CN109308542A - Landslide earth's surface partition method, equipment and storage equipment based on block chain frame - Google Patents

Landslide earth's surface partition method, equipment and storage equipment based on block chain frame Download PDF

Info

Publication number
CN109308542A
CN109308542A CN201810929804.8A CN201810929804A CN109308542A CN 109308542 A CN109308542 A CN 109308542A CN 201810929804 A CN201810929804 A CN 201810929804A CN 109308542 A CN109308542 A CN 109308542A
Authority
CN
China
Prior art keywords
landslide
sliding block
sliding
block
earth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810929804.8A
Other languages
Chinese (zh)
Inventor
刘勇
胡宝丹
陈喆
吴钊
金靖坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Geosciences
Original Assignee
China University of Geosciences
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Geosciences filed Critical China University of Geosciences
Priority to CN201810929804.8A priority Critical patent/CN109308542A/en
Publication of CN109308542A publication Critical patent/CN109308542A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"

Abstract

The present invention provides landslide earth's surface partition method, equipment and storage equipment based on block chain frame, landslide earth's surface partition method based on block chain frame is the Intelligent partition that the frame of block chain is introduced into landslide earth's surface, realizes that the intelligence of landslide section sliding block divides using the method for intelligent contract.Landslide earth's surface zone devices and storage equipment based on block chain frame, for realizing the landslide earth's surface partition method based on block chain frame.The beneficial effects of the present invention are: being considered as an entirety the same or similar region is moved, comprehensively considers the characteristics of motion of different zones, avoid Points replacing surfaces, the research defect taken a part for the whole.Carrying out subregion to landslide earth's surface can be preferable to retain landslide local motion deformation data while being fully described by landslide mass motion deformation.

