CN109327025A - Consider the power grid N-1 safety economy method for optimizing scheduling of transmission operation elastic space - Google Patents

Consider the power grid N-1 safety economy method for optimizing scheduling of transmission operation elastic space Download PDF

Info

Publication number
CN109327025A
CN109327025A CN201810999580.8A CN201810999580A CN109327025A CN 109327025 A CN109327025 A CN 109327025A CN 201810999580 A CN201810999580 A CN 201810999580A CN 109327025 A CN109327025 A CN 109327025A
Authority
CN
China
Prior art keywords
unit
formula
power
interconnection
constraint
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810999580.8A
Other languages
Chinese (zh)
Other versions
CN109327025B (en
Inventor
张�林
杨高峰
张同尊
古济铭
陈涛
吴迎霞
金黎明
汪洋
夏清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Qingneng Internet Technology Co Ltd
Tsinghua University
State Grid Corp of China SGCC
State Grid Chongqing Electric Power Co Ltd
Original Assignee
Beijing Qingneng Internet Technology Co Ltd
Tsinghua University
State Grid Corp of China SGCC
State Grid Chongqing Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Qingneng Internet Technology Co Ltd, Tsinghua University, State Grid Corp of China SGCC, State Grid Chongqing Electric Power Co Ltd filed Critical Beijing Qingneng Internet Technology Co Ltd
Priority to CN201810999580.8A priority Critical patent/CN109327025B/en
Publication of CN109327025A publication Critical patent/CN109327025A/en
Application granted granted Critical
Publication of CN109327025B publication Critical patent/CN109327025B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/46Controlling of the sharing of output between the generators, converters, or transformers
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/76Power conversion electric or electronic aspects

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses the power grid N-1 safety economy method for optimizing scheduling for considering transmission operation elastic space, key steps are as follows: 1) obtains power grid master data.2) transmission line malfunction increase-volume elastic model in short-term is established.3) interconnection adjustment elastic model is established.4) the N-1 safety economy scheduling model for considering transmission operation elastic space is established.5) according to the N-1 safety economy scheduling model for considering transmission operation elastic space, power grid is optimized.The present invention improves the optimizing space of unit output, expands operation of power networks feasible zone when considering failure increase-volume in short-term and interconnection adjustment transmission operation elastic space.The optimization method of the considerations of present invention constructs transmission operation elastic space further improves the ability that power grid receives wind-powered electricity generation under the premise of reducing operating cost.

