CN109252454A - A kind of adjustable large span combined system arch bridge incremental launching construction engineering method of Construction State - Google Patents

A kind of adjustable large span combined system arch bridge incremental launching construction engineering method of Construction State Download PDF

Info

Publication number
CN109252454A
CN109252454A CN201811140835.1A CN201811140835A CN109252454A CN 109252454 A CN109252454 A CN 109252454A CN 201811140835 A CN201811140835 A CN 201811140835A CN 109252454 A CN109252454 A CN 109252454A
Authority
CN
China
Prior art keywords
construction
arch
girder
pushing tow
sunpender
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811140835.1A
Other languages
Chinese (zh)
Inventor
邵长宇
吴霄
陈亮
周伟翔
张洪金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201811140835.1A priority Critical patent/CN109252454A/en
Publication of CN109252454A publication Critical patent/CN109252454A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/06Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D4/00Arch-type bridges

Abstract

The present invention relates to a kind of adjustable large span combined system arch bridge incremental launching construction engineering methods of Construction State, it is characterized in that by the interim strut of steel arch, girder steel, sunpender and connection steel arch, girder steel, earlier spelling is beam and arch combined system on the coast, and initial tensioning is carried out to sunpender, during integrally will carry out pushing tow with sunpender and interim strut combination arch bridge, it is basic conformation function function with component stress limit value, the Construction State during pushing tow is adjusted by optimization boom tensile force.The construction adjusts combination arch bridge integral pushing process stress by adjusting boom tensile force in real time, guarantee arched girder collaborative to a certain extent, improve the stress performance of structure, reduce Temporary Piers quantity and the interim strut quantity of arched girder in water, reduce the complexity of structure construction, it has higher promotional value in aspects such as applicability, economy, construction quality, construction periods, has developing meaning to some reference.