Description

Landslide earth's surface partition method, equipment and storage equipment based on block chain frame
Technical field
The present invention relates to landslide data processing fields, more particularly to the landslide earth's surface square partition based on block chain frame Method, equipment and storage equipment.
Background technique
With the improvement of landslide monitoring means and method, for the ease of to fairly large landslide carry out it is comprehensive understand and Analysis, it will usually multiple monitoring points are arranged on slip mass.Because multiple monitoring point present positions are different, the displacement between each point Time series has certain correlation and otherness.It is the landslide analysis based on landslide displacement monitoring point that is proposed at present, pre- Model is surveyed, one of them representational monitoring point is generally all only chosen and is analyzed, forecast.Such as Wang Xiang text uses for 2016 When total station carries out the precision analysis of landslide monitoring, by taking a landslide monitoring point a certain phase as an example, its horizontal displacement point is analyzed The precision of error and vertical displacement mean square error of height in position;Yan Li is at 2014 on the basis for briefly introducing time series models On, by taking certain opencut landslide as an example, difference regression model is established to certain data of monitoring point tranquilization processing, analysis model is answered With;It is calculated within ten thousand roc of Tan et al. 2010 and is considered under rheology situation using FLAC3D, landslide displacement corresponding to different safety coefficients Trend curve, by the corresponding key point monitoring displacement trend curve of comparative analysis, quantitative, overall process determines the locating stabilization in landslide State;On the one hand similar processing relies on the accuracy of reconnaissance, still further aspect has ignored the otherness of different zones, in turn Lead to not carry out comprehensive and accurate judgement.It is analyzed for the misalignment of different monitoring points, is by gliding mass classifying rationally Several different regions are subsequent to the whole basis for carrying out research and analysis in landslide.Current many researchers divide landslide Area has carried out many beneficial comprehensive discoveries.Such as use GIS space interpolation and raster symbol-base in Zhu's generation illuminate et al. 2014, in conjunction with Force equation carries out the calculating of three-dimensional stability and the subregion of safety coefficient to ditch I landslide of horse man;Sun Chao et al. 2013 with Yalongjiang River middle reaches some hydropower station engineering reservoir area horse section river valley slip mass is example, passes through field geology data and geological process point The method that phase separation combines, to the partition characteristics and slip regime deployment analysis of slip mass;Combine within Fang Juyang 2015 east wind pavilion sliding Slope engineering geological condition takes the differentiation of subregion piecemeal pointedly to propose to integrate according to topography and geomorphology, engineering geological condition Disposal Measures.
The essence of block chain is a kind of distributed data base of decentralization, wherein the application of intelligent contract being capable of expansion area The function of block chain.Intelligent contract is a kind of computer protocol for being intended to propagate, verify or execute in a manner of information-based contract.With The development of block chain technology, it will drive more distributed infrastructures, the frame of block chain is introduced by the technical program In the earth's surface partition method on more monitoring point landslides, the deficiency of previous single monitoring point monitoring landslide method is avoided, to more monitorings The subregion of the landslide earth's surface of point can help the motion conditions that analysis of landslide body different zones are distinguished in subsequent research, development pair Come down the type of sports of each different zones and motion morphology studied, the movement of more comprehensively more accurate analysis of landslide, by Power situation and the prediction and warning on landslide etc..
Summary of the invention
To solve the above-mentioned problems, the present invention provides based on block chain frame landslide earth's surface partition method, equipment and Equipment is stored, the landslide earth's surface partition method based on block chain frame mainly comprises the steps that
S101: obtaining landslide profile information data and landslide depth displacement data, according to landslide profile information data and cunning Slope deep displacement data, using the section that comes down as benchmark face, the uniform item of section that will come down is divided into several sliding blocks, each sliding block is corresponding The data block of one storage sliding block information data, wherein the sliding surface angle stored in each data block and residual pushing force are to connect The chain of each sliding block is connect, i.e., the residual pushing force of previous sliding block and sliding surface angle are the chain for connecting next sliding block;
S102: being arranged intelligent contract, and the intelligence contract includes response condition and rule of response, and response condition is to exist to remain Remaining sliding force is less than or equal to 0 sliding block, and it is an area that rule of response, which is less than sliding block corresponding to the residual pushing force equal to 0 not, The last one sliding block;
S103: the residual pushing force of each sliding block is calculated, residual pushing force is obtained using imbalanced thrust method in the t month Calculated result, t > 0;