Description

Consider the power grid N-1 safety economy method for optimizing scheduling of transmission operation elastic space
Technical field
The present invention relates to Economic Dispatch fields, specifically the power grid N-1 peace of consideration transmission operation elastic space Full economic load dispatching optimization method.
Background technique
Probabilistic increase, power grid security are injected due to the growth of network load and by the power grid of representative of new energy The feasible zone of operation is gradually reduced, and operation of power networks approaches the limit.The new change and neomorph of electric system are electrical network economy, peace Row for the national games proposes new challenge.Have numerous scholars to ask for keys such as the probabilistic operation of power networks optimization methods of consideration Topic conducts a research, and such methods can improve the safety and economy of operation of power networks in safe operation of electric network domain.However, if The safe operation of power system problem in the case of load growth and the uncertain increase of power grid injection is fundamentally solved, is needed Expand the running boundary of power grid, the feasible zone of extended power running Optimization problem.Therefore, if can be set according to power grid The physical essence of received shipment row constraint, excavates " elastic space " in safe operation of electric network domain, will more fully utilize existing power grid Equipment extends the optimizing space of network optimization, improves the breadth and depth that power network resources are distributed rationally.
In network optimization problem, the major constraints for link of transmitting electricity are that transmission line of electricity capacity-constrained and regional power grid are got in touch with The planned transmission power constraint of line, the elastic space that can be excavated mainly include failure
Increase-volume in short-term and interconnection adjust two aspects.In terms of failure increase-volume in short-term, existing document is in risk node at present Boundary price meter and increase-volume in short-term, the proposition of part document consider the dispatching method of the failure elasticity of increase-volume in short-term, but mostly with voltage Phase angle mode models, and whens large-scale calculations introduces a large amount of optimized variables;Interconnection adjustment elasticity aspect, existing Method Modeling It is more rough, do not account for influence of the outer net to interconnection power transmission;Also, existing method not comprehensively meter and failure in short-term The transmission operations elastic spaces such as increase-volume, interconnection adjustment, analyze its economic benefit and the influence to new energy consumption.
Summary of the invention
Present invention aim to address problems of the prior art.
To realize the present invention purpose and the technical solution adopted is that such, consider the power grid of transmission operation elastic space N-1 safety economy method for optimizing scheduling, mainly comprises the steps that
1) power grid master data is obtained.Further, the power grid master data mainly includes system loading data, new energy Source predicts force data, unit, network parameter and interconnection parameter.
2) transmission line malfunction increase-volume elastic model in short-term is established, key step is as follows:
2.1) route trend constraint under basic status is determined, it may be assumed that
In formula, fk×1Line Flow vector is tieed up for k.K is power network line number.Unit output vector is tieed up for u.U is Power grid unit number.Node load, which is tieed up, for n injects vector.Matrix Cn×uFor power grid unit-node connection matrix.Matrix Ak×nFor the transfer distribution factor matrix of power grid.Matrix Ak×nThe linear coupling relationship of node injection and Line Flow is described.Line threshold transmission capacity vector is tieed up for k.
2.2) Line Flow constraint when moment, unit output not yet adjust after failure is determined, it may be assumed that
In formula, parameter kcFor the increase-volume coefficient in short-term of route under malfunction.kc≥1.(c) N-1 that route c is disconnected is indicated Fault scenes.C is N-1 failure collection.The new transfer distribution factor matrix of power grid after being disconnected for route c.
2.3) failure TaIn time, unit output adjusts Line Flow.The route tide that unit output adjusts after consideration failure Stream constraint is as follows:
In formula,For failure unit output vector adjusted,For unit Line Flow adjusted to Amount.
2.4) unit output adjusts TaThe climbing capacity of unit, obtains T in timeaThe climbing capacity constraint of unit in time It is as follows:
In formula,For TaThe climbing capacity of unit in time.Unit output vector is tieed up for u.
2.5) constraint condition according to formula 2 to formula 4 establishes the transmission operation elasticity for considering failure increase-volume in short-term Spatial model.
3) interconnection adjustment elastic model is established.
The key step for establishing interconnection adjustment elastic model is as follows:
3.1) the equivalent constraint of confirmation outer net operation, key step are as follows:
3.1.1 equivalent optimization mould) is established according to the operations constraint such as generator capacity, line transmission of interconnection external network Type.
The objective function of equivalent Optimized model is as shown in formula 5 and formula 6.
CBi'=maxPBi'(i'=1,2 ..., NB)。 (5)
In formula, NBIt is interconnection boundary node number.CBi'For boundary node Bi'The active volume at place.I' is Arbitrary Boundaries Node.PBi'For boundary node Bi'The active power of transmission;
In formula, CB-allFor section active volume.I' is Arbitrary Boundaries node.PBi'For boundary node Bi'What is transmitted is active Power.NBIt is interconnection boundary node number.