Description

A kind of adjustable large span combined system arch bridge incremental launching construction engineering method of Construction State
Technical field
The present invention relates to technical field of bridge engineering, specifically a kind of adjustable large span combined system of Construction State Arch bridge incremental launching construction engineering method.
Background technique
Combined system arch bridge is with its graceful shape, reasonable stress performance and good economy in Longspan Bridge It occupies a tiny space in construction.Common combination arch bridge construction method include rack construction, rotator construction, cable-hoisting construction with And incremental launching construction etc..
Rack construction method can first install girder steel part for steel construction combined system arch bridge, then in girder steel upper bracket Assembled steel arch, i.e., the construction method of first beam rear arch.No matter using which kind of method construction girder steel, the construction of steel arch is required in girder steel On set up bracket, generally require more Temporary Piers are arranged just and can guarantee the stress of girder steel, and Temporary Piers are set in river and are taken If the cost and difficulty of bracket are very high, and for there is the river opened the navigation or air flight and required, Temporary Piers setting position and quantity will receive logical Boat limitation.
Arch rib or entire superstructure are divided into two and half across then sharp respectively in two sides manufacture semiarch by construction by swing Two halves donor is turned into bridge axle line position closure arching with power device, this method speed of application is fast, cost is lower, but right In being located in river, apart from the farther away arch bridge in two sides or multispan continuous arch bridge and be not suitable for.
Cable-hoisting construction is carried out using CABLEWAY ERECTION SYSTEM without branch by construction installations such as setting pylon, anchorage, cables Frame construction.But for being located in river, apart from the farther away arch bridge in two sides, the setting cost of pylon and anchorage is carried out in river very Height, it is extremely uneconomical, and difficulty of construction is also very big.
Incremental launching construction method is to set up top pushing platform in bank side, in place by arch rib, the assembled pushing tow forward whole after the completion of girder. This method is quickly, environmental protection, on opening the navigation or air flight, influence is small, is more and more favored in recent years." large-tonnage multispan combination arch bridge band arch is whole Pushing method " (number of patent application: CN101793010) proposes the method with arch integral pushing, but only leads between this method arched girder It crosses strut temporarily to connect, sunpender is installed again after the completion of pushing tow, the stress of arched girder during sunpender adjustment pushing tow can not be efficiently used, And extend temporary rest pier in water there are the time, influence flood passage and navigation under bridge;" integral pushing of network tied arch bridge is applied Engineering method " (number of patent application: 2011101028797) propose network tied arch bridge without nose girder integral pushing method, but the program The adjustability of entire work progress middle hanger power is not considered, and without nose girder integral pushing method for Longspan Bridge Construction cost is high;In addition in the construction process, structure is Time variable structure, and the drag of structure is a stochastic variable, load also with Construction speed constantly changes, and carrys out the safety that guiding construction is difficult to general warranty structure with certainty theory.So for greatly across Spend incremental launching construction engineering method Shortcomings current for arch bridge.
Summary of the invention
The purpose of the present invention is to provide a kind of adjustable large span combined system arch bridge incremental launching construction engineering method of Construction State, Pushing tow process hogging, beam stress are controlled within zone of reasonableness by sunpender and interim strut, it is interim during reduction pushing tow Pier quantity and there are the time, reduces the influence to flood passage under bridge and navigation.
To achieve the goals above, technical scheme is as follows: a kind of adjustable large span assembly of Construction State Be arch bridge incremental launching construction engineering method, it is characterised in that the engineering method includes: to set up top pushing platform by land, by steel arch, girder, sunpender with And earlier spelling is beam and arch combined system to the interim strut of connection steel arch, girder on the coast, and carries out initial tensioning to sunpender, is being incited somebody to action During beam and arch combined system with sunpender and interim strut integrally carries out pushing tow, boom tensile force is adjusted constantly to adapt to system Variation until pushing tow in place.
Further, when spelling is beam and arch combined system, then girder assembled first is spelled arch rib and is led to girder top surface is sleeping Cross vertical transfer arch rib is in place, after arched girder connection to be done, sunpender and interim strut between installation arch, beam.After the completion of girder assembly, The assembly encircleed using girder top surface as platform for lining, it is then by vertical transfer technique that arch rib is in place, without setting up arch rib Bracket.
Further, the sunpender is preassembled before pushing tow starts, and band sunpender carries out pushing tow, pushing tow process In, it is basic conformation function function with component stress limit value, determines boom tensile force during pushing tow, by optimizes suspender tension Power adjusts the Construction State during pushing tow, guarantees the reliability of overall process.
Further, the interim strut is mounted between arch and beam, and interim strut has enough rigidity, top It is dismountable to shift a rear onto.
Further, the integral pushing be will encircle, beam, sunpender, interim strut as one carry out pushing tow.
Further, the engineering method specifically includes the following steps:
Step 1:
(1) trestle and foundation construction platform structure are set up, Temporary Piers are set;
(2) basis, pier construction, Temporary Piers construction in pushing tow water, pushing tow is constructed with falsework on permanent pier;
(3) girder steel, steel lagging jack segment unit factory process, live spelling;
(4) arched girder assembly, top pushing platform, lifting station, using multi-point pushing are set up.
Step 2:
(1) the assembled steel girder on top pushing platform;
(2) the assembled arch rib on beam, and vertical transfer construction is in place;
(3) interim strut between installation arch, beam, and sunpender is subjected to initial tensioning;
(4) pushing tow front launching nose is installed;
(5) beam-arch composite bridge is integrally carried out continuing incremental launching construction, guarantees construction overall process by adjusting boom tensile force Reliability.
Step 3:
(1) in place to beam-arch composite bridge pushing tow, remove interim strut;
(2) Temporary Piers and platform for lining are gradually removed;
(3) suspender force is adjusted.
Step 4:
(1) accessory structure is constructed;
(2) full-bridge is completed.
Above-mentioned construction technology and interim measure can guarantee to push up due to there is the presence of permanent sunpender and interim strut The common stress of journey hogging and beam is pushed through, the quantity of temporary rest pier in water is reduced, is solved in large span combination arch bridge incremental launching construction Crucial stress problem, the construction by adjusting boom tensile force to combination arch bridge integral pushing process stress carry out Adjustment in real time guarantees arched girder collaborative to a certain extent, improves the stress performance of structure, reduces Temporary Piers quantity and arch in water The interim strut quantity of beam, reduces the complexity of structure construction, in applicability, economy, construction quality, construction period etc. Aspects has higher promotional value, has developing meaning to some reference.
