CN109210688A - Multi fan clarifier control method and device, clarifier - Google Patents

Multi fan clarifier control method and device, clarifier Download PDF

Info

Publication number
CN109210688A
CN109210688A CN201811117469.8A CN201811117469A CN109210688A CN 109210688 A CN109210688 A CN 109210688A CN 201811117469 A CN201811117469 A CN 201811117469A CN 109210688 A CN109210688 A CN 109210688A
Authority
CN
China
Prior art keywords
blower
clarifier
work
work order
control method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811117469.8A
Other languages
Chinese (zh)
Inventor
王剑
李艳明
梅术华
段洁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Haike Electronic Technology Co Ltd
Original Assignee
Guangzhou Haike Electronic Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Haike Electronic Technology Co Ltd filed Critical Guangzhou Haike Electronic Technology Co Ltd
Priority to CN201811117469.8A priority Critical patent/CN109210688A/en
Publication of CN109210688A publication Critical patent/CN109210688A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/30Control or safety arrangements for purposes related to the operation of the system, e.g. for safety or monitoring
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/62Control or safety arrangements characterised by the type of control or by internal processing, e.g. using fuzzy logic, adaptive control or estimation of values
    • F24F11/63Electronic processing
    • F24F11/64Electronic processing using pre-stored data
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/70Control systems characterised by their outputs; Constructional details thereof
    • F24F11/72Control systems characterised by their outputs; Constructional details thereof for controlling the supply of treated air, e.g. its pressure
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F2110/00Control inputs relating to air properties
    • F24F2110/50Air quality properties
    • F24F2110/64Airborne particle content
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]
    • Y02B30/70Efficient control or regulation technologies, e.g. for control of refrigerant flow, motor or heating

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Signal Processing (AREA)
  • Physics & Mathematics (AREA)
  • Fuzzy Systems (AREA)
  • Mathematical Physics (AREA)
  • Control Of Multiple Motors (AREA)

Abstract

This application involves a kind of multi fan clarifier control method and device, clarifier, multi fan clarifier control method includes: acquisition work order, and work order is used to indicate the working condition of each blower of control clarifier;If work order is low-grade bit instruction, controls each blower and circuit sequentially work.By obtaining work order, according to work order, when instruction is low-grade bit instruction, the blower for controlling clarifier is in single blower circulating working mode, each blower cycle operation in order is controlled, to guarantee that each blower resource is equalized utilization, to improve the service life of clarifier.