3.1.2) constraint condition of equivalent Optimized model is to interconnect the operation constraint of outer net, such as formula 7 to 9 institute of formula Show.
Trend Constraints of Equilibrium is as follows:
PE=BEθE。 (7)
In formula, PEFor outer net and boundary node injecting power vector.θEFor outer net and boundary node phase angle vector.BEBe for Establish the susceptance submatrix of outer net and boundary node injecting power to the relationship between corresponding phase angle.
Generator capacity constraint is as follows:
In formula, PGEIt is outer net generator active power vector.
Line transmission power constraint is as follows:
In formula, PlEIt is transmission line of electricity active power vector.
3.1.3) the constraint condition according to formula 7 to formula 9, to objective function CBiAnd CB-allIt is updated, obtains The equivalent constraint of interconnection outer net operation.
fL≤fc。 (10)
In formula, fLFor tie-line power transmission.fcFor equivalent optimum results.
3.2) determine that power stepization constrains, it may be assumed that
In formula,WithRespectively interconnection transmission capacity bound.Zi”For characterization equivalent generator unit fortune The 0-1 variable of row state.Pi”It contributes for the i-th " platform equivalent unit, and unit output is fixed value Pd
3.3) daily electricity constraint independent of time is determined, it may be assumed that
In formula, D is interconnection day to exchange electricity, is determined by trading program.fL,tFor interconnection period t transmission function Rate.
3.4) constraint condition according to formula 10 to formula 12, to objective function CBiAnd CB-allIt is updated, thus Establish interconnection adjustment elastic model.
4) the N-1 safety economy scheduling model for considering transmission operation elastic space is established.
It establishes and considers that the key step of the N-1 safety economy scheduling model of transmission operation elastic space is as follows:
4.1) objective function min F is determined, it may be assumed that
In formula, F is total power production cost.T is scheduling time.U is unit number.CGi,tFor unit i period t power generation Expense.CL,tFor the power purchase expense of outer net day part.Cw,tFor Wind turbines period t abandonment punishment cost.
Abandonment punishment cost C of the Wind turbines in period tw,tIt is as follows:
In formula, λwFor abandonment penalty factor.Activity of force is predicted for period t Wind turbines. Pw,tFor Wind turbines Practical activity of force out.
Unit i mainly includes coal consumption cost C in the power generation expense of period tCi,t, unit starting cost Ci,t,UIt is closed with unit Stop cost Ci,t,D
4.2) increase-volume elastic safety constraint formula and interconnection transmit elastic restraint formula to combined circuit in short-term, establish optimization about Beam condition, as shown in formula 15 to 19.
Account load balancing constraints are as follows:
In formula, NgFor system convention generator number of units.Pgi,tFor unit i period t power output.fL,tIt is interconnection in the period The transimission power of t.Pw,tFor the wind power output of period t.Pd,tFor total power load of period t.
The constraint of unit output bound is as follows:
In formula, Ii,tEach unit is characterized in the start and stop state of period t.For each unit period t most Greatly, minimum load.Pgi,tFor unit i period t power output.
Unit minimum start-off time constraints are as follows:
In formula, ti,t,onAnd ti,t,offRespectively unit i moment t lasting booting and shut down the time. Ti,onAnd Ti,off Respectively unit i is switched on and shuts down the time in the minimum of period t.Ii,tEach unit is characterized in the start and stop state of period t.Ii,t-1Table Each unit is levied in the start and stop state of period t-1. Ti,UStart the time for unit i.Ti,DThe time is shut down for unit i.
Unit Commitment expense restriction is as follows:
In formula, KiAnd JiThe single startup-shutdown expense of respectively unit i and unit j.
Unit ramp loss is as follows:
Ii,t-1Pi,t-1idown≤Pgi,t≤Ii,t-1Pi,t-1iup。 (19)
In formula, λiupFor the ratio of slope of climbing of unit i.λidownFor the downward climbing rate of unit i.
4.3) linear solution formula 15 is updated objective function min F, to formula 19 to obtain considering transmission of electricity Run the N-1 safety economy scheduling model of elastic space.
1) method of linear solution, which specifically includes that, carries out linear solution using CPLEX software.2) GUROBI software is utilized Carry out linear solution.
5) according to the N-1 safety economy scheduling model for considering transmission operation elastic space, power grid is optimized.
The solution have the advantages that unquestionable.The present invention is considering that failure increase-volume in short-term and interconnection adjustment are defeated When electricity operation elastic space, the optimizing space of unit output is improved, operation of power networks feasible zone is expanded.What the present invention constructed The optimization method of transmission operation elastic space is considered under the premise of reducing operating cost, is further improved power grid and is received wind The ability of electricity.The present invention improves the transmission capacity of route, alleviates backlog degree, it is feasible to expand unit output Domain.The present invention can precisely portray interconnection " true " elastic space, under the premise of guaranteeing the safety of operation of power networks, expand Operation of power networks feasible zone.The operating cost of power grid can be effectively reduced in the present invention, promotes the consumption of wind-powered electricity generation.
Detailed description of the invention
Fig. 1 is interconnection active volume equivalence schematic diagram;
Fig. 2 is IEEE30 node and IEEE9 node interacted system figure;
Fig. 3 is typical day load curve and wind-powered electricity generation prediction graph;
Fig. 4 is that interconnection can transmission capacity analogous diagram;
Fig. 5 is the practical power output situation of each scheduling strategy wind-powered electricity generation.