S104: do you judge that the residual pushing force calculated result reaches stable condition? if so, arriving step S109;If It is no, then step S105 is arrived, the stability condition refers to: the residual pushing force of all sliding blocks is all 0;
S105: do you judge that the residual pushing force calculated result reaches response condition? if so, arriving step S106;If It is no, then arrive step S108;
S106: do you judge that the residual pushing force calculated result reaches rule of response? if so, arriving step S107;If It is no, then arrive step S108;
S107: triggering intelligent contract, carries out subregion response to all sliding blocks, obtains the division result of landslide section, and will Division result is stored into the corresponding data block of each sliding block;
S108: do you judge that t reaches setting value? if so, obtaining step S109;If it is not, t is updated to t+1, return step S103;
S109: the division result of landslide earth's surface is obtained using plane conversion according to the division result of landslide section.
Further, sliding block information data described in step S101, the residue at sliding surface angle, each sliding block including each sliding block Sliding force, sliding block weight, sliding surface length, shear strength parameter, stability coefficient.
Further, in step S103, using imbalanced thrust method, the specific step of the residual pushing force of each sliding block is calculated It is rapid as follows:
S201: the processing of broken line geometrical characteristic is carried out to landslide depth displacement data acquired in step s101, is come down Integrity metrics data;
S202: according to landslide integrity metrics data, the shear strength parameter to be come down;Using each sliding block volume and Density parameter calculates the weight for obtaining each sliding block;The normal pressure of each sliding block is acquired using the stability coefficient on landslide, is glided Power and skid resistance;
S203: using all data for calculating acquisition in step S202, using imbalanced thrust method, each sliding block is obtained Residual pushing force.
Further, in step S107, the concrete operations of subregion response are as follows: the chain for meeting the sliding block of intelligent contract breaks It opens, the pervious sliding block of chain gap is divided into an area, and the later sliding block of chain gap is divided into another area, thus to landslide section Carry out subregion.
Technical solution provided by the invention have the benefit that landslide earth's surface carry out subregion after, movement it is identical Or similar region is considered as an entirety, comprehensively considers the characteristics of motion of different zones, avoids Points replacing surfaces, takes a part for the whole Study defect.Carrying out subregion to landslide can be preferable to retain landslide while being fully described by landslide mass motion deformation Local motion deformation data.
Detailed description of the invention
Present invention will be further explained below with reference to the attached drawings and examples, in attached drawing:
Fig. 1 is the flow chart of the landslide earth's surface partition method in the embodiment of the present invention based on block chain frame;
Fig. 2 is the schematic diagram of the block diagram of plain boiled water river landslide hatching III and saturation in the embodiment of the present invention;
Fig. 3 is the schematic diagram of landslide section sliding block in the embodiment of the present invention;
Fig. 4 is the schematic diagram of landslide section sliding block intelligence contract working principle in the embodiment of the present invention;
Fig. 5 is in May, the 2015 part sliding block residual pushing force schematic diagram in the embodiment of the present invention;
Fig. 6 is the plain boiled water river landslide subzone schematic diagram in the embodiment of the present invention;
Fig. 7 is the schematic diagram that hardware device works in the embodiment of the present invention.
Specific embodiment
For a clearer understanding of the technical characteristics, objects and effects of the present invention, now control attached drawing is described in detail A specific embodiment of the invention.
The embodiment provides landslide earth's surface partition method, equipment and storage equipment based on block chain frame.
Referring to FIG. 1, Fig. 1 is the process of the landslide earth's surface partition method in the embodiment of the present invention based on block chain frame Landslide earth's surface partition method based on block chain frame is applied to landslide shown in Fig. 2 by figure, carries out landslide earth's surface subregion, tool Body includes the following steps:
S101: obtaining landslide profile information data and landslide depth displacement data, according to landslide profile information data and cunning Slope deep displacement data, using the section that comes down as benchmark face, the uniform item of section that will come down is divided into several sliding blocks, each sliding block is corresponding The data block of one storage sliding block information data, wherein the sliding surface angle stored in each data block and residual pushing force are to connect The chain of each sliding block is connect, i.e., the residual pushing force of previous sliding block and sliding surface angle are the chain for connecting next sliding block;
S102: being arranged intelligent contract, and the intelligence contract includes response condition and rule of response, and response condition is to exist to remain Remaining sliding force is less than or equal to 0 sliding block, and it is an area that rule of response, which is less than sliding block corresponding to the residual pushing force equal to 0 not, The last one sliding block;
S103: the residual pushing force of each sliding block is calculated, residual pushing force is obtained using imbalanced thrust method in the t month Calculated result, t > 0;
S104: do you judge that the residual pushing force calculated result reaches stable condition? if so, arriving step S109;If It is no, then step S105 is arrived, the stability condition refers to: the residual pushing force of all sliding blocks is all 0;