Description

Multi fan clarifier control method and device, clarifier
Technical field
The present invention relates to clarifier technical fields, more particularly to a kind of multi fan clarifier control method and device, only Change device.
Background technique
Clarifier in people's lives using more and more extensive, blower is the Primary Component of clarifier, blower workability Clean-up effect can be directly affected.The operating mode of current clarifier is single, particularly with the clarifier of multi fan, in low-grade location When work, separate unit fan operation is only needed sometimes, in traditional technology, Fans work, longtime running are often fixed in low-grade location When, the availability difference for often resulting in each blower is big, leads to the reduction of clarifier bulk life time.
Summary of the invention
Based on this, it is necessary to which for the problem that multi fan cannot be used uniformly, caused bulk life time is reduced, and provides one Kind multi fan clarifier control method and device, clarifier.
On the one hand, the embodiment of the invention provides a kind of multi fan clarifier control methods, comprising:
Work order is obtained, work order is used to indicate the working condition of each blower of control clarifier;
If work order is low-grade bit instruction, each blower for controlling clarifier circuits sequentially work.
Multi fan clarifier control method in one of the embodiments, further includes:
If work order is high-grade bit instruction, controls at least two blowers and work at the same time.
Controlling the step of each blower circuits sequentially work in one of the embodiments, includes:
It controls each blower and circuits sequentially work according to default operating time.
If being in one of the embodiments, low-grade bit instruction in work order, controls each blower and circuit sequentially work It is further comprised the steps of: before step
Blower identification information is obtained, the blower sum of clarifier is obtained according to identification information.
In one of the embodiments, before obtaining blower identification information step further include:
It detects whether to receive power-on instruction.
Controlling the step of at least two blowers work at the same time in one of the embodiments, includes:
Obtain air mass signal;
Controlling the step of at least two blowers work at the same time includes:
According to air mass signal, general power needed for clarifier is determined;
According to the blower of the operating power parameter of each blower prestored and clarifier sum, first object quantity is determined;
The blower of control first object quantity works at the same time, wherein the general power of the blower of first object quantity is not less than General power needed for clarifier, and first object quantity is no more than the blower sum of clarifier.
If receiving high-grade bit instruction in one of the embodiments, the step that at least two blowers work at the same time is controlled Suddenly include:
High-grade bit instruction is parsed, the operating power of the second destination number and each blower is obtained;
The blower for controlling the second destination number works by corresponding operating power.
Each blower is controlled in one of the embodiments, circuit sequentially work step include:
According to air mass signal, the operating power of each blower is determined;
It controls each blower and circuits sequentially work by operating power.
On the other hand, the embodiment of the invention also provides a kind of multi fan clarifier control devices, comprising:
Work order acquiring unit, for obtaining work order, work order is used to indicate each blower of control clarifier Working condition;
Low-grade location air-blower control unit, for controlling each blower and circuiting sequentially work when work order is low-grade bit instruction Make.
A kind of clarifier, including controller and multiple blowers, controller are electrically connected with each blower, and controller is stored with journey The step of sequence, controller realizes above-mentioned multi fan clarifier control method when executing program.
One or more embodiment provided by the invention at least has the advantages that multi fan clarifier controlling party Method, comprising: obtain work order;If work order is low-grade bit instruction, controls each blower and circuit sequentially work.Pass through acquisition Work order, according to work order, the blower for controlling clarifier is in single blower circulating working mode, controls each blower in order Cycle operation, it is ensured that the utilization rate of each blower is more balanced, to improve the service life of clarifier.
Detailed description of the invention
Fig. 1 is the flow diagram of multi fan clarifier control method in one embodiment;
Fig. 2 is the flow diagram of multi fan clarifier control method in another embodiment;
Fig. 3 is the flow diagram of multi fan clarifier control method in further embodiment;
Fig. 4 is the flow diagram of multi fan clarifier control method in another embodiment;
Fig. 5 is the flow diagram of multi fan clarifier control method in a still further embodiment;
Fig. 6 is the structural block diagram of multi fan clarifier control device in one embodiment;
Fig. 7 is the internal structure chart of computer equipment in one embodiment.
Specific embodiment
To facilitate the understanding of the present invention, a more comprehensive description of the invention is given in the following sections with reference to the relevant attached drawings.In attached drawing Give preferred embodiment of the invention.But the invention can be realized in many different forms, however it is not limited to this paper institute The embodiment of description.On the contrary, purpose of providing these embodiments is make it is more thorough and comprehensive to the disclosure.
It should be noted that it can be directly to separately when an element is considered as " connection " another element One element and it is in combination be integrated, or may be simultaneously present centering elements.Term as used herein " installation ", " one End ", " other end " and similar statement are for illustrative purposes only.