Specific embodiment
Below with reference to embodiment, the invention will be further described, but should not be construed the above-mentioned subject area of the present invention It is only limitted to following embodiments.Without departing from the idea case in the present invention described above, according to ordinary skill knowledge and Customary means makes various replacements and change, should all include within the scope of the present invention.
Embodiment 1:
Referring to Fig. 1 to Fig. 4, the power grid N-1 safety economy method for optimizing scheduling of transmission operation elastic space is considered, mainly The following steps are included:
1) power grid master data is obtained.
Further, the power grid master data mainly includes grid generator quantity, power grid unit number, interconnection transmission Power, wind power output, electric load, power purchase expense and power generation expense.
N-1 principle is to determine a kind of criterion of power system security, also known as single failure safety criterion.
Any independent component (generator, transmission line of electricity, transformer according to N-1 criterion, in N number of element of electric system Deng) break down and be removed after, should not cause because All other routes overload trip due to cause user to have a power failure, do not destroy system Stability, do not occur the accidents such as collapse of voltage.Compared with fail-safe analysis, N-1 principle is not required to collect element outage rate It is a kind of extremely easy safety inspection criterion etc. a large amount of initial data, is widely applied in Utilities Electric Co..
In Electric Power Network Planning, N-1 verification should be carried out to the planning done, check whether to meet N-1 principle.If satisfied, then electric Network planning, which is drawn, to meet the requirements.
2) transmission line malfunction increase-volume elastic model in short-term is established.
The present embodiment uses transfer distribution factor modeling pattern of the unit output as optimized variable, with current power grid tune The scheduling modeling method that degree center uses is adapted.Without loss of generality, the present embodiment puts aside Line Flow after N-1 failure Multistage adjustment requirement, only consider the interim increase-volume of trend under line fault conditions, and power grid required to adjust in T time.It is more The requirement of section adjustment can also be modeled by the method for the present invention.
Generating set is engine, generator and control system composition.
It establishes and considers that the key step of the transmission operation elastic space model of failure increase-volume in short-term is as follows:
2.1) route trend constraint under basic status is determined, it may be assumed that
In formula, fk×1Line Flow vector is tieed up for k.K is power network line number.Unit output vector is tieed up for u.U is Power grid unit number.Node load, which is tieed up, for n injects vector.Matrix Cn×uFor power grid unit-node connection matrix.Matrix Ak×nFor the transfer distribution factor matrix of power grid.Matrix Ak×nThe linear coupling relationship of node injection and Line Flow is described.Line threshold transmission capacity vector is tieed up for k.
2.2) Line Flow constraint when moment, unit output not yet adjust after failure is determined, it may be assumed that
In formula, parameter kcFor the increase-volume coefficient in short-term of route under malfunction.kc≥1.(c) N-1 that route c is disconnected is indicated Fault scenes.C is N-1 failure collection.The new transfer distribution factor matrix of power grid after being disconnected for route c.For route K ties up Line Flow vector under the N-1 fault scenes that c is disconnected.Power grid turns under the N-1 fault scenes disconnected for route c Move distribution factor matrix.
2.3) failure TaIn time, unit output adjusts Line Flow.The route tide that unit output adjusts after consideration failure Stream constraint is as follows:
In formula,For failure unit output vector adjusted,For unit Line Flow adjusted to Amount.
2.4) unit output adjusts TaThe climbing capacity of unit, obtains T in timeaThe climbing capacity constraint of unit in time It is as follows:
In formula,For TaThe climbing capacity of unit in time.Unit output vector is tieed up for u.
2.5) constraint condition according to formula 2 to formula 4 establishes the transmission operation elasticity for considering failure increase-volume in short-term Spatial model.
3) interconnection adjustment elastic model is established.
Currently, the mode that the operational mode of interconnection mainly uses in transmission of electricity link immobilizes for dominant eigenvalues, on Grade scheduling institution formulates tie-line power transmission plan in a period of time, is issued to each subdispatch mechanism.The mode advantage exists In easy to accomplish point of electric power saving electric quantity balancing, but the elastic space of interconnection is not made full use of to expand electric power netting safe running domain, Realize that the coordination of the energy between region is mutually helped.In conjunction with power grid actual operating mode, the present invention proposes that interconnection adjusts springform Type, tie-line power transmission can adjust, but need to consider the constraint of following three aspect:
It I is) constraint for meeting interconnection outer net service condition, it is equivalent that tie-line power transmission cannot cross the operation of its outer net Constraint (maximum power that interconnection outer net can support interconnection transmission).
II) consideration convenient for electric network reliability and scheduling, tie-line power transmission meet ladderization constraint.
It III) is the limitation for meeting transregional electricity trading program, the constraint that day exchange electricity need to remain unchanged.