S105: do you judge that the residual pushing force calculated result reaches response condition? if so, arriving step S106;If It is no, then arrive step S108;
S106: do you judge that the residual pushing force calculated result reaches rule of response? if so, arriving step S107;If It is no, then arrive step S108;
S107: triggering intelligent contract, carries out subregion response to all sliding blocks, obtains the division result of landslide section, and will Division result is stored into the corresponding data block of each sliding block;
S108: do you judge that t reaches setting value? if so, obtaining step S109;If it is not, t is updated to t+1, return step S103;
S109: the division result of landslide earth's surface is obtained using plane conversion according to the division result of landslide section.
Sliding block information data described in step S101, including the sliding surface angle of each sliding block, the residual pushing force of each sliding block, cunning Block weight, sliding surface length, shear strength parameter, stability coefficient.
In step S103, using imbalanced thrust method, calculating the residual pushing force of each sliding block, specific step is as follows:
S201: the processing of broken line geometrical characteristic is carried out to landslide depth displacement data acquired in step s101, is come down Integrity metrics data;
S202: according to landslide integrity metrics data, the shear strength parameter to be come down;Using each sliding block volume and Density parameter calculates the weight for obtaining each sliding block;The normal pressure of each sliding block is acquired using the stability coefficient on landslide, is glided Power and skid resistance;
S203: using all data for calculating acquisition in step S202, using imbalanced thrust method, each sliding block is obtained Residual pushing force.
In step S103, the value of t generally recommends to take 12, can carry out a subzone to landslide within 1 year.
Stability condition described in step S104 refers to: the stress between all sliding blocks for the section that comes down is reached common understanding shape At stable state, i.e., the residual pushing force of all sliding blocks is all 0.
In step S107, the concrete operations of subregion response are as follows: disconnect the chain for meeting the sliding block of intelligent contract, chain gap Pervious sliding block is divided into an area, and the later sliding block of chain gap is divided into another area, to carry out subregion to landslide section.
The pseudocode of the embodiment of the present invention is as follows:
As shown in figure 3, the chain between each sliding block mainly includes the residual pushing force of current slide, sliding surface angle.
As shown in figure 4, when the residual pushing force of a certain sliding block is zero or negative value, being said when occurring in addition to the last one sliding block Bright sliding block thereon does not generate the effect of power to lower slider, will then be considered as at drawing crack at this at this time, and chain herein is disconnected, and On the basis of gap, sliding block is divided into the area Liang Ge.
The present invention choose plain boiled water river landslide section III be used as research object, extract plain boiled water river section sliding surface 02 and The section of slope surface 03 is uniformly divided into 84 sliding blocks by slope surface 03, and each 01 average length of sliding block takes L=9.66m, wherein finally One piece of sliding block L=9.06m.The a certain moment is chosen, by taking in May, 2015 as an example, the saturation 04 of the reservoir level 05 of this month is considered, draws Result processed is as shown in Figure 2.Come down the block diagram of hatching III and drawing result and the shearing strength ginseng of saturation according to plain boiled water river Number initial value acquires the shear strength parameter value of this month.Finally develop to the thrust-drag margin of this month (residual pushing force), portion Divide shown in sliding block result figure 5.
There is negative value in the residual pushing force of the 35th block, shows to generate drawing crack between the 35th block and the 36th.The knot Fruit deduce at any time further calculate in strengthened.Therefore, according to the rule of intelligent contract, by plain boiled water river landslide section It is divided into the area Liang Ge here, as shown in Figure 6.
Fig. 7 is referred to, Fig. 7 is the hardware device operation schematic diagram of the embodiment of the present invention, and the hardware device specifically includes: Landslide earth's surface zone devices 701, processor 702 and storage equipment 703 based on block chain frame.
Landslide earth's surface zone devices 701 based on block chain frame: the landslide earth's surface subregion based on block chain frame Equipment 701 realizes the landslide earth's surface partition method based on block chain frame.
Processor 702: the processor 702 loads and executes the instruction in the storage equipment 703 and data for real The existing landslide earth's surface partition method based on block chain frame.
Store equipment 703: 703 store instruction of storage equipment and data;The storage equipment 703 is for realizing described Landslide earth's surface partition method based on block chain frame.
The beneficial effects of the present invention are: being considered as one the same or similar region is moved after carrying out subregion to landslide earth's surface A entirety comprehensively considers the characteristics of motion of different zones, avoids Points replacing surfaces, the research defect taken a part for the whole.To come down into Row subregion can be preferable to retain landslide local motion deformation data while being fully described by landslide mass motion deformation.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, it is all in spirit of the invention and Within principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (6)