Unless otherwise defined, all technical and scientific terms used herein and belong to technical field of the invention The normally understood meaning of technical staff is identical.Term as used herein in the specification of the present invention is intended merely to description tool The purpose of the embodiment of body, it is not intended that in the limitation present invention.Term " and or " used herein includes one or more phases Any and all combinations of the listed item of pass.
On the one hand, as shown in Figure 1, the embodiment of the invention provides a kind of multi fan clarifier control methods, comprising:
S20: obtaining work order, and work order is used to indicate the working condition of each blower of control clarifier;
S40: it if work order is low-grade bit instruction, controls each blower and circuits sequentially work.
Wherein, work order is to be used to indicate the instruction for controlling each blower work.Low-grade bit instruction is to be used to indicate control Clarifier is in low-grade location operating mode, and with low power run, the same time only controls the work of separate unit blower.Circuit sequentially work Refer to, the same time only has the work of separate unit blower, and each blower in sequence, after the completion of foreground fanman makees, open by latter Fans Beginning takes over work, and in a cycle period, every Fans only work once.Specifically, detection work refers to after obtaining work order It is then to illustrate currently to need clarifier in lower function if low-grade bit instruction for low-grade bit instruction or high-grade bit instruction in order Rate work can meet demand, only need single blower work, can be obtained to guarantee each blower during the work time at this time Equilibrium utilizes, and controls each blower and circuits sequentially work, purifies to environment.
In one of the embodiments, as shown in Fig. 2, multi fan clarifier control method further include:
S60: if work order is high-grade bit instruction, at least two blowers is controlled and are worked at the same time.
Wherein, high-grade bit instruction is to be used to indicate control clarifier to run with relatively high power, same time control at least two A blower work.Specifically, illustrate currently clarifier to be needed to work with higher-wattage if work order is high-grade bit instruction, The work of single blower can not meet required, at this point, at least two blowers of control work at the same time, purify to environment.
In one of the embodiments, as shown in Fig. 2, controlling the step of each blower circuits sequentially work and including:
S41: each blower is controlled according to identical default operating time and circuits sequentially work.
Under low-grade bit instruction, in order to more balanced using each blower resource, control each blower work it is identical Next blower work is switched to after duration, for example, if clarifier is two fans clarifier, if work order is low-grade bit instruction, It then controls after No. 1 blower works 30 minutes and stops, being switched to No. 2 blower work, control No. 2 blowers and work 30 minutes, then switch It works 30 minutes to No. 1 blower, is recycled with this.
If in one of the embodiments, as shown in Fig. 2, being low-grade bit instruction in work order, control each blower according to It is further comprised the steps of: before secondary cycle operation step
S30: obtaining blower identification information, and the blower sum of clarifier is obtained according to identification information.
Currently, occurring modular clarifier in order to better meet user demand, being connect between multiple blowers by correspondence Mouth may be implemented to splice, and according to environment space size, clarifier can be spliced using the blower of different numbers.In order to better At work, the work for rationally controlling each blower, in booting, available blower identification information is obtained according to identification information The blower sum of the clarifier of clarifier.Wherein, identification information can be current signal, can control each in starting up Blower operates, and each blower fed-back current signals are given to the module that controller etc. has computing capability, and controller is according to receiving Current signal number, obtain clarifier blower sum.Identification information can also be that blower is numbered, and each blower has only The number of one of one number, each blower is different, and when clarifier is opened, feedback blower is numbered to controller etc. to be had each blower The module of computing capability, controller are purified the blower sum of device according to blower number.Obtain the blower of clarifier clarifier Sum, the job acceptance decision for each blower of subsequent control provide data foundation.
In one of the embodiments, as shown in Fig. 2, before obtaining blower identification information step further include:
S10: it detects whether to receive power-on instruction.
Before obtaining blower identification information, first detects whether to receive power-on instruction, if receiving power-on instruction, obtain Work order and blower identification information are taken, according to required, controls the working condition of each blower.
In one of the embodiments, as shown in Figure 3, further includes:
S61: air mass signal is obtained;
Controlling the step of at least two blowers work at the same time includes:
S62: according to air mass signal, general power needed for clarifier is determined;
S63: according to the blower of the operating power parameter of each blower prestored and clarifier sum, first object number is determined Amount;
S631: the blower of control first object quantity works at the same time, wherein the general power of the blower of first object quantity is not Less than general power needed for clarifier, and first object quantity is no more than the blower sum of clarifier.