As shown in Figure 1, the active volume of interconnection is limited by generator capacity, the line transmission etc. of interconnection external network Operation constraint.But the information between regional power grid is difficult to real-time exchange, and this section proposes the outer net static equivalence method of active volume, By establishing equivalent Optimized model, retain the operation constraint of outer net.
The key step for establishing interconnection adjustment elastic model is as follows:
3.1) the equivalent constraint of confirmation outer net operation, key step are as follows:
3.1.1 equivalent optimization mould) is established according to the operations constraint such as generator capacity, line transmission of interconnection external network Type.
The objective function of equivalent Optimized model is as shown in formula 5 and formula 6.
CBi'=maxPBi'(i'=1,2 ..., NB)。 (5)
In formula, NBIt is interconnection boundary node number.CBi'For boundary node Bi'The active volume at place.I' is Arbitrary Boundaries Node.PBi'For boundary node Bi'The active power of transmission;
In formula, CB-allFor section active volume.I' is Arbitrary Boundaries node.PBi'For boundary node Bi'What is transmitted is active Power.NBIt is interconnection boundary node number.
3.1.2) constraint condition of equivalent Optimized model is to interconnect the operation constraint of outer net, such as formula 7 to 9 institute of formula Show.
Trend Constraints of Equilibrium is as follows:
PE=BEθE。 (7)
In formula, PEFor outer net and boundary node injecting power vector.θEFor outer net and boundary node phase angle vector.BEBe for Establish the susceptance submatrix of outer net and boundary node injecting power to the relationship between corresponding phase angle.
Generator capacity constraint is as follows:
In formula, PGEIt is outer net generator active power vector.(*)max、(*)minRespectively represent the bound of variable *.It is outer net generator active power lower limit.It is the outer net generator active power upper limit.
Line transmission power constraint is as follows:
In formula, PlEIt is transmission line of electricity active power vector.(*)max、(*)minRespectively represent the bound of variable *. It is transmission line of electricity active power lower limit.It is the transmission line of electricity active power upper limit.
3.1.3) the constraint condition according to formula 7 to formula 9, to objective function CBiAnd CB-allIt is updated, obtains The equivalent constraint of interconnection outer net operation.
fL≤fc。 (10)
In formula, fLFor tie-line power transmission.fcFor equivalent optimum results.
3.2) tie-line power transmission is thought of as by NEPlatform equivalent generator composition, is realized by Unit Combination and is got in touch with The ladder of linear heat generation rate, so that it is determined that power stepization constrains, it may be assumed that
In formula,WithRespectively interconnection transmission capacity bound.Zi”For characterization equivalent generator unit fortune The 0-1 variable of row state.Pi”It contributes for the i-th " platform equivalent unit, and unit output is fixed value Pd。NEFor outer net node Number.
3.3) daily electricity constraint independent of time is determined, it may be assumed that
In formula, D is interconnection day to exchange electricity, is determined by trading program.fL,tFor interconnection period t transmission function Rate.
3.4) constraint condition according to formula 10 to formula 12, to objective function CBiWith objective function CB-allIt carries out more Newly, to establish interconnection adjustment elastic model.
4) the N-1 safety economy scheduling model for considering transmission operation elastic space is established.
It establishes and considers that the key step of the N-1 safety economy scheduling model of transmission operation elastic space is as follows:
4.1) with 1h for a period, T=24 is established and is considered grid power transmission operation elastic space for the present embodiment scheduling Power grid N-1 safety economy scheduling model, by optimizing each unit output and outer net tie-line power transmission, and by abandonment electricity It is added in objective function in the form of penalty term, keeps overall running cost minimum, available objective function min F:
In formula, F is total power production cost.T is scheduling time.U is unit number.CGi,tFor unit i period t power generation Expense.CL,tFor the power purchase expense of outer net day part.Cw,tFor Wind turbines period t abandonment punishment cost.
Abandonment punishment cost C of the Wind turbines in period tw,tIt is as follows:
In formula, λwFor abandonment penalty factor.Activity of force is predicted for period t Wind turbines. Pw,tFor Wind turbines Practical activity of force out.
Unit i mainly includes coal consumption cost C in the power generation expense of period tCi,t, unit starting cost Ci,t,UIt is closed with unit Stop cost Ci,t,D
4.2) combination failure increase-volume elastic safety constraint formula (formula 3 to 4) in short-term and interconnection transmit elastic restraint formula (formula 11 to 12) establishes optimization constraint condition, as shown in formula 15 to 19.
Account load balancing constraints are as follows:
In formula, NgFor system convention generator number of units.Pgi,tFor unit i period t power output. fL,tFor interconnection when The transimission power of section t.Pw,tFor the wind power output of period t.Pd,tFor total power load of period t.
The constraint of unit output bound is as follows:
In formula, Ii,tEach unit is characterized in the start and stop state of period t.For each unit period t most Greatly, minimum load.Pgi,tFor unit i period t power output.
Unit minimum start-off time constraints are as follows:
In formula, ti,t,onAnd ti,t,offRespectively unit i moment t lasting booting and shut down the time. Ti,onAnd Ti,off Respectively unit i is switched on and shuts down the time in the minimum of period t.Ii,tEach unit is characterized in the start and stop state of period t.Ii,t-1Table Each unit is levied in the start and stop state of period t-1. Ti,UStart the time for unit i.Ti,DThe time is shut down for unit i.