Detailed description of the invention
Fig. 1 pushing tow process schematic.
Fig. 2 is Temporary Piers arrangement.
Fig. 3 is main bridge general arrangement.
Fig. 4 is main bridge optimal crosssection figure.
Specific embodiment
Below in conjunction with drawings and concrete examples to a kind of adjustable large span combined system of Construction State proposed by the present invention Arch bridge incremental launching construction engineering method is described in further detail.According to following explanation and claims, advantages and features of the invention It will become apparent from.It should be noted that attached drawing is all made of very simplified form and using non-accurate ratio, only to it is convenient, Lucidly aid in illustrating the purpose of present example.
Illustrate the adjustable large span combination arch bridge incremental launching construction engineering method of this example Construction State in conjunction with Fig. 1 to Fig. 4, it is main to flow Journey is as follows: land to set up top pushing platform 7, girder 2 assembled first, then crouches in girder top surface and spells arch rib 1 and pass through vertical transfer and will encircle Rib is in place, and after arched girder connection to be done, sunpender 4 and interim strut 3 between installation arch, beam will be combined with sunpender 4 and interim strut 3 System arch bridge integrally carries out pushing tow, and constantly adjustment boom tensile force is during pushing tow to adapt to the variation of system until pushing tow arrives Position.
It is background engineering in conjunction with certain bridge, introduces specific implementation step.The bridge is (95m+280m)+420m+(280m+95m) Network tied arch bridge.420m across arch ratio of rise to span be 1/6, rise 70m, 3.5 ° of inclined angle;280m is also 1/ across arch ratio of rise to span 6, rise 46.67m, 5.3 ° of inclined angle, arch rib uses pentagon steel case section.Arch rib horizontal-associate form is supportted using a word, strut For octagon steel case section.Sunpender uses mesh arrangement, and normal pitch is 9m on girder, along bridge to about 60 ° of inclination angle.Girder uses Orthotropic combined bridge deck combination beam, deck-molding 4.15m.Substructure uses tip-type Thin-Wall Piers form, rectangle cushion cap, drilling Bored concrete pile foundation.95m+280m mono- is continuous, and 420m is across freely-supported.Here specific embodiment is introduced by taking 420m simple span as an example.
When incremental launching construction, floorings are not yet laid with, and the sunpender between arch, beam has been installed and carried out initial tensioning, steel arch and steel Beam forms a beam-arch composite bridge.In addition the interim strut of connection steel arch, girder steel is set between steel arch and girder steel, so that The characteristics of arch bridge is provided with truss-type bridges during pushing tow improves the stress performance during pushing tow;In 420m across setting two A Temporary Piers 8, pushing tow front and back end are respectively provided with the sinciput that length is 45m and derive beam 5, rear pushing tow nose girder 6.Each permanent pier and face When pier top be respectively provided with incremental launching device, constructed using multi-point pushing.
The more detailed construction procedure of this bridge is as follows:
Step 1:
(1) trestle and foundation construction platform structure are set up, Temporary Piers are set;
(2) basis, pier construction, Temporary Piers construction in pushing tow water, pushing tow is constructed with falsework on permanent pier;
(3) girder steel, steel lagging jack segment unit factory process, live spelling;
(4) arched girder assembly, top pushing platform, lifting station, using multi-point pushing are set up.
Step 2:
(1) the assembled steel girder on top pushing platform;
(2) the assembled arch rib on beam, and vertical transfer construction is in place;
(3) interim strut between installation arch, beam, and sunpender is subjected to initial tensioning;
(4) pushing tow nose girder is installed;
(5) beam-arch composite bridge is integrally carried out continuing incremental launching construction, adjusts boom tensile force.
Step 3:
(1) when the position shown in across the beam-arch composite bridge pushing tow to Fig. 2 of 420m, removing nose girder, to then proceed to pushing tow in place;
(2) the interim strut of part main arch is removed;
(3) tensioning part sunpender;
(4) remaining interim strut is removed;
(5) the remaining sunpender of tensioning.
Step 4:
(1) Temporary Piers and platform for lining are gradually removed;
(2) suspender force is adjusted.
Step 5:
(1) it is laid with prefabricated bridge;
(2) according to the wet seam of sequence paragraph by paragraph pouring concrete from span centre to arch springing.
Step 6:
(1) accessory structure is constructed;
(2) full-bridge is completed.
In the construction process, various influence factors are not determining variable to bridge, can have certain range of variation, lead Causing total Construction State is a random process, and the case where reliable or failure may occur under certain probability in structure, There is certain limitation with certainty theory guiding construction.It is reliable that construction overall process is calculated based on theory of stochastic finite element thus Degree has developed a set of method for being suitable for the adjustment of combination tied arch bridge Construction State, and this method is based on component stress limit value Conformation function function meets design requirement using structural reliability and calculates each pushing tow stage boom tensile force as target, reaches and apply The adjustable purpose of work state.
Assuming that the power function of i-th of construction stage is represented byZ=R ﹣ S,In formula Z be the construction stage power function, Z > 0 representative structure safety, the representative structure of Z < 0 failure, R be material corresponding stress permissible value, be included in material property uncertainty, The uncertainty of geometric parameter and the uncertainty for calculating mode, S is the maximum stress in the key member section being calculated, For using the construction stages such as boom tensile force, jacking force, dead load, wind load load as the implicit function of design variable, as base Plinth calculates the probability of Z > 0 in work progress, and is converted into structural reliability degree index, is guaranteeing construction stage reliability satisfaction Under the conditions of design requirement, construction stage i boom tensile force is calculated.Specific implementation process is as follows:
(1) determine imposed load during pushing tow, according to situ measurements determine boom tensile force, jacking force, gravity and Other imposed load sizes and its statistical nature;
(2) material parameter provided according to steel construction processing factory, and experimental study achievement is combined, determine steel box-girder and steel arch timber The statistical nature for expecting the factors such as intensity, sectional dimension, establishes the probability statistics model of drag R;
(3) its statistical law is determined according to live sunpender power measurement result, according to boom tensile force, pushing tow process imposed load with And the statistical model of material parameter calculates the size and its probability Distribution Model of each crucial section stress;
(4) RELIABILITY INDEX that each pushing tow process middle girder and arch rib are calculated using theory of stochastic finite element, is referred to reliability Mark is greater than 4.7 and calculates each pushing tow stage boom tensile force for target, carrys out guiding construction with this.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this hair Any change, the modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to the protection of claims Range.