Wherein, air mass signal can be the signal including parameters such as PM2.5 value, air pollution indexs.When work refers to When order is high-grade bit instruction, air mass signal is obtained, present circumstances are judged according to air mass signal, if judging environment It is relatively severe, then need more blower to work at the same time, so as to quickly fall the pollutant loads such as dust in environment Come, the blower sum of different air mass signal, clarifier corresponds to different first object quantity, this corresponding relationship, can be with It stores in advance, can be the forms such as homologous thread or the table of comparisons.By tabling look-up or obtaining the first mesh according to homologous thread Quantity is marked, after obtaining first object quantity, the blower that first object quantity is chosen from all blowers is worked at the same time.Optionally, According to air mass signal, the operating power of each blower can also be obtained, for example, there are three blowers if clarifier is total to, works as root When detecting PM2.5 data according to air mass signal as greater than 35 μ g/m3 less than 75 μ g/m3, two of them blower can control Simultaneously low power run, when PM2.5 data be greater than 75 μ g/m3 less than 115 μ g/m3 when, can control three blowers simultaneously with Mid power operation, when PM2.5 data are greater than 115 μ g/m3, three blowers are simultaneously with high power operation.
In one of the embodiments, as shown in figure 4, controlling at least two wind if work order is high-grade bit instruction The step of machine works at the same time include:
S64: parsing high-grade bit instruction, obtains the operating power of the second destination number and each blower;
S65: the blower of the second destination number of control works by corresponding operating power.
When receiving high-grade bit instruction, the second destination number can also be obtained by parsing to high-grade bit instruction With the operating power of each blower, for example, when being parsed to high-grade bit instruction, available clarifier current environment institute The general power needed, obtains that several blowers is needed to work at the same time according to required general power, and the blower respectively to work is needed with what Kind Power operation, then, the blower of the second destination number of control work according to corresponding operating power.For example, if clarifier is total There are three blowers, and after parsing to high-grade bit instruction, general power needed for being purified device, such as general power are 20W, separate unit For blower tool there are three gear, low-grade operating power is 4W, and middle-grade operating power is 8W, and highest operating power is 10W, then according to total Power, available second destination number is 2, and two blowers of work needs are run under 10W power.It is also possible that the Two destination numbers are 3, and two of them blower works under 8W power, and third blower is run under 4W low grade power, general power Meet 20W demand.
In one of the embodiments, as shown in figure 5, controlling each blower and circuiting sequentially work step and include:
S43: according to air mass signal, the operating power of each blower is determined;
S44: each blower is controlled by operating power and circuits sequentially work.
Wherein, air mass signal etc. is same with the above-mentioned embodiment, and this will not be repeated here.Specifically, receiving low grade After bit instruction, according to air mass signal, the operating power of each blower is determined, control each blower and circuit sequentially according to operating power Work.For example, detecting that air PM2.5 data are less than 35 μ g/m according to the air mass signal received3Hereinafter, at this time When each blower single machine works, with the low power run of 4W, then each blower is controlled according to the operating power of 4W and circuits sequentially fortune Row.
It should be understood that although each step in the flow chart of Fig. 1-5 is successively shown according to the instruction of arrow, These steps are not that the inevitable sequence according to arrow instruction successively executes.Unless expressly stating otherwise herein, these steps Execution there is no stringent sequences to limit, these steps can execute in other order.Moreover, at least one in Fig. 1-5 Part steps may include that perhaps these sub-steps of multiple stages or stage are not necessarily in synchronization to multiple sub-steps Completion is executed, but can be executed at different times, the execution sequence in these sub-steps or stage is also not necessarily successively It carries out, but can be at least part of the sub-step or stage of other steps or other steps in turn or alternately It executes.
On the other hand, as shown in fig. 6, the embodiment of the invention also provides a kind of multi fan clarifier control devices, comprising:
Work order acquiring unit 1, for obtaining work order, work order is used to indicate each blower of control clarifier Working condition;
Low-grade location air-blower control unit 2, for when work order is low-grade bit instruction, control each blower of clarifier according to Secondary cycle operation.
Wherein, the nouns paraphrase such as work order is same with the above-mentioned embodiment, and this will not be repeated here.Specifically, work refers to It enables acquiring unit 1 obtain work order and is sent to low-grade location air-blower control unit 2, when work order is low-grade bit instruction, Low-grade location air-blower control unit 2 controls each blower and circuits sequentially work.
Multi fan clarifier control device in one of the embodiments, further include:
High tap position air-blower control unit 3, for when work order is high-grade bit instruction, at least two blowers of control to be simultaneously Work.
Specifically, work order acquiring unit 1 obtains work order and is sent to high tap position air-blower control unit 3, work as work When work instruction is high-grade bit instruction, high tap position air-blower control unit 3 controls at least two blowers and works at the same time.