Unit Commitment expense restriction difference is as follows:
In formula, KiAnd JiThe respectively booting of the single of unit i and unit j, idleness expense.
Unit ramp loss is as follows:
Ii,t-1Pi,t-1idown≤Pgi,t≤Ii,t-1Pi,t-1iup。 (19)
In formula, λiupFor the ratio of slope of climbing of unit i.λidownFor the downward climbing rate of unit i.Pgi,t-1For unit i when The power output of section t-1.
4.3) linear solution formula 15 is updated objective function min F, to formula 19 to obtain considering transmission of electricity Run the N-1 safety economy scheduling model of elastic space.
It is linear function or quadratic function according to cost function under normal operating condition of unit, which is MIXED INTEGER Linear optimization problem (MILP) or MIXED INTEGER double optimization problem (MIQCP), can be by business softwares such as CPLEX or GUROBI Efficient Solution.
1) method of linear solution, which specifically includes that, carries out linear solution using CPLEX software.2) GUROBI software is utilized Carry out linear solution.
5) according to the N-1 safety economy scheduling model for considering transmission operation elastic space, power grid is optimized.
Embodiment 2:
A kind of comparative test for the power grid N-1 safety economy method for optimizing scheduling considering transmission operation elastic space, mainly The following steps are included:
1) test macro is established, that is, establishing IEEE30 node, (No. 7 nodes meet 150MW with IEEE9 node interacted system figure Wind turbines).
2) different comparison models
The power grid N-1 safety economy method for optimizing scheduling for considering transmission operation elastic space is mentioned for verifying embodiment 1 Validity, assessment considers the economic benefit dispatched a few days ago and wind electricity digestion situation after transmission operation elastic space, using as follows 4 kinds of models are compared:
M1: the conventional economical scheduling scheme of route N-1 failure does not consider failure increase-volume in short-term and interconnection adjustment elasticity. If route increase-volume coefficient kcIt is 1, the constant 80MW of day part tie-line power transmission.
M2: only consider that the economic dispatch program of failure increase-volume in short-term elasticity (refers to New England of U.S. power grid (ISO- NE).Line Flow transmission capacity setting: setting route increase-volume coefficient kcIt is 1.2, failure adjustment time T is 15min, day part The constant 80MW of tie-line power transmission.
M3: only consider the economic dispatch program that interconnection is adjusted flexibly.If route increase-volume coefficient kcIt is 1, interconnection transmission Power can be adjusted flexibly under the premise of guaranteeing that daily electricity is constant in the case where interconnection transmits security constraint.
M4: while considering the economy of two aspect transmission operation elastic space of failure increase-volume in short-term and interconnection transmission capacity Scheduling scheme considers the power grid N-1 safety economy method for optimizing scheduling of transmission operation elastic space.If route increase-volume coefficient kcIt is 1.2, failure adjustment time T is 15min, and tie-line power transmission can be adjusted flexibly in the case where interconnection transmits security constraint.
3) simulation analysis.As shown in Figures 2 and 3, IEEE30 node and IEEE9 node interacted system figure are given, it is typical Daily load curve and wind-powered electricity generation prediction curve.
First to interconnection can transmission capacity carry out simulation analysis, due to M3, M4 consider interconnection adjustment elasticity, Interconnection can transmission capacity optimum results it is as shown in Figure 4.
Simulation result shows after considering interconnection safe transmission capacity, transmits safety about compared to traditional interconnection Beam, more accurate features tie-line power transmission feasible zone, ensure that the safety of contact linear elasticity adjustment
Then the economic benefit of transmission operation elastic space is analyzed.The economic benefit of 4 kinds of scheduling strategies such as table 1 It is shown.As can be seen that M2, M3, M4 reduce 4.3%, 4.1%, 8.9% relative to M1 overall running cost respectively.Simulation result Show overall running cost all decreases to some degree after considering transmission operation elastic space, considers that failure is short at the same time When Shi Zengrong and interconnection adjust transmission operation elastic space, operating cost reduction is further decreased.
The economic efficiency contrast of 14 kinds of scheduling strategies of table is analyzed
Further analysis considers the wind electricity digestion benefit of each scheduling strategy of transmission operation elastic space.Fig. 3 is each scheduling The practical power output situation of tactful wind-powered electricity generation, it can be seen that after considering transmission operation elastic space, in the abandonment amount of abandonment period There is apparent reduction, table 2 lists the wind electricity digestion index of each scheduling strategy, when consideration transmission operation elastic space carries out Optimized Operation a few days ago, M2, M3, M4 reduce 4.7%, 2.9%, 7.8% relative to the full scheduling slot abandonment ratio of M1 respectively, Have relative to M1 wind-powered electricity generation abandonment ratio reduces to a certain extent, considers faulty line increase-volume in short-term and interconnection tune at the same time When whole transmission operation elastic space, abandonment ratio is further decreased.Simulation result shows after considering transmission operation elastic space The feasible zone for expanding unit output improves the transmission capacity of route, improves the ability that power grid receives wind-powered electricity generation.
The wind electricity digestion Comparative result of 24 kinds of scheduling strategies of table is analyzed