1. the landslide earth's surface partition method based on block chain frame, it is characterised in that: the following steps are included:
S101: obtaining landslide profile information data and landslide depth displacement data, deep according to landslide profile information data and landslide Portion's displacement data, using the section that comes down as benchmark face, the uniform item of section that will come down is divided into several sliding blocks, each sliding block is one corresponding Store the data block of sliding block information data, wherein the sliding surface angle stored in each data block and residual pushing force are each for connection The chain of a sliding block, i.e., the residual pushing force of previous sliding block and sliding surface angle are the chain for connecting next sliding block;
S102: being arranged intelligent contract, and the intelligence contract includes response condition and rule of response, and response condition is existed under residue Sliding power is less than or equal to 0 sliding block, and rule of response is less than sliding block corresponding to the residual pushing force equal to 0 not and is an area most The latter sliding block;
S103: calculating the residual pushing force of each sliding block using imbalanced thrust method in the t month, obtains residual pushing force calculating As a result, t > 0;
S104: do you judge that the residual pushing force calculated result reaches stable condition? if so, arriving step S109;If it is not, then To step S105, the stability condition refers to: the residual pushing force of all sliding blocks is all 0;
S105: do you judge that the residual pushing force calculated result reaches response condition? if so, arriving step S106;If it is not, then To step S108;
S106: do you judge that the residual pushing force calculated result reaches rule of response? if so, arriving step S107;If it is not, then To step S108;
S107: triggering intelligent contract, carries out subregion response to all sliding blocks, obtains the division result of landslide section, and by subregion As a result it stores in the corresponding data block of each sliding block;
S108: do you judge that t reaches setting value? if so, obtaining step S109;If it is not, t is updated to t+1, return step S103;
S109: the division result of landslide earth's surface is obtained using plane conversion according to the division result of landslide section.
2. as described in claim 1 based on the landslide earth's surface partition method of block chain frame, it is characterised in that: in step S101 The sliding block information data, including the sliding surface angle of each sliding block, the residual pushing force of each sliding block, sliding block weight, sliding surface length, shearing resistance Intensive parameter, stability coefficient.
3. as described in claim 1 based on the landslide earth's surface partition method of block chain frame, it is characterised in that: step S103 In, using imbalanced thrust method, calculating the residual pushing force of each sliding block, specific step is as follows:
S201: the processing of broken line geometrical characteristic is carried out to landslide depth displacement data acquired in step s101, it is complete to obtain landslide Property achievement data;
S202: according to landslide integrity metrics data, the shear strength parameter to be come down;Utilize the volume and density of each sliding block Parameter calculates the weight for obtaining each sliding block;Using the stability coefficient on landslide acquire the normal pressure of each sliding block, sliding force and Skid resistance;
S203: the surplus of each sliding block is obtained using imbalanced thrust method using all data for calculating acquisition in step S202 Remaining sliding force.
4. as described in claim 1 based on the landslide earth's surface partition method of block chain frame, it is characterised in that: step S107 In, the concrete operations of subregion response are as follows: disconnect the chain for meeting the sliding block of intelligent contract, the pervious sliding block of chain gap is divided into one A area, the later sliding block of chain gap are divided into another area, to carry out subregion to landslide section.
5. a kind of storage equipment, it is characterised in that: the storage equipment store instruction and data are for realizing Claims 1 to 4 Landslide earth's surface partition method of any one described based on block chain frame.
6. the landslide earth's surface zone devices based on block chain frame, it is characterised in that: include: described in processor and claim 5 Storage equipment;The processor loads and executes the instruction in the storage equipment and data for realizing Claims 1 to 4 Landslide earth's surface partition method of any one described based on block chain frame.
CN201810929804.8A 2018-08-15 2018-08-15 Landslide earth's surface partition method, equipment and storage equipment based on block chain frame Pending CN109308542A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810929804.8A CN109308542A (en) 2018-08-15 2018-08-15 Landslide earth's surface partition method, equipment and storage equipment based on block chain frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810929804.8A CN109308542A (en) 2018-08-15 2018-08-15 Landslide earth's surface partition method, equipment and storage equipment based on block chain frame

Publications (1)

Publication Number Publication Date
CN109308542A true CN109308542A (en) 2019-02-05

Family

ID=65224023

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810929804.8A Pending CN109308542A (en) 2018-08-15 2018-08-15 Landslide earth's surface partition method, equipment and storage equipment based on block chain frame

Country Status (1)

Country Link
CN (1) CN109308542A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113076650A (en) * 2021-04-09 2021-07-06 重庆市地质矿产勘查开发局107地质队 Optimized calculation method for landslide saturation line and thrust in reservoir operation period
CN113436415A (en) * 2021-06-09 2021-09-24 北京京东乾石科技有限公司 Alarm device control method, device, electronic device and computer readable medium
CN114722566A (en) * 2022-03-02 2022-07-08 中铁二院工程集团有限责任公司 Stability processing method based on bank landslide partition

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105442620A (en) * 2015-11-17 2016-03-30 青岛理工大学 Optimized design method for position of slide-resistant pile of partial slippage side slope
CN106767613A (en) * 2016-12-14 2017-05-31 中国地质大学(武汉) A kind of method of the motion morphology that come down based on information fusion monitoring analysis
CN107330224A (en) * 2017-07-24 2017-11-07 中国地质大学(武汉) A kind of Analysis of Slope Stability slices method of the non-hypothesis in slitting intermolecular forces inclination angle

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105442620A (en) * 2015-11-17 2016-03-30 青岛理工大学 Optimized design method for position of slide-resistant pile of partial slippage side slope
CN106767613A (en) * 2016-12-14 2017-05-31 中国地质大学(武汉) A kind of method of the motion morphology that come down based on information fusion monitoring analysis
CN107330224A (en) * 2017-07-24 2017-11-07 中国地质大学(武汉) A kind of Analysis of Slope Stability slices method of the non-hypothesis in slitting intermolecular forces inclination angle

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
卢应发 等: ""边坡力的分布特征和稳定性分析"", 《岩土工程学报》 *
王博 等: ""以区块链为基础打造智慧城市大数据基础平台"", 《智慧城市评论》 *
罗丽娟 等: ""基于剩余推力法的黄土高边坡稳定性可靠度分析"", 《长安大学学报(自然科学版)》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113076650A (en) * 2021-04-09 2021-07-06 重庆市地质矿产勘查开发局107地质队 Optimized calculation method for landslide saturation line and thrust in reservoir operation period
CN113436415A (en) * 2021-06-09 2021-09-24 北京京东乾石科技有限公司 Alarm device control method, device, electronic device and computer readable medium
CN114722566A (en) * 2022-03-02 2022-07-08 中铁二院工程集团有限责任公司 Stability processing method based on bank landslide partition
CN114722566B (en) * 2022-03-02 2023-07-28 中铁二院工程集团有限责任公司 Stability processing method based on reservoir bank landslide partition

Similar Documents

Publication Publication Date Title
CN109308542A (en) Landslide earth's surface partition method, equipment and storage equipment based on block chain frame
CN107330224B (en) A kind of Analysis of Slope Stability slices method of point of non-hypothesis in force of inter-slice inclination angle
US7966165B2 (en) Soil-water coupled analyzer and soil-water coupled analysis method
CN111814369B (en) Strip division method capable of accurately calculating force inclination angle between strips and stability safety coefficient of side slope
CN110210621A (en) A kind of object detection method based on residual error network improvement
Armin et al. On the FE modeling of soil–blade interaction in tillage operations
CN108594261A (en) A kind of slip mass change detecting method based on laser radar technique
CN105354542B (en) A kind of video accident detection method under crowd scene
CN107092751B (en) Variable weight model combination forecasting method based on Bootstrap
CN103942433A (en) Building settlement prediction method based on historical data analysis
CN110489928A (en) Shallow buried coal seam mining area water flowing fractured zone development height method for predicting and system
WO2013151686A2 (en) System and method for reservoir pressure data analysis
Patinet et al. Atomic-scale avalanche along a dislocation in a random alloy
CN114238540A (en) Construction method of open caisson monitoring digital interaction platform for real-time data
CN104036362A (en) Rapid detection method of transformer power load abnormal data
Habousha et al. Plan‐form evolution of drainage basins in response to tectonic changes: Insights from experimental and numerical landscapes
CN108460422B (en) Submarine geomorphy kind identification method based on depth distribution feature
CN111524323B (en) Slope fission early warning method and system
CN109783991B (en) Landslide sliding process simulation method without known bottom sliding surface
CN115597664B (en) Method and system for constructing digital fully-mechanized coal mining face of coal mine
CN109165780A (en) Landslide monitoring point partition method, equipment and storage equipment based on block chain frame
CN106759083B (en) Form general model design method suitable for deep water discharging type sheet pile bulkhead structure
Berglund Ice fracture model for real-time shipsimulator
Liu et al. Modelling of landslide runout in sensitive clays
Hiscock Australian point and core reduction viewed through refitting

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190205

RJ01 Rejection of invention patent application after publication