Wherein, it may refer to about the specific restriction of multi fan clarifier control device above for multi fan clarifier The restriction of control method, details are not described herein.Modules in above-mentioned multi fan clarifier control device can be all or part of It is realized by software, hardware and combinations thereof.Above-mentioned each module can be embedded in the form of hardware or independently of in computer equipment Processor in, can also be stored in a software form in the memory in computer equipment, in order to processor call execute The corresponding operation of above modules.
A kind of clarifier, including controller and multiple blowers, controller are electrically connected with each blower, and controller is stored with journey The step of sequence, controller realizes above-mentioned multi fan clarifier control method when executing program.Purification provided in an embodiment of the present invention Device, at work, controller obtain work order, and detect in work order whether have low-grade bit instruction and high-grade bit instruction, If detecting low-grade bit instruction, controls each blower and circuit sequentially work, if detecting high-grade bit instruction, control at least two Blower works at the same time.According to purification demand, the operating mode of each blower of intelligentized control method, equilibrium uses each blower, improves purification The service life of device.
In one embodiment, a kind of computer equipment is provided, which can be terminal, internal structure Figure can be as shown in Figure 7.The computer equipment includes processor, the memory, network interface, display connected by system bus Screen and input unit.Wherein, the processor of the computer equipment is for providing calculating and control ability.The computer equipment is deposited Reservoir includes non-volatile memory medium, built-in storage.The non-volatile memory medium is stored with operating system and computer journey Sequence.The built-in storage provides environment for the operation of operating system and computer program in non-volatile memory medium.The calculating The network interface of machine equipment is used to communicate with external terminal by network connection.When the computer program is executed by processor with Realize a kind of multi fan clarifier control method.The display screen of the computer equipment can be liquid crystal display or electric ink Display screen, the input unit of the computer equipment can be the touch layer covered on display screen, be also possible to outside computer equipment Key, trace ball or the Trackpad being arranged on shell can also be external keyboard, Trackpad or mouse etc..
It will be understood by those skilled in the art that structure shown in Fig. 7, only part relevant to application scheme is tied The block diagram of structure does not constitute the restriction for the computer equipment being applied thereon to application scheme, specific computer equipment It may include perhaps combining certain components or with different component layouts than more or fewer components as shown in the figure.
A kind of computer equipment, including memory and processor, memory are stored with computer program, and processor executes meter Step as shown in Figure 1 is realized when calculation machine program:
S20: obtaining work order, and work order is used to indicate the working condition of each blower of control clarifier;
S40: it if work order is low-grade bit instruction, controls each blower and circuits sequentially work.One kind is computer-readable to deposit Storage media, is stored thereon with computer program, and step as shown in Figure 1 is realized when computer program is executed by processor:
S20: obtaining work order, and work order is used to indicate the working condition of each blower of control clarifier;
S40: it if work order is low-grade bit instruction, controls each blower and circuits sequentially work.
Those of ordinary skill in the art will appreciate that realizing all or part of the process in above-described embodiment method, being can be with Relevant hardware is instructed to complete by computer program, the computer program can be stored in a non-volatile computer In read/write memory medium, the computer program is when being executed, it may include such as the process of the embodiment of above-mentioned each method.Wherein, To any reference of memory, storage, database or other media used in each embodiment provided herein, Including non-volatile and/or volatile memory.Nonvolatile memory may include read-only memory (ROM), programming ROM (PROM), electrically programmable ROM (EPROM), electrically erasable ROM (EEPROM) or flash memory.Volatile memory may include Random access memory (RAM) or external cache.By way of illustration and not limitation, RAM is available in many forms, Such as static state RAM (SRAM), dynamic ram (DRAM), synchronous dram (SDRAM), double data rate sdram (DDRSDRAM), enhancing Type SDRAM (ESDRAM), synchronization link (Synchlink) DRAM (SLDRAM), memory bus (Rambus) direct RAM (RDRAM), direct memory bus dynamic ram (DRDRAM) and memory bus dynamic ram (RDRAM) etc..
Each technical characteristic of embodiment described above can be combined arbitrarily, for simplicity of description, not to above-mentioned reality It applies all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited In contradiction, all should be considered as described in this specification.
The embodiments described above only express several embodiments of the present invention, and the description thereof is more specific and detailed, but simultaneously Limitations on the scope of the patent of the present invention therefore cannot be interpreted as.It should be pointed out that for those of ordinary skill in the art For, without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to guarantor of the invention Protect range.Therefore, the scope of protection of the patent of the invention shall be subject to the appended claims.

Claims (10)

1. a kind of multi fan clarifier control method characterized by comprising
Work order is obtained, the work order is used to indicate the working condition of each blower of control clarifier;
If the work order is low-grade bit instruction, each blower for controlling the clarifier circuits sequentially work.
2. multi fan clarifier control method according to claim 1, which is characterized in that further include:
If the work order is high-grade bit instruction, at least two blowers of control are worked at the same time.
3. multi fan clarifier control method according to claim 1 or 2, which is characterized in that each blower of the control according to The step of secondary cycle operation includes:
It controls each blower and circuits sequentially work according to identical default operating time.
4. multi fan clarifier control method according to claim 2, which is characterized in that in the step of obtaining work order Before, further includes:
Blower identification information is obtained, the blower sum of the clarifier is obtained according to the identification information.
5. multi fan clarifier control method according to claim 1 or 2, which is characterized in that know in the acquisition blower Before other information Step, further includes:
It detects whether to receive power-on instruction.
6. multi fan clarifier control method according to claim 4, which is characterized in that further include:
Obtain air mass signal;
Controlling the step of at least two blowers work at the same time includes:
According to the air mass signal, general power needed for clarifier is determined;
According to the blower of the operating power parameter of each blower prestored and clarifier sum, first object number is determined Amount;
The blower of control first object quantity works at the same time, wherein the general power of the blower of the first object quantity is not Less than general power needed for the clarifier, and the first object quantity is no more than the blower sum of the clarifier.
7. multi fan clarifier control method according to claim 4, which is characterized in that if the work order is top grade Bit instruction, then controlling the step of at least two blowers work at the same time includes:
The high-grade bit instruction is parsed, the operating power of the second destination number and each blower is obtained;
The blower for controlling the second destination number works by the corresponding operating power.
8. multi fan clarifier control method according to claim 1, which is characterized in that control each blower and circuit sequentially work Include: as step
According to the air mass signal, the operating power of each blower is determined;
It controls each blower and circuits sequentially work by the operating power.
9. a kind of multi fan clarifier control device characterized by comprising
Work order acquiring unit, for obtaining work order;
Low-grade location air-blower control unit, for controlling each blower and circuiting sequentially work when work order is low-grade bit instruction;
High tap position air-blower control unit, for when work order is high-grade bit instruction, at least two blowers of control to be simultaneously Work.
10. a kind of clarifier, which is characterized in that including controller and multiple blowers, the controller is electrically connected with each blower It connects, the controller is stored with program, and the controller is realized of any of claims 1-8 when executing described program The step of multi fan clarifier control method.
CN201811117469.8A 2018-09-20 2018-09-20 Multi fan clarifier control method and device, clarifier Pending CN109210688A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811117469.8A CN109210688A (en) 2018-09-20 2018-09-20 Multi fan clarifier control method and device, clarifier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811117469.8A CN109210688A (en) 2018-09-20 2018-09-20 Multi fan clarifier control method and device, clarifier

Publications (1)

Publication Number Publication Date
CN109210688A true CN109210688A (en) 2019-01-15

Family

ID=64985195

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811117469.8A Pending CN109210688A (en) 2018-09-20 2018-09-20 Multi fan clarifier control method and device, clarifier

Country Status (1)

Country Link
CN (1) CN109210688A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110986220A (en) * 2019-12-30 2020-04-10 南京云天节能环保科技有限公司 Air purifier of modularization fan

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60152846A (en) * 1984-01-23 1985-08-12 Nippon Denso Co Ltd Blower provided with electrostatic air purifier
CN101915246A (en) * 2010-07-22 2010-12-15 中兴通讯股份有限公司 Box-shaped network equipment and blower control method thereof
CN204084625U (en) * 2014-07-16 2015-01-07 宁波横河模具股份有限公司 A kind of two fans air purifier
CN104896653A (en) * 2014-03-07 2015-09-09 珠海格力电器股份有限公司 Control method of air purifier
CN105444350A (en) * 2015-12-01 2016-03-30 杭州钛合智造电器有限公司 Air purifier and air quality control method and system
CN105465023A (en) * 2015-11-16 2016-04-06 珠海格力电器股份有限公司 Control method and device of multi-fan system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60152846A (en) * 1984-01-23 1985-08-12 Nippon Denso Co Ltd Blower provided with electrostatic air purifier
CN101915246A (en) * 2010-07-22 2010-12-15 中兴通讯股份有限公司 Box-shaped network equipment and blower control method thereof
CN104896653A (en) * 2014-03-07 2015-09-09 珠海格力电器股份有限公司 Control method of air purifier
CN204084625U (en) * 2014-07-16 2015-01-07 宁波横河模具股份有限公司 A kind of two fans air purifier
CN105465023A (en) * 2015-11-16 2016-04-06 珠海格力电器股份有限公司 Control method and device of multi-fan system
CN105444350A (en) * 2015-12-01 2016-03-30 杭州钛合智造电器有限公司 Air purifier and air quality control method and system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110986220A (en) * 2019-12-30 2020-04-10 南京云天节能环保科技有限公司 Air purifier of modularization fan

Similar Documents

Publication Publication Date Title
CN109639751B (en) Block chain link point monitoring method, device and system and computer storage medium
CN107291950B (en) Form data updating method and device and computer equipment
CN101840216B (en) Programmable logical controller parameter setting system and method thereof
CN106899649A (en) A kind of task requests processing method, device and user equipment
CN105094736A (en) Display control method and device and electronic device
CN108959139A (en) A kind of CPLD pin multiplexing method and device
CN111158806B (en) Interface display method, device, computer equipment and storage medium
CN101149690A (en) Computer system including device conducting independent system management operation and control method thereof
CN103543901A (en) Method and device for generating menus
CN104035921A (en) Information processing method and electronic devices
CN105138227A (en) Icon display method and terminal
CN109210688A (en) Multi fan clarifier control method and device, clarifier
CN105677233A (en) Storage method and storage device for real-time data
CN101753360B (en) Method applying system start-up, parallel management system and application management system
WO2018040271A1 (en) Thread processor and thread processing method
CN101685396A (en) System and method for controlling function icon
CN114461462B (en) BIOS debugging information output method, device, equipment and storage medium
CN106648794A (en) Component loading method and device
CN104461603A (en) Information processing method and electronic equipment
CN108491287A (en) Memory address monitoring method, device and electronic equipment
CN113064833A (en) Single chip microcomputer simulation method, system, device, equipment and storage medium
CN104063192A (en) Display method and electronic equipment
CN105138666A (en) Data processing method and terminal
CN107273328B (en) Interface management method and system
CN105573870A (en) Control method and device for starting load device based on multi-way redundant power supply modules

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190115

RJ01 Rejection of invention patent application after publication