Claims (5)

1. a kind of adjustable large span combined system arch bridge incremental launching construction engineering method of Construction State, it is characterised in that the engineering method includes: Top pushing platform is set up by land, by the interim strut earlier spelling on the coast of steel arch, girder, sunpender and connection steel arch, girder For beam and arch combined system, and initial tensioning is carried out to sunpender, the beam and arch combined system with sunpender and interim strut is integrally being carried out During pushing tow, constantly adjust boom tensile force with adapt to system variation until pushing tow in place.
2. the adjustable large span combination arch bridge incremental launching construction engineering method of Construction State according to claim 1, it is characterised in that: When spelling is beam and arch combined system, girder assembled first, then girder top surface it is sleeping spell arch rib and by vertical transfer arch rib is in place, After arched girder connection to be done, sunpender and interim strut between installation arch, beam.
3. the adjustable large span combination arch bridge incremental launching construction engineering method of Construction State according to claim 1, it is characterised in that: During pushing tow, it is basic conformation function function with component stress limit value, determines boom tensile force during pushing tow, pass through optimization Boom tensile force adjusts the Construction State during pushing tow, guarantees the reliability of overall process.
4. the adjustable large span combination arch bridge incremental launching construction engineering method of Construction State as described in claim 1, it is characterised in that: face When strut be supported between girder and arch rib, pushing tow is removed afterwards in place.
5. the adjustable large span combination arch bridge incremental launching construction engineering method of Construction State as described in claim 1, it is characterised in that should Construction the following steps are included:
Step 1:
(1) trestle and foundation construction platform structure are set up, Temporary Piers are set;
(2) basis, pier construction, Temporary Piers construction in pushing tow water, pushing tow is constructed with falsework on permanent pier;
(3) girder steel, steel lagging jack segment unit factory process, live spelling;
(4) arched girder assembly, top pushing platform, lifting station, using multi-point pushing are set up;
Step 2:
(1) the assembled steel girder on top pushing platform;
(2) the assembled arch rib on beam, and vertical transfer construction is in place;
(3) interim strut between installation arch, beam, and sunpender is subjected to initial tensioning;
(4) pushing tow front launching nose is installed;
(5) beam-arch composite bridge is integrally carried out continuing incremental launching construction, guarantees construction overall process by adjusting boom tensile force Reliability;
Step 3:
(1) in place to beam-arch composite bridge pushing tow, remove interim strut;
(2) Temporary Piers and platform for lining are gradually removed;
(3) suspender force is adjusted;
Step 4:
(1) accessory structure is constructed;
(2) full-bridge is completed.
CN201811140835.1A 2018-09-28 2018-09-28 A kind of adjustable large span combined system arch bridge incremental launching construction engineering method of Construction State Pending CN109252454A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811140835.1A CN109252454A (en) 2018-09-28 2018-09-28 A kind of adjustable large span combined system arch bridge incremental launching construction engineering method of Construction State

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811140835.1A CN109252454A (en) 2018-09-28 2018-09-28 A kind of adjustable large span combined system arch bridge incremental launching construction engineering method of Construction State

Publications (1)

Publication Number Publication Date
CN109252454A true CN109252454A (en) 2019-01-22

Family

ID=65048740

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811140835.1A Pending CN109252454A (en) 2018-09-28 2018-09-28 A kind of adjustable large span combined system arch bridge incremental launching construction engineering method of Construction State

Country Status (1)