Claims (6)

1. consider transmission operation elastic space power grid N-1 safety economy method for optimizing scheduling, it is characterised in that: mainly include with Lower step:
1) the power grid master data is obtained;
2) transmission line malfunction increase-volume elastic model in short-term is established;
3) interconnection adjustment elastic model is established;
4) the N-1 safety economy scheduling model for considering transmission operation elastic space is established.
5) according to the N-1 safety economy scheduling model for considering transmission operation elastic space, power grid is optimized.
2. a kind of power grid N-1 safety economy optimizing scheduling side for considering transmission operation elastic space according to claim 1 Method, it is characterised in that: the power grid master data mainly includes that system loading data, new energy predict force data, unit, net Network parameter and interconnection parameter.
3. a kind of power grid N-1 safety economy optimizing scheduling for considering transmission operation elastic space according to claim 1 or 2 Method, it is characterised in that: establish and consider that the key step of the transmission operation elastic space model of failure increase-volume in short-term is as follows:
1) route trend constraint under basic status is determined, it may be assumed that
In formula, fk×1Line Flow vector is tieed up for k;K is power network line number;Unit output vector is tieed up for u;U is power grid machine Group number;Node load, which is tieed up, for n injects vector;Matrix Cn×uFor power grid unit-node connection matrix;Matrix Ak×nFor electricity The transfer distribution factor matrix of net;Matrix Ak×nThe linear coupling relationship of node injection and Line Flow is described;Line is tieed up for k Road Total transfer capability vector;
2) Line Flow constraint when moment, unit output not yet adjust after failure is determined, it may be assumed that
In formula, parameter kcFor the increase-volume coefficient in short-term of route under malfunction, kc≥1;Subscript (c) indicates the N-1 that route c is disconnected Fault scenes;C is N-1 failure collection;The new transfer distribution factor matrix of power grid after being disconnected for route c;
3) failure TaIn time, unit output adjusts Line Flow.The Line Flow constraint that unit output adjusts after consideration failure is such as Shown in lower:
In formula,For failure unit output vector adjusted;For unit Line Flow vector adjusted;TaFor Fault time;
4) unit output adjusts TaThe climbing capacity of unit, obtains T in timeaThe climbing capacity of unit constrains following institute in time Show:
In formula,For TaThe climbing capacity of unit in time;Unit output vector is tieed up for u.
4. a kind of power grid N-1 safety economy optimizing scheduling for considering transmission operation elastic space according to claim 1 or 3 Method, which is characterized in that the key step for establishing interconnection adjustment elastic model is as follows:
1) the equivalent constraint of confirmation outer net operation, key step are as follows:
1.1) equivalent Optimized model is established according to the operations constraint such as generator capacity, line transmission of interconnection external network;
The objective function of equivalent Optimized model is as shown in formula 5 and formula 6;
CBi'=maxPBi'(i'=1,2 ..., NB); (5)
In formula, NBIt is interconnection boundary node number;CBi'For boundary node Bi'The active volume at place;I' is Arbitrary Boundaries node; PBi'For boundary node Bi'The active power of transmission;
In formula, CB-allFor section active volume;I' is Arbitrary Boundaries node;PBi'For boundary node Bi' transmission active power;NB It is interconnection boundary node number;
1.2) constraint condition of equivalent Optimized model is to interconnect the operation constraint of outer net, as shown in formula 7 to formula 9;
Trend Constraints of Equilibrium is as follows:
PE=BEθE; (7)
In formula, PEFor outer net and boundary node injecting power vector;θEFor outer net and boundary node phase angle vector;BEIt is to establish The susceptance submatrix of outer net and boundary node injecting power and the relationship between corresponding phase angle;
Generator capacity constraint is as follows:
In formula, PGEIt is outer net generator active power vector;(*)max、(*)minRespectively represent the bound of variable *;
Line transmission power constraint is as follows:
In formula, PlEIt is transmission line of electricity active power vector;(*)max、(*)minRespectively represent the bound of variable *;
1.3) constraint condition according to formula 7 to formula 9, to objective function CBi'And CB-allIt is updated, obtains outside interconnection The equivalent constraint of net operation;
fL≤fc; (10)
In formula, fLFor tie-line power transmission, fcFor equivalent optimum results;
2) determine that power stepization constrains, it may be assumed that
In formula,WithRespectively interconnection transmission capacity bound;Zi”Shape is run for characterization equivalent generator unit The 0-1 variable of state;Pi”For the i-th " platform equivalent unit power output;Unit output is fixed value Pd
3) daily electricity constraint independent of time is determined, it may be assumed that
In formula, D is interconnection day to exchange electricity, is determined by trading program;fL,tFor interconnection period t transimission power;
4) constraint condition according to formula 10 to formula 12 establishes interconnection adjustment elastic model.
5. a kind of power grid N-1 safety economy optimizing scheduling for considering transmission operation elastic space according to claim 1 or 2 Method, which is characterized in that establish and consider that the key step of the N-1 safety economy scheduling model of transmission operation elastic space is as follows:
1) objective function min F is determined, it may be assumed that
In formula, F is total power production cost;T is scheduling time;U is unit number;CGi,tFor unit i period t power generation expense; CL,tFor the power purchase expense of outer net day part;Cw,tFor Wind turbines period t abandonment punishment cost;
Abandonment punishment cost C of the Wind turbines in period tw,tIt is as follows:
In formula, λwFor abandonment penalty factor;Activity of force is predicted for period t Wind turbines;Pw,tFor the practical power output of Wind turbines Power;
Unit i mainly includes coal consumption cost C in the power generation expense of period tCi,t, unit starting cost Ci,t,UCost is shut down with unit Ci,t,D
2) increase-volume elastic safety constraint formula and interconnection transmit elastic restraint formula to combination failure in short-term, establish optimization constraint condition, As shown in formula 15 to 19;
Power-balance constraint is as follows:
In formula, NgFor system convention generator number of units;Pgi,tFor unit i period t power output;fL,tIt is interconnection period t's Transimission power;Pw,tFor the wind power output of period t;Pd,tFor total power load of period t;
The constraint of unit output bound is as follows:
In formula, Ii,tEach unit is characterized in the start and stop state of period t;For each unit period t maximum, most Small power output;Pgi,tFor unit i period t power output;
Unit minimum start-off time constraints are as follows:
In formula, ti,t,onAnd ti,t,offRespectively unit i moment t lasting booting and shut down the time;Ti,onAnd Ti,offRespectively Unit i is switched on and shuts down the time in the minimum of period t;Ii,tEach unit is characterized in the start and stop state of period t;Ii,t-1Characterize each machine Start and stop state of the group in period t-1;Ti,UStart the time for unit i;Ti,DThe time is shut down for unit i;
Unit Commitment expense restriction is as follows:
In formula, KiAnd JiThe single startup-shutdown expense of respectively unit i and unit j;
Unit ramp loss is as follows:
Ii,t-1Pi,t-1idown≤Pgi,t≤Ii,t-1Pi,t-1iup; (19)
In formula, λiupFor the ratio of slope of climbing of unit i;λidownFor the downward climbing rate of unit i;
3) linear solution formula 15 is updated objective function min F, to formula 19 to obtain considering transmission operation elasticity The N-1 safety economy scheduling model in space.
6. a kind of power grid N-1 safety economy optimizing scheduling for considering transmission operation elastic space according to claim 1 or 2 Method, which is characterized in that the 1) method of linear solution, which specifically includes that, carries out linear solution using CPLEX software;2) it utilizes GUROBI software carries out linear solution.
CN201810999580.8A 2018-08-30 2018-08-30 Power grid N-1 safe economic dispatching optimization method considering transmission operation elastic space Expired - Fee Related CN109327025B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810999580.8A CN109327025B (en) 2018-08-30 2018-08-30 Power grid N-1 safe economic dispatching optimization method considering transmission operation elastic space

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810999580.8A CN109327025B (en) 2018-08-30 2018-08-30 Power grid N-1 safe economic dispatching optimization method considering transmission operation elastic space

Publications (2)

Publication Number Publication Date
CN109327025A true CN109327025A (en) 2019-02-12
CN109327025B CN109327025B (en) 2020-10-09

Family

ID=65263909

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810999580.8A Expired - Fee Related CN109327025B (en) 2018-08-30 2018-08-30 Power grid N-1 safe economic dispatching optimization method considering transmission operation elastic space

Country Status (1)

Country Link
CN (1) CN109327025B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109993407A (en) * 2019-02-28 2019-07-09 重庆大学 Consider the renewable energy digestion capability Static Equivalent appraisal procedure of elastic space
CN110165711A (en) * 2019-02-28 2019-08-23 重庆大学 Consider the geomantic omen fire combined dispatching optimization method of generator operation elastic space
CN110445189A (en) * 2019-07-18 2019-11-12 国家电网有限公司 Consider the operation of power networks state evaluating method in water power elasticity of storage ability space
CN110880751A (en) * 2019-04-04 2020-03-13 重庆大学 Method for expanding power feasible region of interconnection network tie line
CN111581809A (en) * 2020-04-30 2020-08-25 华北电力大学 Comprehensive energy scheduling method for multi-energy coupling elasticity
CN113659579A (en) * 2021-08-11 2021-11-16 国网福建省电力有限公司 N-1 safety constraint considered regional power grid tie line power transmission capability calculation method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104182850A (en) * 2014-09-05 2014-12-03 国家电网公司 Interconnection line plan formulating method based on demand response
US20150310366A1 (en) * 2012-11-09 2015-10-29 Tianjin University Security region based security-constrained economic dispatching method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150310366A1 (en) * 2012-11-09 2015-10-29 Tianjin University Security region based security-constrained economic dispatching method
CN104182850A (en) * 2014-09-05 2014-12-03 国家电网公司 Interconnection line plan formulating method based on demand response

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
任建文 等: "考虑直流联络线功率调整的跨区风电消纳模型", 《电力建设》 *
张衡 等: "考虑N-1安全网络约束的输电网结构优化", 《电力自动化设备》 *
杨洋 等: "超高压输电电缆动态增容计算及双线增容策略", 《华东电力》 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109993407A (en) * 2019-02-28 2019-07-09 重庆大学 Consider the renewable energy digestion capability Static Equivalent appraisal procedure of elastic space
CN110165711A (en) * 2019-02-28 2019-08-23 重庆大学 Consider the geomantic omen fire combined dispatching optimization method of generator operation elastic space
CN110880751A (en) * 2019-04-04 2020-03-13 重庆大学 Method for expanding power feasible region of interconnection network tie line
CN110880751B (en) * 2019-04-04 2021-06-22 重庆大学 Method for expanding power feasible region of interconnection network tie line
CN110445189A (en) * 2019-07-18 2019-11-12 国家电网有限公司 Consider the operation of power networks state evaluating method in water power elasticity of storage ability space
CN110445189B (en) * 2019-07-18 2023-08-29 国家电网有限公司 Power grid operation state evaluation method considering water reservoir capacity elastic space
CN111581809A (en) * 2020-04-30 2020-08-25 华北电力大学 Comprehensive energy scheduling method for multi-energy coupling elasticity
CN111581809B (en) * 2020-04-30 2024-02-06 华北电力大学 Comprehensive energy scheduling method of multi-energy coupling elasticity
CN113659579A (en) * 2021-08-11 2021-11-16 国网福建省电力有限公司 N-1 safety constraint considered regional power grid tie line power transmission capability calculation method

Also Published As

Publication number Publication date
CN109327025B (en) 2020-10-09

Similar Documents

Publication Publication Date Title
CN109327025A (en) Consider the power grid N-1 safety economy method for optimizing scheduling of transmission operation elastic space
Chen et al. Multi-time step service restoration for advanced distribution systems and microgrids
Caramanis et al. Co-optimization of power and reserves in dynamic T&D power markets with nondispatchable renewable generation and distributed energy resources
Shi et al. Enhancing distribution system resilience against extreme weather events: Concept review, algorithm summary, and future vision
Mehrjerdi Dynamic and multi-stage capacity expansion planning in microgrid integrated with electric vehicle charging station
Vijayapriya et al. Smart grid: an overview
Li et al. Transmission contingency analysis based on integrated transmission and distribution power flow in smart grid
CN109146706A (en) A kind of Transmission Expansion Planning in Electric method considering the flexibility equilibrium of supply and demand
Kreikebaum et al. Smart Wires—A distributed, low-cost solution for controlling power flows and monitoring transmission lines
He et al. Enhancing the power grid flexibility with battery energy storage transportation and transmission switching
Ghasemi et al. A two-stage resilience improvement planning for power distribution systems against hurricanes
CN106549420B (en) Consider the electric power system operation standby optimization method of risk and wind-power electricity generation
Ilo “Link”—The smart grid paradigm for a secure decentralized operation architecture
Zarei et al. Multi‐objective optimization model for distribution network reconfiguration in the presence of distributed generations
CN112183855A (en) Regional power spot market clearing method and device and electronic equipment
Janfeshan et al. Hierarchical supervisory control system for PEVs participating in frequency regulation of smart grids
Saadatmand et al. Optimal PID controller of large‐scale PV farms for power systems LFO damping
Wang et al. Equilibrium allocation strategy of multiple ESSs considering the economics and restoration capability in DNs
Saadatmand et al. Optimal coordinated tuning of power system stabilizers and wide‐area measurement‐based fractional‐order PID controller of large‐scale PV farms for LFO damping in smart grids
Zhao et al. Distributed multi-objective day-ahead generation and HVDC transmission joint scheduling for two-area HVDC-linked power grids
Li et al. Optimization method of skeleton network partitioning scheme considering resilience active improvement in power system restoration after typhoon passes through
CN105226649B (en) One kind predicting improved provincial power network power generation dispatching optimization method based on bus load
Yang et al. A multi-state control strategy for battery energy storage based on the state-of-charge and frequency disturbance conditions
Li et al. Optimal planning energy storage for promoting renewable power consumption in the urgent situation of UHV systems
CN102054234B (en) Method for checking reserve capacity of power system based on random optimal power flow

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201009

Termination date: 20210830

CF01 Termination of patent right due to non-payment of annual fee