure: 1- grid cross rib, 2- grid longitudinal rib, 3- longitudinal drainage band, 4- lower layer reinforcement Net, 5- drainage belt ribs, 6- suction water cellulose, the upper layer 7- reinforced bar net, 8- geotextiles filter membrane, 9- water suction cotton pad.
Specific implementation method:
The present invention is described in further details with specific implementation method with reference to the accompanying drawing:
One, grid cross rib and longitudinal rib are specially treated with high tensile steel wire (or other fibers), and polyethylene (PE), and add Add other auxiliary agents, makes compound high-strength pulling-resisting band by squeezing out, and there is coarse embossing on surface;
Two, the production of drainage belt ribs, lower layer's reinforced bar net and upper layer reinforced bar net: raw material can select polyethylene (PE), the thermoplastics such as high density polyethylene (HDPE) (HDPE) or polypropylene (PP), are first moulded thermoplasticity with injection molding machine of plastic Material melting, then pressurization is injected in corresponding mold, and drainage belt ribs, lower layer's reinforced bar net and upper layer is made in last cooling and demolding Reinforced bar net, referring to shown in Fig. 2, Fig. 3 and Fig. 4;
Three, the production of monolith grid
Step 1: assembled longitudinal drainage band
A) lower surface of drainage belt ribs is weldingly fixed on to two alar parts of lower layer's reinforced bar net using welding technology;
B) suction water cellulose is longitudinally laid with above lower layer's reinforced bar net, suction water cellulose can use 4DG nylon Wicking fibers has multichannel cross section and biggish ratio using nylon and water suction additive as made of raw material Surface area, the diameter of micro-channel is between 5.7-47.8 μm;
C) upper layer reinforced bar net is covered above suction water cellulose;The vertical supporting plate of lower layer's reinforced bar net is set to be inserted into upper layer first Then two alar parts of upper layer reinforced bar net are weldingly fixed on drainage belt branch using welding technology by the support plate fixing groove of reinforced bar net The upper surface of stake rib;D) one layer of geotextiles filter membrane is respectively covered in the outer surface of upper layer reinforced bar net and lower layer's reinforced bar net, and uses glue Glutinous agent is adhesively fixed, and then respectively places one layer of water suction cotton pad at longitudinal drainage band both ends, is in contact with discharging water fiber end, Thus longitudinal drainage band is made;Geotextiles filter membrane is using nonwovens geotechniques such as short fine geotextiles, long fine geotextiles, Singed non-woven fabrics Cloth, the thickness for the cotton pad that absorbs water is between 3~5mm.
Step 2: completing the assembly of entire grid
A) position that grid longitudinal rib is marked first on grid cross rib, is then successively inserted perpendicularly into longitudinal row for grid cross rib Hole of the water with side, and melting welding is adhesively fixed in intersection;
B) grid longitudinal rib is laid on the position that grid cross rib marks in advance, the two is viscous using melting welding at crossover location It connects, a kind of TGXG with drain function is finally made.

Claims (4)

1. a kind of TGXG with drain function, which is characterized in that the TGXG with drain function is by lattice Grid cross rib (1), grid longitudinal rib (2) and longitudinal drainage band (3) composition;Grid cross rib (1) is inserted perpendicularly into longitudinal drainage band (3) side The hole in face, and be bonded in intersection melting welding;Grid longitudinal rib (2) and grid cross rib (1) are welded at square crossing;
The longitudinal drainage band (3) is by lower layer's reinforced bar net (4), drainage belt ribs (5), suction water cellulose (6), upper layer reinforcement Net (7), geotextiles filter membrane (8) and water suction cotton pad (9) composition;Upper layer reinforced bar net (7) and lower layer's reinforced bar net (4) row of being bonded in respectively Upper and lower surfaces of the water with ribs (5), and the vertical supporting plate of lower layer's reinforced bar net (4) is inserted into upper layer reinforced bar net (7) Support plate fixing groove in, suction water cellulose (6) is longitudinally arranged between upper layer reinforced bar net (7) and lower layer's reinforced bar net (4), geotechnique Cloth filter membrane (8) is covered on the outer surface of upper layer reinforced bar net (7) and lower layer's reinforced bar net (4), and water suction cotton pad (9) is placed on longitudinal drainage Band (3) both ends, and be in contact with suction water cellulose (6) end.
2. a kind of TGXG with drain function according to claim 1, it is characterised in that the upper layer reinforcement Net (7) and lower layer's reinforced bar net (4) cross section are designed as arc, the aperture of arch section surface, and mesh size is (3~6) mm × (3 ~6) mm wherein has vertical supporting plate, has on the inside of upper layer reinforced bar net (7) arch section on the inside of lower layer's reinforced bar net (4) arch section Support plate fixing groove.
3. a kind of TGXG with drain function according to claim 1, it is characterised in that the drainage belt branch Stake rib (5) side hole, end one end are that the fastener other end of buckle structure is then fixings.
4. a kind of production method with drain function TGXG according to claim 1, it is characterised in that it is pressed Column step carries out: (referring to Figure 5)
Step 1: assembled longitudinal drainage band
The lower surface of drainage belt ribs (5) a) is weldingly fixed on to using welding technology two alar parts of lower layer's reinforced bar net (4);
B) longitudinal above lower layer's reinforced bar net (4) to be laid with suction water cellulose (6);
C) upper layer reinforced bar net (7) are covered above suction water cellulose (6);First insert the vertical supporting plate of lower layer's reinforced bar net (4) Enter the support plate fixing groove of upper layer reinforced bar net (7), is then welded two alar parts of upper layer reinforced bar net (7) using welding technology solid It is scheduled on the upper surface of drainage belt ribs (5);
D) one layer of geotextiles filter membrane (8) is respectively covered in the outer surface of upper layer reinforced bar net (7) and lower layer's reinforced bar net (4), and uses glue Glutinous agent is adhesively fixed, and then respectively places one layer of water suction cotton pad (9) at longitudinal drainage band (3) both ends, holds with suction water cellulose (6) Portion is in contact, and longitudinal drainage band (3) thus are made.
Step 2: completing the assembly of entire grid
Grid cross rib (1), is then successively inserted perpendicularly by the position that grid longitudinal rib (2) a) are marked first on grid cross rib (1) The hole of longitudinal drainage band (3) side, and melting welding is adhesively fixed in intersection;
B) grid longitudinal rib (2) is laid on the position that grid cross rib (1) marks in advance, the two uses melting welding at crossover location Bonding, is finally made a kind of TGXG with drain function.
CN201811150363.8A 2018-09-29 2018-09-29 A kind of production method with drain function TGXG Pending CN109339022A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811150363.8A CN109339022A (en) 2018-09-29 2018-09-29 A kind of production method with drain function TGXG

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811150363.8A CN109339022A (en) 2018-09-29 2018-09-29 A kind of production method with drain function TGXG

Publications (1)

Publication Number Publication Date
CN109339022A true CN109339022A (en) 2019-02-15

Family

ID=65307476

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811150363.8A Pending CN109339022A (en) 2018-09-29 2018-09-29 A kind of production method with drain function TGXG

Country Status (1)

Country Link
CN (1) CN109339022A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109339023A (en) * 2018-09-29 2019-02-15 湖南大学 A kind of TGXG with drain function
CN114606820A (en) * 2022-02-17 2022-06-10 深圳大学 Soil body reinforcement-active water absorption material and manufacturing device

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19820951A1 (en) * 1998-05-11 1999-11-18 Huesker Synthetic Gmbh & Co Compound material for prevention of ground erosion
CN202543949U (en) * 2012-02-29 2012-11-21 建伟建设有限公司 Drainage geogrid
CN202543884U (en) * 2012-02-29 2012-11-21 浙江省东阳市江南建设有限公司 Composite reinforced water drainage type geogrid
CN202787227U (en) * 2012-07-30 2013-03-13 浙江诸安建设集团有限公司 Three-dimensional composite plastic water discharging body
CN203855973U (en) * 2014-05-26 2014-10-01 中冶集团武汉勘察研究院有限公司 Ribbed-box type reinforced seepage-eliminating composite component
CN206599771U (en) * 2016-12-13 2017-10-31 山东科技大学 A kind of Combined earthwork cell compartment

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19820951A1 (en) * 1998-05-11 1999-11-18 Huesker Synthetic Gmbh & Co Compound material for prevention of ground erosion
CN202543949U (en) * 2012-02-29 2012-11-21 建伟建设有限公司 Drainage geogrid
CN202543884U (en) * 2012-02-29 2012-11-21 浙江省东阳市江南建设有限公司 Composite reinforced water drainage type geogrid
CN202787227U (en) * 2012-07-30 2013-03-13 浙江诸安建设集团有限公司 Three-dimensional composite plastic water discharging body
CN203855973U (en) * 2014-05-26 2014-10-01 中冶集团武汉勘察研究院有限公司 Ribbed-box type reinforced seepage-eliminating composite component
CN206599771U (en) * 2016-12-13 2017-10-31 山东科技大学 A kind of Combined earthwork cell compartment

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109339023A (en) * 2018-09-29 2019-02-15 湖南大学 A kind of TGXG with drain function
CN114606820A (en) * 2022-02-17 2022-06-10 深圳大学 Soil body reinforcement-active water absorption material and manufacturing device

Similar Documents

Publication Publication Date Title
CN109339023A (en) A kind of TGXG with drain function
CN101182709B (en) Method of composite electroosmosis, vacuum precipitation and vacuum preload reinforcement foundation and device thereof
JP2011513610A (en) Sleeper foundation for railway sleepers
CN109339022A (en) A kind of production method with drain function TGXG
CN103228845B (en) formwork element
CN202787227U (en) Three-dimensional composite plastic water discharging body
CN103321258B (en) PFF integral composite reversed filtering layer and construction method thereof
CN202543949U (en) Drainage geogrid
CN111705578B (en) Special composite geotechnical material for higher subgrade and preparation method thereof
CN203452062U (en) Groove type reinforcement and drainage composite member
CN210341882U (en) Novel degradable plastic drainage board
CN206128142U (en) Be applied to landfill yard seepage prevention structure of mountain valley type landfill yard sludge sump solidification back ground
CN213952123U (en) Drainage structure for construction for improving seepage-proofing effect of geomembrane
KR20100090179A (en) Method for reinforced of soft ground by using top pile
KR100920688B1 (en) Structure for reinforced of soft ground by using top pile
CN107842016A (en) A kind of hot melting cohesion type catheter type plastic draining board
CN108755778B (en) Sodium bentonite waterproof blanket and construction method thereof
CN1129691C (en) Process for manufacturing frames for civil engineering works
KR101175122B1 (en) Structure of reinforced for retaining wall and method for manufacturing of method install reinforced for retaining wall
CN105735327A (en) Riverway or construction cofferdam protection slope and construction method
CN214497758U (en) A drain bar and compound drainage structure for sponge city siphon drainage collection system
CN216635658U (en) High-strength composite geotechnical net
CN206529809U (en) A kind of leakage preventing structure of refuse landfill
JP4523711B2 (en) Three-dimensional network and method for producing the same
CN219862659U (en) Seepage-proof hydraulic engineering dykes and dams

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190215