Country Link
CN (1) CN109252454A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110055901A (en) * 2019-05-16 2019-07-26 中铁十五局集团第五工程有限公司 A kind of control method for realizing pushing tow steel tube arch rib closure precision based on BIM technology
CN110184893A (en) * 2019-06-28 2019-08-30 中铁大桥局集团有限公司 A kind of mounting device and arch rib construction method for Butterfly Arch Bridge arch rib
CN110348130A (en) * 2019-07-13 2019-10-18 山西省交通规划勘察设计院有限公司 A kind of prestretched strand stretching force optimum design method applied to incremental launching method
CN110387833A (en) * 2019-07-29 2019-10-29 北京九州动脉隧道技术有限公司 A kind of beam body erection method
CN111074790A (en) * 2019-12-17 2020-04-28 湖南鸿云杭萧绿建科技有限公司 Incremental launching construction method for bridge erection
CN112342917A (en) * 2020-10-20 2021-02-09 上海市政工程设计研究总院(集团)有限公司 Combined construction method for pushing beam first and then lifting arch of large-span tied arch bridge
CN113863151A (en) * 2021-10-21 2021-12-31 中铁第四勘察设计院集团有限公司 Steel box tied arch bridge construction method

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110055901A (en) * 2019-05-16 2019-07-26 中铁十五局集团第五工程有限公司 A kind of control method for realizing pushing tow steel tube arch rib closure precision based on BIM technology
CN110184893A (en) * 2019-06-28 2019-08-30 中铁大桥局集团有限公司 A kind of mounting device and arch rib construction method for Butterfly Arch Bridge arch rib
CN110348130A (en) * 2019-07-13 2019-10-18 山西省交通规划勘察设计院有限公司 A kind of prestretched strand stretching force optimum design method applied to incremental launching method
CN110387833A (en) * 2019-07-29 2019-10-29 北京九州动脉隧道技术有限公司 A kind of beam body erection method
CN111074790A (en) * 2019-12-17 2020-04-28 湖南鸿云杭萧绿建科技有限公司 Incremental launching construction method for bridge erection
CN112342917A (en) * 2020-10-20 2021-02-09 上海市政工程设计研究总院(集团)有限公司 Combined construction method for pushing beam first and then lifting arch of large-span tied arch bridge
CN113863151A (en) * 2021-10-21 2021-12-31 中铁第四勘察设计院集团有限公司 Steel box tied arch bridge construction method

Similar Documents

Publication Publication Date Title
CN109252454A (en) A kind of adjustable large span combined system arch bridge incremental launching construction engineering method of Construction State
CN108374347A (en) A kind of high-speed railway large span cable-carried arch bridge steel lagging jack buckling and hanging system construction method
CN109972517B (en) Construction method of main beam of cable-stayed bridge with steel-concrete composite beam
CN101418543B (en) Self-anchored rope-suspension bridge inclined drawing construction method
CN103938552B (en) Steel truss arched bridge self-balancing cantilever construction method and the spacing bearing of main pier
CN101158146A (en) Cable-stayed bridge main-beam sliding form frame system and construction method
CN105603881A (en) Integral erecting system for large sea-crossing arch bridge and construction method thereof
CN110761168A (en) Design and construction method of cable-first beam-second self-anchored suspension bridge
CN109750600B (en) Construction method of asymmetric cable crane
CN205399220U (en) Whole system of erectting of large -scale arched bridge over strait
CN102418315A (en) Construction method for concrete-filled steel tube arched bridge with large low-buckle tower erection bridge width
CN106087752A (en) Multispan cable-carried arch bridge construction method
CN109457615A (en) A kind of construction method of installation of abnormity bowstring arch bridge arch ring
CN105648917A (en) Cable-beam synchronization construction method for composite beam self-anchored suspension bridge
CN106522112A (en) Cable-stayed bridge side span beam section erecting system and method thereof
CN209227394U (en) A kind of large span combined system arch bridge incremental launching construction measure
CN104929044A (en) Construction method for offshore steel trestle
CN206538687U (en) Cable-stayed bridge end bay beam section construction system
CN105696470B (en) Synchronous quick steel box girder in-situ incremental launching and tower column construction method
CN203741729U (en) Pre-stress supporting system used for bridge incremental launching construction method
CN106968178B (en) Construction method for main beam of cable-stayed suspension bridge
CN104963292A (en) Construction method of reinforced concrete multi-span arch bridge or continuous box structure bridge
US2914783A (en) Bridge construction
CN112523097A (en) Large-span bridge gantry crane and construction method thereof
CN207933870U (en) A kind of asymmetric assembled steel cable-stayed bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination